Page 1: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

Community Update

June 30, 2011

Presented at: York Civic Centre

Presented by: Honourable Kathleen Wynne, Minister of TransportationMPP Laura Albanese

Councillor Frances Nunziata, Councillor Frank Di Giorgio

Page 2: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

7/5/2011 Community Update 2

Eglinton-Scarborough Crosstown Community Meeting Agenda

– Introduction

– Eglinton-Scarborough Crosstown Project Status Presentation

– Questions and Answers

– Wrap Up

Page 3: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

7/5/2011 Community Update 3

New Transit Plan For Toronto

• New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March 31, 2011

• Plan will improve mobility in Toronto• Enhance economic, social and environmental well

being• Accommodate new growth

Page 4: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

7/5/2011 Community Update 4

Page 5: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

7/5/2011 Community Update 5

Page 6: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

7/5/2011 Community Update 6

Eglinton-Scarborough Crosstown

• Funded by the Province through Metrolinx • Faster travel times (35 min from Kennedy to Jane)• Through service from Scarborough Centre to Jane (45 min)• Increase SRT capacity with new and larger light rail vehicles• Connections east to west across the city• Support to future growth across the city• Thousands of jobs during construction • Easy quick connections to the TTC subway system and GO Transit

network• Implements PRESTO transit fare card

Page 7: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

Eglinton Bus Service Today

Eglinton 32 and 34 bus routes:66,000 combined daily weekday riders

Eglinton 32 West buses account for 41,500

Top local intersecting routes per weekday35 Jane – 41,00041 Keele – 23,00089 Weston – 13,000

7/5/2011 Community Update 7

For Comparison:Scarborough RT route – 45,000 daily weekday riders

Page 8: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

Project UpdateJune 30, 2011

Presented at: York Civic Centre

Jack Collins, Vice-President Rapid Transit Implementation, MetrolinxAnna Pace, Director Strategic Partnerships – Transit Expansion Department - TTC

Community Update 8

Page 9: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

7/5/2011 Community Update 9

Outline

• Metrolinx Mandate and Responsibilities– Jack Collins, Metrolinx

• Overview of Project and Approvals– Jack Collins, Metrolinx

• Design and Construction Update– Anna Pace, TTC

Page 10: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

7/5/2011 Community Update 10

Metrolinx

• Created in 2006, Metrolinx provides residents and businesses in the GTHA with a transportation system that is modern, efficient and integrated.

• As a provincial agency, Metrolinx was created to play a critical role in planning for a seamless, integrated transit network across the region. In 2009, GO Transit became a division of Metrolinx. The Air Rail Link is also a division of Metrolinx, and PRESTO will become a division of Metrolinx shortly.

Page 11: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

7/5/2011 Community Update 11

Metrolinx

Our Mandate is to do three things:• Deliver the best possible transportation services today

while leading the way to an even better, more convenient service tomorrow.

• Make the best possible use of public transportation investment dollars.

• Measurably improve the quality of life in our region.

Page 12: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

7/5/2011 Community Update 12

Key Responsibilities for Project

Key Responsibilities:

― Metrolinx is responsible for securing funding and environmental approvals, designing, coordinating, planning, constructing and implementing the Eglinton-Scarborough Crosstown LRT project. Metrolinx will own and control this project.

― Metrolinx is contracting with the TTC to act as its agent in the delivery of the project

Page 13: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

7/5/2011 Community Update 13

Eglinton-Scarborough Crosstown PlanKey facts:

• 25 km east-west transit corridor between Scarborough Centre and Jane Street / Black Creek

• 19 km of tunnelled transit along Eglinton connected with continuous through-running service along upgraded SRT alignment (6 km, elevated and at-grade, 0.5 km tunnelled) to Scarborough Centre

• Up to 26 stations

• Metrolinx cost estimate for the combined project is $8.2B (2010$)

