keltbray piling capability document (circa 2013)

31
Capability Document

Upload: sandycastle

Post on 02-Jan-2016

69 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Keltbray Piling Capability Document (Circa 2013)

London Underground

Capability Document

Page 2: Keltbray Piling Capability Document (Circa 2013)

Keltbray Piling comprises a team of experienced and dedicated personnel able to

identify, eliminate and manage ground risk from initial enquiry stage through to

successful completion on site.

Keltbray Piling possess modern CFA and traditional Rotary Bored piling rigs and

equipment, capable of installing piles of up to 2.4m in diameter to depths in excess

of 50m. We have a growing track record in piling related activities such as pile

removal, plunge column installation and the harnessing of geothermal energy

through piling.

One of the significant advantages of Keltbray Piling is that we are able to work

integrally with our sister companies, reducing interfaces on site to the benefit of the

project as a whole. In order to bridge these interfaces we are able to work either as

principle contractor or as traditional sub-contractors, managing all issues

associated with our works.

We pride ourselves in offering solutions that best fit the problems presented rather

than simple product selling. To support this philosophy our experienced staff are

able to specify, design, manage and install a broad range of piling and

geotechnical solutions including Rotary & CFA piles and retaining walls, sheet piles

and ground anchors.

Through our close relationship with our in-house Geotechnical and Structural

Engineers, Wentworth House Partnership, we are able to offer a full design and

construction service package. Our design team consistently develop sustainable

and innovative solutions, working in accordance with the latest codes and

standards.

We are proud to be active members of the Federation of Piling Specialists.

As befits the philosophy of the Keltbray group, Keltbray piling welcome the

opportunity for early contractor involvement in order to develop the right solution

for your project.

We look forward to working with you.

Stuart Norman

Managing Director, Keltbray Piling

Our Capability

Lancaster Gate

Page 3: Keltbray Piling Capability Document (Circa 2013)

“To provide our clients with a

quality foundation design and

construction service. Where

possible we will draw on our

broad range of skills and

services as Keltbray Group to

deliver a shorter construction

programme, safely and

economically”

Our Mission

Sample of Keltbray Group Projects within Central London

R-622 CFA mode at Project Aurora, Gatwick

R-622 CFA mode at 375 High Street Kensington

Page 4: Keltbray Piling Capability Document (Circa 2013)

How Piling fits in with the Keltbray Group

Sample of Keltbray Group Projects within Central London

Piling

Wentworth House

Partnership

Rail

Environmental

Demolition

Page 5: Keltbray Piling Capability Document (Circa 2013)

Reasons to choose Keltbray Piling – Our Key Strengths

1. Being part of the Keltbray Group

enables Keltbray Piling to overlap with

the demolition phase and the following

ground works packages offering a

shorter programme and reduced

interfaces on site.

2. Our technical expertise through support

of in-house Structural & Geotechnical

Engineering consultants WHP.

3. Engineering, co-ordination and

integration of temporary works with the

permanent works piling solution

4. Flexibility and commitment to our

customers - A quality product delivered

safely, on time and to budget.

5. Strong service offering to include: CFA,

Rotary Bored, Mini and Rail Piling,

Deep Basement Construction, Rotary

Coring and Plunge Column Installation.

St. James Square

Page 6: Keltbray Piling Capability Document (Circa 2013)

David Roy

Estimating & Proposals

Manager

Team Structure

John Price

Keltbray Group

Managing Director

Stuart Norman

Managing Director

(Piling)

Lee Cain

Senior Contracts

Manager

Stuart Marchand

Wentworth House

Director

Jan Jones

Business Development

Leader

Wentworth House

Structural &

Geotechnical Design

Engineers

John Sykes

HSEQ

Keltbray Group

Greg Haynes

Commercial Manager

Team Structure

Keltbray Piling

Keltbray Group

Wentworth House

Page 7: Keltbray Piling Capability Document (Circa 2013)

Technical Excellence

We work closely with our in-house Geotechnical and Structural Engineers.

Wentworth House Partnership (WHP). We therefore are able to offer a full

design and construction service package. Our design team are driven to

develop sustainable and innovative solutions, working in accordance with the

latest Eurocodes and design standards.

WHP have a dedicated Geotechnical Engineering team offering all aspects of

support from practical advice through to complete finite element based

design. We currently comprise of a team of 4 Geotechnical Engineers from

Director to Graduate level.

We pride ourselves in designing value Engineered, alternative solutions for

our clients and our current Geotechnical services include:

• Piling, temporary works and basement construction advice

• Specification , supervision and management of site investigation works

• Detailed Retaining Wall and Bearing Pile Design across a multitude of

techniques and disciplines

• Mini & Micro Pile Design

Our design capability is enhanced through the use of the latest software

packages including PLAXIS, Adsec, WALLAP, PIGLET, Geoslope & CADS

and is further supplemented through extensive experience and use of in-

house design programs.

