The Kingdom of Cambodia Ministry of Public Works and Transport Key Logistics and Transport Systems and Facilities along the Asian Highway and Trans Asian Railway 1 Hong Sinara, DDG of Public Works /MPWT Suon Vanhong, DD of Transport/ MPWT

Upload: others

Post on 28-Sep-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210

The Kingdom of Cambodia

Ministry of Public Works and Transport

Key Logistics and Transport Systems and Facilities along the Asian Highway and Trans Asian

Railway

1

Hong Sinara, DDG of Public Works /MPWTSuon Vanhong, DD of Transport/ MPWT

Page 2: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210
Page 3: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210

• Signed and Ratified  all Protocols and Annexes of GMS CBTA

• Implementation on GMS CBTA  between Cambodia and Thailand: signed:  ‐ MOUon  GMS  IICBTA  Through  the  Aranyaprathet‐Poipet  Border  Crossing Points‐MOU on the Exchange of Traffic Rigth (to allow 40 vehicles from each country to perform   the  cross‐border transportation) ‐ Addendum to the MOU between on the Exchange of Traffic Rights for Cross‐Border  Transport  Through  the  Aranyaprathet‐Poipet  Border  Crossing  Points.      ( De‐Linking The MOU2 from MOU1) on 2 November 2009 – 18 July 2012, open ceremony for exchange of traffic rigth, at Poi pet‐Aranyaprathet, on 40 quotas vehicles,.

Cross-Border Transportation FacilitationInternational Agreement on Cross-Border Transportation Facilitation

Page 4: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210

•• Implementation  of  Bilateral  Road  Transport  Agreement  (BRTA)  betwImplementation  of  Bilateral  Road  Transport  Agreement  (BRTA)  between  Cambodia een  Cambodia and Vietnam :and Vietnam :Cambodia  has  signed  Agreement  and  Protocol  on  Road  Transportation  between Cambodian and Vietnam .Allow 40 vehicles (truks and buses ) to perform cross‐border transportation between Cambodia and Vietnam;  More 6 border gates between two countries has signed open and perform cross‐border transpotation;MOU on Type and Quantity of conmercial vehicles has  signed on  17 March 2009  to increased quotas from 40 to 150 vehicles;MOU to increased quotas from 150 to 300 vehicles,signed in 2011.Working  on Draft MOU‐ to  increased quotas  from  300  to  500  vehicles,requested by Viet Nam, included 2 more border gates;

•• Implementation  of  Bilateral  Road  Transport  Agreement  (BRTA)  betwImplementation  of  Bilateral  Road  Transport  Agreement  (BRTA)  between  Cambodia een  Cambodia and Lao PDR :and Lao PDR :Cambodia  has  signed  Agreement  and  Protocol  on  Road  Transportation  between Cambodian  and  Lao  PDR;  40  Trucks  from  each  countries will  perfom cross‐border transportation.  Bus\Passenger  services  will  perform    saperately  by  partner  contract between  the  association  and  company(s)  of    the  two  countries. The  route,  stations, prices, quota number, and other condition of the contract should be agreed upon and certify by two authorities/ministries (MPWTs);    In 2012, September, 21‐22, both sides are working  for establishement of   more opened of buses operations beweet  the  two countries,

International Agreement on Cross-Border Transportation Facilitation

Page 5: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210

Development of International Border PointsDevelopment of International Border Points

Barail‐Samlot

Hatlet‐Chamyeam

BanKlongYai‐Chamyeam

Pakkard‐Pailen

Loem‐Kamreing

Aranyaprathet‐Poipet

Ban Sangae pass

Chong Krang pass

Chong Chompass

Chong Sangampass

Chong Ammapass

Chong Bok passDesignated Entry‐Exit points for BRTA (CAM/VN, CAM/LAOS)

Oyadav(CAM)‐LeThanh (VN)

Dak Dam(CAM)‐Bou Prang(VN)

TrapeingSre(CAM)‐Bou Nou(VN)

TrapeingPlongCAM)‐Sa mat(VN)

Bavet(CAM)‐Moc Bai(VN)

Phnom Den(CAM)‐Tinh Bean(VN)

PreakChak(CAM)‐Ha Tieng(VN)

Trapeing krealCAM)‐

Nang Nokheang Laos)

VN

TH

Page 6: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210

Major Ports in Cambodia

There are 7 domestic ports in the Mekong River system and two international ports in Cambodia are:

1. Phnom Penh Port on the Mekong river

2. Sihanouk ville Port on the Gulf of Thailand

6

Page 7: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210

Sihanoukville Autonomous Port(Sea Port)

