Phase 2A In this slide show: Brick pavers for Jackson Plaza and lower station pathway March 30, 2011

Upload: allieger

Post on 15-May-2015

1.585 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: King Street Station 3.30.11 slide show

Phase 2AIn this slide show:

Brick pavers for Jackson Plaza and lower station pathway

March 30, 2011

Page 2: King Street Station 3.30.11 slide show

Reinforced architectural stamped curb casted to protect the red brick pavers next to the station from vehicles.

Page 3: King Street Station 3.30.11 slide show

The stamped curb is separately casted in blocks and connected with an expansion joint. Groove details aid with traction.

Page 4: King Street Station 3.30.11 slide show

Stamped curb shown above is partially casted. It follows the contour of the station southward.

Page 5: King Street Station 3.30.11 slide show

Red pavers are individually hand set to the tightest fit. Sand sub base helps create a level surface for the pavers.

Page 6: King Street Station 3.30.11 slide show

Most of the west walkway pavers are in place.

Page 7: King Street Station 3.30.11 slide show

A large crane pumped gravel which will be use as sub base for the Jackson Plaza above.

Page 8: King Street Station 3.30.11 slide show

The gravel was spread over the black drain mats.

Page 9: King Street Station 3.30.11 slide show

An overview of Jackson Plaza with the gravel in place and insulation being installed.

Page 10: King Street Station 3.30.11 slide show

Bedding sand between the crushed base help level the red brick pavers.

Page 11: King Street Station 3.30.11 slide show

The new pedestrian pathway for the station entry is almost fully paved.

Page 12: King Street Station 3.30.11 slide show

All planters were painted with black color sealer to help prevent dirt moisture from escaping and help reduce effervescence..

Page 13: King Street Station 3.30.11 slide show

A northeast sidewalk section was leveled to match Jackson Plaza.

Page 14: King Street Station 3.30.11 slide show

Planting dirt filled all of the planters.

Page 15: King Street Station 3.30.11 slide show

Waterproof membrane shown helps prevent leaks in the 12th floor level.