jukka lassila - lut
TRANSCRIPT
Jukka Lassila
STRATEGIC DEVELOPMENT OF ELECTRICITY
DISTRIBUTION NETWORKS – CONCEPT AND METHODS
Thesis for the degree of Doctor of Science
(Technology) to be presented with due
permission for public examination and
criticism in the Auditorium 1382 at
Lappeenranta University of Technology,
Lappeenranta, Finland, on the 19th
of
December, 2009, at noon.
Acta Universitatis Lappeenrantaensis 371
Supervisor Professor Jarmo Partanen
Institute of Energy Technology
Lappeenranta University of Technology
Lappeenranta, Finland
Reviewers Professor Kimmo Kauhaniemi
Department of Electrical Engineering and Automation
University of Vaasa
Vaasa, Finland
Adjunct Professor Veli-Pekka Nurmi
Department of Electrical Energy Engineering
Tampere University of Technology
Tampere, Finland
Opponents Professor Kimmo Kauhaniemi
Department of Electrical Engineering and Automation
University of Vaasa
Vaasa, Finland
Adjunct Professor Veli-Pekka Nurmi
Department of Electrical Energy Engineering
Tampere University of Technology
Tampere, Finland
ISBN 978-952-214-872-8 ISBN 978-952-214-873-5 (PDF)
ISSN 1456-4491
Lappeenrannan teknillinen yliopisto Digipaino 2009
ABSTRACT
Jukka Lassila
Strategic Development of Electricity Distribution Networks – Concept and
Methods
Lappeenranta 2009 156 p. Acta Universitatis Lappeenrantaensis 371 Dissertation. Lappeenranta University of Technology ISBN 978-952-214-872-8, ISBN 978-952-214-873-5 (PDF), ISSN 1456-4491 Strategic development of distribution networks plays a key role in the asset management in electricity distribution companies. Owing to the capital-intensive nature of the field and long-span operations of companies, the significance of a strategy is emphasised. A well-devised strategy combines awareness of challenges posed by the operating environment and the future targets of the distribution company. Economic regulation, ageing infrastructure, scarcity of resources and tightening supply requirements with challenges created by the climate change put a pressure on the strategy work. On the other hand, technology development related to network automation and underground cabling assists in answering these challenges. This dissertation aims at developing process knowledge and establishing a methodological framework by which key issues related to network development can be addressed. Moreover, the work develops tools by which the effects of changes in the operating environment on the distribution business can be analysed in the strategy work. To this end, the work discusses certain characteristics of the distribution business and describes the strategy process at a principle level. Further, the work defines the subtasks in the strategy process and presents the key elements in the strategy work and long-term network planning. The work delineates the factors having either a direct or indirect effect on strategic planning and development needs in the networks; in particular, outage costs constitute an important part of the economic regulation of the distribution business, reliability being thus a key driver in network planning. The dissertation describes the methodology and tools applied to cost and reliability analyses in the strategy work. The work focuses on determination of the techno-economic feasibility of different network development technologies; these feasibility surveys are linked to the economic regulation model of the distribution business, in particular from the viewpoint of reliability of electricity supply and allowed return. The work introduces the asset management system developed for research purposes and to support the strategy work, the calculation elements of the system and initial data used in the network analysis. The key elements of this asset management system are utilised in the dissertation. Finally, the study addresses the stages of strategic decision-making and compilation of investment strategies. Further, the work illustrates implementation of strategic planning in an actual distribution company environment.
Keywords: Strategy process, electricity distribution business, long-term planning,
investment strategies, medium-voltage networks, supply reliability, regulation
UDC 621.316 : 621.3.027.5 : 620.9 : 657.424 : 65.012.23
List of publications
I. Lassila J., Viljainen S. and Partanen J. 2002. “Analysis of the benchmarking
results of the electricity distribution companies in Finland.” In Proceedings of
the IEEE Postgraduate Conference on Electric Power Systems. Budapest,
Hungary.*
II. Lassila J., Viljainen S., Honkapuro S. and Partanen J. 2003. “Data Envelopment
Analysis in the benchmarking of electricity distribution companies.” In
Proceedings of the CIRED 2003, International Conference on Electricity
Distribution. Barcelona, Spain.*
III. Lassila J., Honkapuro S., Viljainen S., Tahvanainen K., Partanen J., Kivikko K.,
Antila S., Mäkinen A. and Järventausta P. 2005. “Power Quality Factors in
Efficiency Benchmarking.” In Proceedings of the CIRED 2005, International
Conference on Electricity Distribution. Turin, Italy.*
IV. Lassila J., Honkapuro S. and Partanen J. 2005. “Economic Analysis of Outage
Costs Parameters and Their Implications on Investment Decisions.” In
Proceedings of the IEEE PES 2005 General Meeting. San Francisco, CA USA.
V. Lassila J., Honkapuro S. and Partanen J. 2006. “Distribution Network
Investment Strategies in the New Business Environment.” In Proceedings of the
IEEE PES 2006 General Meeting. Montréal, Canada.
VI. Lassila J., Kaipia T., Partanen J., Järventausta P., Verho P., Mäkinen A.,
Kivikko K. and Lohjala J. 2007. “A Comparison of the Electricity Distribution
Investment Strategies.” In Proceedings of the CIRED 2007, International
Conference on Electricity Distribution. Vienna, Austria.
VII. Lassila J., Kaipia T., Partanen J. and Lohjala J. 2007. “New Investment
Strategies in the Modern Electricity Distribution Business - Reliability in the
Long-Term Planning.” In Proceedings of the IEEE PES 2007 General Meeting.
Tampa, FL USA.
VIII. Lassila J., Tanskanen A., Lohjala J. and Partanen J. 2009. “Unbundling of
Operation and Network Development Activities in Electricity Distribution.”
International Journal of Energy Sector Management. Volume 3, No. 4, 2009,
pp. 383–405.
*) Published also in Research Methodology on Data Envelopment Analysis (DEA). Mantri, J. B. (Ed.). Boca Raton, FL USA: Universal-Publishers.
Acknowledgments
The results of this doctoral thesis are mainly based on the research projects carried out during
the years 2001–2009 at the Laboratory of the Electricity Markets and Power Systems, Institute
of Energy Technology (LUT Energia) at Lappeenranta University of Technology. Several
people have contributed to the work, and it is a pleasure to thank all those who have made this
thesis possible.
First, I owe my deepest gratitude to my supervisor Professor Jarmo Partanen for his guidance,
encouragement, valuable contribution during this work and long-time support on my research
path.
I would also like to thank my colleagues Mr. Tero Kaipia, Professor Samuli Honkapuro, Mr.
Juha Haakana, Mr. Pasi Salonen, Professor Satu Viljainen and Ms. Kaisa Tahvanainen for their
help and valuable ideas during various stages of my study. I wish also to thank Dr. Juha Lohjala
from Suur-Savon Sähkö Oy for working as an important link between researchers and
electricity distribution industry.
I thank the pre-examiners Professor Kimmo Kauhaniemi from the Department of Electrical
Engineering and Automation, University of Vaasa and Adjunct Professor Veli-Pekka Nurmi
from the Department of Electrical Energy Engineering, Tampere University of Technology for
their feedback and comments, as well as their genuine interest in the topic and their willingness
to engage in the pre-examination process.
Special thanks are reserved for Dr. Hanna Niemelä for her valuable assistance in the preparation
of this manuscript.
This thesis was financially supported by Ulla Tuominen Foundation, the Finnish Foundation for
Technology Promotion and the Lappeenranta University of Technology Foundation.
Finally, my sincerest appreciation goes to my parents Eero and Pirkko, my sisters Henna,
Annika, Anna-Maija and my brother Hannu for their time, energy and loyalty.
Lappeenranta, December 2009
Jukka Lassila
Contents
Abstract
List of publications
Acknowledgments
Nomenclature
1. Introduction ................................................................................................................... 13 1.1. Main objective of the work.................................................................................. 14 1.2. Outline of the work .............................................................................................. 15 1.3. Scientific contribution.......................................................................................... 16 1.4. Summary of publications ..................................................................................... 17
2. Introduction to strategic planning............................................................................... 21 2.1. Network strategy process..................................................................................... 23
3. Changes in the operating environment ....................................................................... 31 3.1. Ageing infrastructure ........................................................................................... 34 3.2. Regulation and ownership ................................................................................... 36 3.3. Quality of supply ................................................................................................. 41 3.4. Climate change..................................................................................................... 49 3.5. Environmental issues ........................................................................................... 51 3.6. Risk of blackouts ................................................................................................. 53 3.7. Scarcity of resources ............................................................................................ 58 3.8. Increase in material and labour costs................................................................... 59 3.9. Energy policy ....................................................................................................... 60 3.10. Distributed generation and smart grids................................................................ 62
3.10.1. Smart grids and electric cars ................................................................ 63 3.11. Technology development..................................................................................... 65
3.11.1. Network data systems and management of information...................... 65 3.11.2. Development of materials, working methods and automation ............ 66
3.12. Summary and conclusions ................................................................................... 67
4. Methodology and tools of strategic analysis ............................................................... 69 4.1. Drivers of the strategy process............................................................................. 72 4.2. Network technologies and potential surveys ....................................................... 73
4.2.1. 1000 V low-voltage technology........................................................... 73 4.2.2. Circuit recloser ..................................................................................... 75 4.2.3. Underground cabling, transfer of lines to roadsides, covered
conductors ............................................................................................ 81 4.2.4. Compensation of earth fault currents ................................................... 84 4.2.5. LVDC................................................................................................... 86 4.2.6. Remote-controlled disconnector .......................................................... 88 4.2.7. Interdependence between network technologies and
reliability .............................................................................................. 89 4.3. Calculation methodology for the analysis of long-term cost and
reliability effects .................................................................................................. 93 4.4. Description of the calculation system.................................................................. 95
4.4.1. Objectives and purpose of the system.................................................. 95 4.4.2. Initial data............................................................................................. 96 4.4.3. Calculation operations of the asset management system..................... 99 4.4.4. Determination of the network value .................................................. 100 4.4.5. Reliability calculation ........................................................................ 105 4.4.6. Determination of long-term costs in distribution system
operation............................................................................................. 110 4.5. Background information required in the process............................................... 113
4.5.1. Power flow calculation....................................................................... 113 4.5.2. Fault current calculation..................................................................... 116 4.5.3. Network age and condition data......................................................... 118 4.5.4. Reliability calculation ........................................................................ 120
5. Strategic decision-making .......................................................................................... 125 5.1. Strategy analyses................................................................................................ 126 5.2. Strategic decisions ............................................................................................. 130 5.3. Implementation of strategic decisions ............................................................... 131 5.4. Impacts of implementation ................................................................................ 135 5.5. Conclusions on strategic decisions .................................................................... 140
6. Conclusions .................................................................................................................. 143
References................................................................................................................................ 147
Appended publications I-VIII
Nomenclature
Roman letters
a, b outage cost factors (€/kW and €/kWh)
C cost
c unit cost
E energy
f fault frequency
i, I network component(s)
j electricity consumer
l length
n number
P power
p interest rate
t (life-, clearance, repair, reference) time
U voltage, outage time (unavailability)
x length of the network after the circuit recloser
Acronyms
AMKA Aerial bundled cable (low-voltage)
AR Autoreclosing
EMA Energy Market Authority
EU European Union
CAPEX Capital Expenditure
CEER Council of European Energy Regulators
CC Covered conductor
CCA Chrome copper arsenic
CHP Combined heat and power
CIS Customer Information System
CPI Consumer price index
DEA Data Envelopment Analysis
DAR Delayed autoreclosing
DG Distributed generation
DMS Distribution Management System
GDP Gross Domestic Product
GIS Gas insulated switchgear
HSAR High-speed autoreclosing
IEEE Institute of Electrical and Electronics Engineers
INV Investment
KAH Keskeytyksestä aiheutunut haitta, Customer outage cost
LTP Long-term planning
LV Low-voltage
LVDC Low-voltage DC
MAIFI Momentary Average Interruption Frequency Index
MV Medium-voltage
NIS Network Information System
NVE Norges vassdrags- og energidirektorat, Norwegian Water Resources and Energy Directorate
OH Overhead line
OPEX Operational Expenditure
PES Power and Energy Society (IEEE)
PQ Power quality
PV Present value (of the network)
RV Replacement value (of the network)
SAIDI System Average Interruption Duration Index
SAIFI System Average Interruption Frequency Index
SCADA Supervisory Control And Data Acquisition
SF6 Sulphur hexafluoride
SFA Stochastic Frontier Analysis
STYV Sähköntuottajien yhteistyövaltuuskunta, a cooperative commission of electricity producers
TKK Helsinki University of Technology
TJSA Toimittamatta jääneen sähkön arvo, cost of non-supplied electricity
TUT Tampere University of Technology
VTT Technical Research Centre of Finland
WACC Weighted Average Cost of Capital
13
1. Introduction
Strategic development of distribution networks plays an essential role in the asset management
in electricity distribution companies. Owing to the capital-intensive nature of the field and long-
span operations of distribution companies, the significance of a strategy is highly emphasised.
A well-devised strategy combines the best knowledge of the challenges posed by the operating
environment and the future targets of the distribution company. Challenges originating from the
operating environment are constantly evolving. The economic regulation, ageing infrastructure,
scarcity of resources and tightening supply requirements together with challenges created by the
climate change put challenges on the energy sector. On the other hand, technology development
for instance related to network automation and underground cabling together with an
opportunity to outsource certain activities assists in answering these challenges.
Introduction of regulation into the electricity distribution network business and the stepwise
changes in the regulatory model have generated understandable uncertainty in the field. The
distribution companies are trying to figure out how the traditional development principles
applied in the companies will reflect through the regulatory model to the financial result of the
company. In particular, the role of reliability of supply has significantly increased during the
past decade. Previously, the outages experienced by the end-customers did not have a direct
impact on the financial result of the company. Since then, regulation has been developed so that
the quality of supply, in the form of reliability of supply, has an effect on the company result.
An evidence of the obvious effects of the regulatory measures is related to the collection of
certain indices. Although distribution companies have compiled statistics on automatic
reclosings at a general level already in the 1980s, the regulator formalised the obligation to
notify automatic reclosings as late as in Finland in 2003. A few years after issuing this
obligation, the regulator included automatic reclosings in the economic regulatory model.
Distribution companies were aware of this and started to seek tools to cut down short
interruptions. The basic idea involved in the regulatory model to create artificial market
pressure is advantageous for the development in the field and in society in general; the
distribution companies have to search cost-efficient solutions to the long-term development of
the distribution networks. The regulatory model has to encourage such investments that
minimise the long-term costs caused to society. However, a challenge posed by the regulatory
14
model is the increasing intricacy and unpredictability of the business. Furthermore, the model
should take into account the individual differences between companies, simultaneously
remaining equitable and understandable.
The intensively developing operating environment forces the distribution companies to focus on
strategic development of their distribution networks. This doctoral dissertation aims at
developing process knowledge and establishing a methodological framework by which key
issues related to network development can be addressed. The management and owners of a
distribution company play a central role in drawing up the guidelines for network development.
It is of high importance that required information concerning the operating environment,
network assets and development needs is available for decision-making and that there are
suitable analysis tools for the purpose. The questions addressed in the strategy process1 are
essential both to the company management and the personnel responsible for the long-term
development work.
1.1. Main objective of the work
The main objective of this work is to develop methodology for strategic planning of electricity
distribution networks. In the development work, for instance changes taking place in the
operating environment, electrotechnical requirements, reliability issues, ageing of the
distribution networks and the needs of the end-customers, network owners and the distribution
company have to be taken into account. Typical strategy-level questions include for instance the
following: what are the objectives set for the development of reliability of supply, and what are
the effects of different development options, such as full-scale underground cabling, on the
price of distributed electricity and the owner’s return on investment. In this doctoral
dissertation, general methodology is proposed for addressing strategic questions related to
network development in distribution companies. The presented methodology provides means to
1 In the context of this doctoral dissertation, the noun ‘strategy’ in the compound ‘strategy process’ is used as a generic term, which is neutral with respect to whether there already exists some distribution network strategy in the distribution company under observation, or a new strategy is developed from scratch.
15
and answer these questions; however, the work does not determine which is the appropriate or
best strategy for the distribution company in a given situation.
The work concentrates on electricity distribution networks in rural areas in Finland.
Nevertheless, the strategic approach and methodology of the kind described in this study can, to
a certain degree, be applied to urban distribution networks also. Forecasting changes in the
operating environment and drawing up detailed development plans are outside the scope of this
doctoral dissertation. Development of optimisation algorithms for single investments is not
among the key targets in this work either.
1.2. Outline of the work
This doctoral dissertation is organised as follows: Chapter 2 provides an introduction to
strategic planning. The chapter introduces in brief factors related to the electricity distribution
business and describes the strategy process at a principle level. Further, the chapter determines
the subtasks included in the strategy process and presents the key questions related to the
strategy work and long-term network planning.
Chapter 3 delineates the key factors related to the electricity distribution network business that
have either a direct or indirect effect on strategic planning and long-term development needs in
the distribution networks. These include for instance the ageing infrastructure, economic
regulation of the distribution business, the network owners, issues related to the quality of
electricity, climate change and blackouts, and shortage of resources.
Chapter 4 introduces and describes the analysis methodology and tools developed in the study
in order to perform the cost and reliability analyses. The chapter focuses on determination of the
techno-economic feasibility of different network development technologies for instance with
respect to underground cabling, circuit reclosers and earth fault current compensation. The
feasibility surveys are strongly linked to the economic regulation model of the distribution
business described in the previous chapter, in particular from the viewpoint of reliability of
16
electricity distribution and allowed return. The chapter introduces the asset management system
developed as a tool for research purposes, the calculation elements of the system and initial data
used in the analysis; the key elements of this asset management system are utilised in this
doctoral dissertation. Chapter 5 addresses the stages of strategic decision-making from cost
and reliability comparison to prioritisation of renovation targets and compilation of investment
strategies. Furthermore, the chapter illustrates implementation of strategic planning on an actual
medium-voltage feeder. The purpose of the example calculations and results presented in
Chapter 5 is to illustrate how the methodology can actually be applied to the strategic
development of the network. Nevertheless, it is pointed out that the results cannot be
generalised as such, but each distribution network has to be considered individually.
1.3. Scientific contribution
The main contribution of this doctoral dissertation is the establishment of the concept of the
strategy process with associated tools for the long-term planning of electricity distribution
networks. The scientific contributions of the dissertation can be summarised as follows:
- Concept of strategy process:
interactive way of thinking and working in the distribution business involving numerous
cross effects and factors that vary over time.
- Calculation and analysis methodology included in the concept of strategy process:
within the concept, plenty of calculation methodology is required both for technical and
economic calculations; in this work, methodology required for the purpose is developed by
simultaneously utilising existing methods.
- Functioning of the concept of strategy process is verified by practical network
development work in an actual distribution network company environment.