Phnom Penh Autonomous Port (River Port)

Cambodia has two major Ports

77

Page 8: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210

Water Transport Projects Water Transport Projects River and Maritime Corridor

From Phnom Penhto Ho Chi Minh 430 Km by Inland Waterway/246km by roadto Cai Mep- Thi Vai 380 Km by Inland Waterway/325km by roadto Sihanoukvill 230 Km by Road No.4

Sihanoukville Port Cai Mep‐Thi Vai Port

Page 9: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210

Present servicesContainer Terminal(Quay): 20m x 300m

Domestic Port: Phnom Penh, Kampong Cham, Siem Reap…Passenger TerminalICD: 92, 000m2

Warehouses: 70m x 50m = 3500m2

50m x 30m = 1500m2

Go to KAMSAB

Page 10: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210

New Container Terminal of Phnom Penh Port

- Location 25 km from PPenh in the lower Mekong river.- Total cost 28 M USD (Chinese loan)- Capacity:120,000 TEUs/Year, - Max. capacity: 300,000 TEUs/year- Berth : 22m x 300m- Area: 12 ha- Start operation 2012

Cargo throughput -PPAP (2000-2012,T)

Page 11: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210

1. Phnom Penh Port and ( SEZ )1. Phnom Penh Port and ( SEZ )

This Project is under Preparatory Survey by JICA.JICA shows strong support for conducting a Feasibility Study in 2013. Construction will start 2014.

Location:at PK 30 along NR1, opposite side of current New Container Terminal.

Area: approximately 250ha

NR1

Page 12: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210

New Container Terminal of Phnom Penh Autonomous Port will be operated soon.

12

New Phnom Penh Port

Page 13: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210

13

2. Sihanouk Ville Port2. Sihanouk Ville Port• Sihanoukville

Autonomous Port (PAS) is the sole international and commercial deep seaport of the Kingdom of Cambodia.

• PAS is located at the bay of Kampong Som, Gulf of Thailand, South China Sea.

• At present, the total operational land area is around 129.6 ha.

Page 14: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210

1. Navigational service2. Handling Service3. Storage and Warehousing  services4. Security services5. Special Economic Zone6. Logistics Supply Base for offshore Oil exploration

Tug boatTug boat Rubber Tired Gantry CraneRubber Tired Gantry Crane

Reach StackerReach Stacker

TruckTruck

SShore Cranehore Crane

MAIN SERVICES

14

Quay Gantry CraneQuay Gantry Crane

Page 15: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210

FACILITIES

15

Equipment Capacity Units

‐ Quay Gantry Crane  30.50t 02

‐Mobile Harbor Crane  60t 02

‐ RTG   35.5t 07

‐ Super Stacker 45t 08

‐ Empty Stacker  7.5t 01

‐ Chassis/Trailer 20'‐40’ 33

‐ Shore Crane  10‐50t 9

‐ Truck for general cargo 10‐20t 08

‐ Forklift  2‐25t 17

Navigational Facilities

Tugboat 800 HP x 2  &  800 HP 

03 &  02

Pilot boat 390 HP 01

Mooring boat 175 HP 01

Patrol boat 210 HP x 2 01

Handling Productivities

Container movement  25 boxes/hr‐QC

General cargo 5 000 tons/day‐berth

Average occupancy rate at new CT/week 

65.7 %  ( 70%~)

Average vessel’s dwell time at berth

25 hrs

Vessel Capacity  Called ~ 2 000 TEUs(<20 000 tons)

Page 16: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210

- Vessel Traffic Management System (VTMS) 1 set- X- Ray Scanner 1 set- Patrol Boat 100HP 1 Unit- Oil Fence with 440 m long 1 set- Oil Skimmer 1 Unit - Oil Barge 100m³ 1 Unit- CCTV Cameras to be equipped with Alarms 25 Sets- ID PAS’s Card Entering System 5 Sets- Security Station 2 Places

Radiation Detector

SECURITY EQUIPMENT

16

Page 17: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210

Sihanouk Ville Port is multi‐transport network connects to Hinterlands/ Consumption/Distribution Centre and to Neighboring Countries. 