Page 14: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

7/5/2011 Community Update 14

Page 15: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

Status: Environmental Assessment /TPAP Updates• Eglinton Crosstown LRT EA/TPAP

Amendment

– Conduct preliminary engineering review for Eglinton east and west tunnel segments

– Review station requirements and locations

– Review and assess Jane / Black Creek alignment, access to yard

• Scarborough RT EA/TPAP Amendment

– Kennedy Station configuration

– McCowan layover yard configuration

• Eglinton Yard EA/TPAP Amendment

• For all EA/TPAP Amendments

– Service plan concepts and modeling

– Public Consultations

– MOE Approval

7/5/2011 Community Update 15

Page 16: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

7/5/2011 Community Update 16

Review of McCowan Yard

Status: Environmental Assessment /Transit Project Assessment Process

Keele to Jane

Laird to Kennedy

Review of Kennedy Station

Station Locations

Sheppard Subway

Eglinton Yard at Black Creek and Eglinton

Page 17: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

7/5/2011 Community Update 17

Crosstown: Keele to Jane Future Study & Consultation

Page 18: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

7/5/2011 Community Update 18

Crosstown: Maintenance and Storage Facility Future Study & Consultation

Page 19: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

7/5/2011 Community Update 19

Maintenance and Storage Facility Context

Eglinton Avenue looking east towards Black Creek Drive

Page 20: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

Eglinton-Scarborough Crosstown is Moving Forward

Design & Construction Progress

Anna Pace, Director, Strategic Partnerships, TTC

7/5/2011 Community Update 20

Page 21: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

7/5/2011 Community Update 21

Local Issues: Bus Services

– Several buses serve Eglinton west of Yonge Street

– TTC will review bus service for future connections to the Crosstown

– Stations will have mainly on-street bus stops

– Will identify bus terminals at busy stations

Page 22: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

Working with the Community

Key to the success – TTC Community relations team working with communities businesses and stakeholders

Identify issues early and mitigate construction impacts

Community liaison staff will be on the ground, meeting face-to-face with community members

Engage with community early and often, flag and address issues related to construction

7/5/2011 Community Update 22

Page 23: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

7/5/2011 Community Update 23

Working with the Community• Community Offices: visible on-street presence and access to updates and

project information

• Working with project team and contractors to resolve issues

• Provide consistent, timely and accurate communication – print, website, signage, etc.

• Consultation and Outreach for each design and construction activity

• New dedicated website coming (interim site www.crosstown.ttc.ca)

• Prepare community for tunnelling and construction of stations

• Working with you to manage disruption

Page 24: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

Working with the Community

• Work in partnership with local businesses to mitigate impacts of construction (e.g. “shop local” programs)

• Work with local community on safe pedestrian and commuter routes, where appropriate (e.g. “safe routes to school”)

7/5/2011 Community Update 24

Page 25: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

Local Community Involvement

• Events • June 14 - Mt Dennis

Neighbours’ Night Out• July 13 – Green Hills

Neighbours’ Night Out• Paulson Rd @ King

George’s Drive

7/5/2011 Community Update 25

Page 26: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

Construction Management Approach• Ensure scope defined before

construction• Pre-qualify contractors• Define utility work before

construction• Ensure consistent and

coordinated approach among contractors

• Include obligations for contractor

• Support of community relations

7/5/2011 Community Update 26

Page 27: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

7/5/2011 Community Update 27

Light Rail Vehicles

Page 28: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

7/5/2011 Community Update 28

Light Rail Vehicles

New LRVs will be:• Low floor & accessible• Air conditioned• Audio and visual passenger informationDesign & Manufacture:• Bombardier Awarded Contract by Metrolinx in June 2010 for

$770 million• TTC Vehicle Engineering staff are managing the contract• Design to be complete by December 2011• Manufactured in Thunder Bay