By utilising the above contributions, a network planner will be able to analyse the effects of
strategies on the costs of electricity distribution business, reliability of distribution networks,
and distribution fees.
17
1.4. Summary of publications
This doctoral dissertation consists of eight publications. Publications I–III concentrate on
development of the regulatory model with a special emphasis on efficiency benchmarking.
Publication IV addresses the interaction between outage costs and investment decisions.
Publications V–VII focus on investment strategies and challenges posed by the operating
environment to the electricity distribution business. The author of this doctoral dissertation has
been the primary (responsible) author in all the above publications.
Figure 1.1 illustrates the publications relevant to this dissertation.
Price for outages through regulation
Outage costs
Outage costs as part of the regulatory model
Effects of outage costs on investment decisions
Calculation of return on investment
Determination of economic rationale for investments, Development strategies
Challenges of outsourcing
IEEE 2002 CIRED 2005CIRED 2003 IEEE PES 2005 IEEE PES 2006 Int. Journal of Energy Sector Management 2009
CIRED 2007,
IEEE PES 2007
Figure 1.1. Timeline of the selected publications constituting the basis for the doctoral dissertation.
Publication I Analysis of the benchmarking results of the electricity distribution companies in
Finland.
Publication I discusses the drivers set by the regulation model on the electricity distribution
business from the perspective of efficiency benchmarking. The publication shows that it is
possible to determine an actual price for the quality of electricity (reliability of supply) through
the regulatory model. Moreover, the publication introduces and highlights some key problems
related to the efficiency benchmarking method applied, such as unpredictability and inequitable
treatment of companies. The analyses showed that changes in the quality of supply did not
necessarily have any effect at all on the efficiency score calculated for a distribution company.
Further, the publication shows that the outage cost parameter applied in the efficiency
benchmarking does not describe the quality of supply to a sufficient extent and accuracy. In this
publication, the author has played a primary role in performing the sensitivity and efficiency
benchmarking analyses and determination of outage costs.
18
Publication II Data Envelopment Analysis in the benchmarking of electricity distribution
companies.
Publication II addresses the drivers set by the regulatory model and the efficiency
benchmarking between distribution companies. The publication shows that the regulatory
model can be developed further by using outage costs, instead of outage duration, as an
indicator of the quality of electricity. Application of outage costs in efficiency benchmarking
ensures a more equitable treatment of distribution companies, simultaneously promoting the
predictability of the regulatory model. In Publication II, the author has played a primary role in
development of the efficiency benchmarking.
Publication III Power Quality Factors in Efficiency Benchmarking.
Publication III focuses on outage costs as part of the regulatory model and assesses the weight
of different quality factors in the model. From the perspective of long-term development of
distribution networks, the outage costs (if applied in the regulatory model) should include both
short and long interruptions, their number and durations, and planned and fault outages. Special
attention has to be paid to the weights of different outage cost components (€/kW, €/kWh) to
ensure that no single outage type receives disproportionate value, or alternatively, is ignored
altogether. Should the outage costs be included in the regulatory model, the effects of outage
costs (and individual outage types) on the development of the distribution have to be
understood. In this publication, the author has played a primary role in assessment of the weight
of the outage cost component applied in the efficiency benchmarking model and the incentives
based on the quality of supply included in the regulatory model.
Publication IV Economic Analysis of Outage Costs Parameters and Their Implications on
Investment Decisions.
Publication IV concentrates on the effects of outage costs on investment decisions. The analyses
establish that outage costs can be applied both to the planning and operation of the distribution
networks and in the regulatory model (e.g. efficiency benchmarking). In the regulatory model,
special emphasis has to be put on determination of outage costs: setting a reference level is a
challenging task, as too short a reference history in outage statistics will result in large annual
variations in the outage cost level, whereas too long a reference history will cause the effects of
19
reliability investments to show slowly in the outage cost level. In Publication IV, the author has
played a primary role in assessment of the significance of parameter selection related to outage
cost calculation and reliability effects of network investments.
Publication V Distribution Network Investment Strategies in the New Business Environment.
Publication V discusses the challenges posed by the operating environment to the electricity
distribution business with special reference to reliability and ageing of distribution networks
and low investment levels. The publication assesses the effects of new and replacement
investments on reliability and development of the network value as well as various
combinations of efficiency benchmarking (such as OPEX alone, OPEX + PQ, OPEX + PQ +
CAPEX). Furthermore, the profitability of different investments has been considered from the
perspective of determination of allowed return. In Publication V, the author has played a
primary role in determination of factors describing different regulatory models and the
operating environment of distribution companies.
Publication VI A Comparison of the Electricity Distribution Investment Strategies.
Publication VI introduces and describes determination of the economic rationale for a single
network investment, such as transfer of lines to roadsides, application of covered conductor
technology and underground cabling. In the analyses, special attention is paid to the effects of
the cost development of different technologies on their economic feasibility. Further, the
publication includes cost analyses of different development options made for an actual example
network. The publication also summarises the effects of investment strategies on the
distribution fees paid by the end customers. In Publication VI, the author has played a primary
role in compilation of feasibility studies of different network technologies, and to the
development of tools applicable to the analysis.
Publication VII New Investment Strategies in the Modern Electricity Distribution Business -
Reliability in the Long-Term Planning.
Publication VII introduces the essential long-term development technologies for distribution
networks and the drivers originating from the operating environment. The issue has been
20
approached in particular from the aspect of reliability. Moreover, the publication includes cost
calculations based on an actual example distribution network. In Publication VII, the author has
played a primary role in assessment of drivers originating from the operating environment and
the cross effects involved in development planning.
Publication VIII Unbundling of Operation and Network Development Activities in Electricity
Distribution.
Publication VIII presents a framework for decision-making in utilities where unbundling
considerations are taking place. The publication analyses the implications of splitting a long-
term network planning activity from the organisation responsible for short-term network
operation activities. It was found out that colliding interests in the new business model can be
avoided if economic and technical targets are mainly set by the regulator for both network
development and operation activities. In particular, the publication approaches the risks of
unbundling of network planning and operative functions with respect to information flows. In
this publication, the author has played a primary role in the analysis of the drivers originating
from the operating environment, both from the viewpoint of operative functions and long-term
network development.
21
2. Introduction to strategic planning
Electricity distribution is undergoing dramatic changes. Supply of electricity, which for decades
was considered to be a fundamental element of modern society, has developed into electricity
distribution business and network asset management (Figure 2.1), and is now evolving towards
intelligent electricity networks. In the branch, this has meant a radical change from the
traditional mindset, in which appropriations for development of electricity distribution networks
were taken for granted, into optimisation-based investment policies and emergence of service
markets. Ageing of electricity distribution systems, increased demands set by society for the
quality of supply and owners’ expectations have created pressure for intense renovation of
distribution networks and renewal of the branch. The emergence of cost-based investment
strategies has created a need for the development of various new planning and optimisation
models.
Electric utility- Generation- Transmission- Distribution- Sale
Electric utility- Generation- Transmission- Distribution- Sale
- Financing arrangements
- Target setting- Network management
agreements
Power generation company
Power generation company
Transmission (grid) companyTransmission
(grid) companyDistribution
companyDistribution
company Sales companySales company
Network ownershipNetwork
ownershipAsset
managementAsset
management Service providersService providers
- Setting principles of operation (= strategy)
- Management of service agreements
- Equipment supplier- System supplier- Network operation- Construction- Measurement
Figure 2.1. From supply of electricity into network asset management.
Electricity distribution business is capital intensive by nature, and it is characterised by long
lifetimes of the network components. Nowadays, the operating environment strongly impacts
the ways of operation and the economic result of the electricity network operators (distribution
companies)2, even though, because of the monopoly position, competition does not put pressure
on the daily business (Figure 2.2). At present, the most essential driver, established by the
operating environment, is the official techno-economic supervision of the electricity distribution
2 In the context of this work, the terms ’network operator’ and ’distribution company’ are treated as synonyms.
22
business. This regulation sets the framework for the network operators, within which they have
to operate. Deviating from this framework may lead to economic losses. Within the framework,
a network operator is relatively free to operate the business.
It depends on the targets set by the company owners how collecting of return allowed by
regulation is taken advantage of in the company and how the owner supervises and participates
in the long-term network development. The owner views may have a strong influence on the
development of the distribution network, for instance with respect to reliability. The ongoing
climate change has also increased the field’s interest in reliability issues. It has been estimated
that the reliability of electricity distribution will suffer from the increased winds and
precipitation, if these changes are not seriously taken into account in the future network
structures. On the other hand, the general technical development has enabled cost-efficient
construction of more reliable distribution networks. Furthermore, national and international
energy policies also have an impact on the electricity distribution business, for instance from
the viewpoint of network loss considerations and distributed generation (DG).
ELECTRICITY DISTRIBUTION BUSINESSEconomic
regulation
Owners
Climate change
Energy policyQuality of electricity
Ageing infrastructure
Technical development
Increase in electricity
consumption
Human and material
resources
Figure 2.2. Electricity distribution business; operating environment.
In this doctoral dissertation, operating environment is mainly treated as a boundary condition
and a variable against which the strategic-level planning has to be reflected at regular intervals.
The dissertation does not aim at compiling models, by which the direction and magnitude of
changes as such could be assessed and predicted. The work focuses on investigating how
different drivers originating from the operating environment affect the electricity distribution
business, how these factors should be taken into account in network strategies, and how the cost
23
and network effects of a single factor can be analysed. Assessment of these effects is based on
total cost models, in which the investment needs caused by the above-mentioned drivers and the
development of the quality of electricity, and the company return are examined.
Considering the levels of planning, the dissertation concentrates on strategic-level network
planning. This means that the work does not include for instance optimisation algorithms for the
choice of conductor cross-section on an economic basis. Instead, the emphasis is on general-
level planning. In the developing electricity distribution business, good knowledge of general-
level strategic planning is a prerequisite of successful business.
OwnershipBusiness planning
Network development
planning
Network planning
Field planning
Construction management
Network construction
Operation and maintenance
Figure 2.3. Electricity distribution business: from ownership to maintenance.
The guidelines drawn up by the distribution company in the strategic-level network planning
are used as the basis for long-term planning. The results of long-term planning are further
applied to network planning, where the design principles are realised in field and work
planning.
2.1. Network strategy process
Because of the capital-intensive nature of the electricity distribution business, network asset
management plays a key role in the operation of an electricity distribution company. A
precondition for successful asset management is an appropriate and consistent network strategy.
A well-prepared and maintained strategy provides valuable and reliable information for the
management in decision-making. Thanks to a feasible and rational strategy, the company
management and other personnel have a clear picture of the principles according to which the
network is developed further.
24
Grünig and Kühn (2006, p. 85) state that all strategic decisions share the following
characteristics: “They deal with complex interrelationships, they occur at irregular intervals,
they are always unique in their scope, in their questions and in the framework of pre-conditions
to be met and they have a long-term influence on the fate of the company.” This describes well
also the significance and characteristics of a network strategy in the electricity distribution
business. Drawing up a network strategy is a multi-stage, iterative process. A successful
strategy process calls for a survey of the distribution company’s operating environment (Figure
2.4). The target of this survey is to determine which operational preconditions and regulatory
effects arise from the surrounding society and which from the company history and background.
Societal factors that have an effect on the progress of the network strategy work and the final
results are for instance the development of the economic regulation model for the energy sector,
requirements related to the quality of supply, ageing of networks, climate change, changes in
energy use, and for instance various environmental regulations. The contents of the strategy
also depend strongly on the background and objectives of the distribution company itself, such
as the present state and condition of the distribution network, available personnel and material
resources and the targets that the network owners have. The strategy work becomes even more
challenging because of the abundant information sources but also information that may be
unreliable, fragmented, and in some cases, contradictory or deficient.
A survey of the operating environment may take quite a long time at the beginning of the
strategy process; however, its importance cannot be underestimated. The techno-economic
choices made in the strategy work concerning the network asset development are based on
information obtained from this survey, and therefore the feasibility and profitability of choices
are highly dependent on the reliability of the background information. The survey and analysis
of the operating environment are carried out by the operative management of the company and
the personnel in charge of network planning and operation; thus, in practice by those people
who will eventually utilise the results obtained from the strategy process in their work.
25
Survey of the operating environment and
collection of initial dataStrategic analyses
Society- Development of regulatory models- Reliability and quality of electricity- Climate change (challenges posed by
weather phenomena)- Network’s susceptibility to blackouts
(standard compensations)- Environmental regulations (e.g.
preservatives) - Technology development (e.g.
telecommunications)
Development in the field- Development of network technologies- Service providers- Distributed generation- Electric cars (energy storages)
Distribution company- Network assets- Human resources, skills and knowledge- Owner expectations and objectives- Return and reliability targets- Challenges posed by the geographic location
of the company (climate, soil)- Development in the area of operation (loads)
Initial data of the analysis- Network data (topology, components) - Load data- Fault history
Which are feasible network strategies in practice?- Transfer of overhead lines to roadsides, covered conductors- Underground and overhead cables, cable ploughing- Network automation (remote-controlled disconnector substations,
circuit reclosers)- Light primary substations, light 110 kV lines- 1000 V technology
Is there techno-economic potential for the technologies?What are the cost effects of the technologies?What are the reliability effects of the technologies?
The analysis is carried out for actual network sections to get usable results. Compact analysis tools and new calculation methodology are required for the analysis of large network entities.
Owners’ objectives (return expectations, investment in network development)?
Which calculation parameters will be used?-Unit costs (network components, losses, outage cost values, OPEX)-Interest rate, lifetime, load growth-Fault rates, switching and repair times
Figure 2.4. Network strategy process: survey of the operating environment and strategic analyses.
A survey of the operating environment provides a foundation for the strategic analysis. This
analysis concentrates for instance on the following issues:
- Which are the most compelling factors driving network renovation (network age,
reliability, ownership issues, pressure from society)?
- What network development alternatives are there; what is their techno-economic
potential?
- What are the cost and reliability effects of different development methods?
- Which calculation parameters are used in the strategy process?
- What are the owners’ objectives, and what are the opportunities and tools provided by the
owner(s) for network development (return expectations, investment in network
development)?
26
Concerning the current state of the distribution system and the distribution company, the most
important question that has to be addressed first is which are the strongest drivers for network
development. Are these drivers arising from the high average age of the network, poor
reliability, changes in the owners’ objectives or other factors related to the operating
environment? In most cases, there is no single driving force, but the need for network
renovation and development is a sum of many factors. In the strategy process, different network
technologies are analysed, from which the development alternatives that are the most suitable
for the operating environment and long-term targets are chosen. Determination of the techno-
economic potential of different technologies calls for extensive network analyses on actual
network sections. The target of the survey on the techno-economic potential is to ensure that
there really are economic grounds for application of the chosen network technologies in a
sufficiently large scale. To this end, various tools have been developed to assess the network
and cost effects of development alternatives with adequate accuracy and reliability. Although in
the past few decades, various optimisation algorithms have been developed for optimal
dimensioning of network structures, some of these being still in use, these algorithms cannot be
used as such to get an overall strategic picture because of the large network mass involved.
These technology-specific selection tools (e.g. selection of conductor cross-section,
determination of the outage cost benefit of network automation, techno-economic comparison
of underground cabling and overhead lines) can only be used in the analysis of a single target
and the technical solutions chosen for it. Getting a strategic overall picture of different
development alternatives requires an analysis of the cost and reliability effects of different
technologies on a large network section. Planning of electricity distribution networks has been
addressed for instance in (Willis, 2004) and (Lakervi and Holmes, 1995). The long-term
planning principles presented in these works can be applied to subtasks of the strategy work, yet
they do not provide direct assistance to the basic questions of strategic network development.
The calculation parameters applied to the strategy work play a key role also when assessing the
economic feasibility and network effects of different development alternatives. The role of
reliability in particular has gained importance along with the adoption of outage cost
parameters. A single distribution company cannot decide which cost parameters are used for the
determination of outage costs, but the unit costs for outages are defined by the authority
(regulator). In the current regulatory model for electricity distribution business, the outage costs
are the same for all distribution companies, and they reflect an average Finnish electricity end-
27
user group. Thus, in the definition of outage costs, the chief task of a network operator is to
compile and provide the required reliability statistics. A network operator is responsible for
monitoring the development of the quality of supply and submitting the reliability statistics
required in the outage cost calculation to the regulator. However, these statistics are not
compiled only for the needs of the authority; long-standing and reliable fault statistics are useful
for a network operator to focus the development actions on those targets where they are needed
most. One of the targets of a network strategy is to establish conditions for cost-efficient
development actions. In addition to reliability data, the company has to observe the
development of its operating area in terms of changes in the number of electricity end-users and
electricity use. Long-term load growth forecasts play a key role in the determination of the
required transformation and transmission capacity and the optimal loss costs.
In the analysis stage of the strategy process, there has to be a clear picture of the challenges that
will burden the network in the future, and of how the different network technologies are able to
answer these challenges. In the strategy work, the network technologies are only roughly
outlined; a more detailed techno-economic selection is made together with the analyses of
delineated network sections. As a whole, the process is iterative and complex by nature. In
particular, the reliability and outage cost aspects involved complicate the analysis because of
the various cross effects between cost components and reliability. For instance, building a new
primary substation is shown in the company turnover as a lump-sum investment cost, but also in
the annual network operation, maintenance and outage costs. Further, when also efficiency
requirements set by the regulatory model are taken into consideration, the final cost effects of a
single investment and larger development alternatives become even more complicated. A basic
investment such as a primary substation is no longer an investment dictated by the technical
network boundary conditions alone, but the obligations and effects related to the investment
extend through different cost components into the entire distribution business of the company.
Achieving successful results in the strategy process requires good knowledge of the reliability
effects of different network technologies and the regulatory model, but also uninterrupted
communication with the owners. The strategic analysis produces guidelines about the network
technologies, owners’ objectives and the investment strategies applied to the long-term planning
in the company (Figure 2.5).
28
Strategic analyses
Long-term plan
Implementation of strategic decisions
Potential use of technologies (%)- Transfer of overhead lines to roadsides (25 %)- Underground cabling (10 %)- Remote-controlled disconnector substations, circuit
reclosers (1 pcs/feeder)- 1000 V technology (30 %)
Cost effects of the technologies- Transfer of overhead lines to roadsides (50 km/a, 1 M€/a)- Underground cabling (5 km/a, 250 k€/a)- Remote-controlled disconnector substations, circuit
reclosers (20 pcs/a = 250 k€/a)- 1000 V technology (50 km/a, 1 M€/a)
A long-term plan for the example area and the whole distribution company taking into account the strategic decisions made in the process.
How a single development technology e.g. underground cabling is implemented in practice?
- Underground cabling: starting from the feeder sections most vulnerable to faults, or from the oldest sections, or by proceeding from the substation downstream from the feeder
- Network automation:…
What are the effects of different development methods?
