COMPANYWIDE HIGHLIGHTS
� Final audit by ASME team completed and N-Stamp certification has been recommended for
the company - KBL will be the 1st company for rotating equipment to receive the ASME N-
stamp.
� Establishment of the PMO (Project Management Office) in progress – with extensive focus
on detailed schedule preparation, training to project management teams and improving
This is a proprietary document of Kirloskar Brothers Ltd. 22This is a proprietary document of Kirloskar Brothers Ltd.
on detailed schedule preparation, training to project management teams and improving
review mechanism and existing systems and processes related to the projects business.
� Ahmedabad plant commenced commercial production in June 2012.
� Improving quality of Balance Sheet continues to be main financial agenda.
SECTOR HIGHLIGHTS
IRRIGATION
� Successfully commissioned the Francis Turbine Pump in Bheema LIS in AP.
� Contractually completed and handed over projects like Jalundara Gujarat, LAOS PDR and Six
Pumping Stations in Egypt.
� Received certificate of completion of work from SSNNL.
3This is a proprietary document of Kirloskar Brothers Ltd. 3This is a proprietary document of Kirloskar Brothers Ltd.
WATER RESOURCE MANAGEMENT
� Physical closure of two projects, Jaipur – Bisalpur at Jaipur, and KMC Sirity Park at Kolkata.
� Contractual closure of two projects - Porur, Tamil Nadu, and AUDA Vinzol, Ahmedabad.
� Received orders from Patel Engg, Mumbai, for 76 Large Diameter Butterfly Valves for BMC.
� Completed erection of all 30 large Horizontal Split case pumps for BWSSB project.
SECTOR HIGHLIGHTS
POWER
� Dispatched first Pelton turbine twin jet horizontal machine for 2x2 MW Panwi HEP.
� Vertical Kaplan machines commissioned in auto mode through PLC SCADA system for the
2x5.5 MW Konal HEP.
� Received appreciation letter from Calik Enerji,Turkey, for successfully commissioning pumps for
420 MW Navoi CCPP, Uzbekistan.
4This is a proprietary document of Kirloskar Brothers Ltd. 4This is a proprietary document of Kirloskar Brothers Ltd.
420 MW Navoi CCPP, Uzbekistan.
GAS OIL & DEFENCE
� 4 offshore fire water packages delivered to ONGC. Remaining four packages to be delivered in
Q2.
� Received first order from Cairn Energy India Pty Ltd. for trolley mounted motor driven pumps.
SECTOR HIGHLIGHTS
INDUSTRY
� Brought about better awareness for the AutoPrime® products by giving demonstration in
coalfields in Northern, Central and Eastern India.
� Continued thrust on LLC pumps by making presentations at CII Meet, Hyderabad, by
targeting the cement and steel industries in general, and Energy Auditors in particular.
5This is a proprietary document of Kirloskar Brothers Ltd. 5This is a proprietary document of Kirloskar Brothers Ltd.
BUILDING & CONSTRUCTION
� Introduced an innovative vertical design pump in the fire fighting market that offers space
saving of up to 30% to developers and shifted demand from the traditional horizontal design
pump house.
� Booked Mumbai, Jaipur & Gurgaon Metro rail orders against major global players.
� Bagged India’s 1st FM/UL VT from automobile institute.
SECTOR HIGHLIGHTS
DISTRIBUTION
� Launch of 4 new pump models and the initial response from the market has been
encouraging.
� Appointment of new dealers progressing as per plan to ensure target of 30 Distributors,
Dealers and 300 retailers under project 'REACH'.
CUSTOMER SERVICE & SUPPORT
6This is a proprietary document of Kirloskar Brothers Ltd. 6This is a proprietary document of Kirloskar Brothers Ltd.
CUSTOMER SERVICE & SUPPORT
� Separate storage / warehouse facility developed at Kirloskarvadi for spare parts made
operational for faster delivery and to garner more market share.
� Entered into an annual rate contract (ARC) with a few large corporate customers.
� Thrust on the sugar industry with five seminars conducted at Pune, Kolhapur, Latur, Solapur &
Ahmednagar.
� Introduced the 'Health Card' monitoring of large VT / CVP pumps of top 50 customers - this will
enable KBL to provide after sales services in a timely manner.
FACTORY HIGHLIGHTS
KIRLOSKARVADI
� Received FM/UL approval for US Market.
� Dispatched the following major orders:
� 6 Nos. Vertical Turbine Pumps against the first prestigious FM_UL order from Chile
7This is a proprietary document of Kirloskar Brothers Ltd. 7This is a proprietary document of Kirloskar Brothers Ltd.
� 6 Nos. Vertical Turbine Pumps against the first prestigious FM_UL order from Chile
� First Pelton turbine to Panwani HEP.
� BHR 60 & BHR 42 - 7 Pumps, RKBV 5 Pumps and Split case 9 Pumps to Portugal.
� KPD 250/50 – 4 Pump Sets A/c. Danieli - China .
� 12 Nos. DB 200/36 A/c. SPP.
FACTORY HIGHLIGHTS
DEWAS, SHIRWAL & COIMBATORE
� Coimbatore plant awarded “Second best Productivity Award” for the year 2011-12 by
Coimbatore Productivity Council.
� Coimbatore plant achieved 4 star rating during 5S certification.
� Received order of 3,793 submersible pumps from Orissa Lift Irrigation Corporation.
