Julia Tuttle Seagrass Mitigation Site - Restoration of a Historic Dredge Hole in Biscayne Bay, Florida Michael R. Barnett, PE, D.CE & Terri Jordan-Sellers April 19, 2016

Upload: lyphuc

Post on 16-Apr-2018

217 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Julia Tuttle Seagrass Mitigation Site - Restoration of a ...conference.ifas.ufl.edu/NCER2016/presentations/15_1550_Barnett.pdf · Julia Tuttle Seagrass Mitigation Site - Restoration

Julia Tuttle Seagrass Mitigation Site - Restoration of a Historic Dredge Hole in Biscayne Bay, Florida

Michael R. Barnett, PE, D.CE & Terri Jordan-SellersApril 19, 2016

Page 2: Julia Tuttle Seagrass Mitigation Site - Restoration of a ...conference.ifas.ufl.edu/NCER2016/presentations/15_1550_Barnett.pdf · Julia Tuttle Seagrass Mitigation Site - Restoration

Project Requirements

• 31 acres available; required to build 16.6 acres • Select fill cap (5 to 10% fines) to -4ft MLLW +/- 0.5ft• Contract specifications dictated ‘Design/Build’

Page 3: Julia Tuttle Seagrass Mitigation Site - Restoration of a ...conference.ifas.ufl.edu/NCER2016/presentations/15_1550_Barnett.pdf · Julia Tuttle Seagrass Mitigation Site - Restoration

Project Challenges and Solutions• Timing/sequencing placement of sediment from both dredge

areas and upland sand sources in less than 2 years

• Maintain water quality standards in an Aquatic Preserve

• Level placement over irregular bottom

• Complete ALL work (including seagrass plantings) by Contract end date

Page 4: Julia Tuttle Seagrass Mitigation Site - Restoration of a ...conference.ifas.ufl.edu/NCER2016/presentations/15_1550_Barnett.pdf · Julia Tuttle Seagrass Mitigation Site - Restoration

Incompatible Dredge Material – 8/18/14

Excerpt from Daily Miami Metropolis – September 3, 1919: “Fourteen old Spanish cannons, recovered by Captain {James} Webster in 30 feet of water a few miles north of Careysfort Light, will be used as mooring anchors for tugs, barges and buoys while working on Government Cut.”

Page 5: Julia Tuttle Seagrass Mitigation Site - Restoration of a ...conference.ifas.ufl.edu/NCER2016/presentations/15_1550_Barnett.pdf · Julia Tuttle Seagrass Mitigation Site - Restoration

Project Photos

Page 6: Julia Tuttle Seagrass Mitigation Site - Restoration of a ...conference.ifas.ufl.edu/NCER2016/presentations/15_1550_Barnett.pdf · Julia Tuttle Seagrass Mitigation Site - Restoration

Takeaways

• 560,000 CY of dredged material ‘Base Fill’ 1,192 scow loads Commence January 8, 2014; complete October 19, 2014

• 85,000 CY of ‘Select Fill’ 2 ft “cap” of upland mined sand over Base Fill 285 barge loads

– 5,500 dump trucks from local quarry

Commence January 8, 2015; complete July 7, 2015

• 17.1 Acres restored to -4 ft MLLW