- Costs, reliability, distribution fee, allowed return
Strategic decisions
Reliability effects of the technologies fault duration rate reclosings
- Transfer of overhead lines to roadsides (x) x x- Underground cabling (x) x x- Remote-controlled disconnector
substations, circuit reclosers x/x -/x -/x- 1000 V technology (x) x x
Owners’ objectives- Reduction in SAIDI 20–40 %- Increase in the present value of the network from 45 to 50 %
Calculation parameters- Unit costs: x €/km, y €/pcs- Losses: 50 €/MWh- Outage cost values: EMA- Interest rate: 5 %- Lifetime: limits set by EMA (maximum)- Load growth: 1–3 %/a (by regions)- Fault rates: x pcs/100km,a (overhead line)…- Switching times: 60 min (manual), 10 min (remote) - Repair times: 4 h (cable), 2 h (overhead line)…
- Main technologies- Owner’s perspectives
(amount and schedule of investments)
Figure 2.5. Network strategy process: from strategic analyses to a long-term plan.
The network technologies that are chosen based on the strategic analysis and that are suitable
for the company’s operating environment are applied to the development planning for target
network areas. Now the cost and reliability benefits as well as application opportunities of
different technologies are specified in more detail. From the viewpoint of network structure,
loads and reliability, the selected example areas that represent actual network sections describe
well the whole operating area of the distribution company and thereby provide a good general
view of the applicability of development technologies to the whole operating range of the
company. As a result of the analysis, the suitable, most cost-efficient network development
technologies, the application potential of the technologies and large-scale cost and reliability
effects are determined for the network operating area in question. Should the development
alternative not meet the objectives set by the owners for instance with respect to reliability or
costs, this alternative can be excluded or redefined so that the set targets are met. If the
boundary conditions and targets determined at the beginning of the strategy process are met, it
29
is possible to make a strategic decision to include the development alternative in the long-term
development plans of the distribution network.
LANDBO
MASSBY
KALLBÄCK
MARTINKYLÄ
– Cabling and covered conductors
– Renovating overhead lines to roadsides
– Distributed protection: reclosers
– Remote-controlled disconnectors
– Low-cost 110/20 kV substations
– Low-cost 110 kV line
– 1000 V technology
– LVDC
– Energy storages
– Distributed generation
– Intelligent customer connections
??__ km/a __ units/a
Effects:- Reliability?- Age and condition?- Distribution fee?- Public relations?- Return?
??
Figure 2.6. Issues to be included and analysed in a general-level network strategy.
Before actual transfer of strategic decisions into the long-term network development, an
investment strategy is compiled including analyses how the different technologies are
eventually put into practice (e.g., in which order). For instance, underground cabling can be
carried out either by starting from those feeder sections that are most vulnerable to faults, or
from the oldest sections, or by proceeding from the substation downstream from the feeder.
These choices may have significant cost and reliability effects; in particular, depending on how
fast the reliability is improved by the investments made. The strategy process now continues so
that the chosen technologies are applied systematically in the long-term network planning in the
entire operating area of the distribution company. Thus, the strategy is incorporated into the
company practices.
In the strategic planning, the achieved results are concretised in long-term planning. Taking the
changing operating environment fully into account requires development of new planning
methodology and tools. Although planning methodology has been developed already from the
1970s and 80s onwards, for instance the arising reliability issues and the profound changes in
the operating environment have led to a situation where the above-mentioned specific planning
methods cannot be applied as such to the present-day network planning. As the electrification
process started in a large scale in the 1950s, and the loads were increasing, it was necessary to
develop the models from the viewpoint of load flow and loss control. Now, instead, the models
30
have to take into account in detail the effects of ageing networks and reliability, and thereby
their economic control effects. On the other hand, a strong increase in loads cannot be excluded
from the future development scenarios, as for instance electric vehicles entering the markets
will have a significant impact on the strategic planning and network structures. Although such a
development trend is not forecast for the very near future, because of the long lifetimes of the
network structures, it is necessary to take this option somehow into account already in the
present-day strategic planning. Further, distributed generation may have a strong regional
impact on electricity distribution networks. However, the issue is outside the scope of this
dissertation owing to its present minor role in electricity distribution networks.
The target of long-term planning is to determine the economically best solutions in terms of
network structure and the type and schedule of investments. To reach the target, the loads,
losses, voltage drops, earth fault and short-circuit currents and outage costs of different network
sections are calculated. Based on these calculations, the development needs in the network are
determined. Efficient long-term planning is based on a systematic planning process and
utilisation of methods that facilitate and promote the planning work. Long-term planning can be
considered to consist of a number of smaller subtasks that support the ultimate target, that is,
minimisation of the total costs of distribution network operations in the long term. For this
purpose, numerous cost optimisation algorithms have been developed for different tasks, such
as choosing an optimal conductor cross-section (a new conductor, reinforcement of an existing
line) and determination of the economic feasibility of underground cabling, using a covered
conductor or transferring a line to the roadside, or application of network automation (e.g.
circuit reclosers).
31
3. Changes in the operating environment
The business operations of electricity distribution companies are strongly dependent on the
operating environment. The main focus of the business is on maintaining and developing the
electricity distribution network. Because of the monopoly nature of the business, official
supervision of the business constitutes an essential part of the business planning. The network
assets of the distribution company may be spread over a very large geographic area, and
depending on the geographic location and network structures, they may be vulnerable to
environmental conditions, such as weather, particularly in rural environments. The boundary
conditions for the quality of electricity, set by the techno-economic regulation of electricity
distribution business, force the distribution companies to constantly develop their operations to
meet the challenges posed by the operating environment.
Evolution of society has reflected the need to develop the electricity distribution networks. The
increase in electricity use has followed the general economic growth. The electrification process
from the 1950s and 60s onwards enabled the introduction of various electric tools and
apparatuses in rural areas. The resulting increase in electricity consumption has forced the
companies to be aware of the loads on the network and to solve the problems arising from the
load growth. The electricity distribution companies also needed to have a good insight into the
development trends in society and thereby in the electricity use within their operating areas, and
plans for how the challenges posed by the changing environment are met. Although load growth
is no longer the major single factor directing the network development, awareness of changes in
the operating environment and the need for a development strategy are still paramount issues in
electricity distribution companies (Van Geert, 1997). As a matter of fact, the growth in energy
use can in some areas be slight or even negative. Although development has been rapid in the
field in the past few years, substantial changes can be expected in the coming years for instance
because of ageing networks (Welch, 2001), increasing demands for reliability, climate change
and introduction of distributed generation (Watson et al., 2001) and intelligent networks
(Ipakchi and Albuyeh, 2009). Hence, the traditional development needs based on
electrotechnical reasons are making way for new challenges.
32
There is a tendency that the passive role of electricity distribution business is turning into active
one (Woodman and Baker, 2008). Previously, the development in the field has followed the
general trends in the demands of society, and the field itself has not shown the way, nor has it
set trends for the development in society. Currently, the more active role of the business is
shown for instance in the market penetration of smart electric meters in remote metering (EU,
2006), (Houseman, 2005) and increased distributed generation (Watson et al., 2001); in the past
few years, considerable resources have been allocated to the research of this subject matter.
Although significant breakthroughs have not yet been made, the evolution of distributed
generation may make it an essential element in the electricity distribution systems. As DG
becomes more common, electricity distribution networks will be a genuine marketplace for
electricity production, transmission and use. Remote metering and bidirectional data transfer
will have a central role in the establishment of this marketplace. As a whole, the amount of
intelligence in the electricity distribution network will increase; this will mean faster and easier
adoption of new technologies compared with the opportunities provided by the present
electricity network infrastructure alone. Electric cars are an example of these new applications;
problems related to the entry of electric vehicles are discussed in more detail in section 3.10.1.
The changing needs of society have made the development of electricity distribution networks
an increasingly complex and demanding task. While in the early days of electrification the
target of the company was to build electricity distribution networks at a minimum investment
cost, various new cost elements and technical boundary conditions have now been introduced
into the optimisation task. These elements and boundary conditions have to be taken into
account especially in the strategic planning of networks.
In the process of electrification of rural areas, the target was to make a basic commodity
available all over the country. First, electricity was mainly used for lighting only; thus, the
power demand of a single end-user was not very large. Consequently, because of these
relatively small loads, the electrotechnical dimensioning of distribution networks was not
considered a key issue. Instead, the availability of materials determined the dimensioning
principles. In practice, the target was thereby to minimise the investment costs at the time of
construction. Later, when electricity became a source of energy in heating and large machines,
the limits of the transmission and transformer capacity of the existing networks became evident
33
by voltage drops and small voltage elasticity. Furthermore, the poor reliability of distribution
networks was shown by repeated supply outages. Poor reliability could be explained by
shortage of material; the conductor lengths had been minimised by drawing the lines directly
from the primary substations through forests to the distribution substations and from there
further to end-users. Moreover, underground cabling was rare because of its high costs. Because
of severe weather phenomena and snow loads, forests constituted a challenging operating
environment for electricity distribution and power lines.
The development of electricity distribution networks has been characterised by long lifetimes of
network components. For instance, the lifetimes of overhead lines are typically 40 to 50 years.
In the field, there have been two dominating trends in the long-term network development: In
the first development model, the key idea is to aim for maximising the network lifetime by
applying various ageing models for distribution systems (Bouford and Willis, 2005), (Hoskins
et al., 1998), (Datla and Pandey, 2006), (Hilber et al., 2005), (Birtwhistle et al., 2006) and
(Schneider et al., 2006). In the second model, the target is to take into account the owners’
objectives and challenges posed by the operating environment in an extensive and
comprehensive manner well ahead in the future. This model, however, is not about system
horizon planning (Fletcher and Strunz, 2007), but the direction of the network development is
adjusted annually in this approach.
In the 1980s, a massive need for distribution network renovations was expected to arise; this
assumption was based on estimates of the lifetimes of wood poles. Initially, it was estimated
that the overhead lines built in the 1950s and 60s would reach the end of their lifetime by the
end of the 20th century. However, these massive replacement operations could be postponed to
the 21st century, partly because the initial estimates for the actual lifetimes of wood poles had
been too pessimistic. It became evident that the pole replacements scheduled for the 1990s
could be put off for at least ten or fifteen years. The delay in replacement work can be said to be
partly due to profound changes in the electricity market. In the field, the liberalised electricity
markets and unbundling of electricity transmission and sale shifted the focus to coping with the
business challenges.
34
It is obvious that a postponed network renovation cannot be put off for ever. When wood poles
are reaching the end of their lifetime, the mechanical condition of a pole deteriorates to such an
extent that it can no longer be used for its purpose. Although replacement of a single pole is a
fairly simple task, at the company level, the large number of poles makes the renovation a
demanding job. In addition to shortage of material, there is a challenge to find enough labour
for planning and actual implementation of the renovation work. And because all the distribution
networks share the same problem of ageing networks, it is a nationwide issue to be dealt with.
The scale of the work can be illustrated by the financial value of the electricity distribution
infrastructure; the replacement value of the Finnish electricity distribution system was estimated
to be 13.6 billion euros in 2007 (Hänninen, 2008).
Because of the strong dependency on the operating environment, compilation of a network
strategy calls for an extensive analysis of this environment. The evolving technical and
economic regulation of electricity distribution business and increasing demands for reliability
together with the climate change and development of loads in the operating environment set
various boundary conditions and requirements for the network strategy; these have to be taken
into account at the very beginning of the strategy process. The starting points for the strategy
work may differ considerably between companies, even though there are certain common
features such as ageing infrastructure or scarce resources. In one company, the owners’ targets
may enable very fast development work in order to improve network reliability and to tackle the
ageing of network structures. In the other company instead, the owner’s conservative policy
concerning investment appropriations may limit the renovation to targets where the need is the
most urgent. Considering the present investment needs, a tight investment policy may make the
long-span network development a challenging process.
3.1. Ageing infrastructure
Extensive electrification of small towns and, in particular, rural areas took place chiefly
between the 1950s and 1970s. This process has been reported for instance in the following
national and international publications: (Lohjala, 2005), (Van Geert, 1997), (Welch, 2001),
(Brown and Humphrey, 2005), (Brown and Willis, 2006), (Li and Guo, 2006), (Hampson,
2001) and (Wijnia et al., 2006). With its problems of ageing and reliability, the electricity
35
distribution network infrastructure shares common features with other large infrastructures,
such as road and railway networks, water supply and sewer systems, and district heating
systems, which are all in need of replacement in the near future (ASCE, 2009), (Civil, 2003)
and (CIBC, 2009).
The age and renovation needs of a distribution network can be illustrated by the age data
concerning the wood poles (Figure 3.1) and transformers on the network. In particular, this
applies to distribution network companies in rural areas, where the network consists
predominantly of overhead lines. By investigating the age distribution of poles in the example
company we can see that the largest network investments took place in the example company in
the 1960s and 70s. This reflects the situation also elsewhere in Finland and in the Scandinavian
operating environment in general. The electrification of rural areas was by no means a minor
task; the scale of the work can be illustrated by the fact that even at present, overhead lines,
which serve as an example of the Finnish electricity distribution network infrastructure in rural
environments, account for 90 % of the total length of 134 600 km of medium-voltage networks.
Their financial value is high; overhead structures in rural areas accounted for about 7 billion €
of the total 13.6 billion € of the mass of property in the electricity distribution sector in 2007
(Hänninen, 2008).
0.0 %
0.5 %
1.0 %
1.5 %
2.0 %
2.5 %
3.0 %
3.5 %
4.0 %
4.5 %
5.0 %
1950 1954 1956 1958 1960 1962 1964 1966 1968 1970 1972 1974 1976 1978 1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008
Pe
rce
nta
ge
va
lue
of a
ll w
oo
d p
ole
s
Figure 3.1. Age distribution of wood poles in a Finnish electricity distribution company (Lohjala, 2009).
36
For the whole electricity sector, simultaneous ageing of the entire distribution network
infrastructure creates a challenging operating environment; however, the arising renovation
needs can also be seen as an opportunity for introduction of new network solutions.
Strategically relevant issues in the future renovations will be: how the network infrastructure is
renewed, how the renovations are scheduled for the coming years, and which technologies are
favoured in the process. The renovation methods will be strongly influenced by the regulation
of the electricity distribution business and the company owners’ objectives.
3.2. Regulation and ownership
In the electricity distribution business, an essential factor associated with the operating
environment is regulation, in other words, supervision of electricity distribution business.
Because an individual electricity end-user can have only a minor impact on the operation of a
distribution company that has a monopoly position in the market, there is regulation to
safeguard the rights of an ordinary electricity user. The authority supervising the electricity
distribution business collects both technical and economic data and determines whether the
company operation has been in compliance with the Electricity Market Act. The increasing and
more detailed regulation also ties up more and more company resources, and the more
complicated regulatory model makes it more difficult to assess the long-term cost effects of
different investments. A single investment, such as construction of a new primary substation,
has an effect on the reliability of supply, operational costs and the value of the distribution
network, and has thereby a direct impact on the allowed rate of return of the company. When
we add the general and company-specific efficiency requirements and the related complex
efficiency measurement models on top of this, we can see that determination of the final
benefits and drawbacks of different investments is a demanding task. The complexity of the
task is illustrated in Figure 3.2. The alternative investment types, a repair investment and a new
investment, are presented in the bottom left corner of the figure.
37
Existing outage costs
AllowedOPEX
(historical data)
Reference for outage costs
OPEX
Existing costs of outages
Allowed profit
Efficiencybenchmarking
(DEA/SFA)
Depreciations (Replacement
value/ life time of network)
Efficiencyrequirement
Quality reward
Quality penalty
Depreciations
Replacementinvestments
Investment for new capacity
Present valueof network asset
Replacement value of network asset
Length of network
Number of customers
Energy deliveredO = operational
activities
P = planning activities
E = environmental factors
o
p
p
o + p
p
o + p
E
E
E
p
p
Figure 3.2. Interconnections between power quality, outage costs and allowed rate of return in the Finnish
regulatory model (adapted from Honkapuro, 2008).
Regulation can thus be considered to have a strong effect on the electricity distribution
business. Regulation determines the maximum return for a certain network solution, which has
an influence on the rate of return on network business and the distribution fees. The current
regulatory model provides good incentives for network renovations. In particular, the role of
reliability has gained significance after the adoption of outage costs in the model. In the current
regulatory model, both short and long supply interruptions are taken into account. Further, both
the planned and fault outages are included in the regulatory model. Although owing to their
duties, the distribution companies have always been interested in the reliability of electricity
supply, reliability had no direct cost effects on the profit and loss (return) of a distribution
company in the early regulatory models. The first cost effects were introduced to the Finnish
regulatory model as the Data Envelopment Analysis (DEA) methodology was applied to the
efficiency measurement in 2001 (EMA, 2001). The efficiency measurement was based on five
parameters (operational costs, duration of outages experienced by customers, network length,
number of customers and energy transferred) (Korhonen et al., 2000). The efficiency score
calculated by the DEA method had an impact on the operators’ obligation to reduce their
operational costs. Although the effect of single factors employed in the DEA method varied
considerably between operators and the predictability of the model was low, a link was
unintentionally established between the quality of supply (reliability) and the economic result
(Lassila et al., 2003b). Since then, the regulatory model has been developed further several
times (Partanen et al., 2002), (Lassila et al., 2003a), (Järventausta et al., 2003), (Partanen et al.,
38
2004), (Viljainen et al., 2004) and (Honkapuro, 2008). The target of the amendments has been
to remove ambiguity and to clarify the role of the quality of supply in the regulatory model. The
main features and effects of the regulatory models for different regulatory periods are presented
in Table 3.1. The role of reliability in the model is discussed in more detail in section 3.3.
Table 3.1. Main features and effects of the regulatory models in different regulatory periods (adapted from Honkapuro, 2008).
Time
period
Main features of the regulatory model Drivers
–2004 • Allowed return = PV * WACC • Reasonable depreciation costs = Average of three
years’ investments • OPEX and outage time in DEA benchmarking
- No penalties for inefficiency
• Return on all investments - Investments can be financed by funds generated from operations
• Some investments may have an efficiency bonus
• However, opportunities for incremental return are slight
2005–2007
• Allowed return = PV * WACC • Reasonable depreciation costs = straight-line
depreciations (= replacement value/lifetime) • Determination of the network value by standard costs • General efficiency target focusing on OPEX
• Return on investments still certain • Incremental return on efficient investments
(actual cost below standard price) • Obligation to reduce OPEX
2008–2011
• Allowed return and depreciations as above • Outage costs, OPEX and straight-line depreciations
included in efficiency benchmarking • Common and company-specific efficiency targets for
OPEX • Outage costs have an effect on allowed return (quality
incentive and efficiency benchmarking) • Standard compensations have an effect on allowed
return
• Investments may also have negative effects (straight-line depreciations in efficiency benchmarking)
• Strong incentives for quality improvement (on the other hand, penalties for reduced quality)
• Economic significance of blackouts emphasised
The regulatory model impacts the network investments not only through the reliability and
outage cost benefits provided by the investment; depending on the nature of the investment, it
may also affect the amount of allowed return determined for the company. If a completely new
network section is built or network capacity is increased, the investment is defined as a new
investment. A new investment increases the replacement value of the network and thereby also
the annual straight-line depreciations that are defined from the replacement value by the
lifetimes of network components. Adding new network components lowers the average age of
the network and increases the present value of the network. This in turn has a positive effect on
the allowed rate of return. Straight-line depreciations determined from the replacement value
make it possible to collect capital from the customers even though the present value of the
network had collapsed because of the high average age of the network. The term ‘replacement
39
investments’ refers to a situation where a network component is replaced with a new similar
component without causing changes in the capacity or replacement value of the network. A
replacement investment lowers the age of the network when the old component is removed
from the network. This change is shown in the present value of the network and in the allowed
rate of return. The replacement value or straight-line depreciations, however, are not influenced
by replacement investments.