Page 8: Keltbray Piling Capability Document (Circa 2013)

Piling Solutions Offered

We offer a range of techniques to support the solutions

we offer outlined as follows:

Small and Large Diameter Piling

• Continuous Flight Auger Piling (CFA)

• Traditional Large Diameter Piling (LDP)

• Plunge Column Piles

• Large diameter coring works

Retaining Wall & Deep Basement Construction

• Secant Piled Walls

• Contiguous Piled Walls

• King Post Walls

Mini & Micro Piles

• Sectional Flight Auger (SFA)

• Mini Case & Auger

• Self Drilled Micro Piles

Rail Piling (off RRV’s)

• Driven Steel tubular piling

• Case & Auger piling

CFA Augers on CM50

Page 9: Keltbray Piling Capability Document (Circa 2013)

Continuous Flight Auger (CFA) Piling

Advantages of CFA Piling:

• Speed – This system is typically quicker to install than traditional

rotary bored piles

• Cost – Owing to it’s speed, costs are also lower than traditional

rotary bored piles

• Low noise & vibration – The system is vibrationless, without large

peaks and troughs in noise emissions

Our CFA Fleet Capability

• We possess a modern fleet of CFA rigs comprising Soilmec R625,

R622, CM50 & R312

• Our rigs are fitted with the Lutz instrumentation system whereby

installation parameters are monitored and recorded for every pile

• 350mm to 1200mm diameter

• Depths of up to 28m

• We carry a range of equipment , including extra heavy duty augers

for deep basement construction

CFA Augers on CM50

Page 10: Keltbray Piling Capability Document (Circa 2013)

Large Diameter Piling (LDP)

Advantages of LDP Piling:

• Ability to core through obstructions – Various tools are available

to ensure coring through a range of obstructions

• Depth capability – With the right kelly bar extension, this system is

capable of installing up to 80m deep piles

• Visual inspection of the piling bore and ground conditions – As

the ground is excavated in short “bites” each layer and the base of the

piles are easily inspected

• Increased load bearing capacity and verticality over CFA

Our LDP Fleet Capability

• Our Fleet is dual capability and the R625, R622 & R312 are all

capable of installing traditional rotary bored, large diameter piles (LDP)

• Diameters of 450mm to 2400mm are available

• Depths of up to 50m are achievable

• We carry a range of equipment , including rock augers, casings and

cleaning buckets to allow deep pile construction within a range of

ground conditions

• We have a growing track record in piling related activities such as pile

removal, plunge column installation and the harnessing of geothermal

energy through piling.

R622 at City Road

Page 11: Keltbray Piling Capability Document (Circa 2013)

Deep Basement Construction

Our specialism as a Piling company and as a group lies within deep basement construction in confined inner city centres.

Below is a project list of our most recent achievements:

Project Scope Max Retained Height

Technique Value

Parabola (Holland Green)

650No 900mm diameter 10m Rotary Bored (Hard/Firm Secant)

£2.3M

259 City Road 173No 900mm dia 10m CFA (Hard/Firm Secant) £0.85M

151 City Road, London

150No 900mm dia 12m Rotary Bored (Hard/Firm Secant)

£1.1M

W4 – Regent Street, London

200No 600mm dia 6m CFA (Hard/Firm Secant) £1.1M

7-8 St James Square, London

100No Secant wall & 30No Contiguous wall piles, 900mm dia

12m Rotary Bored £1.25M

Page 12: Keltbray Piling Capability Document (Circa 2013)

Deep Basement Construction

151 City Road 151 City Road

259 City Road, CFA Secant

Page 13: Keltbray Piling Capability Document (Circa 2013)

Mini, Micro and Restricted Access Piling

We have the capability to design and install the following mini and

micro pile techniques in restricted access conditions:

Sectional Flight Auger (SFA) 350mm to 600mm diameter

Mini Case & Auger – 350mm to 600mm in diameter

Self Drilled Micro Piles – Various diameters up to 250mm

Through our network of contacts either by cross hire or sub-contract

we have the flexibility to design, manage and install an extensive

range of mini and micro piling techniques.

Our labour force is multiskilled across a range of disciplines and

through our network of contacts we have the flexibility to design,

manage and install an extensive range of mini and micro piling

techniques.

Casagrande C6 in Micro Piling mode at Three Quays

Page 14: Keltbray Piling Capability Document (Circa 2013)

Trackside/Rail Piling

Having recently completed the first phase of the Liverpool to

Manchester piling works for overhead line electrification, our Rail piling

division has growing expertise and experience.

Keltbray Piling in conjunction with our Keltbray Rail division can work

via our own Principal Contractors licence and fleet of 228 Road Rail

Vehicles (RRVs).

We have a growing fleet of Movax vibratory and Fambo hydraulic

hammers capable of installing 610mm diameter steel piles to depths

in excess of 15m.

We have also developed a range of solutions to overcome pile

installation issues in difficult ground conditions in association with our

clients.