Page 29: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

Potential Interior Layout

7/5/2011 Community Update 29

Page 30: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

Tunnel Boring Machines• On July 28, 2010, Metrolinx

ordered four tunnel boring machines at $54 million

• Machines will commence midtown tunnel in mid-2012

• Manufactured by Lovat Inc., a Toronto company employs 380 people in Etobicoke

• Valiant Machine and Tool will manufacture electrical and mechanical trailing gear assemblies in Windsor

• A single machine’s average mining rate for lined tunnel is 75 metres a week

7/5/2011 Community Update 30

Page 31: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

Tunnel Liners• Metrolinx awarded

contract in February 2011 to Munro Concrete Products Limited (Essa Township)

• Munro is adding in excess of 100 jobs and expanding their plant

7/5/2011 Community Update 31

Page 32: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

Station Design• Minimize property and construction impacts

• Minimize disruption to extensive utilities around stations

• Accommodate local traffic during construction

7/5/2011 Community Update 32

Page 33: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

Station Design

Approach for Station Design:• Enhance accessibility• Minimize impact on adjacent

areas• Understand development

potential• Preserve opportunities for

integration

Key Design Elements:• Main entrance & secondary

entrance• Elevators and escalators• Fare payment-PRESTO

7/5/2011 Community Update 33

Page 34: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

7/5/2011 Community Update 34

Station Design

• Metrolinx Board recently approved station design, preliminary engineering

• Design concepts being developed for 7 stations:

– Eglinton West, Keele, Caledonia, Dufferin, Bathurst, Oakwood & Chaplin

• Public consultation and information during design process

Page 35: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

7/5/2011 Community Update 35

Pre-construction InvestigationsUtility location Geotechnical survey 

Soil sampling and testing Analyses and Follow‐up

Page 36: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

7/5/2011 Community Update 36

Construction starts this Summer in West • Final design underway for midtown tunnel section

(Black Creek to Laird)• Black Creek Tunnel Launching shaft tenders - June 6 • Black Creek Tunnel Launch shaft construction

starts this summer• Tunnel construction to start mid 2012• Development of construction schedule and Project

Implementation Plan• SRT Replacement and Upgrade - tentative start

late 2015

Page 37: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

First Construction Contract• Tunnel launch site at Black

Creek scheduled to begin work in Summer 2011

• Tunnelling will start summer 2012 and head east

• Public information with community before construction starts

7/5/2011 Community Update 37

Page 38: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

Crosstown Launch Shaft Rendering

Launch Shaft• 60m Long• 20m wide• 16m deep

7/5/2011 Community Update 38

Page 39: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

Future Keelesdale Park Bridge • Portion of Park required to

store construction equipment & launch tunnel boring machines

• Existing entrance from Eglinton Avenue will be used by construction vehicles

• Bridge will maintain convenient access to Chris Tonks Arena during tunneling construction in 2012

7/5/2011 Community Update 39

Entrance To Keelesdale Park

Future York Community Centre

Chris Tonks Arena

West Launch Area

Page 40: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

Future Keelesdale Park Bridge

Long Term Benefits• Bridge will link Community

Centre to Chris Tonks Arena

• Provides access to both facilities from Eglinton Avenue or Black Creek Drive

7/5/2011 Community Update 40

Page 41: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

Get in Touch

E-mail:[email protected]

Tel: 416-338-6310

Fax: 416-397-8193

TTY: (416) 481-2523

Interim Website: www.crosstown.ttc.ca

Community Office:1848 Eglinton Avenue West (at Dufferin)

Summer Hours:Mon, Wed, Friday 9:00am – 5:00pm Tues8:00am – 4:00pmThurs12:00pm – 8:00pm

7/5/2011 Community Update 41

Page 42: June 30, 2011 - TTC Civic... · 7/5/2011. Community Update. 3. New Transit Plan For Toronto • New Transit Plan announced by Mayor Ford, Premier McGuinty and Minister Wynne on March

7/5/2011 Community Update 42

Thank you