For the long-span electricity distribution business, the rapidly developing regulation constitutes
a risk known as ‘regulatory risk’. Until now, regulation has been characterised by low
predictability and uncertainty. Essential questions that remain open are for instance: what will
happen after the present regulatory period, how is the quality of supply weighted, and which are
advisable investment targets for the distribution companies? Will the regulations on standard
compensations be tightened even further or will the long supply interruptions be “banned”
altogether?
Generally speaking, the regulation of the electricity distribution network business is being
intensified in Europe. General targets of regulation are to intensify the operation of monopoly
operators, to reduce the monopoly power of operators and to establish an artificial market. The
regulation of costs and quality of supply is emphasised; however, the recent long and extensive
supply outages have brought up a justified concern about maintaining sufficient investment
levels. Abrupt stepwise changes in regulation cause considerable changes in the business
environment of distribution companies. If these changes are repeatedly introduced within a very
short period, this may at worst lead to a state of stagnation, where the operators concentrate on
waiting for the regulator’s next move without any intention to develop the operations in the
long term. To ensure an incentive for long-term development, the strategic targets of regulation
have to be clear and consistent. Regulation is a continuous process, and thus, the regulatory
models will evolve and change; despite this, the regulatory signals have to be continuous. The
regulator has to be able to outline the changes that are to be expected a few years in advance so
that the operators have enough time to prepare for changes. If the regulation sets more detailed
company-specific targets for cost efficiency and quality of supply for the distribution
companies, it will be even more important for the operators that they are informed of the
evaluation criteria well in advance.
40
Hence, regulation has a strong impact on network development. How the regulatory effects are
manifested in the long-term network development depends on the ownership structures of the
network company. Depending on the targets the owner has set for collecting return, the owner
may either hold back or speed up the network development. It is the owner’s responsibility to
draw up a network strategy that determines the guidelines for distribution pricing, use of profit
and the level of quality. These are all key elements in the implementation of strategic planning.
Alternative models for collection and use of return are
a) The owner allows a raise in distribution fees required for network development,
however, does not collect this return but directs it to network development
b) The owner allows a raise in distribution fees, but takes the return
c) The owner requires that the distribution fees are kept at the present level, but directs
the return to network development
d) The owner requires that the distribution fees are kept at the present level and collects
the maximum return
In the two first alternatives, the owner takes full advantage of the limit that the regulator has set
for the maximum allowed rate of return by allowing a raise in prices. In the two latter
alternatives, the owner wants to keep the present price level.
Although regulation adds to the obligations and workload of a distribution company for
instance because of the data required to describe the operation of the company, the situation
cannot be regarded as a burden only. When considering from the network strategy viewpoint,
we can see that, to a large extent, the data required by the authority are such that the operator
has to gather anyway in order to be able to develop its operations. Hence, the data are not
collected for the authority only but to make sure that all the essential information required in the
strategic planning is available to support decision-making. Table 3.2 provides some examples of
the data gathered by the authority; the table also shows how this data can be applied to the
strategic development of the operations by the distribution company.
41
Table 3.2. Background data gathered by the regulator and application targets of these data in the development of the operations of an electricity distribution company.
Data gathered by the regulator Application target in strategic planning
Network components: number, age and lifetime data
Basic data applied to the analysis of the present state of the electricity distribution network and future investment needs
Annual investments General view of the network development history
Outage statistics Survey of the present quality level and possible problems in quality, allocation of renovation investments
Paid standard compensations Standard compensation costs with the present network, used as initial data for instance when analysing the effects of blackouts and network development needs
Financial statement information Some of the data applied to the analysis of the cost level of the present network
3.3. Quality of supply
Quality of supply is one of the key issues in electricity distribution network business. For
instance, monitoring schemes for continuity of supply are taking place in over 20 European
countries (CEER, 2008). From the regulatory perspective, the aims of quality control include
measuring actual and perceived levels of quality, promoting continuity improvement and
ensuring good continuity levels to consumers (CEER, 2005). In this work, the term ‘quality of
supply’ refers to the reliability of operation of the electricity distribution system. In the early
days of electricity distribution, unlike today, the quality of supply was not among the primary
questions. Shortage of materials forced to favour simple and straightforward solutions in
network planning and construction. This, in turn, led to line routing and network structures that
were challenging from the network reliability point of view. The interest in reliability issues
awoke in the 1970s; those days, the first reports were published on the harm caused to
customers by interruptions in the electricity supply (Billinton and Grover, 1975). Such
extensive customer surveys made it possible to assess the economic effects of outages, which
brought an entirely new, comparable element to network development. For the first time, an
outage cost element was introduced along with investment and outage costs. In Finland,
electricity end-users were interviewed for the first time in 1978 by Sähköntuottajien
yhteistyövaltuuskunta (STYV), a cooperative commission of electricity producers (STYV,
1979). The results of the survey were published in the report ”Selvitys toimittamatta jääneen
sähkön arvosta (TJSA)” (Report on the value of non-distributed energy). Ten years later, in
1988, a cooperative body Ryhmä 10, which consisted of the largest distribution companies,
42
made a survey on the harm caused to the customers by outages, and introduced a new term,
‘keskeytyksestä aiheutunut haitta’, KAH (customer outage cost), which later on established
itself as one of the key terms in the field. After this, an interview survey was conducted between
1992 and 1993 by VTT Energia (VTT Technical Research Centre of Finland), financed by the
Nordic Council. The survey was addressed to customers of 28 electricity distribution network
companies in Finland, Denmark and Iceland (Lemström and Lehtonen, 1994). The most recent
Finnish survey on outage costs in electricity distribution networks was carried out in 2005 by
Helsinki University of Technology (TKK) and Tampere University of Technology (TUT)
(Silvast et al., 2005). Figure 3.3 illustrates how the valuation of costs has developed in the past
three decades. Although there is an evident connection between the extent of outage costs and
the general increase in welfare, the outage cost values in the outage cost surveys of the past
decades have not increased at the same rate as the gross domestic product (GDP).
Consumer price index (CPI)
Electricity consumption
Gross domestic product (GDP)
GDP/electricity consumption
Households
Agriculture
Industry
Public
Services
Inde
x
Figure 3.3. Development of outage cost values and different indices between 1978 and 2004 (1 = 100 %;
1978) (Silvast et al., 2005).
Considering the quality of electricity, a challenge to the field was that although the indirect and
direct economic effects of outages were recognised already in the 1970s, the outages had no
direct effect on the actual business operations and investment considerations of electricity
distribution companies. An electricity end-user could of course complain about poor quality of
supply directly to the distribution company or the authority, but eventually, progressing the
matter was left to the distribution company. The authority had no incentives or penalties at its
disposal for the distribution companies to make the companies to be more active in the issue.
The practices associated with the development of reliability varied considerably between
43
companies. According to the results of the above customer surveys, the customers’ valuation of
uninterrupted supply has gained increasingly more importance over the years. According to the
most recent survey, a rough estimate is that the outage cost value has doubled in ten years.
Liberalisation of electricity markets and development of regulation promoted the recognition of
the role of reliability in the business of a distribution company. In the 21st century, along with
the overall development in society, the quality of supply (in particular reliability) has become
more and more important. The role of quality is gaining significance in the economic
regulation, and consequently, reliability issues will be increasingly emphasised in the
investment strategies. The first Nordic experiments on including outage costs in the regulation
of distribution companies took place in Norway in 2001 (Langset et al., 2001). In the regulatory
model, outage costs became part of rate-of-return regulation. Based on historic data, a target
level was set for all distribution companies; exceeding this level caused a penalty, whereas
going under the level was rewarded. In Finland, quality of supply was included in regulation in
the form of outage duration in 2000. Those days, outage duration (long supply interruptions)
was introduced as a parameter in the calculation of efficiency scores between distribution
companies. It soon became evident that using interruptions as an environmental factor involved
a problem that was shown by a biased treatment of companies in the calculation of efficiency
scores. The analyses showed that changes in the quality of supply did not necessarily have any
effect at all on the efficiency score calculated for a distribution company (Lassila et al., 2002).
As a consequence, the model was developed by abandoning outage duration as a parameter and
introducing a new outage cost model. This way, the role of electricity quality as an insignificant
factor was considerably reduced (Figure 3.4) (Lassila et al., 2003b).
44
0
10
20
30
40
50
60
Operational costs Quality of supply Distributed energy Netw ork length Customers
Dis
trib
utio
n co
mpa
nies
Original DEA model
Developed DEA model
Figure 3.4. Number of companies having insignificant factors in inputs. In the original DEA model,
quality of supply was measured as the total time of interruption (sum of long supply interruptions) and it
was a separate factor in the model. In the developed DEA model, quality of supply is not a separate factor.
It is taken into account in the input of the developed DEA model by adding it to operational costs (Lassila
et al., 2003b).
The regulatory model was developed further by including more and more detailed information
about the quality of supply in the calculation of efficiency scores. In addition to outage
duration, the quality of electricity, in the form of outage costs, included outage rates of long and
short outages as well as rates and durations of planned work outages (Lassila et al., 2005b).
From society’s perspective, the quality of supply and interruptions have a significant economic
impact. It has been estimated that for instance in Norway the annual economic harm caused by
long electricity supply outages has varied from 350 to 550 MNOK/a (42–66 M€/a) between
2001 and 2008 (NVE, 2009). In Finland, this economic harm was estimated to be 116 M€/a
(Paananen, 2008) for all distribution companies in 2006. When the extent of this harm is
compared with the operational costs of operators (340 M€/a) and with the annual investment
rate of 330 M€/a determined from the replacement value of the distribution network, we can see
that the outage cost component is a significant factor in the regulatory model (Paananen, 2008).
For a single electricity customer (total 3.1 M customers), the average annual outage cost was 37
€/customer,a in 2006. Other examples of European regulatory models in which reliability of
supply has some influence on the company income are for instance Italy, Ireland, Great Britain,
Hungary, Portugal, Sweden and Estonia (Losa and Bertoldi, 2009).
45
Table 3.1 demonstrates that the role of the quality of electricity, that is, reliability of supply, has
gained significance over the past few years. From the perspective of distribution network
development, the main factors relating to the quality of supply in the present regulatory model
can be presented as shown in Figure 3.5.
Change in outage costs
Change in quality incentives
Efficiency benchmarking
Change in efficiency score
Change in allowed return
Figure 3.5. Effects of changes in outage costs.
Quality incentive
A quality incentive is created, when actual outages and outage costs are compared with the
company’s historic data on reliability, that is, with a reference level. An improvement in
reliability increases the return of the company, while degrading reliability has an opposite effect
on the return thereby constituting a strong economic incentive for the quality of supply and
development efforts.
Efficiency benchmarking
Distribution companies are compared with each other by employing Data Envelopment
Analysis and Stochastic Frontier Analysis. The quality of supply is included in this efficiency
benchmarking through outage costs. Reduction of outage costs has a positive effect on the
efficiency score thereby increasing the allowed return of the company. In practice, the
efficiency score increases if the total costs reduce in proportion to efficient cost level.
Standard compensations
The term ‘exceptional events’ (major storms) is widely used all over Europe, but the term is
applied to classify very different kinds of situations in different countries. In Finland, from the
beginning of September 2003, the distribution companies have been obliged to pay standard
46
compensations to their customers, if the customer has experienced an interruption of supply that
has lasted at least 12 hours (Electricity Market Act, 2003). The amounts of the standard
compensations of the annual system service fee are:
- 10 % if the duration of the interruption has been at least 12 but less than 24 hours,
- 25 % if the duration of the interruption has been at least 24 but less than 72 hours,
- 50 % if the duration of the interruption has been at least 72 but less than 120 hours, and
- 100 % if the duration of the interruption has been at least 120 hours.
The maximum amount of the standard compensation because of an interruption of the system
service is however 700 €/a per customer. Contrary to almost all other European countries,
exceptional events are not excluded from compensation payment in Finland (CEER, 2008).
Standard compensations are included in the controlled OPEX, and thus, long supply
interruptions have a direct effect on the company return and thereby on the efficiency target for
the next period. Figure 3.6 illustrates the penalty structure of the Finnish electricity distribution
business regulation model by the variation of interruption duration. The case feeder has 300
customers (10 MWh/customer) and the distribution fee is 5 cent/kWh. Penalties for outages of
excessive duration (> 12 hours) are based on the limits presented above in this chapter. It is
assumed that the whole feeder is without electricity.
0
20 000
40 000
60 000
80 000
100 000
120 000
140 000
160 000
1 6 12 18 24 30 36 42 48 54 60 66 72 78 84 90 96 102 108 114 120 126 132 138
Duration of supply interruption [h]
Inte
rru
ptio
n c
ost
s (o
uta
ge
co
sts
an
d s
tan
da
rd
com
pe
nsa
tion
s) [€
]
Standard compensation
Out
age
cost
24–72 h
12–24 h
72–120 h
> 120 h
Annual income
Figure 3.6. Penalty structure in the Finnish electricity distribution business regulation model. The figure is
based on the example feeder (300 customers, 10 MWh/customer and 5 cent/kWh).
47
The economic effect of the outage cost component depends on how close to the limit set for
allowed return the distribution company is operating. At present, the effect of customer outage
cost may be at maximum 10 % of the allowed return calculated for the company. If the
accumulated previous customer outage costs exceed the maximum limits for the year in
question (“customer outage cost cutter”), the customer outage cost does not have a direct
economic effect. On the other hand, if the accumulated outage costs remain clearly below the
maximum level, the customer outage cost has an effect as illustrated by the outage cost curve in
Figure 3.6. After 12 hours from the occurrence of the outage, in addition to customer outage
costs, standard compensations start to accumulate for the company.
In Hungary, Portugal and Italy (Fumagalli et al., 2007) and in Canada (Billinton and Pan, 2002),
a reward/penalty structure has been suggested to be applied to the regulation of the distribution
companies (Figure 3.7). Large annual natural deviations are taken into account in the regulatory
model by allowing a certain dead zone for each company; changes in the reliability indices
remaining within this dead zone do not have an effect on the rewards or penalties paid. A
maximum level is set for both the rewards and penalties to ensure the reasonableness of the
system.
Figure 3.7. Reward/penalty structure (Fumagalli et al., 2007).
Although there is an obvious need for an outage cost component in the regulatory model,
uncertainties related to the use of this component should be recognised. Despite the fact that the
48
quality indices SAIFI, SAIDI and MAIFI3, on which the calculation of outage cost is based, are
simple and unambiguous, the reporting practices related to the compilation of statistics vary
considerably between distribution companies. For instance, surveys carried out in the U.S.A. in
1990 and 1995 revealed that the distribution companies had no uniform practices relating to the
compilation of outage statistics. Although many operators collect IEEE-approved indices, there
is a great disparity in the actual calculation of indices in the companies (Warren et al., 1999). In
Europe, the use of different weighting methods for indices with the same term (SAIFI, SAIDI)
makes international comparisons difficult (CEER, 2009). This is a fact that may reduce the
usability of the outage cost component in the regulation of the electricity distribution business.
However, a study made in the Nordic countries shows that very versatile interruption statistics
are collected for different purposes. In all countries, the statistics are used both for the energy
sector’s own aims and for regulatory purposes (Kivikko et al., 2005).
As was shown in the previous chapter, the objectives of the owner have an impact on the
development of the distribution network. From the viewpoint of the quality of electricity, the
owner views strongly impact the aims set for the desired level of reliability in the distribution
networks and the schedule for reaching these aims. Alternative targets can be for instance
- Maintaining reliability at the present level
- Improving reliability in fast, cost-efficient and flexible ways, with the aim of minimising
total costs (investments, outages, operational costs)
- Improving reliability in the long term, with the aim of minimising total costs (investments,
outages, operational costs)
- Aiming at a distribution system that is immune to weather phenomena irrespective of cost
The role of reliability and the quality of supply is emphasised in the Nordic environment, which
is characterised by a high forest rate and overhead lines that are vulnerable to adverse weather
phenomena. In Finland, about half of the outages experienced by end-customers are caused by
3 SAIFI: System Average Interruption Frequency Index, the average number of interruptions per customer per annum, SAIDI: System Average Interruption Duration Index, the total interruption duration per customer per annum, MAIFI: Momentary Average Interruption Frequency Index, the total number of customer momentary interruptions (Standard IEEE 1366-2001).
49
trees falling on the lines (Finnish Energy Industries, ET, 2009). If the climate change increases
windiness, the amount of storms and swift temperature variations around zero degrees Celsius,
the problems related to reliability will definitely increase in forest areas. Simultaneously, as the
challenges of reliability are aggravated by the climate change, also the issue of quality is
emphasised among the electricity end users. This poses a challenge to the asset management
and long-term network development. In Figure 3.8, the annual outage statistics of an example
distribution company illustrate how the years differ from each other with respect to fault rate.
From the regulatory perspective, annual variations in reliability are challenging; the regulatory
model should react fast enough to the development actions carried out on the network, yet
simultaneously, the model should be able to filter out the annual natural variations.
Thunder
9 %Snow and ice loads
1 %
Trees falling because of
snow load
11 %
Other weather condit ions
5 %
Animals
6 %
Incautious tree falling
4 %
Incautiousness, external
persons
2 %
Erroneous operation or
installation
1 %
Structural fault
6 %Unknown
10 %
Other
1 %
Wind and storms
44 %
0
50
100
150
200
250
300
350
400
450
500
1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 Average
Num
ber
of p
erm
anen
t fa
ults
[fa
ults
/a]
.
Other
Unknown
Structural fault
Erroneous operation orinstallationIncautiousness, externalpersonsIncautious tree falling
Animals
Other weather conditions
Wind and storms
Trees falling because ofsnow loadSnow and ice loads
Thunder
Figure 3.8. Examples of the causes of outages experienced by electricity end-users in an example
distribution company.
Similar statistics on the causes of interruptions are compiled in most European countries
(CEER, 2008). This information is important for the regulators and is essential to enable
distribution companies to improve the continuity of supply.