Liverpool to Manchester, Fambo Driving Hammer

Page 15: Keltbray Piling Capability Document (Circa 2013)

Proven Ability to Deliver: Our Recent Project History (2011-2013)

Most Recent Projects

Bearing Piles Retaining Walls Coring &/or Plunge Cols

Value

Mini Piling or restricted access

CFA 350-1200 Mm

LDP 750 mm or less

LDP >750 mm

Contiguous - CFA 600mm dia or less

Contiguous -CFA >600mm

Secant CFA

Secant Rotary Bored

Holland Green (formerly The Parabola)

£2.3M

259 City Road, London

£0.85M

151 City Road, London £1.10M

W4 – Regent Street, London

£1.10M

7-8 St James Square, London

£1.25M

261 City Road, London £0.78M

2-14 Baker Street

£0.60M

Page 16: Keltbray Piling Capability Document (Circa 2013)

Proven Ability to Deliver: Our Recent Project History (2011-2013)

Most Recent Projects

Bearing Piles Retaining Walls Coring &/or Plunge Cols

Value

Mini Piling or restricted access

CFA 350-1200 Mm

LDP 750 mm or less

LDP>750 mm

Contiguous - CFA 600mm dia or less

Contiguous -CFA >600mm

Secant CFA

Secant Rotary Bored

3 Quays, London £1.1M

Fulham Reach £630K

Tesco, Woolwich £500K

Caius House, Battersea £500K

Pembury Circus, Hackney

£500K

Witanhurst House, London

£1.2M

Wapping Lane Phases 1 & 2

£420K

Bolsover Street £155K

Sea Containers House £600K

Aurora, Gatwick £350K

Page 17: Keltbray Piling Capability Document (Circa 2013)

Contract Profile

Holland Green (formerly The Parabola)

Challenging Projects Require Innovative Solutions

Keltbray Group were appointed by Chelsfield Developments for

the demolition, enabling works, piling and bulk excavation for a

new extensive basement on the site of the former

Commonwealth Institute in Kensington.

A 465lm hard/firm secant piled wall, designed by the Clients

Engineer, Arup was required to be installed for a new double

storey basement. The project has been made all the more

complex owing to the existing grade 1 listed structure of the

commonwealth institute and it’s requirement to be retained and

incorporated into the new structure.

Utilising low headroom piling techniques in pre-defined locations

around the existing structure, the secant wall was installed under

the extended canopy of the existing signature Parabolic roof. The

remaining locations of the wall were installed with large 90Ton

piling rigs with the tight programme calling for a peak of 5 piling

rigs working on site at any one time.

The Clients specification called for pile verticality tolerances

of 1:200 determining the need for traditional, rotary bored

techniques

Pile installation took place in a defined sequence, adjacent to

controlled demolition activities with the Keltbray Group works

package offering the Client significant programme saving as

opposed to more traditional procurement methods.

Keltbray delivered a high quality product under the

supervision of the Arup resident Engineer with the works also

completed on programme.

Keltbray Piling were also responsible for the installation of the

small diameter mini piles in order to support the Parabolic

roof in the temporary condition. These piles were designed in

accordance with Euro codes and installed in restricted

headroom conditions to stringent settlement criteria.

Location: High Street Kensington, London

Client: Chelsfield Developments

Main Contractor: MACE

Quantity Surveyor: Davis Langdon

Structural Engineer: Arup

Value: £2.3M

Programme: 13 Weeks

Scope: 653No, 900mm dia Rotary Bored hard/firm

secant piled wall with pile lengths up to 24m.

Page 18: Keltbray Piling Capability Document (Circa 2013)

Contract Profile

257-259 City Road, London

The original scope of works comprised a cantilever contiguous

pile wall and 900mm diameter bearing piles for the construction

of a new 25 storey tower with double basement.

As a direct result of the Keltbray works at 151 City Road and after

close inspection of the ground investigation report, we

recommended the use of a partially propped secant piled wall to

limit the horizontal deflection along the sensitive boundary with

the deep lying LUL Northern Line. Also, to speed the basement

excavation process and keep the internal space as free from

temporary works as possible, Keltbray designed and installed a

connecting contiguous piled buttress wall behind and

perpendicular to the secant wall.

The 900mm diameter Continuous Flight Auger (CFA) secant piled

wall was installed to a verticality of 1:75 with hard/firm piles spaced

typically at 0.7m c/c.

Piles were designed in accordance with Euro code 7 and

during the installation of the secant wall a rotary bored rig

was mobilised to site to install a 780mm diameter preliminary

test pile. The test pile was instrumented with Brillouin Optical

Time-Domain Reflectometry with support from Cambridge

University as well as traditional strain gauges.

Unusually for the laminated bed lithogy of the Lambeth

Group, the rotary bearing piles were bored dry and concreted

within 30 minutes of exposing the base. This methodology

was adopted for the test pile, which performed extremely well

allowing all subsequent contract bearing piles to be installed

at the reduced diameter of 780mm.

This reduction in diameter ensured increased bearing pile

production rates allowing the overall piling programme to be

completed on time and to budget.

Location: 257-259 City Road, London

Client: Ardmore

Main Contractor: Ardmore Construction

Quantity Surveyor: Ardmore

Structural Engineer: URS

Value: £830,000

Programme: 10 weeks

Scope: 173No 900mm CFA Secant Piles 18m

deep for a retained height of up to 9.3m.

88No 880/780mm dia, 12No 600mm dia

Rotary Bored bearing piles to depths of

31m below ground level.

Challenging Projects Require Innovative Solutions

Page 19: Keltbray Piling Capability Document (Circa 2013)

Challenging Projects Require Innovative Solutions

Contract Profile

W4, Regent Street

Keltbray Group were appointed by the Client Crown Estates for the

demolition, facade retention and piling works at the W4 site

immediately behind Regents Street in London.

Keltbray Piling were employed to design and construct rotary bored

bearing and Continuous Flight Auger (CFA) hard/firm retaining wall

piles. The original scheme showed 1800mm diameter piles around

the perimeter which Keltbray value engineered to be pairs of 600mm,

750mm & 900mm diameter.