8This is a proprietary document of Kirloskar Brothers Ltd. 8This is a proprietary document of Kirloskar Brothers Ltd.
� Received order of 3,793 submersible pumps from Orissa Lift Irrigation Corporation.
KONDHAPURI
� Received approvals from Cethar Vessels, EDAC Engineering and Tata Steel.
� Completed development of 21 models of Suction Diffuser.
AHMEDABAD PLANT HIGHLIGHTS
07.01.1110This is a proprietary document of Kirloskar Brothers Ltd. 10This is a proprietary document of Kirloskar Brothers Ltd.
COMPANYWIDE PENDING ORDERS
(Rs.In Crores)
Sector 4Q 1Q 1QMar-12 Jun-12 %of Total
IRRIGATION 1,310 1,277 51%
WATER RESOURCE MANAGEMENT 243 237 12%
POWER 616 633 26%
GAS, OIL, DEFENSE 145 111 5%
INDUSTRY 72 85 3%
This is a proprietary document of Kirloskar Brothers Ltd. 1111This is a proprietary document of Kirloskar Brothers Ltd.
INDUSTRY 72 85 3%
BUILDING & CONSTRUCTION 30 30 1%
DISTRIBUTION 38 43 1%
CUSTOMER SUPPORT & SERVICES 30 31 1%
TOTAL (Standalone) 2,484 2,447 100%
Rs. In crores
KBL Standalone
4Q
(2011 - 12)
1Q
(2012 - 13)
Orders Received 366 401
Rs. In crores
KBL Consolidated
4Q
(2011 - 12)
1Q
(2012 - 13)
Orders Received 578 588
Pending orders on hand 2,842 2,809
Q1 FINANCIALS – STANDALONE HIGHLIGHTS
� Cash generation of Rs. 40 crores in Q1 FY13 as compared to negative cash generation of 37
crores in Q1 FY12.
� Reduction in borrowings by Rs. 11 crores during Q1 FY13
� Control over receivables through matching of sector wise sales with recoveries.
12This is a proprietary document of Kirloskar Brothers Ltd. 12This is a proprietary document of Kirloskar Brothers Ltd.
� Reduction in net current assets of Rs. 25 crores during the quarter.
� Income tax refund of Rs. 35 crores during the quarter.
Q1 FINANCIALS – STANDALONE HIGHLIGHTS …
CONT’D …
� Revenue from operations is at Rs. 442 crores as against Rs.430 crores in PY – rise of 3%. All
sectors have crossed sales over previous year except Irrigation, and Power sectors.
� KBL continued to be selective with orders and execution to improve sales mix, which resulted
13This is a proprietary document of Kirloskar Brothers Ltd. 13This is a proprietary document of Kirloskar Brothers Ltd.
in civil sale going down to 4% as against 13% in the similar quarter in the previous year.
� PBT is Rs. 11crs as against Rs. 46 crores in PY. PY includes non-operating income of Rs. 35
crores being profit on sale of investment in Gondwana Engineers Ltd.
� CY included notional exchange loss on foreign currency loans – Rs. 9 crores as against 1.2
crores in PY.
Q1 KEY FINANCIALS - STANDALONE
Rs. Crs
Particulars
Jun-12 Jun-11 Jun-10
KEY FINANCIALS
Total Income 444 467 394 1,828
P B D I T 26 62 24 102
P B T 11 47 6 34
Year Ended
Mar 31,
2012
Quarter Ending
14This is a proprietary document of Kirloskar Brothers Ltd. 14This is a proprietary document of Kirloskar Brothers Ltd.
P B T 11 47 6 34
P A T 9 36 4 31
CASH PROFIT 17 44 11 61
KEY FINANCIAL RATIOS
P B I D T % AGE 6% 13% 6% 6%
P B T % AGE 3% 10% 2% 2%
R O C E % AGE 6.9% 17.6% 5.7% 6.5%
Note: Figures of period ending June 2011 & March 2012 includes profit on sale of investment Rs. 35 crores
Q1 KEY FINANCIALS - STANDALONE
Balance sheet Key Figures Rs. Crs
Particulars
Jun-12 Jun-11 Jun-10
Total Assets 1,098 1,241 1,182 1,101
Quarter Ending Year Ended
Mar 31,
2012
15This is a proprietary document of Kirloskar Brothers Ltd. 15This is a proprietary document of Kirloskar Brothers Ltd.
Total Assets 1,098 1,241 1,182 1,101
Gross Current Assets 1,504 1,753 1,765 1,536
Gross Current Liabilities 979 1,060 1,088 986
Net Current Assets 525 693 677 550
Borrowings 339 457 457 350
Q1 KEY FINANCIALS -CONSOLIDATED
( Rs in Crores )
Particulars
Jun-12 Jun-11 Jun-10
KEY FINANCIALS
Total Income 617 647 547 2,603
P B D I T 49 74 34 194
Quarter Ending Year Ended
Mar 31,
2012
16This is a proprietary document of Kirloskar Brothers Ltd. 16This is a proprietary document of Kirloskar Brothers Ltd.
P B D I T 49 74 34 194
P B T 23 55 15 75
P A T 18 41 9 51
CASH PROFIT 30 51 19 97
KEY FINANCIAL RATIOS
P B I D T % AGE 8% 11% 6% 7%
P B T % AGE 4% 8% 3% 3%
R O C E % AGE 12% 18% 7% 12%
Note: Figures of period ending June 2011 & March 2012 includes profit on sale of investment Rs. 35 crores