3.4. Climate change
Climate change has had and will have a strong influence on electricity distribution. All the
effects are not known yet; however, the most obvious effects are an increase in extreme weather
phenomena such as storms and increased snow loads (European Commission, 2005). The
blackout risk caused by storms will be discussed in more detail later in this section. In addition,
the temperature increase will have an effect on electricity distribution business and pricing, as
50
the consumption of energy will decrease. The temperature increase will also result in longer
growing periods, which in turn will increase the need for pruning and cutting of trees in
overhead line networks. Measured both by extreme and average values, the temperatures will
increase both in summer and in winter (FMI, 2009a; 2009b). Although there will be an average
increase in temperature, it is also likely that the range of extreme temperatures will be wider.
This would also mean higher requirements for design powers on the electricity networks. Yet
another factor that has a strong impact on overhead networks is an increase in such weather
conditions in which the temperatures lie around zero degrees Celsius, which increases the
occurrence of severe snow loads on the distribution network. Milder winters will affect the
thickness of ground frost, which may cause unexpected problems for instance to guyed poles in
overhead networks.
Precipitation is predicted to increase in Finland, which softens the soil and reduces the strength
of ground. Soft soil hampers the use of equipment required in the maintenance and construction
of power lines. Further, because of soft soil, especially trees growing on hill slopes may fall
more easily on overhead lines. The possible rise in ground water level has an impact on
underground cabling, as the cables may not be able to withstand the stress caused by a
continuous contact with water. As a result of the rising ground water level, the electrical
conductivity of soil increases, thereby increasing also the risk of corrosion in the guy structures
of poles. Moreover, as a result of heavy rain, floods in cities are possible, if the rainwater
drainage system does not manage to remove water from the streets. In such situations, there is a
danger that water gets into the basements of buildings and causes damage to basement
distribution substations. Floods in cities may also damage underground cable networks and
distribution cabinets.
On the basis of the observed and predicted climate changes, we may state that the expenses of a
distribution company will increase while the income will decrease. However, regional
differences between distribution companies may be significant. In Finland, the temperature rise
caused by climate change is estimated to affect electricity consumption as shown in Table 3.3.
51
Table 3.3. Effect of temperature on energy consumption and peak power, 2016–2045 (Martikainen, 2005).
Change in electricity
consumption [%]
Change in peak power
[%]
Customer group
minimum maximum minimum maximum
Agriculture -1.7 -3.2 -4.4 -6.6
Residential, dual heating -3.4 -6.1 -6.8 -10.1
Department stores and shopping centres 0.5 1.2 0.0 2.4
Hotel and accommodation services -1.5 -2.8 -4.1 -6.1
Restaurants and cafés 0.2 0.6 0.0 2.2
Financial institutions and insurance companies 0.4 0.8 0.0 2.1
If the demand for energy decreases in the Nordic countries as a result of the temperature rise,
the change will sooner or later also have an influence on transmission pricing structures of
distribution companies. As a response to extreme weather phenomena (hot weather, severe
frost), it may be necessary to dimension the distribution network in a way that is
disadvantageous to power distribution, which may lead to an emphasis on standard tariffs in the
tariff structures.
3.5. Environmental issues
Considering environmental issues, the use of impregnated wood in network construction has
been a topic that has received most attention in recent years. In Finland, impregnated wood has
been commonly used in the construction of overhead lines (the proportion of wood poles of all
impregnated wood products is shown in Figure 3.9). The popularity of wood poles has been
explained primarily by their low cost compared with the concrete and steel poles common in
Central Europe. Another reason for the large-scale use of wood poles is their good insulation
capacity against atmospheric overvoltages. In Finland, a new act became effective in 2002
adding impregnated wood to the list of hazardous wastes. As a result, all treated wood, wood
poles included, is regarded as hazardous waste, the disposal of which has to be carried out in
compliance with the regulations concerning hazardous waste. The regulations focus on CCA
preservatives (Chrome Copper Arsenic), which exited the markets permanently in 2006. In
Finland, 70 % of the industrially treated wood still in use has been impregnated with water-
based salt preservatives (C and CCA), and about 29 % with creosote oil. For creosote the
situation remains unresolved, and the use of creosote will probably continue until further notice.
52
0
50 000
100 000
150 000
200 000
250 000
300 000
350 000
400 000
450 000
500 000
1960 1963 1966 1969 1972 1975 1978 1981 1984 1987 1990 1993 1996 1999 2002 2005
Pre
ssur
e im
preg
nate
d w
ood
[m3 ]
Sleepers
Poles
Sawn timber
Figure 3.9. Production of pressure impregnated wood in Finland in 1960–2007 (Kestopuu, 2009).
The environmental effects of transformer oil are emphasised in areas where the transformer
substations are located in groundwater areas. Although the probability of transformer failure
and escape of oil is very small in groundwater areas, the authorities have requested for
compilation of protective action plans. Alternatives and additional structures suggested for
traditional transformer structures are construction of an oil catchment tank, placing a control
blanket into the ground, replacing an oil-insulated transformer with a dry-type transformer, or
replacing conventional transformer oil with an environmentally friendly oil.
At present, magnetic and electric fields do not seem to constitute a significant problem in
electricity distribution networks. The maximum values for exposure to electric and magnetic
fields are 5 kV/m for and 100 µT, respectively. In distribution networks, the values for electric
and magnetic fields are typically < 2 kV/m and 3 µT. If these limit values are to be tightened, it
may prove difficult to meet the requirements in some cases in urban networks, where the
distribution substations are placed in the basements of residential buildings.
The use of sulphur hexafluoride (SF6) in electricity transmission and distribution has been under
threat for some time already. Although SF6 is an extremely ”strong” greenhouse gas, its use has
not been restricted so far, because the minor emissions in the field have been considered
insignificant from an environmental point of view. However, the operators are conscious of the
53
problem and have been taking various actions either to abandon SF6 and to find some other
alternatives such as vacuum switchgear.
In the future, landscape issues will gain importance. Solving questions related to land use will
be more and more time consuming, as the land owners have negative attitudes towards
construction of overhead lines and substations on their property. Underground cabling, instead,
is seen in more positive light. Hence, this creates incentives for wider-scale adoption of
underground cable alternatives in network construction.
3.6. Risk of blackouts
Climate change has raised the question of an increase in severe weather phenomena. Such
extreme weather phenomena may cause a large-scale blackout in the overhead line networks.
Recent years have witnessed some severe storms both in Finland and abroad. In 2005, the storm
Gudrun caused major damage to the electricity distribution infrastructure in Sweden; according
to the statistics, the storm damaged over 20 000 km of power lines. Although such massive
damages are less likely in Finland, the network operators have to be aware of the risk of
blackouts and prepare for large-scale supply interruptions both by network technology and at
the level of organisation. The large overhead networks in rural areas in particular are vulnerable
to blackouts. There have been attempts to reduce the risk of blackouts by preparing various
contingency plans. To this end, distribution network operators are required to devise a
contingency plan that is approved by the authority. A blackout is defined as an electrical power
failure, during which more than 20 % of the end-customers are left without electricity supply or
there is a sustained fault (several hours) in a primary substation or a main transformer. A
contingency plan shall include action plans for the distribution network, the personnel and the
organisation, which will be followed through on the occurrence of a blackout. The contingency
plan also includes a description of situations for which the operator prepares (risk analysis) and
objectives at which the plan is targeted. The objectives may differ between distribution
companies operating under different conditions; in large, densely populated urban areas and
cities, the target may be 100 % backup capacity, whereas in rural areas, the target may be set at
70 % (of the peak load). In rural areas, also longer target values can be accepted for restoration
times compared with those for large urban areas. On the occurrence of blackouts, the network
54
operator shall report the actions taken; on the basis of these reports, the Energy Market
Authority will be able to assess how the distribution company has met its obligation to develop
its operations.
The focus of the contingency plan has primarily been on providing the resources for fault repair
as efficiently and fast as possible. In the long run, the risk of blackouts can be reduced by
modifying the network structure and topology: by increasing the proportion of underground and
overhead cables in medium- and low-voltage networks and by replacing pole-mounted
distribution substations with kiosk substations. In the regulation, economic incentives for
preparing for blackouts are realised through the compensation system, according to which the
electricity users are entitled to financial compensations if they experience interruptions that
exceed 12 h (Electricity Market Act). The compensation that the distribution system operator
has to pay depends on the duration of the interruption and the annual system service fee of the
customer. The amounts of the standard compensations of the annual system service were
presented in section 3.3.
Considering the public image and reputation of the distribution companies, it is in the operators’
interest to reduce the risk of blackouts: large and long-lasting supply outages are bad publicity.
Figure 3.10 illustrates the effects of a severe weather phenomenon on the reliability of a
distribution network in a rural area in Finland. A major storm was experienced at the end of
November in 2008 in the operating area of the distribution company Järvi-Suomen Energia Oy.
The weather event lasted over 30 hours. At the worst, over 20 % of the end-customers were
affected by the electricity outage. Development of the faults and the number of end-customers
without electricity during the storm is illustrated in Figure 3.11.
55
Helsinki
Turku
Lappeenranta
LappeenrantaLappeenranta
100 km
Figure 3.10. Example of the effects of a severe weather event on the reliability of a distribution network.
The white line illustrates a network section that is left de-energised as a result of a fault. The total length
of the medium voltage network is over 8500 km.
Because of the unpredictability and complexity of blackout phenomena, taking the risk of
blackouts into account in the network strategy is a challenging task. Furthermore, forecasting
the climate change and susceptibility to blackouts in the future, for instance for 20 years ahead
is very challenging if not impossible. In general, the risk of blackouts can be reduced by
network technology (e.g. underground cabling) and by developing the fault contingency
organisation of the distribution company. In the strategy work, preparing for the risk of
blackouts calls for background information about the previous blackouts in the operating area
with the emphasis on the effects of blackouts and operation of the network organisation. Figure
3.11 presents the temporal effects of the blackout in a distribution company based on the major
storm depicted in Figure 3.10. The figure shows the number of customers left without electricity
supply in a blackout that lasted about two days. The mathematical and techno-economic
modelling of blackouts is discussed in more detail for instance in (Kaipia et al., 2007) and
(Brown, 2009).
56
77
19944
0
10
20
30
40
50
60
70
80
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
23.11.2008 24.11.2008
Num
ber
of fa
ults
in th
e ne
twor
k
0
5 000
10 000
15 000
20 000
25 000
End
-cus
tom
ers
with
out e
lect
ricity
Faults
New faults during therepair work
End-customers
Figure 3.11. Development of the number of customers left without electricity supply during a blackout
(Lohjala, 2009).
Figure 3.11 illustrates the curve form typical of blackouts: first, the numbers of faults and end-
customers without supply are fast increasing; then, after peaking, the number of end-customers
without supply reduces first rapidly in proportion to faults cleared, and after that at a
diminishing rate. In the example case, the first effects of the storm were shown on the
distribution network at noon on 23 November 2008. During the first six hours (12–18 hours),
the effects were at their largest; in this time period, almost 20 000 end-customers were left
without electricity. In the following six hours (18–24 hours), the influence of faults could be
limited to 8 000 customers by focusing on faults on the medium-voltage network; this result
was largely due to calming down of the storm and the efficient operation of the repair
organisation. About a day after the storm, only a few hundred customers remained without
supply. The small number of customers without supply is explained by the fact that the faults in
the medium-voltage network had been repaired already and the repair activities were focused on
low-voltage networks. Depending on the scope and strength of a storm, this ”tail” owing to the
repair operations in the low-voltage networks can become very long; for instance, in the storm
Unto, the last faults on the low-voltage network were repaired five days after the storm had
started. This tail (duration of repair work) can be cut by the choice of low-voltage network
components, such as underground cabling.
57
In Finland, standard compensations paid to end-customers between 2005 and 2008 amounted to
6.6 M€, as shown in Figure 3.12 (EMA, 2009b). During this period, the number of distribution
companies paying standard compensations has varied between 18 and 29. The average
compensation has been 44–64 €/customer,a depending on the year. When the standard
compensations paid to the customers are divided equally between the distribution companies
paying these compensations, the average compensation becomes 0.7–4.7 €/customer,a. The
compensations proportioned to the network length (MV + LV) have varied between 1.4 and
10.4 €/km,a. The highest standard compensations in proportion to the network length have been
102 €/km in a single distribution company in a year. The figure illustrates the numbers of end-
customers entitled to standard compensations in each year. The figure shows that although more
compensations were paid in 2006 than in the previous year, the number of customers entitled to
compensations was smaller.
0
500 000
1 000 000
1 500 000
2 000 000
2 500 000
3 000 000
2005 2006 2007 2008
Year
Sta
nd
ard
co
mp
en
satio
ns
[€/a
]
0
10 000
20 000
30 000
40 000
50 000
60 000
Nu
mb
er
of c
ust
om
ers
Over 120 hours
72-120 hours
24-72 hours
12-24 hours
Number of customers
Figure 3.12. Standard compensations paid to customers in Finland in 2005–2008.
In the last two years, the standard compensations have been considerably lower than in the first
two years; however, it is not possible to give a reason for this because of the relatively short
time period of standard compensations paid in Finland.
58
3.7. Scarcity of resources
An emerging challenge for distribution companies is the retiring personnel and disappearance of
tacit knowledge and know-how. The electricity distribution sector has for a long time been
characterised by a high average age of the workforce; the field has not managed to attract young
skilled people similarly as for instance the electronics industry. On the other hand, over the past
years, distribution companies have sought cost efficiency by cutting personnel expenses, which
has reduced the number of young workers, both electricians and planning staff. An analysis of
the personnel age structure and the ageing network infrastructure raises a justifiable concern
about how to meet the challenges related to the future extensive network renovations. Although
there are more and more external service providers available both in the construction and
planning industry, these alone cannot meet such a massive need for labour in the entire field in
the near future. There are already signs of the increased retirement of personnel both in Finland
(Adato, 2009) and abroad (Lave et al., 2007) and (Wijnia et al., 2006).
0
5
10
15
20
25
- 19 20-24 25-29 30-34 35-39 40-44 45-49 50-54 55-59 60-
Personnel age group
Per
cent
age
[%]
2001
2002
2003
2004
2005
2006
2007
Figure. 3.13. Age distribution of personnel in electricity distribution and district heating companies in
2001–2007 (Adato, 2009).
Key questions are which of these operations will be organised in-house and which will be
outsourced. Before answers can be found to these questions, it is necessary to define the
essential functions and operations on which the business of the company is based and which
constitute the company’s core competences. Obviously, work done by human labour will be
59
more expensive in the future. This encourages to adopt network automation and other solutions
that reduce the dependency on human resources.
3.8. Increase in material and labour costs
Large renovation investments taking place in the distribution network companies and the
simultaneous strong growth in Asia have an influence on the availability and price of materials
(cables, transformers) and labour. This forces to extend the timetable of investments, and on the
other hand, to find alternative structural solutions. The recent price development in the
construction industry can be illustrated by the building cost index as shown in Figure 3.14.
Total index
Labour
Other inputs
Materials
Rel
ativ
e va
lue
Total indexMaterial
Labour
Other i
nputs
Figure. 3.14. Development of building cost index in 2000–2009 (Statistics Finland, 2009).
The latest financial crisis may promote network renovations as resources are released from the
slowing building and dwelling production to the construction of basic infrastructure. The
current recession is also shown by decreased sales in the distribution network companies; this
trend, however, makes it possible to direct resources to network renovation targets. On the other
hand, closing down production units makes the implementation of large renovation projects
more difficult because of arising material acquisition problems.
The increase in labour costs is reflected both in the network construction technologies and in
the price differences between different technologies. In the field, labour costs will gain even
more significance in years to come. The phenomenon manifests itself in particular in the
juxtaposition of underground cables and overhead lines. Compared with underground cabling,
60
construction of traditional overhead lines requires more labour for maintenance and repair of
the line structures. The current increase in labour costs together with the downward-sloping
trend of underground cabling costs promote the penetration of underground cabling into
network renovation projects (Figure 3.15).
UNDERGROUND CABLING
OVERHEAD LINE CONSTRUCTION
TIME
INV
ES
TM
EN
T C
OS
TS
Finland Sweden
Figure 3.15. Development of overhead line and underground cable construction costs.
The above-described quality incentives from the regulation of electricity distribution network
business and the factors related to the risks of blackouts also speak for more extensive use of
underground cabling in distribution networks.
3.9. Energy policy
The national and international energy policies create various drivers also for the electricity
distribution business. Energy efficiency, distributed generation and reduction of dependency on
oil are key issues in the international energy policy. Some definitions of policy and targets set
by the EU are given below (European Council, 2007).
Energy must be sourced as diversely as possible
Energy must be sourced as diversely as possible. This promotes competition in the energy
market and improves reliability and ability to survive on the occasion of disturbances. Therefore
it is of high importance that no form of energy generation is excluded from the consideration.
61
Considering the development of electricity distribution networks, the above may result in an
increase in distributed generation and smaller generation units on the distribution networks. In
the future, the networks have to be designed so that the possible small hydro power plants can
be more easily connected to the electricity distribution system. This may pose a challenge
especially in rural areas, where the transmission capacity is usually limited because of small
loads on the network. As a result of these future changes, network protection issues will also
become more complicated.
Climate change will be mitigated with emissionless sources of energy
Climate change can best be mitigated by using emissionless sources of energy, such as nuclear
energy and renewable energy, and by improving energy efficiency. To this end, it is necessary
to provide for the conditions for production of emissionless sources of energy. The
competitiveness of renewable energy sources has to be promoted by research and development
activities. When promoting the use of bio-based energy in the industry, it has to be ensured that
the acquisition of raw material at a competitive price is not endangered.
Considering the development of electricity distribution networks, special attention has to be
paid to fields that provide potential application areas for instance for small-scale hydro power.
Increase in the cost of energy should be curbed
Cost of energy can also be influenced by efficient use of energy. A challenge will be to find
suitable incentives to encourage all energy users to improve the energy efficiency of their
operations. The energy efficiency of enterprises, which is already at a good level, is best
promoted by energy-efficiency contracts.
In electricity distribution network operations, energy efficiency aspects are reflected in the
selection of conductor cross-sections and transformer structures. At the power system level,
answers are sought from DC distribution, where the present transformer structures could be
replaced by power electronics components. This would reduce the dependency on transformer
62
construction materials, the prices of which are increasing, and cut losses in the low-voltage
network.
In March 2007, the Council of Europe defined energy efficiency as a key issue in the energy
and climate change strategy. The Council set a target to reduce energy consumption by 20 % by
2020. The EU Directive on energy end-use efficiency sets out an obligation to save 9 % of final
energy by 9 % by 2016 (European Council, 2007).
3.10. Distributed generation and smart grids
The impacts of distributed generation on electricity distribution business will be significant in
the future. In the past few years, substantial sums of money have been invested in research on
distributed generation. Potential forms of generation that will have an influence on distributed
generation are fuel cell technology, wind power, solar and bio-based energy and diesel power.
Fuel cell technology as a source of energy in every home would radically change electricity
distribution. For the time being, the technology is not an economically feasible solution yet.
