TAHAPAN PEMASANGAN BEGISTING KOLOM
1. SETING PANEL KOLOM
SECTION MIN 0,35X0,35 MTRSECTION MAX 1,20X1,20 MTR
-
7/25/2019 Kist Sateco
3/20
TAHAPAN PEMASANGAN BEGISTING KOLOM
2. SETING PANEL KOLOM
-
7/25/2019 Kist Sateco
4/20
TAHAPAN PEMASANGAN BEGISTING KOLOM
3. SETEL PRESISI KOLOM
-
7/25/2019 Kist Sateco
5/20
TAHAPAN PEMASANGAN BEGISTING KOLOM
4. SETEL VERTICAL KOLOM 5. SETEL VERTICAL & HORISONTAL
-
7/25/2019 Kist Sateco
6/20
TAHAPAN PEMASANGAN BEGISTING KOLOM
6.PEMBERIAN BETON DEKING 7. BEGISTING SIAP COR
-
7/25/2019 Kist Sateco
7/20
TAHAPAN PEMASANGAN BEGISTING DINDING
1. SETING PANEL DINDING
PANEL 2,4 X 3 MTR
-
7/25/2019 Kist Sateco
8/20
TAHAPAN PEMASANGAN BEGISTING DINDING
2. SETING PANEL DINDING
ADJUSTABLE BRACING
Untuk panel dinding 2 muka
POTONGAN SAMPING
PANEL BEGISTING DINDING
-
7/25/2019 Kist Sateco
9/20
TAHAPAN PEMASANGAN BEGISTING
RETENING WALL
POTONGAN SAMPING
ADJUSTABLE BRACING
PANEL DINDING
PLAT LANTAI BETON
CLIMBING
-
7/25/2019 Kist Sateco
10/20
BORE PILE
RETAINING WALLININ! 1 MU"A
PANEL
-
7/25/2019 Kist Sateco
11/20
%A&&
PANEL DINDING DILETAKKAN PADA AREA
$AA A"#IR SECTION I'ERI STO$ COR
MEN(ETE& &E)E& AN $ERI"SA $ER"UATAN
-
7/25/2019 Kist Sateco
12/20
PEMASANGAN CORE
WALL$ANE& CORE ITEM$AT"AN $AA
AREA EN!AN 'ANTUAN TC
-
7/25/2019 Kist Sateco
13/20
$EN!ECORAN ININ! CORE
-
7/25/2019 Kist Sateco
14/20
$ANE& ININ! A$AT I$A"AI UNTU" "O&OM
-
7/25/2019 Kist Sateco
15/20
TAHAPAN PEMASANGAN BEGISTING
BALOK
1. DETAIL BEGISTING BALOK
ADJUSTER
SQ 50x50x2,3
SURI-SURI CNP 125x50x20x3,2 (2X)
VERTICAL FRAME
TIEROD/ WING NUT
CNP 5x!5x"5x2,3
UNP 5x!2x5
UNP 50x3#$5
U%HEAD
PLATE T&5MM
PLATE T& 2MM
-
7/25/2019 Kist Sateco
16/20
TAHAPAN PEMASANGAN BEGISTING
BALOK
2. DETAIL BEGISTING BALOK
ADJUSTER
SQ 50x50x2,3
SURI-SURI CNP 125x50x20x3,2 (2X)
VERTICAL FRAME
TIEROD/ WING NUT
CNP 5x!5x"5x2,3
UNP 5x!2x5
UNP 50x3#$5
U%HEAD
PLATE T&5MM
PLATE T& 2MMSQ 50x50x2,3
-
7/25/2019 Kist Sateco
17/20
TAHAPAN PEMASANGAN BEGISTING
BALOK
3. TAMPAK SAMPING
-
7/25/2019 Kist Sateco
18/20
P"#$%&' K%"*+ %&'. /+ 200
http://rkap%20%20inves.xls/http://rkap%20%20inves.xls/http://rkap%20%20inves.xls/http://rkap%20%20inves.xls/ -
7/25/2019 Kist Sateco
19/20
S'()*+ B')-.)+ PJA
PROEKKOLOM 1 2 DINDING 1 2
V46' S'()**+ V46' S'()**+
S*768+* 2,!00 !9 2,350 5
CBD C)'(6 !,"93 5
P*:* ,300 ; !,000 9;
P'8(**+*+ "0,099 ; 2,9#5 "39
P4+(4 G'(' !,000 "#
J6*< 5 P84=' 2,#" 2; #,2!5 29"
T4.* I+>'-.*-) 59 J. 29 S'. ;00 J. !0 -'.
PJA ," T*
-
7/25/2019 Kist Sateco
20/20
A+*)-* H*8* S*.6*+ B')-.)+
U8*)*+ T*