Piles were designed in accordance with Eurocode 7

Bearing Piling works commenced with the use of an R312 rig in June

2012 with all works undertaken from existing basement level. The site

was typical of inner city London being logistically challenging with all

deliveries and spoil removal taking place via an access ramp.

Pile installation took place in a defined sequence, adjacent to

controlled demolition activities allowing Keltbray to offer the Client

significant programme saving as opposed to more traditional

procurement methods.

A CM50 piling rig was mobilised to install the 600mm diameter

CFA secant box, with piles supporting vertical and additional

horizontal loads from the adjacent grade 1 listed vaults. The

secant piles were installed to a verticality tolerance of 1:75 with

the wall alignment adjusted to suit the boundary conditions

around the site.

Within the area of the listed vaults, 450mm diameter mini piling

works were completed based on the use of a Klemm 709 piling

rig. Concrete for these piles was lifted across site by the Tower

Crane involving detailed, daily co-ordination between ourselves

and all parties on site.

The successful piling works were completed on programme.

Location: Regents Street, London

Client: Mace

Main Contractor: Mace

Quantity Surveyor: TBC

Structural Engineer: Waterman

Value: £1.1M

Programme: 19 Week Piling Programme

Scope: Design and installation of 113No 900mm,

750mm & 600mm diameter traditional rotary

bored bearing piles to depths of 35m. Installation

of guide walls and 115lm of 12m deep 600mm

diameter CFA piles for the additional storey

basement comprising a hard/firm secant wall

box.

Design and installation of 40No, 450mm

diameter case & auger mini piles, 24m deep.

Page 20: Keltbray Piling Capability Document (Circa 2013)

Contract Profile

151 City Road

Located on City Road just off Old Street roundabout in

London is the site of the new Montbatton Hotel. The

proposed hotel is a 22 storey structure with a 3 level

basement.

Directly opposite the site is Moorfields eye hospital. During

the construction phase Keltbray Piling had to ensure that the

induced vibrations were at an absolute minimum.

Wentworth House Partnership were responsible for the

geotechnical design on behalf of Keltbray Piling. The scheme

was designed in accordance with Eurocode 7 and group

analysis was carried out on the bearing piles to reduce the

overall number of piles. Engineering advice was also

provided in order to transfer structural load to the perimeter

retaining wall.

Keltbray Pilings scope was to install guide walls, secant piled

wall, construct load bearing piles and remove pile arisings

from site.

The 880mm diameter secant piled wall was installed using

the traditional rotary bored method to achieve verticality

tolerances of 1 in 150. The wall comprised of 92no male and

female piles with interlock to a level of 12 metres and male

piles extending to 22m.

The 750mm diameter bearing piles were also constructed

using the rotary bored method from the high level and

concrete cut off at formation level some 11 metres below

ground. The piles were up to 30m long and were founded in

the Lambeth formation.

The works were completed on time and to budget, for a very

satisfied client.

Location: 151 – 157 City Road, London

Client: SGP Contracts

Main Contractor: SGP Contracts

Quantity Surveyor: n/a

Structural Engineer: Curtins Consulting

Value: £1,300 000

Programme: 16 weeks

Scope: Installation of guide walls, 880mm secant wall,

750mm diameter bearing piles , Fully

instrumented preliminary test pile and removal of

pile spoil.

Picture size is 5.7

x 8.1 position is

9.68 x 6.62

Picture size is 5.7

x 8.1 position is

1.19 x 6.62

Picture size is 5.7

x 8.1 position is

18.16 x 6.62

Challenging Projects Require Innovative Solutions

Page 21: Keltbray Piling Capability Document (Circa 2013)

Location: 7-8 St James Square, London

Client: Galliford Try

Main Contractor: Galliford Try

Quantity Surveyor: Galliford Try

Structural Engineer: Price & Myers

Value: 1,178,380.02

Programme: 39 weeks

Scope: 39No 900mm Rotary Contiguous Wall Piles

11 no 900mm Temporary Contiguous Wall piles.

95 no 900/750mm Secant Wall piles 37 no

750mm CFA Temporary Secant Wall, 61 no

750mm bearing piles 19 no 750mm Temporary

works piles 8 no 750mm tower crane piles and 22

no 340mm restricted headroom mini piles.

Challenging Projects Require Innovative Solutions

Contract Profile 7-8 St. James Square

Piles were designed in accordance with Eurocode 7 and

Keltbray designed a scheme with all bearing piles being

880/750mm diameter to minimise the amount of plant and

tool on site. A number of the wall piles and bearing piles had

UC installed for either propping the wall or for temporary

works.

Works in the basement of no 7 St James consisted of

340mm restricted headroom mini piles, these where

constructed using bored or SFA techniques depending on

the ground conditions. These piles then had UC or

reinforcement cages installed in 1.5m sections to support the

internal columns or walls and allow the basement to be

deepened.

Keltbray Piling were appointed by Galliford Try Construction for

the piling works at 7-8 St James Square, London. The original

scope of works comprised a propped contiguous pile wall and

600/750/900mm diameter bearing piles for the construction of a

new office development and mini piling for the extension of the

basement to no 7 St James Sq.