Wind power is gaining ground especially in coastal areas and open mountain regions. In
distribution networks, wind power has chiefly cost-increasing effects. Solar power instead has
no direct impact on distribution networks. Bio-based energy may reduce the need for energy
transfer, while the need for power transmission will remain. The use of bio-based energy may
increase considerably in the years to come. Considering hydro power, the situation is more
established, as the capacity available has in practice been harnessed already. The use of diesel
power as backup power is increasing.
Although no significant breakthroughs have been made in distributed generation, the general
technology advancements may make distributed generation an essential element in distribution
systems. Electricity distribution network will then function as a genuine marketplace for energy
generation and use (Figure 3.16). Every electricity user will be able to participate in the markets
by reducing power consumption by an agreed amount at a defined moment, and obtain as
income a sum proportioned to the difference of the market price and the user’s contract price.
63
Figure 3.16. Principle of a smart grid (European Commission, 2006).
An increase in distributed generation has to be taken into account in network dimensioning, and
in particular, in protection arrangements and automation. For the time being, distributed
generation plays only a minor role in electricity distribution networks, and is therefore outside
the scope of this work.
3.10.1. Smart grids and electric cars
The character of transport and energy use is radically changing along with the upward trend of
electric cars. This creates a challenge to the existing electricity distribution infrastructure.
Depending on the electric car charging method, the peak load may increase considerably on the
distribution network. This means additional investments in larger cross-sections of underground
cables and overhead lines and more transformer capacity. Several analyses have been made to
investigate the network effects of additional charging power. Figure 3.17 illustrates a simulation
example of the effect of the vehicle charging load on the loading of a medium-voltage feeder in
four different charging alternatives (Lassila et al., 2009a).
64
0
1
2
3
4
5
6
7
8
9
10
0 2 4 6 8 10 12 14 16 18 20 22
0
1
23
4
5
6
78
9
10
0 2 4 6 8 10 12 14 16 18 20 22
0
1
2
3
45
6
7
8
9
10
0 2 4 6 8 10 12 14 16 18 20 220
1
2
3
4
5
6
7
8
9
10
0 2 4 6 8 10 12 14 16 18 20 22
Direct night-time charging Split-level night-time charging
Optimised charging
20 kV feeder
(densely populated area)
- Peak load of the day: 6.6 MW
- Minimum load of the day: 4.0 MW
- Number of electric cars: 2000
- Driving distance: 57 km/car,day
- Energy consumption: 0.2 kWh/km
- Charging energy: 11.5 kWh/car,day
� 22.9 MWh/day for all cars on the feeder
- Charging power: 3.6 kW/car
- Additional power on the feeder: 0–3.5 MW
(depending on charging method)
Charging energy (E) is equal in each charging alternative.
Pea
k p
ow
er [
MW
]
Working-hour and time-off charging
EE
Figure 3.17. Four vehicle charging models for a feeder in a densely populated area. In each figure, the
lower curves (black) represent the existing peak load, while the upper curves (blue) represent the load
when the charging power is taken into account (Lassila et al., 2009a).
The amount of investments required can be estimated by defining the average marginal cost of
the network. It is based on the network replacement value and the maximum load of the year,
and it describes how much the network capacity has cost for the distribution company per each
peak load kilowatt. In the example network of Figure 3.18, the network value compared with
the peak load is 320 €/kW in the low-voltage networks, 300 €/kW in the medium-voltage
networks and 100 €/kW at the primary substation level.
The additional network investments are paid by the end-customers. Because the replacement
value of the case network is 50 M€ (2.9 M€/a calculated by p = 5 % and t = 40 a) and the
annual delivered energy in the distribution company is 200 GWh, the network value per
delivered energy is 1.46 cent/kWh. The estimated additional annual charging energy required
by electric cars would be 46 GWh (11 000 cars, 20 900 km/car,a and 0.2 kWh/km,car).
Depending on the charging method and the voltage-level-specific analysis of the increase in
power, a rough estimation of the required investments in a new transformer and transmission
capacity in the whole distribution network would be 0–20 M€ (0–1060 k€/a), which equals 0–
1800 €/customer. The new distribution fee would be 1.18–1.66 cent/kWh after the network
reinforcement. This fee range shows that when the peak power of the network increases more
than the delivered energy, the distribution fee will increase. If the additional charging load has a
slight effect on the peak power, it is possible to cut the distribution fees.
65
3.11. Technology development
The above issues constitute the major challenges for the present electricity distribution business.
From the perspective of business, in addition to challenges, considerable advancements have
also taken place, for instance related to information systems and network technologies. The
most significant steps forward have been the AMKA aerial bundled cables introduced in the
1960s to replace bare low-voltage overhead lines, the remote operation systems taken into use
in the 1970s, network data management systems and remote-controlled disconnectors in the
1980s and the distribution management systems for distribution systems in the 1990s (Figure
3.18).
1950 1960 1970 1980 1990 2000 2010
Electrification of rural areas
Remote-controlled network systems
Remote-controlled disconnectorsNetwork information systems
Distribution management systemsFault location function
Organisational changesService providers Renovation of distribution networks in rural areas
Market liberalisationSupervision of distribution companies
Aerial bundled cables (AMKA)
Underground cabling in medium-voltage networks in rural areas
Figure 3.18. Development of electricity distribution business and significant advances in the field.
3.11.1. Network data systems and management of information
Electricity distribution companies in Finland are generally becoming more dependent on data
systems such as the GIS-based network data system, SCADA, and the distribution management
system. As a result of an expanding use of real-time metering points and advanced network
automation in distribution networks, the total amount of available real-time network status
information to be processed and analysed by distribution companies is growing. This
development trend on the one hand is setting the road for service providers specialised in
collection and analysis of network data, but on the other hand, new competence requirements
are set for the distribution companies. All in all, the network operation function is becoming a
strategically important knot within the management and sharing of network data.
Fully digitalised medium- and low-voltage networks require the use of special tools such as a
distribution management system. The role of reporting is becoming central especially towards
the energy authorities regarding the reimbursement proceeding and the end-customer service as
66
a part of fault management. In this sense, the distribution companies will be increasingly
dependent on network databases and their maximum use of capacity in the future (Brådd et al.,
2006).
3.11.2. Development of materials, working methods and automation
The increasing needs for improved reliability, lower operational costs (reduction in the need for
human resources) and better access to detailed network information create incentives for
development of materials, working methods and network automation.
Underground cabling
The high price of underground cabling limits the larger-scale use of cables in network
construction. The construction of a medium-voltage cable is particularly expensive. Nowadays,
underground cables are chiefly installed by applying excavation technology, and the cable itself
is notably more expensive than for instance a low-voltage cable. Therefore, preconditions for
wider utilisation of underground cabling are the development and application of lower-cost
cabling methods. Cost savings can be achieved by developing the cable structures, by using
low-voltage cables instead of medium-voltage cables (utilisation of 1 kV and LVDC
technology) and by developing the cable ploughing methods. Cost components related to
underground cabling are presented in Figure 3.19. The highest pressures are put to reduce costs
at the distribution substations and cabling structures.
For instance 95 mm2
25 €/m
Excavation:
10-15 €/m
Ploughing:
2-4 €/m
Depending on transformer density in the area, for instance
5 €/m
Depending on technology (centralisedor distributed), for instance
1-3 €/m
For instance 500 kVA50 k€/unitCase area 500 km:���� 0.1 €/m
CABLE CABLING RENOVATION OF DISTRIBUTION TRANSFORMER
COMPENSATION OF EARTH FAULT CURRENTS
BACKUP POWER
Figure 3.19. Cost components in underground cabling.
67
Ploughing and excavation of underground cables
Cable ploughing as a low-voltage cable installation method is becoming increasingly common
especially in rural areas. Nowadays, when the circumstances allow it, nearly all low-voltage
underground cables are installed by ploughing. This way, the installation costs can be kept
reasonable; consequently, low-voltage cabling is a more inexpensive solution than the
conventional AMKA aerial bundled cable structures. In rural areas, the overall cable ploughing
costs are in average 50 % lower than the excavation costs of a cable trench alone. The soil
somewhat restricts the potential targets for cable ploughing; nevertheless, ploughing is possible
everywhere except in a very stony or rocky soil. A survey in the area of the distribution
company Järvi-Suomen Energia Oy showed that ploughing is an applicable method in 80 % of
the total low-voltage network. Usually, preferable areas for cable ploughing can be found by the
roadsides and road beds. The ploughing speed depends on the scope of the target; however, it
can be several kilometres a day.
3.12. Summary and conclusions
The strong dependency on the operating environment creates various obligations for the coming
years. In particular, the ageing networks together with the regulation of electricity distribution
business bring challenges to the long-term development of distribution networks. Rather than
challenges, the large-scale renovation needs and the general technological advancement can
also be seen as an opportunity. By adopting new structural solutions in a cost-efficient way, the
renovation can be carried out so that the obligations defined by the authority will be met, and
the asset management in the distribution company develops in a favourable direction. There are
various issues that require the renovation of the network; and most obviously, with other than
the present technology. Table 3.4 presents the most central environmental factors affecting the
distribution network business.
68
Table 3.4. Summary of the effects of operating environment on the distribution network business.
Phenomenon Consequence Remarks
Ageing of networks Renovation needs Opportunity
Regulation Outage costs
Outage cost (KAH) values
Profit
Standard compensations
Reliability criteria
Efficiency measurement (benchmarking)
Lifetimes
Short and long supply interruptions
Minimisation of total costs
Owner policy
Penalty
Development obligation
OPEX limit
Risks
Owner policy Profit target
Pricing target
Reliability target (media)
Investment resources
Quality of electricity Outages through regulation
Voltage dips
Voltage
Backup supplies
Climate change Blackouts
Changes in loading
Weather-proof network
Environment Wood poles, restrictions Competitiveness of overhead lines suffers
Labour costs Construction of overhead lines becomes
more expensive
Underground cabling costs are reduced
Mutual position of overhead lines and
underground cables changes
Distributed generation Bidirectional power transfer Challenge of manageability
Smart grids Active loads and generation Reduction in energy transfer
Cost pressures
Electric cars New load on the network
Energy storage
Energy efficiency
Technology advancement
(1 kV, DC)
Transmission capacity of the low-voltage
network
Mutual position of medium- and low-
voltage networks changes
Decreased load growth Less electrotechnical development needs Age and reliability requirements
emphasised
69
4. Methodology and tools of strategic analysis
Electricity distribution network business is characterised by management and analysis of large
amounts of data. In the development of business activities, statistics covering a long time span
are utilised for instance when analysing the development of costs and reliability of electricity
supply. In (Grünig and Kühn, 2006, p. 53) “the main emphasis is on data collection in three
fields; global environment, specific task environments or industries and the company itself.” ---
“In practice, it is often difficult to determine the scope of strategic analysis; at this stage in
strategy development we do not yet have a clear view about the target market positions and
competitive advantages. Therefore we do not know what information we will need. For this
reason there is the danger that a large amount of data will be gathered which will later turn out
to be irrelevant to decisions being taken. This must be avoided, because strategic analysis is a
particularly expensive undertaking.”
Figure 4.1 illustrates the diversity of the operating environment and network company
operations especially from the viewpoint of asset management and information flows. A
successful network strategy calls for commitment of all parties to the collection of data. Single
information sources and stakeholders in the process constitute a foundation for the practical
strategy work. The figure does not depict all the actors and information sources required in the
development, but serves as an example only.
70
NISNIS
LTPLTP
Trends and guidelines for the long-term network development and information management
Asset management
Network operation
• Load development and historic data• Outage statistics• Network switching times (fault
isolating) and alternatives
• Interest rates• Valuation of losses• Component lifetimes and age
distribution• Outage cost parameters• Pricing of components and work,
cost development
Network construction
Maintenance and fault repair
Network planning
• Present state of the network (loads, power losses, voltage drops, backup supply considerations)
• Maintenance and fault repair costs• Fault repair times• Empirical data on components
• Actual cost of network construction• Actual application potential of different network
technologies• Soil properties (cabling)
Research and consulting• New network technologies• Analysis models and tools• Utilisation of the experiences of
other actors in the field
LONG-TERM PLANNINGTarget group and information flows
Society• Land use planning, growth forecasts• Land use options• Finnish Meteorological Institute: climate, weather• Environmental office and ground water areas
Figure 4.1. Targets, information flows and stakeholders in the operating environment of a distribution
company.
“Correctly understood and unbureaucratically applied strategies will generally increase the
quality of daily operational decision-making. Strategies used as management tools can help to
prevent companies from slipping into competitive positions and markets which offer little hope
of success” (Grünig and Kühn, 2006, p. 17).
As the network operations are increasingly turning towards service production, it is necessary to
guarantee uninterrupted information flows between the distribution company and service
providers (Lassila et al., 2009c). The situation may prove very challenging especially if the
network planning and operative functions (network management) are to be unbundled. Now
there is a risk that the targets and actions defined by the company owners for the network
development are not conceived in the same way at all levels of network planning and operation.
71
The survey of the operating environment presented in Chapter 3 may reveal new issues that
oblige the company to draw up or update a development strategy and to radically renovate the
distribution network. The needs of society, technical solutions and development methods have
evolved in the course of time to such an extent that it is no longer either economically or
technically feasible to carry out renovation according to the traditional principles. Because of
the long lifetimes of network investments, the operating environment data have to be taken into
account as extensively as possible in strategic decision-making. The structural choices made
today will at best or worst be visible in the distribution systems for half a century. So far, major
changes in the policy have been avoided either consciously or unconsciously, or changes have
been postponed by concentrating for instance on replacing wood poles instead of making more
radical changes in the network structure or topology. Taking into account the essential needs for
changes (Chapter 3) in network development requires an in-depth analysis of the following
issues.
- Which are the most compelling factors driving network renovation (network age,
reliability, ownership issues, pressure from society)?
- What network development alternatives are there; what is their techno-economic potential
in the company’s area of operation?
- What are the long-term cost and reliability effects of different development methods?
- What background information, calculation parameters and methods are used in the
strategy process?
- What are the owners’ objectives, and what are the opportunities and tools provided by the
owner(s) for network development (return expectations, investment in network
development)?
Finding answers to the above questions calls for an adequate and covering analysis of the
operating environment but also development of various analysis tools and calculation
methodology as well as interactive discussion with the network owners. The process is
challenging and time consuming, but necessary in order to find cost-efficient solutions.
This analysis related to the above questions can be referred to as ‘strategic analysis’ or ‘strategy
process’.
72
4.1. Drivers of the strategy process
In the network strategy work, the focus is on defining the most critical needs that require and
direct network renovation. The reasons for large-scale renovation can be found among the
environmental factors described in Chapter 3, such as the age of the network, poor reliability,
changes in the owners’ objectives, development of the needs of society or changes in
legislation. Figure 4.2 sums up the most essential reasons, or drivers, for network renovation.
The dashed line illustrates the cross effects of authority operation.
Reliability of networks
Network renovation
needs
- Increase in fault rates- Threat of climate change- Risk of blackouts- Public image of the company
Owner
- Return expectations (asset management)- Public image of the company- Reliability and quality of electricity- Susceptibility to blackouts (standard
compensations)- Environmental regulations (e.g.
preservatives) - Maintenance of human resources, skills
and knowledge- Development in the operating area (loads)Load development
- Insufficient distribution and transformation capacity
- Tighter requirements set by owners and authorities e.g. from the aspect of backup power situations
- Development needs in declining areas
Authority
- Obligation to develop the network (Electricity Market Act)
- Threat of reduced return- Tightening distribution reliability criteria
and entry of outage costs - Public image of the company (e.g.
efficiency benchmarking)- Susceptibility to blackouts
(standard compensations)- Environmental regulations (e.g.
preservatives) - Increase in the weight of operational costs
(has an effect on selection of network structures, e.g. automation issues)
- Electrical and occupational safety requirements
New technologies
- Renovation can be carried out cost efficiently
- Investment, operating and outage costs can be affected
- Amount of automation can be increased (has an effect especially on operating and outage costs)
- Risk of blackouts can be reduced byunderground cabling
Network age and condition
- Distribution network reaching its lifetime- Has a strong impact on allowed return - Electrical and occupational safety aspects
Resources
- Increasing shortage of labour?- National and global shortage of materials
and increase in prices- Simultaneous renovation needs
everywhere
Figure 4.2. Drivers for network renovation.
There is seldom only a single reason for network renovation. For instance, in network areas
suffering from poor reliability, the high network age and poor mechanical condition may be
reasons for renovation. In large-scale network renovation, some compromises may also be
necessary. Although the age or reliability of the network do not necessarily require any actions,
shortage of distribution capacity may force to renovation. This may lead to renovation of such
network sections, the age of which does not call for renewal yet. Such situations have to be
evaluated case by case, as replacing network components in the middle of their lifetime reduces
the efficiency of operations and increases costs.
73
4.2. Network technologies and potential surveys
As described above, the reasons for large-scale distribution network renovation can be diverse.
Once the need for renovation has been recognised, different renovation methods suitable for the
areas of operation are determined. Depending on the initial situation, the targets for the
renovation may be to improve the age structure of the network to ensure better return, or to
make the distribution network completely immune to adverse weather phenomena. For the
evaluation of the feasibility and strategic value of different network technologies, it is essential
to know how much economic potential there is for the technology in question in the operating
environment. Even a network technology and development solution that could be economically
adopted to the system may be strategically irrelevant if the number of economically feasible
targets is marginal in the distribution network.
The possible boundary conditions set for the network for instance with respect to reliability may
rule out some development technologies. Similarly, boundary conditions set by the operating
environment, such as a high forest rate or restricted amount of land suitable for underground
cabling may limit the number of technical structural solutions available. In the following, some
development technologies that are feasible in the Nordic distribution operating environments
are introduced and discussed. For each technology introduced, it is described how the techno-
economic feasibility of the technology can be analysed. Typical network technologies available
are transfer of overhead lines to roadsides and replacement of lines with covered conductors
(plastic-covered conductors), overhead and underground cabling, circuit reclosers, primary
substations, suppression of earth fault currents and the 1000 V low-voltage technology.
4.2.1. 1000 V low-voltage technology
An example of a novel electricity distribution technology and a techno-economic potential
survey is the 1000 V low-voltage technology. Since 80–90 % of the outages experienced by
end-users result from faults in the 20 kV medium-voltage network, the reliability of electricity
distribution can be considerably improved by reducing the size of supply sections and thereby
the areas of influence of faults. The technology is particularly applicable to rural areas, where
medium-voltage networks typically include a lot of branches; in these areas, the powers are
74
relatively low and reliability poses challenges to the system (Kaipia, 2004), (Lohjala et al.,
2004), (Lohjala, 2005) and (Lohjala et al., 2005). In such places, the 1000 V system can be used
to economically replace medium-voltage branch lines of a few kilometres. As the 1000 V
system constitutes a protection zone of its own, the length of the medium-voltage network will
decrease and the reliability of electricity distribution in the area will improve. The potential
surveys made for Nordic distribution companies have shown that up to 40 % of the total length
of the medium-voltage networks could be replaced with the 1000 V low-voltage technology
when the system is renovated for the next time. Considering the financial value of the medium-
voltage networks in the distribution network business as a whole, we may state that the 1000 V
technology has significant economic potential.
