Overview of TFTR D&D
• Schedule: October 1999 through September 2002
• Original Estimated Project Cost: $40.3M
• Projected Project Cost at Completion: $36.8M
• Objectives:– Remove activated and/or contaminated components from
the TFTR Test Cell, Test Cell Basement and Tritium Area. (Tritium Area later changed to mothball)
– Provide data for the decommissioning of future fusion projects.
June 25-26, 2002 D&D Lessons Learned Workshop 3
TFTR D&D Summary Schedule
June 25-26, 2002 D&D Lessons Learned Workshop 4
TFTR Before D&D
June 25-26, 2002 D&D Lessons Learned Workshop 5
Overview of TFTR D&D cont
• Not a typical decontamination and decommissioning (D&D) project
• Will not be returned to “green field” conditions
• Facility will not be released for unrestricted use
• Not a capital project - funded with operating money
June 25-26, 2002 D&D Lessons Learned Workshop 6
TFTR D&D Organization
TFTR D&D Project Organization
PPPL Director
Engineering
Department
Head
TFTR D&D
Project
Manager
Planning and
Control
Engineering Construction HP /
Radwaste
June 25-26, 2002 D&D Lessons Learned Workshop 7
Management of TFTR D&D Project
• Used existing PPPL Project Control Systems (PCS)
• Cost - Performance Measurement System employed utilizing earned value techniques
• Schedule - PC based “Primavera” System
• Management Meetings / Project Reports
June 25-26, 2002 D&D Lessons Learned Workshop 8
Work Breakdown Structure
• 1.0 Engineering• 1.1 Oversight & Planning
• 1.2 Area Preparations
• 1.3 Non-Tokamak Removals
• 1.4 Tokamak Removal Engineering
• 2.0 Field Operations• 2.1 Oversight & Support (Field Ops)
• 2.2 Area Preparations (Field Ops)
• 2.3 Non-Tokamak Removals (Field Ops)
• 2.4 Tokamak Removals (Field Ops)
June 25-26, 2002 D&D Lessons Learned Workshop 9
Work Breakdown Structure cont
• 3.0 Project Management• 3.1 Project Office
• 3.2 Work Control Center
• 3.3 Configuration and Document Control
• 4.0 Health Physics and Safety• 4.1 HP Oversight
• 4.2 Safety Oversight
June 25-26, 2002 D&D Lessons Learned Workshop 10
Work Breakdown Structure cont
• 5.0 Radwaste Operations• 5.1 Radwaste Management
• 5.2 Containers and Supplies
• 5.3 Transportation and Disposal
• 5.4 Mixed Waste
June 25-26, 2002 D&D Lessons Learned Workshop 11
Conduct of Operations
• Worker safety highest priority
• Protecting environment from tritium release
• Different set of hazards than TFTR operations
• Centralized control of work activities
• Procedure compliance mandatory
• Clear responsibility and accountability
June 25-26, 2002 D&D Lessons Learned Workshop 12
Work Package Process• Engineering
» Define work scope
» Conduct Peer Reviews and Design Reviews
» Prepare installation/removal procedure
» Define prerequisites for field work
» Update or void drawings after removal is complete
June 25-26, 2002 D&D Lessons Learned Workshop 13
Work Package Process cont
• Work Control Center» Review Engineering Package for completeness
» Ensure prerequisites are completed prior to issuing package for work
» Arrange for all permits
» Release work package to field per schedule
» Arrange for resolution of field problems
» Return completed work package to Engineering for drawing update/voiding
June 25-26, 2002 D&D Lessons Learned Workshop 14
Work Package Process cont
• Construction» Verify and/or perform safing / lockout/tagout per
PPPL procedures as required
» Perform field work per procedure
» Return completed work package to Work Control Center
June 25-26, 2002 D&D Lessons Learned Workshop 15
Summary
• The TFTR D&D Project has been performed safely, on time and within budget