TRANSPORT NETWORKS : SEA,LAND&AIR CONNECTIONS TO PAS

17

Page 18: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210

Lines Calling Schedule Frequency Rotation PortsRCL(3 calls/week)

1. Wed 08:00 – Thu 16:002. Thu 14:00 – Fri 22:003. Fri 20:00 – Sat 23:59

1 call/week1 call/week1 call/week

1. SIN-SHV-SGZ-SIN2. HKG-SHV-SGZ-HKG-(HPH-TXG-KEL)3. KUN-SHV-SGZ-SIN-KUN

MAERSK(2 calls/week)

1. Tue 15:00 – Wed 07:00

2. Fri 22:00 – Sun 00:01

1 call/ week

1 call/ week

1. SGN-SHV-LZP-TPP-SIN-BTG-MNL-KAO-YAT-HKG-SGN2. SIN-SHV-TPP-SIN

SITC (BEN LINE)( 1 call/week) Sun 09:00 – 23:00 1 call/week HCM-SHV-BKK-LZP-HCM-NSA-NBO-

SGH-OSA-KOB-BUS-SGH-HGK-HCM

ITL (ACL)(1 call/week) Sat 06:00 – Sun 08:00 1 call/week SGZ-SHV-SIN-SGZ

APL(1 call/week) Fri 08:00 – Sun 06:00 1 call/week SIN-SHV-SIN

COTS(1

call/2weeks)Mon 08:00 – 13:00 1 call/2 weeks

(~3 Call / month) BKK-SHV-BKK- (LZP)

Total 9 Calls / week

18

REGULAR  SHIPPING  LINES  SCHEDULES  

AND  CALLING  PORT  ROTATION

Remarks

BKK : BangKok, Thailand KUN : Kuantan,Malaysia SHV : Sihanoukville Port, Cambodia

YAT : Yantian,China

BUS : Busan, South Korea KEL : Keelung,Taiwan SGN : Saigon,Vietnam

BTG : Bantagas, Philippine LZP : LaemChabang,Thailand SIN : Singapore

HKG : HongKong MNL : Manila, Philippine SGH : Shanghai, China

HPH : Hai Phong, Vietnam NSA : Nansha, China SGZ : Songkhla,Thailand

HCM : Ho Chi Minh, Vietnam

NBO : Ningbo, China TXG : Taichung,Taiwan

KOB : Kobe Japan OSA : Osaka Japan TPP : Tanjung Pelepas Malaysia

Page 19: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210

Cruise Ships

Year Vessel No. Passenger No. 

2009 17 20,217

2010 17 24,261

2011 15 7,958

2012 (8 m.)  21 16,287

Passenger Terminal

Page 20: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210

The Average Growth  of the last three years (2009‐2011):‐Gross Throughput 14.09%, and‐Container Throughput 7% .

The 2012 Prognoses:‐Gross Throughput 2,850,000 tons, and‐Container Throughput 260,000 TEUs.

IMPORTS : Fuel, GC, Fabric, Steam coal, Constr. materials, Machinery, Clothing, Car, Cigarette, Vehicle.EXPORTS : Garment&Shoes, Rice, GC, Wood Processing, Cigarette, Rubber, Machinery, Aluminum, SeaFood, Medicine,    Beer.                     

Cargo Statistics (Cont’)

20

Page 21: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210

21

Page 22: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210

DEVELOPMENT  PHASES

22

Page 23: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210

Lease fee is a variable depending on lease space and period factors.*The prices range from USD 40/ m2 up to USD 65/ m2

23

LAND LEASE CONDITIONS

Period 20-year 30-year 40-year 50-year

10ha US$40 US$45 US$51 US$55

5ha US$44 US$49 US$56 US$61

2ha US$47 US$52 US$59 US$64

~1ha US$48 US$53 US$60 US$65

(Land lease period is complied with new Civil Code of Royal Government of Cambodia that has taken effect on December 20, 2011)

* The above fees are not inclusive of 10% withholding TAX .

Page 24: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210

Port General Layout and Future Perspectives

1144

22

3355

1. Passenger Terminal2. Container Terminal3. Special Economic Zone4. Multipurpose Terminal &

Logistics5 Future Expansion

24

Page 25: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210

25

Poipet O’neag 

Neang Kok K.K 

Kompong Som SEZ

Kirisakor Koh Kong SEZ

Sihanoukville SEZ1

Sihanoukville SEZ2

Stung Hao SEZ

S.N.C SEZ

Oknha Mong SEZ

Kampot SEZ

Sihanoukville PortSEZ

in operation

under construction

Dry Ports in Cambodia

1‐Olair Dry Port2‐ Tex Srun Dry port3‐ ICWT  Dry Port  4‐ Tenglay  Dry  port 

Page 26: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210

26

Page 27: Key Logistics and Transport Systems and Facilities along ...Navigational Facilities Tugboat 800 HP x 2 & 800 HP 03 & 02 Pilot boat 390 HP 01 Mooring boat 175 HP 01 Patrol boat 210

Thank You