The first phase of the works were carried out from street level

from a propped slab to allow demolition work to continue.

During this first phase we had a change in ground conditions as

we discovered and old tributary to the river Tyburn. This

change in ground conditions lead to change from a contiguous

wall design around the parameter to secant wall design and a

change in the temporary pile layout due to increased prop

forces. Due to the river Tyburn clay levels would vary

dramatically over the site with levels changing by a much as 5m

within 3m horizontally.

Page 22: Keltbray Piling Capability Document (Circa 2013)

Contract Profile

Three Quays

Keltbray Piling have completed works on the piling phase of the

Three Quays project. The site is located adjacent to the Tower of

London and has been developed for both retail and residential

purposes. The site is of significant archaeological interest, on the

banks of the Thames and additional geotechnical challenges

have been overcome relating to the tidal influence on the

groundwater and the sub-artesian groundwater pressures within

the Lambeth Group.

Keltbray Piling were employed initially to install 128no bearing

piles with diameters ranging from 600mm to 1500mm and to

depths of 32 metres.

The project was particularly challenging as there were several

existing piles and quay wall that had to be cored out to allow the

installation of the new piles.

The pile design was carried out in accordance with Euro code

7, an early working test pile to a load of 10MN was carried out

to ensure any risk was mitigated with results being better than

predicted.

Keltbray Piling had a 10 week programme and completed

works two weeks ahead of contract completion date.

Keltbray Piling were responsible for providing all attendances

required and removing the pile arisings from site which was all

carried out by in house divisions allowing the Main Contractor

to liaise with one single management interface.

On the strength of the relationship that was formed during the

piling phase Keltbray have now secured the substructure and

temporary works package for the project.

Challenging Projects Require Innovative Solutions

Location: Lower Thames Street, London

Client: Cheval Group

Main Contractor: Mace

Quantity Surveyor: Gardiner & Theobald

Structural Engineer: Ramboll

Value: £1.6M

Programme: 10 weeks

Scope: Installation of 128no LDA piles from 600mm-

1500mm diameter, 10MN load test, Provide on

site welfare, provide piling and attendance and

muck away and associated attendances.

Page 23: Keltbray Piling Capability Document (Circa 2013)

Challenging Projects Require Innovative Solutions

Contract Profile

2-14 Baker Street

Challenges – Site is a small site bounded on 4 sides by public

highways including Baker Street to the west. During the

demolition and enabling works, prior to our involvement, there

was a poor relationship with some residents of the adjacent

Bakers Mews properties. This resulted in additional restriction

being placed on deliveries by Westminster Council.

The piling platform was provided at 2 levels, further restricting the

available working space on site.

Bearing piles and 600mm secant piled wall were completed on

programme without significant difficulties, despite the mobilisation

to site of additional contractors to carry out construction of tower

crane base and installation of 160m deep geothermal boreholes.

Construction of 900mm secant wall piles was complicated by the

presence of existing temporary works soldiers and raking props.

It was necessary to construct the secant wall in short sections

including the provision of new temporary works kingposts to

allow removal of the original temporary works before

completing the secant wall. This requirement made

sequencing and construction of the secant wall construction

difficult with the requirement to cut female piles with a large

difference in age, (up to 20 days in some locations).

Location: 2-14 Baker Street

Client: British Land

Main Contractor: Mc Aleer & Rushe

Quantity Surveyor: n/a

Structural Engineer: Ian Black Consulting

Value: £608,871.03

Programme: Original contract period 10 weeks

Scope: Construction of bearing piles and secant wall piles

for construction of nominal 6m deep basement and

structure above. ( to be extended due to additional

works instructed and delays).

Page 24: Keltbray Piling Capability Document (Circa 2013)

Challenging Projects Require Innovative Solutions

Contract Profile

Holiday Inn, Commercial Road

The project location was originally a fuel garage, which was taken

down to commence the works for the proposed Holiday Inn.

Ashridge Construction Limited (ACL) were awarded this major

hotel construction project with Willmott Dixon, where works

comprise of enabling works and piling mat, ring beam and

support system, basement dig, drainage and storage tank

system, 1200m2 basement slab and an all concrete works

package which includes walls, columns, lift shafts, in-situ stairs

and access ramp from basement to 2nd floor. ACL commenced

work on site in December 2010 with a planned completion date of

May 2011. There were under ground large fuel tanks which

were removed so that foundation works could commence.

Keltbray’s scope of works were to install the continguous wall

piles, 254 nr, using CFA technology and the internal bearing

piles using the rotary piling method, 107 nr piles. The challenge

on this job was the restricted site size. Keltbray had 2 rigs, the

CM50 and R312, to do the two different piling techniques. A

Kobelco crane serviced the rotary rig by installing 9m long

casings by vibrating them into the ground. The upper layers of

ground above London clay were unstable that a 9m length liner

had to be used for all bearing piles.

Due to the initial delays owing to “TFL” consents ACL had to

work beside our piling to make sure that the project was well

on its course for completion within time. ACL had their crew

and 3 excavators. All works were planned and executed

carefully and safely to make sure there were no delays.