Targets on a MV feeder
Economically feasible area
Figure 4.3. Feasibility study of the 1000 V technology. In the area between the curves, the lifetime costs of
the 1000 V technology are lower than the costs of the conventional technology. The dots indicate real
network line sections (Lohjala et al., 2005).
The feasibility curves plotted in Figure 4.3 are based on principles given in (Lohjala, 2005). The
upper limit of the techno-economic range of use is defined by the maximum allowed voltage
drop in the system. The lower limit is defined by the differences in investment, operation,
maintenance and outage costs between the 1000 V technology and the conventional network
construction method. The economic feasibility of the 1000 V technology relies strongly on
outage cost benefit, which in turn depends on the target area; that is, whether the technology is
used for feeders in urban or rural areas. All in all, there are significant incentives to apply the
1000 V technology in the Nordic operating environment. When appropriately applied to the
75
network strategy, the 1000 V would improve the cost efficiency of investments and quality of
supply experienced by the end-customers. The cost efficiency benefit of an investment is
manifested in particular when overhead lines are replaced with underground cables, and
alternative solutions are sought for costly medium-voltage underground cables.
4.2.2. Circuit recloser
A circuit recloser improves the reliability of network by increasing the number of protective
zones in the network. From the end-user’s perspective, the number and duration of faults
decrease as the faults occurring before the recloser are not shown to the customers at the
substation end of the feeder. The benefit reached depends on the network length downstream
from the circuit recloser (number of faults) and the number, type and energy consumption of the
customers before the recloser. The benefit reached with the recloser can be analysed with the
example of Figure 4.4, where the power of a single medium-voltage feeder is P and the total
length of lines is l.
P
l
Figure 4.4. Schematic of a circuit recloser on a medium-voltage feeder.
Now the outage cost is proportional to the power and line length P*l. It is assumed that the
loads and faults are evenly distributed on the feeder. The recloser is placed on the feeder so that
the power and line length both up- and downstream from the feeder are equal. The outage cost
of the feeder is proportional to the sum
PllPl
P ⋅=⋅+⋅ 43
222 (4.1)
Thus, the outage costs are reduced by 25 % compared with the initial state. In an actual
distribution network, typical questions are: a) on what conditions is a circuit recloser
economically feasible, b) in the case of a single circuit recloser, where is the best location of the
circuit recloser and c) in the case of several circuit reclosers, which are the best locations for the
76
recloser. In the optimisation task, a further challenge is provided by the fact that the loads and
faults are not evenly distributed on the feeder.
The techno-economic feasibility of a circuit recloser can be determined based on the acquisition
cost, fault rate and power demand of the customers in the target area. Equation (4.2) determines
what is the magnitude of power demand in the network section protected by the circuit closer
required for the circuit recloser to be economically feasible. The equation takes into account the
outage cost benefit for the customers before the circuit recloser in proportion to the annuity of
the recloser investment.
[ ])(
)1(1)(
dfault,operationnfault,faultDARDARHSARHSAR
INV
ctcncncnx
Cp
p
xPt
⋅+⋅+⋅+⋅⋅
⋅+−
=−
(4.2)
P = power demand
p = interest rate
t = reference period
CINV = investment cost of the circuit recloser
x = length of the network after the circuit recloser
nHSAR = number of high-speed reclosings (HSAR = high-speed autoreclosing)
cHSAR = unit outage cost of a high-speed reclosing
nDAR = number of delayed autoreclosings (DAR = delayed autoreclosing)
cDAR = unit outage cost of a delayed autoreclosing
nfault = number of long supply interruptions
cfault,n = unit outage cost of long supply interruptions (number)
tOperation = disconnection time of a faulted section
cfault,d = unit outage cost of long supply interruptions (duration)
Equation (4.2) can be illustrated by the example curve of Figure 4.5, where the feasibility limit
of the circuit recloser is given as a function of network length after the recloser and the power at
the substation end of the feeder.
77
0
200
400
600
800
1 000
1 200
0 5 10 15 20 25 30 35 40
Mea
n lo
ad o
f the
feed
er b
etw
een
supp
lyin
g en
d of
the
feed
er a
nd th
e ci
rcui
t rec
lose
r [k
W]
Techno-economic feasibility curve for a circuit recloser-
+
Network length downstream from the circuit recloser [km]
Figure 4.5. Techno-economic feasibility curve for a circuit recloser.
Cost calculation related to the position of the circuit recloser can be illustrated with the
following example. Here, the target of analysis is a medium-voltage overhead line feeder that is
experiencing reliability problems owing to the structure and location of the line. The reliability
of the network can be improved and outage costs can be reduced by limiting the most
vulnerable network section to constitute a protection zone of its own. In our example case, there
are four alternative positions for the recloser, shown in Figure 4.6. The target is that faults
occurring in the network section downstream from the circuit recloser will not be seen by the
customers in the network section before the circuit recloser.
3) ?
2) ?
1) ?
Feeder 1
Feeder 2
4) ?
Sustained faults: 5 pcs/100km,aHigh-speed ARs: 51 pcs/100km,aDelayed ARs: 11 pcs/100km,aReconnection time: 10 minutes
110/20 kV
1422 kW24 km4
1330 kW29 km3
1062 kW34 km2
455 kW36 km1
Mean load of the feeder between supplying end of the feeder and the circuit recloser
Network length downstream from the circuit recloser
1422 kW24 km4
1330 kW29 km3
1062 kW34 km2
455 kW36 km1
Mean load of the feeder between supplying end of the feeder and the circuit recloser
Network length downstream from the circuit recloser
Figure 4.6. Alternative positions for the circuit recloser on a 20 kV feeder 1. The total length of the feeder
is 44 km and the peak power is 4.1 MW.
78
Thus, the feasibility analysis of a circuit recloser is based on optimisation between the
investment cost and the outage cost benefit given by Eq. (4.2). In the calculation of outage cost
an average power is applied, as the moment of occurrence of a fault cannot be exactly
determined. The outage cost benefit depends on the customer distribution in the area. Table 4.1
presents the customer distribution and the weighted outage costs of the feeder.
Table 4.1. Customer distribution and weighted outage costs for the feeder in the example for a circuit recloser (HSAR = high-speed autoreclosing, DAR = delayed autoreclosing).
HS-AR DE-AR Customer
Weighted outage cost parameters
€/kW €/kWh €/kW €/kW sharesResidential 0.36 4.29 0.11 0.48 65 % 0.23 2.79 0.07 0.31Agriculture 0.45 9.38 0.2 0.62 2 % 0.01 0.19 0.00 0.01Industry 3.52 24.45 2.19 2.87 14 % 0.49 3.42 0.31 0.40Public 1.89 15.08 1.49 2.34 3 % 0.06 0.45 0.04 0.07Service 2.65 29.89 1.31 2.44 16 % 0.42 4.78 0.21 0.39
100 % 1.22 11.63 0.64 1.19
Sustained fault HS-AR DE-AR€/kW €/kWh €/kW €/kWSustained faultHSAR DAR HSAR DAR
In this simplified example, it is assumed that the customer distribution (in percent) is equal at
any part of the feeder. In reality, customer distribution may vary considerably between network
sections and the supply area of the distribution transformer. However, it is fairly safe to use the
average customer distribution as a basis in the calculations without obtaining too optimistic
results. This is explained by the fact that considering the outage costs, the most challenging
customers (services, industry and public loads) are typically located closer to the primary
substation, in other words, upstream from the circuit recloser. This is illustrated by Figure 4.7,
which shows the calculated outage costs experienced by the supply area of distribution
transformers of a distribution company during a fault interruption of one hour in relation to the
distance between the distribution transformer and the primary substation. The figure shows that
the largest outage costs occur chiefly in the supply area of distribution transformers close to the
primary substation. Therefore, in reality, the benefit of a circuit recloser is higher than what
would be expected from the calculations based on average customer distribution.
79
0 €
500 €
1 000 €
1 500 €
2 000 €
2 500 €
3 000 €
0 5 10 15 20 25 30
M uunt amon etäisyys sähköasemasta [ km]
Yh
de
m t
un
nin
vik
ak
es
ke
yty
ks
en
k
es
ke
yty
sk
us
tan
nu
s [
€/k
pl]
Distance between the transforming district and the primary substation [km]
Out
age
cost
s ex
perie
nced
by
tran
sfor
min
g di
stric
ts d
urin
g a
faul
t int
erru
ptio
n of
one
hou
r [€
/faul
t]
Figure 4.7. Outage costs experienced by the supply area of distribution transformers of an electricity
distribution company during a fault interruption of one hour in relation to the distance between the
distribution transformer and the primary substation. The outages are limited to 3000 €/pcs to enhance the
readability of the graph.
To explicate the techno-economic feasibility of the circuit recloser, by applying Eq. (4.2), it is
possible to plot a feasibility curve as shown in Figure 4.8. The figure shows that all the four
example locations of the circuit recloser are on the positive side of the feasibility curve. Curves
have been plotted for two different circuit recloser investment costs, 14 k€ and 28 k€. In
practice, the investment cost depends on such issues as how familiar the distribution company is
with the technology and how much has to be invested in information communications
technology in commissioning of the circuit recloser. In the unit price list of network
components for 2009, the price of a circuit recloser was 22,140 € (EMA, 2009a).
80
0
200
400
600
800
1000
1200
1400
1600
1800
2000
0 5 10 15 20 25 30 35 40
Network length downstream from the circuit recloser [km]
Mea
n lo
ad o
f th
e fe
eder
bet
wee
n su
pply
ing
end
of th
e fe
eder
and
the
circ
uit r
eclo
ser
[kW
] 3)+ 23 639 €/a
2)+ 22 130 €/a
1)+ 10 039 €/a
4)+ 20 917 €/a
Investment price: 28 000 €
Investment price: 14 000 €
Figure 4.8. Techno-economic feasibility studies on the selection of a circuit recloser and the calculated
annual savings in outage costs for four alternative locations (investment cost 28 000 €, p = 5 % and
reference period t = 30 a � annuity 1821 €/a).
In the example, the locations of the circuit reclosers are alternatives to each other. The techno-
economic benefit of the use of several circuit reclosers in series cannot be calculated by simply
summing up the benefits of single circuit reclosers. In the feasibility studies, there is a strong
interdependence between the circuit reclosers, similarly as between other investments affecting
reliability. This poses a challenge to the considerations of the development of optimal network
solutions. If the target is to place several circuit reclosers in series on the feeder, it is necessary
to take into account the presence of each circuit recloser when calculating the outage cost
benefit. In promoting a network strategy, advantages of a circuit recloser are its fast
implementation, cost efficiency and adaptability. If the calculations required to define the
optimal position of the circuit recloser and the set values of the control relay have already been
made and the required communications connections are available (e.g. if the circuit recloser is
placed at an existing disconnector substation), the circuit recloser can be installed in a quite
short time. The effects on the quality of supply are immediate and can be seen by a large
number of customers. Adaptability, that is, an opportunity to move the circuit recloser to a new
location, is an advantage especially when a long-term target in the strategy is to change over to
underground cabling, and there is a need to change the position of the circuit recloser at the
interface of the underground cable and overhead line networks.
81
4.2.3. Underground cabling, transfer of lines to roadsides, covered conductors
Pressures put on reliability and, on the other hand, the development of technical structural
solutions have led to a situation where attitudes towards renovation of overhead line structures
are becoming more critical. Underground cabling, transfer of lines to roadsides, or application
of covered conductors serve as alternatives to overhead line renovation. The techno-economic
feasibility of these solutions can be assessed by comparing the long-term investment, operation,
maintenance and outage costs between the solutions. The effects of renovation on the network
reliability are illustrated by the cabling example of Figure 4.9. In the example, the total length
of the network is l and the load P. The loads are evenly distributed along the feeder. Cabling is
carried out for the first half of the feeder.
P
l
fcable= 1 fault/100km,a foverhead line= 10 fault/100km,a
Figure 4.9. Schematic of a medium-voltage feeder with overhead and underground sections.
The outage cost is proportional to the power and line length P*l. With underground cabling, the
fault frequency of the underground section of the feeder reduces and the outage costs will
change compared with the initial situation as follows:
line overheadcableline overhead 22f
lPf
lPflP ⋅⋅+⋅⋅→⋅⋅ (4.3)
If the fault frequency of the cable is selected to be one tenth of the fault frequency in the
overhead line (Figure 4.9), the outage costs will reduce to 55 % of the initial costs (= 55/100).
Equation (4.4) provides a feasibility comparison between medium-voltage overhead and
underground cable networks. The equation is applied to determine the power of the feeder at
which the renovation alternative, the investment costs of which are higher, pays itself back as a
result of improved reliability and lower outage costs, also taking into account the differences in
repair and maintenance costs.
82
( ) numberPl,Pldurationfault,clearancenumberfault,faultDARDARHSARHSAR
repairemaintenancBINV,AINV,
fault
)()1(1
)(cnctcncncn
CCCCp
p
nP
t
⋅∆+⋅+⋅∆+⋅∆+⋅∆
∆+∆+−⋅+−
=∆
− (4.4)
P = power demand
p = interest rate
t = reference period
CINV,A = investment cost of the renovation alternative A (e.g. underground cabling)
CINV,B = investment cost of the renovation alternative B (e.g. overhead line)
∆Cmaintenance = change in the maintenance costs between the renovation alternatives [€/km,a]
∆Crepair = change in the unit prices of repair costs between the renovation alternatives [€/km,a]
∆nHSAR = change in the number of high-speed reclosings
cHSAR = unit outage cost of a high-speed reclosing
∆nDAR = change in the delayed automatic reclosings
cDAR = unit outage cost of a delayed automatic reclosing
∆nfault = change in the number of long supply interruptions
tclearance = clearance time (long supply interruption)
cfault,number = unit outage cost of long supply interruptions (number)
cfault,duration = unit outage cost of long supply interruptions (duration)
∆nPl = change in the number of work outages
cPl,number = unit outage cost of work outages (amount)
Figure 4.10 illustrates example curves for the applicability of underground cabling in the target
area. It is assumed that the overhead line structure has reached the end of its lifetime, and thus,
it is assumed to have no service value after the cable renovation. In Figure 4.10, the x-axis
shows the decrease in fault frequency when changing from overhead lines over to underground
cables (pcs/100km,a). The y-axis shows the peak power of the feeder in question.
83
0
200
400
600
800
1 000
1 200
1 400
1 600
1 800
2 000
2 4 6 8 10 12 14 16 18 20
Joht
oläh
dön
huip
pute
ho [k
W]
Roadside (from 5 � 1 faults/100km,a)Based on long-term statistics:
Fault rate UG cable OH forest OH roadside - Sustained faults 1 10 5 faults/100km,a
- HSAR - 25 14 pcs/100km,a
- DAR - 10 5 pcs/100km,a
- Maintenance 58 153 124 €/km,a
- Fault repair 44 100 60 €/km,a
HSAR = High-speed autoreclosing (~ 0.3–0.5 s)DAR = Delayed autoreclosing (~ 1–2 minutes)OH = Over head lineUG = Underground cable
z
z
110/20 kVFeeder 1
Feeder 2
a) Line in forest
b) Line next to road
Forest (from 10 � 1 faults/100km,a)
9
Analysis includes:
- Investment costs
- Operational costs
- Outage costs
P [kW]
Change in number of sustained faults [faults/100km,a]
Figure 4.10. Techno-economic ranges of use for 20 kV medium-voltage underground cables when the
existing OH line is in forest and next to a road.
It is assumed that when the existing roadside overhead line is changed over to an underground
cable, the rate of long supply interruptions will decrease from 5 to 1 faults/100km,a (= change is
4 faults). It can be seen from the figure that if the peak power of the feeder is more than 1700
kW, the renovation is profitable. When a forest-located overhead line is replaced by
underground cabling, the rate of long supply interruptions will decrease from 10 to 1
faults/100km,a (= change 9 faults). Now, if the peak power of the feeder is more than 700 kW,
the renovation is profitable.
Figure 4.11 illustrates example curves for the applicability of underground cabling taking into
account several cost factors. The approach provides the first insight into the assessment of the
practical techno-economic potential of the network technology in question. The different
feasibility curves in the figure are based on the different costs taken into account in the
underground cabling.
84
0
200
400
600
800
1 000
1 200
1 400
1 600
1 800
2 000
0 2 4 6 8 10 12 14
Change in long supply interruptions [faults/100km,a]
Pea
k po
wer
of t
he fe
eder
[kW
]
1) Cable + cabling = 30 k€/km
2) Cable + cabling + distribution substation renovation = 35 k€/km
3) Cable + cabling + distribution substation renovation + compensation = 37 k€/km
1) 2) 3) Interest rate p = 5 %, load growth r = 1 %/a and time period t = 40 a
For overhead line:- Unit price: 22 k€/km - High-speed autoreclosings 25 pcs/100km,a - Delayed autoreclosings 10 pcs/100km,a
Figure 4.11. Examples of the techno-economic ranges of use for 20 kV MV underground cables.
In the strategy-level planning, uncertainty related to statistics and fault frequency can be
managed by drawing up guidelines so that in the feasibility analysis of different structural
solutions, the parameters that are the most difficult to determine are left as variables in the
initial stage of the planning process. For instance, in the profitability comparison between
underground cables and overhead lines, when plotting the curves, the designer does not have to
consider and decide on the absolute fault frequency but rather on the amount by which the
target-specific fault frequency can change as a result of cabling.
The effects of underground cabling on reliability can be intensified by combined network
automation solutions. Now, after the cable section at the beginning of the feeder, a circuit
recloser is placed on the feeder to prevent the faults at the far end of the feeder from showing to
the customers at the substation end (beginning) of the feeder.
4.2.4. Compensation of earth fault currents
In a neutral-isolated medium-voltage network, the single-phase short circuit and earth fault
currents usually remain low. A typical overhead line structure produces, at a 20 kV supply
voltage, 4–5 A per hundred kilometres. In an underground cable network, the amount of
capacitive current is 1.5–3 A/km depending on the cable type. As a result of poor earthing
85
conditions, a situation may occur, in which, considering electrical safety, the earth fault taking
place in the medium-voltage network cannot be suppressed fast enough. Earth fault currents
increase considerably in areas where the medium-voltage network is renovated by replacing
overhead lines with underground cables. To compensate the increasing fault currents, earth fault
arc suppression coils have to be connected to the network.
Another significant benefit of earth fault compensation is the automatic suppression of the arc
occurring during an earth fault. This way, it is possible to avoid most of the earth-fault-related
reclosings required by non-suppressed networks. By investing in earth fault compensation, the
number of interruptions caused by high-speed auto-reclosings can be reduced by 50 %.