Location: 261-267, Commercial Road

Client: Holiday Inn

Main Contractor: Willmott Dixon

Quantity Surveyor: n/a

Structural Engineer: One Creative Environment Ltd

Value: £250,000.00

Programme: 7 weeks

Scope: 254 CFA piles and 107 rotary bearing piles

Page 25: Keltbray Piling Capability Document (Circa 2013)

Challenging Projects Require Innovative Solutions

Contract Profile

Selbourne House

Selbourne house included the demolition and redevelopment

of a large commercial building.

Keltbray Ltd were responsible for the demolition of the

existing building and the permanent enabling works on site.

Due to the existing basement, the site surround needed to be

retained to enable the demolition and future redevelopment

works to continue.

A sheet pile wall was used as the retaining wall but the

removal of the redundant foundations was required before its

installation. Keltbray Piling were responsible for removing

such obstructions which included a layer of solid concrete,

sometimes over a meter thick located roughly 6 meters

below GL.

Keltbray Piling identified a Coring method to be suitable to

remove the obstructions. Due to the depth of the concrete in

the ground, a large Rig (SR-60 Piling Rig) was required to

undertake the work.

As the demolition works was incomplete, the basement first

floor needed to be Back Propped to support the Coring

operations which were already restricted to a tight space on

site.

Considering the sizeable ground obstructions and the

limitation to piling operations, the job was very successful as

80 meters of Coring work was completed within a 6 week

period

Location: Victoria, London

Client: Sir Robert McAlpine

Main Contractor: Keltbray LTD

Quantity Surveyor: n/a

Structural Engineer: n/a

Value: £100K

Programme: 6 Weeks

Scope: Coring Works – Removal of redundant

foundations

Page 26: Keltbray Piling Capability Document (Circa 2013)

Challenging Projects Require Innovative Solutions

Contract Profile

Witanhurst House

Located in Highgate in a quiet residential area, the

redevelopment of Witanhurst House will be one of impressive

prestige considering the scale of this privately owned

property. Having demolished the north-eastern wing of the

existing house, the construction of a 10m deep basement

beneath the front courtyard was required in the development.

We were required to design and construct a retaining wall to

facilitate Top Down Construction of the double basement .

The only means of access to the site for all plant and

equipment was through an 2.9m wide by 3.7m high gateway

which required intricate logistics planning.

Ground conditions basically consist of a thin upper layer

(1m) of made ground overlying a sandy silt clay proven up to

25m.

Site restrictions required an initial King Post Retaining Wall to

maximise space and to ensure the protection of the existing

trees which was achieved using a Mini-Piling Rig.

The Basement Enabling Works entailed a Retention Pile

design where both a Secant Pile Wall and a Contiguous Pile

Wall were used. Concerns about ground water required both

methods to be employed.

Bearing Piles were constructed using a Rotary LDA method

where some piles required the installation of Plunge Columns

to facilitate Top Down Construction assisting in decreasing the

projects construction period. A Soilmec R-625 Piling Rig was

used to construct both the retaining wall and the Load Bearing

Piles. Plunge Columns were placed using a Specially

Fabricated Frame to achieve the required precision tolerances.

Location: Highgate

Client: WCML

Main Contractor: WCML

Quantity Surveyor: n/a

Structural Engineer: Michael Barclay Partnership

Value: £1.2m

Programme: 3 months

Scope: Design and Construction of:

•Contiguous Pile Wall

•Secant Pile Wall

•LDA Bearing Piles

•Plunged Columns

Page 27: Keltbray Piling Capability Document (Circa 2013)

Contract Profile

365 High Street Kensington

Located in the heart of the Royal Borough of Kensington and

Chelsea, one of London's most prestigious neighbourhoods,

375 Kensington High Street will offer a selection of luxurious

one, two and three bedroom apartments and penthouses. Each

home will combine the finest quality materials with the highest

levels of design and the latest innovations in technology to

create the very best in modern city living.

St Edward Homes were the client on the project, Keltbray Piling

were employed by PJ Carey who were the substructure

contractor.

Keltbray scope was to install guide walls, install 450 linear

metres of secant piling, pile attendances and clearing of pile

spoil.

The secant wall is to be one of the largest walls constructed

using CFA techniques with a retained height of 8 metres. The

wall was part cantilevered using 750mm and 900mm diameter

piles and part propped using 600mm diameter piles.

Keltbray utilized two high torque Soilmec R625 rigs to execute

the works and completed works in 9 weeks, some 3 weeks

ahead of schedule.

Location: 375 High Street Kensington

Client: St. Edward Homes

Main Contractor: PJ Carey

Quantity Surveyor: St Edward Homes

Structural Engineer: Manhire Associates

Value: £1.4M

Programme: 12 weeks

Scope: Guide walls, secant pile installation, pile

attendances and clearing of pile spoil.

Challenging Projects Require Innovative Solutions

Page 28: Keltbray Piling Capability Document (Circa 2013)

Stuart Norman

Managing Director (Piling)

Stuart is a professionally qualified Civil Engineer with 12 years

experience at industry leading contracting companies, he manages a

core group of design engineers using their skills to the maximum benefit

of our Clients. He has extensive experience in the design and

estimating of a broad range of piling and foundation systems with a

particular interest in bored displacement piling. Stuart has also worked

overseas managing diaphragm walling works at a major inner-city civil

engineering site.

Responsibilities

Key

Competencies

• Excellent communication & leadership skills,

• Management of complex piling, groundworks and rail projects,

• Adaption & compliance with processes & procedures,

• Proactive problem solving approach,

• Management of relationships including 3rd

party,

• Understanding of key project activities and successful delivery.

• The day to day management of the geotechnical design resource

(internal & external as required)

• Help prepare and authorise geotechnical designs/solutions for all

tenders and contracts in accordance with the latest CDM

regulations

• Assist and check designs prepared by the design team

• Attend meetings and communicate design requirements to internal

and external project teams

• Ensure that the content of technical design manuals and technical

procedures are rigorous and fully communicated

• Help Keltbray learn from works on site and to communicate good

and bad experiences

• Attend technical meetings such as ICE, FPS, seminars and

conferences

• Give training both internally and externally

• Prepare and present articles and papers on technical issues

• Undertake technical audits

• Identify areas for technical training of design staff

• Lead the development of new products, systems and procedures

• Perform role as Delegated Civil Engineer assisting in the training of

graduate Civil Engineers

• To develop personal capability in all aspects of temporary works

Design Co-ordinator and later Diaphragm wall station manager for Rokin Station. Responsible for supervision and organisation of

all construction activities associated with the installation of 1200mm wide diaphragm wall panels installed to depths of up to 45m

as part of the foundations for the new Metro Station. Development of steering system for Hydraulic Grabs to allow panels to be

constructed to verticality tolerances of up to 1:400.

Rokin Metro Station - Amsterdam

Location:

Client:

Main Contractor:

Consulting Engineer:

Value:

Programme:

Scope:

Metro Station Rokin, Amsterdam

Amsterdam City Council

Max Bogl

Witteveen & Bos

£40M

3 Years

Design of deep foundations for 34 Storey residential and commercial development as part of the regeneration of Elephant &

Castle. 1500mm diameter Rotary Bored bearing piles under polymer support fluid, 45m deep founding in Thanet Sand. Individual

pile load = 12MN. Pile design to BS8004 and structural design to BS8110. Analysis of sonic logging results and polymer testing

procedures.

Location:

Client:

Main Contractor:

Quantity Surveyor:

Consulting Engineer:

Value:

Programme:

Scope:

Elephant & Castle – Strata Tower

Brookfield

Brookfield

n/a

WSP

£1.2M

10 Weeks

33No Bearing Piles up to 1500mm

diameter, 45m deep constructed under

polymer support fluid

Strata Tower, Elephant & Castle

City Road, London Location:

Client:

Main Contractor:

Quantity Surveyor:

Structural Engineer:

Value:

Programme:

Scope:

151 City Road,

London Soneva Properties

SGP

N/A

Curtins Consulting Engineers

£1.5M

8 Weeks

900mm dia Secant wall @ 1500c/c with

retained height 11m. 86No Bearing piles,

900mm dia 28m deep

Design of an 11m retained height secant piled wall, single prop at capping beam level. 900mm diameter bearing piles in addition

founded in the Laminated Beds of the Lambeth Group and bored dry. Piles and retaining wall designed to Eurocode 7. Preliminary

test pile and pile group analysis required to verify the design approach.

450No Diaphragm Wall panels,

1200mm wide with depths up to 45m

including glass fibre panels for soft

eye.

Page 29: Keltbray Piling Capability Document (Circa 2013)

• Lee Cain (CSCS, IIF , PTS trained)

Contracts Manager for Keltbray Piling

Lee has over ten years experience in the construction industry gained

in piling, ground works and rail works. Lee joined Keltbray two years

ago as contracts manager and has managed projects in both the UK

and the Gulf region. He enjoys the continued daily challenges offered

by the multi-disciplinary projects Keltbray undertake.

Responsibilities

Key

Competencies

• Excellent Communication and leadership skills

• Management of complex piling, groundwork's and rail projects

• Adaption and compliance with processes and procedures

• Proactive problem solving approach

• Management of relationships including third party

• Understanding the key project activities & their role towards the

successful delivery.

• Ensuring the successful delivery of the project and that the defined

scope is delivered to cost and programme.

• Provide safe working conditions for all site operatives, visitors and

third parties

• Understand and implement the project and specific specifications

and deliverables

• Ensure that the projects, as well as Keltbray’s procedures/systems

are adhered to

• Oversee administration and record keeping for the duration of the

project

• Report to operations director

The redevelopment of a large commercial building. Employed by Sir Robert McAlpine, we were responsible for

the demolition of the existing building. A sheet pile wall was used as the retaining wall but the removal of the

redundant foundations was required before its installation. We were responsible for removing obstructions

including a layer of solid concrete, over 1m thick located roughly 6m below ground level.

Selborne House

Location:

Client:

Main Contractor:

Consulting Engineer:

Value:

Programme:

Scope:

Selborne House

Sir Robert McAlpine

Keltbray Ltd

N/A

100k

6 weeks

We were employed by PJ Carey the substructure contractor. Our scope was to install guide walls, install 450

linear meters of secant piling, pile attendances and clearing of piling spoil. The secant wall is said to be the

largest wall constructed using CFA techniques with a retained height of 8m. The wall was part cantilevered

using 750mm and 900mm diameter piles and part propped using 600mm diameter piles. Keltbray utilizes 2 high

torque Soilmec R625 rigs to execute the works and complete works in 9 weeks, some 3 weeks ahead of

schedule.

Location:

Client:

Main Contractor:

Quantity Surveyor:

Consulting Engineer:

Value:

Programme:

Scope:

375 Kensington High Street

Edward Homes

Edward Homes

N/A

N/A

£1.2M

34 weeks

Coring Works-removal of redundant

foundations.

375 Kensington

High Holborne

Location:

Client:

Main Contractor:

Quantity Surveyor:

Structural Engineer:

Value:

Programme:

Scope:

280 High Holborne

MACE

MACE

N/A

N/A

£139,788,88

4 Weeks

Design and Construction of CFA Piles

Subcontracted by Ballymore, we completed 436 piles of 450 mm and 600mm diameters. This included 3 crane

base piles as well. The piling platform was spread evenly across 3 levels of 7.00, 3.95 and 3.20 m OD. The strata

consisted of made ground over old dock remains & London clay. We installed and tested a non-working pile with

brilliant results. Moreover, 4 working pile tests were conducted on piles nominated by Ballymore and Tower

Hamlets Building Control. These tests were also very good to show that the pile design was apt for the strata.

Coring Works-removal of redundant

foundations.

Challenging Projects require Innovative Solutions

Page 30: Keltbray Piling Capability Document (Circa 2013)

David Roy (MSc, FGS)

Proposals Manager for Keltbray Piling

David is a Geotechnical Engineer with 9 years experience within the

construction and ground engineering industry. Initially working as part

of a busy regional estimating team, David has built up a wide

experience of a range of ground improvement and piling techniques.

His technical knowledge, particularly in the design of deep foundations

and retaining structures, was further developed after working for several

years as a Design Engineer, leading the design development and

detailing of several major projects in London.

Responsibilities

Key

Competencies • Extensive knowledge of ground improvement and piling techniques

• Ability to organise and communicate within a project team

• Producing high quality bid and supporting technical documentation

• Assessment of tender enquiries and production of competitive

bids for bearing pile and retaining wall schemes

• Assist design engineers in producing efficient, value engineered

foundation designs

• Advise clients on value engineering options for foundation

schemes

• Regularly attend meetings with Clients and Engineers to discuss

and develop schemes

• Carry out tender pile and retaining wall designs to latest standards

• Attend industry events and keep up to date with new products and

techniques

• Maintain current customer base and ensure high quality of service

to key clients.

• Develop industry presence and market visibility

• Develop internal estimating systems to increase efficiency

Responsible for the design of deep foundations and retaining walls to Eurocode 7. Attended design team

meetings for 4months prior to construction to explore numerous value engineering schemes with the team.

Bearing piles up to 2.4m diameter, 65m deep, constructed under bentonite support fluid were required to

support structural loads of up to 40MN. Plunge columns of 750mm sq were installed to allow a top down

methodology to be adopted. Secant wall up to 1200mm diameter was designed to retain 15m deep basement

excavation in a single span.

100 Bishopsgate, City of London Location:

Client:

Main Contractor:

Consulting Engineer:

Value:

Programme:

Scope:

Bishopsgate, City of London

Brookfield / Great Portland Estates

Brookfield Multiplex

Robert Bird Group

£10M

34 weeks

Bid Manager for piling and ground improvement package for this landmark bridge on the London Olympic site.

The scope of work changed dramatically during construction, requiring detailed redesign and on-going design

development. Design had to integrate both Olympic and legacy mode uses for the bridge. Project won Best

International Project at the Irish Architecture Awards 2012 and shortlisted for the British Construction Industry

Awards 2012 and Prime Ministers Better Public Building Awards 2012.

Central Park Bridge – London Olympic Site

5-7 St Helen’s Place, City of London Location:

Client:

Main Contractor:

Structural Engineer:

Value:

Programme:

Scope:

St Helen’s Place, City of London

The Leathersellers’ Company

O’Keefe Construction

Robert Bird Group

£1.3M

16 weeks

900mm diameter secant wall retaining up

to 12m height. Temporary and permanent

bearing piles 600-900mm in diameter.

Lead designer for this project, involving installation of secant piled wall and bearing piles within and adjacent to

existing retained facades and a 13th century church. The façade retention system imposed a complex set of

design loads onto the secant wall in addition to temporary bearing piles. Stringent deflection criteria for the

retaining wall was required due to the proximity of St Helen’s Church along one side of the site.

338linm secant wall and152 bearing

piles including 60 plunge columns

constructed up to 65m depth

Location:

Client:

Main Contractor:

Consulting Engineer:

Value:

Programme:

Scope:

Queen Elizabeth Park

Olympic Delivery Authority

Lagan Construction

AKTII / Mott MacDonald

£1.2M

20 weeks

CFA bearing piles at bridge abutments, vibro

concrete columns supporting approach

embankments & reinforced earth retaining

walls.

Challenging Projects require Innovative Solutions

Page 31: Keltbray Piling Capability Document (Circa 2013)

Keltbray Ltd St Andrew’s House Portsmouth Road Esher KT10 9TA | T 020 7643 1000 | F 020 7643 1001 | E

Stuart Norman, MD, M 07793 650 514 E [email protected]

David Roy, Proposals Manager, M 07827 351 495 E [email protected]

Charlotte Howe, Administrator, D 0207 643 1094 E [email protected]

www.keltbray.com