Suppression of earth fault currents is common in the Nordic countries. In Finland, 46 % of the
medium-voltage networks are provided with arc suppression (Finnish Energy Industries, ET,
2009). According to the statistics, there are on average 21 interruptions per 100 km caused by
high-speed auto-reclosings. In the network with a 50 km long feeder, the number of high-speed
auto-reclosings (HSAR) is
ar,HSAR/feede11km 100
HSAR21km 05 =⋅
(4.5)
The outage cost is proportional to the power and line length P*l. With suppression, the number
of reclosings decreases and the outage costs change from the initial situation as follows:
dcompensate line, overheaddcompensate-non line, overhead flPflP ⋅⋅→⋅⋅ (4.6)
If the reclosings are assumed to be halved by suppression, also the outage costs caused by
reclosings will be cut to half. If the average power of the medium-voltage line in question is 500
kW and the outage cost of a high-speed reclosing is 0.55 €/kW, the outage costs caused by
high-speed auto-reclosings are for one feeder:
afeeder,/€3025 0.55kW50011 kW€
aHSAR
feeder-HSAR =⋅⋅=C (4.7)
86
At a typical primary substation in a rural area, there can be for instance ten feeders, and the
annual outage cost saving for the entire network of this primary substation would be
a€k
feeder€
HSAR 3.30 302510 =⋅=C (4.8)
According to nationwide statistics, even 50–80 % of short interruptions can be reduced by earth
fault current compensation. The cost of the earth fault compensation equipment varies typically
between 1,000–3,000 €/A depending on the compensation method (centralised or distributed
compensation) and unit size. In the case of an overhead network, earth fault compensation for
the whole network of the primary substation would require capacity according to empirically
derived Eq. (4.9) (Pöyhönen, 1978).
A33A10300
50020
10300km
3A
V3=
⋅
⋅=
⋅
⋅
=
lU
I
(4.9)
The cost of compensation would be 33–99 k€ for the example network. If it is assumed that the
high-speed autoreclosings could be reduced by 50 % (= 15.13 k€/a) by this investment, the
repayment period (the interest rate p is 5 %), of this investment would be 2.4–8.1 years. In other
words, an investment pays itself back in eight years (Lassila et al., 2005a).
4.2.5. LVDC
Among the network technologies available, the low-voltage DC distribution (LVDC) represents
the newest technology (Kaipia et al., 2006) and (Salonen, 2006). With the LVDC technology it
is possible to transmit significantly larger powers than with the present 400 V low-voltage AC
system, or to use conductors with smaller cross-sections than the present ones. Although the
LVDC technology is still at a very early stage, and there is uncertainty involved in the prices of
power electronic components, it is possible to determine feasibility ranges at a principle level
for this technology also. Figure 4.12 presents a simplified example of an imaginary supply area
87
of the distribution transformer structure used in the cost comparison; in the comparison, the
structure is implemented with the present 20/0.4 kV technology and the LVDC technology.
20/0.4 kV (Pmax = 34 kW)20 kV
1 km
200 m0.4 kV
0.4 kV 0.4 kV
20/1 kV
± 750V
800 mAC/DC
± 750V
200 m
± 750V
200 m
DC/AC400 VAC
200 m0.4 kV
Pmax = 10 kW/cust
Figure 4.12. Example supply area of the distribution transformer implemented with the present and LVDC
technology.
Figure 4.13 gives feasibility curves for the LVDC technology and traditional technologies (20
kV overhead line, covered conductor (CC) and underground cable). Based on a case network,
the figure shows that the total costs of the LVDC solution (investments, OPEX and outage
costs) are the same as the total costs of an 20 kV overhead line, if the length of the medium-
voltage branch to be renewed is about 1000 m. The bars in the figure represent medium-voltage
branch lines in the actual network area.
0
5 000
10 000
15 000
20 000
25 000
0 0.5 1 1.5 2 2.5 3
Length of a 20 kV branch line [km]
Diff
ere
nce
in to
tal c
ost
s (i
nve
stm
en
ts, o
pe
x,
ou
tag
es)
[€/k
m]
0
2
4
6
8
10
12
14
16
18
20L
en
gth
of 2
0 k
V b
ran
ch li
ne
s in
the
targ
et a
rea
[k
m]
Length of 20 kV branch lines
20 kV UG
20 kV CC
20 kV OH
Figure 4.13. Comparison of network structures (LVDC vs. 20 kV OH line, 20 kV CC line and 20 kV UG
cable) and number of actual targets in the studied area (bars in the figure) (Lassila et al., 2009b).
88
In the case of LVDC technology, numerous challenges remain to be overcome. However, as
continuity is established in the field, the technology is taking steps forward and the criteria
related to the quality of supply are gaining ground, LVDC technology may become an essential
development tool in the network strategies in the future.
4.2.6. Remote-controlled disconnector
Large uniform network areas are challenging from the viewpoint of reliability of supply. A fault
occurring on a medium-voltage feeder starting from a primary substation is shown as an outage
to all customers on the feeder. In rural areas, the length of a feeder is on average 30–40 km, and
the number of customers on the feeder is typically 300–500. Although the number of faults
experienced by the customer can only be affected by adding circuit reclosers to the system or by
changing the network structure from overhead lines over to underground cables, disconnector
solutions are an efficient means to influence the duration of faults experienced by customers.
The better the network sections can be split into smaller parts, the easier the fault can be
isolated from the healthy network. If the disconnector is remote controlled, isolation of a fault
can be carried out faster than what is manually possible. The profitability of a single remote-
controlled disconnector can be determined fairly simply according to the example presented
below. In the example, there are already three manually operated disconnectors in the junction
of lines. The benefit (saving in time) of the remote control is estimated to be 0.8 h, if a backup
connection is not needed (the fault is on section C) or 0.4 h, if a backup connection is needed
(the fault occurs either on section A or B). The energy-weighted outage unit cost for the
duration of interruption is 4.3 €/kWh for the case area.
89
Fault frequency : 0.05 faults/km,aOperating time (manual disconnecor) : 1 hOperating time (remote-controlled) : 0.2 hand 0.6 h if reserve line is neededRepair time : 3 hRemote-controlled disconnector : 22 000 Eur(lifetime 25 years � 1560 Eur/a, p = 5 %)
Fault frequency : 0.05 faults/km,aOperating time (manual disconnecor) : 1 hOperating time (remote-controlled) : 0.2 hand 0.6 h if reserve line is neededRepair time : 3 hRemote-controlled disconnector : 22 000 Eur(lifetime 25 years � 1560 Eur/a, p = 5 %)
Primarysubstation
3 km, 40 kW
3 km, 60 kW
6 km, 200 kW3 km, 150 kW4 km, 150 kW 2 k
m, 1
50 kW
Remote-controlled disconnector ?
A
B
C
A reserve line
Fault, effect
Saving [h]before–after
Saving [€/a]
A B 1 – 0.6 = 0.4 (0.05 . 4 km) . 250 kW . 0.4 h . 4.3 €/kWh = 86 €/aC 1 – 0.6 = 0.4 (0.05 . 4 km) . 350 kW . 0.4 h . 4.3 €/kWh = 120 €/a
B A 1 – 0.2 = 0.8 (0.05 . 8 km) . 150 kW . 0.8 h . 4.3 €/kWh = 207 €/aC 1 – 0.2 = 0.8 (0.05 . 8 km) . 350 kW . 0.8 h . 4.3 €/kWh = 482 €/a
C A 1 – 0.2 = 0.8 (0.05 . 9 km) . 150 kW . 0.8 h . 4.3 €/kWh = 233 €/aB 1 – 0.2 = 0.8 (0.05 . 9 km) . 250 kW . 0.8 h . 4.3 €/kWh = 388 €/a
Total saving: 1 516 €/a
Fault, effect
Saving [h]before–after
Saving [€/a]
A B 1 – 0.6 = 0.4 (0.05 . 4 km) . 250 kW . 0.4 h . 4.3 €/kWh = 86 €/aC 1 – 0.6 = 0.4 (0.05 . 4 km) . 350 kW . 0.4 h . 4.3 €/kWh = 120 €/a
B A 1 – 0.2 = 0.8 (0.05 . 8 km) . 150 kW . 0.8 h . 4.3 €/kWh = 207 €/aC 1 – 0.2 = 0.8 (0.05 . 8 km) . 350 kW . 0.8 h . 4.3 €/kWh = 482 €/a
C A 1 – 0.2 = 0.8 (0.05 . 9 km) . 150 kW . 0.8 h . 4.3 €/kWh = 233 €/aB 1 – 0.2 = 0.8 (0.05 . 9 km) . 250 kW . 0.8 h . 4.3 €/kWh = 388 €/a
Total saving: 1 516 €/a
Figure 4.14. Example of outage cost benefits provided by a remote-controlled disconnector (Lassila et
al., 2005a).
By adding disconnectors to the network, only the duration of faults experienced by customers
can be reduced, not the number of faults. In the case of a circuit recloser, both the number of
faults and their durations can be reduced. Because of this essential difference, it is not possible
to determine universal feasibility ranges and curves for (remote-controlled) disconnectors
similarly as in the above examples for circuit reclosers and underground cabling. The
profitability of a disconnector solution is also strongly influenced by the number of backup
connections, in other words, to which extent the network is mesh operated. Therefore, the
profitability of a disconnector has always to be determined for each case individually.
4.2.7. Interdependence between network technologies and reliability
There is a strong interdependence between the reliability of electricity distribution and the
business income. In the strategic planning, information is required on the fault frequencies and
fault types in different operating areas when considering different network renovation
strategies. Table 4.2 illustrates the principles of the reliability effects of various network
solutions (effects on the fault rate, duration, short and long interruptions). The table shows that
the numbers of faults experienced by end-customers can be affected in particular by decreasing
90
the size of uniform supply sections by new primary substations or circuit reclosers or by
converting medium-voltage networks to low-voltage networks (1000 V technology). The
absolute numbers of faults occurring in the network can be affected only through technical
structural solutions, for instance by replacing overhead lines with underground cables. The
durations of faults experienced by customers can be reduced by investing on network
automation and fault restoration and repair organisation.
Table 4.2. Effects of different network technologies on the fault rate and duration (�� significant improvement, � some improvement, - slight or no improvement.
Number of sustained faults
Absolute pcs/customer
Duration of
sustained
faults/customer
Work
outages/
customer
Number of
reclosings/
customer
New primary substations - � � � - � �
UG cabling (medium- and low-
voltage networks)
� � � � - - � �
Covered conductors � � - - �
Construction by roadsides � � � - �
1000 V distribution � � � - - � �
Circuit reclosers - � � - - � �
Remote-controlled
disconnectors
- - � � - -
Backup connections - - � � � � -
Control room automation ( � ) ( � ) � � � -
Earth fault current suppression - - - - � �
Backup power - - � � � -
Cooperation � � � - -
In the strategy development work, it is necessary to be able to assess the cost and reliability
benefits of different alternatives at a sufficient accuracy. In practice, it will be challenging to
determine in detail the effects of different structural solutions on the development of reliability
indices; for instance, how much the fault frequency is assumed to decrease if a medium-voltage
line, located initially in the middle of a forest is transferred to the roadside or the line is
replaced with a covered conductor. If a distribution company already has statistical data on the
above-discussed technologies, this information can be utilised to some extent. However, the
emphasis is on national statistics compiled by central organisations in the field (Sener, Finnish
91
Energy Industries ET, Adato). Nevertheless, these statistics pose certain challenges, and they
are not always applicable as such owing, for instance, to the short history of the statistics, small
sample data and diverging practices and accuracy of statistics in the distribution companies. In
the future, information systems and substation automation play a central role in compilation of
more extensive and reliable statistics, which would facilitate the strategy work in distribution
companies. The needs related to these background data are described in more detail in section
4.5.
When considering the reliability of distribution networks, the effects of different network
solutions on the reliability of electricity distribution can be roughly described by the example of
Figure 4.15. In the figure, different network technologies are placed according to the time
required for implementation (x-axis) and change/improvement in reliability (y-axis). The figure
shows for instance that the most significant improvement in reliability can be reached by
extensive underground cabling of the medium-voltage network. However, implementation of
such a large project is time consuming. Automation solutions, instead (e.g. circuit reclosers,
disconnector automation, light primary substations) provide improvements in reliability already
in a shorter time span. In some cases, a 20–30 % improvement in the average outage duration
on the overhead feeder in one year has been achieved by implementation of automation
(Northcote-Green and Wilson, 2006). Nevertheless, underground cabling of the low-voltage
network is not considered to have a significant impact on customers’ statistical outage rates.
92
REMARKABLE
INSIGNIFICANT
TIME SCALE
TIME-CONSUMING IMPLEMENTATION
FAST IMPLEMENTATION
A CHANGE IN RELIABILITY
UNDERGROUND CABLING (MV NETWORKS)
RENOVATION WITH OLD TECHNOLOGY
COVERED CONDUCTORS
OVERHEAD CABLING
1000 V LOW-VOLTAGE SYSTEMSIMPLE, LOW-COST
PRIMARY SUBSTATIONS
RECLOSERSREMOTE-CONTROLLED DISCONNECTORS
EARTH FAULT CURRENT COMPENSATION
UNDERGROUND CABLING (LV NETWORKS)
BUILDING BY THE ROADSIDES
Figure 4.15. Effects of different network technologies on statistical (i.e., normal) reliability.
The network strategy process also delineates how the risk of blackout is taken into account in
the network development. In this context, a blackout is an extensive and long supply
interruption caused by trees or poles falling in a severe storm. In Figure 4.16, the same
technologies have been placed into the frame of reference similarly as in Figure 4.15, but with
respect to the risk of blackouts. The figure shows that the blackout risk can be minimised by
underground cabling of medium- and low-voltage networks. Now, the benefit of underground
cabling is based on the fact that damages caused by large storms do not have to be repaired in
the low-voltage network. Unlike in the previous figure, light and fast network automation
solutions do not improve reliability with respect to the risk of blackouts.
93
TIME SCALE
TIME-CONSUMING IMPLEMENTATION
FAST IMPLEMENTATION
RISK OF MAJOR STORMS
LOW RISK LEVEL
HIGH RISK LEVEL
UNDERGROUND CABLING (BOTH MV AND LV NETWORKS)
COVERED CONDUCTORS
BUILDING BY THE ROADSIDES
OVERHEAD CABLING
1000 V LOW-VOLTAGE SYSTEM
SIMPLE, LOW-COST PRIMARY SUBSTATIONS
RECLOSERSREMOTE-CONTROLLED DISCONNECTORS
EARTH FAULT CURRENT COMPENSATION
RENOVATION WITH OLD TECHNOLOGY
Figure 4.16. Effects of different network technologies in the case of major storms.
4.3. Calculation methodology for the analysis of long-term cost and reliability effects
The detailed cost and reliability effects of network choices related to the network strategy can
only be analysed by applying the results of the operating environment and technology potential
surveys to the actual electricity distribution environment. The network area to be analysed has
to be large enough to ensure the reliability of the analysis. On the other hand, the area to be
analysed has to be small enough so that the effects of parameter variation can be detected fast
and easily. It is also of utmost importance to find such a network section that adequately and
well describes the operating environment and the structure of the distribution system and
thereby makes it possible to bring the results to a more general, company level. The issues
related to the selection of areas to be analysed are addressed in more detail in Chapter 5.
94
Compared with the feasibility studies for different technologies presented in section 4.2, the
analyses made for actual network sections provide more truthful results about the application
potential of different network technologies. The local boundary conditions set by the operating
environment become more visible when the potentials of different network technologies are
analysed with the accuracy of a medium-voltage feeder. For instance, in the feasibility studies
of underground cabling, it is possible to include cost components that better correspond to
reality as the cabling installation costs can be specified according to the soil analyses of the
operating environment. The feasibility of underground cabling depends highly on whether the
soil allows cable installation by ploughing, or traditional excavation methods are required. This
information is specified further when plans are drawn up for the target areas. Furthermore,
distribution management systems (DMS) and fault location records can be utilised to define
fault frequencies that more accurately describe the area under observation; this way, the
development of outage costs can be assessed more accurately.
The cost and reliability analyses made for target network areas require suitable analysis tools
and calculation methodology. Calculation methodology related to individual network
technologies were introduced and discussed in section 4.2. As the above introduction to these
technologies showed, outage costs have a significant weight in the feasibility studies. One of the
major challenges in strategic planning is to determine the cost and reliability effects of different
network structural solutions and development alternatives at a general level without going into
too detailed and time-consuming analysis. The development of strategic planning in this
direction has partly been restricted by the incomplete analysis methodology and limited analysis
tools of the present asset management systems (such as network information systems,
distribution management systems and condition monitoring systems). Enlightening examples of
large strategy-related issues are: is there room for network automation in the present electricity
distribution network, how does wide-scale underground cabling affect the costs, reliability
indices, the company’s result, distribution fees paid by the customers or the network’s
susceptibility to blackouts. So far, such large issues have not been dealt with in the long-term
network development and asset management, but the approach has been limited to single
targets. However, too detailed an analysis does not give a reliable picture of the total effects.
Furthermore, carrying out a highly detailed analysis for the entire company is so time and
resource consuming that it is not possible in practice. The iterative and interactive nature of the
process makes the analysis even more complicated. Unreliable and insufficient initial data
95
together with the limitedness of the calculation parameters to correctly describe the operating
environment inevitably lead to an iterative analysis process. Therefore, the methodology and
analysis tools have to be flexible to enable alteration of the initial data. For the strategic
planning as a whole, it is vital to recognise the interdependencies between different factors
involved in the distribution networks.
4.4. Description of the calculation system
To enable the development of the strategy process, a calculation system has been developed for
research purposes. In the following, an asset management system developed as a tool for a
researcher is introduced; the core results of this dissertation are based on application of this
system.
4.4.1. Objectives and purpose of the system
The targets in the system development have been better manageability of large masses of data
required in the electricity distribution business, assessment of the reliability of information,
understanding of the mutual interaction between different factors (and parameters) and strategy-
related cost and reliability calculation. The system developed here does not function
independently, but requires a large amount of data from other information sources such as the
distribution company’s network information system, customer information system, distribution
management system and condition management system. The information systems currently in
use in distribution companies serve well the different subtasks related to asset management, yet
they are not able to produce holistic results to support strategy-level decision-making. To reach
the set research targets, a system has been developed to combine initial data and subresults into
compilations useful for the purposes of asset management. The developed asset management
system includes a number of different calculation elements starting from determination of
feasibility ranges for specific network technologies to determination of the value of large
network masses and reliability calculation.
96
4.4.2. Initial data
“The quality and quantity of data produced in strategic analysis will affect both the cost and the
quality of strategic decisions” (Grünig and Kühn 2006, p. 53). Successful asset management
calls for extensive and reliable initial data and efficient data processing. In the analysis system
developed in this work, the initial data comprises technical network data of the distribution
network, customer data, cost data and other long-term statistics. Both the technical and
economic background data are collected into the asset management system according to the
primary substations and medium-voltage feeders. The feeder approach has been taken to avoid
collection and allocation of data at too detailed (and time-consuming) a level, but
simultaneously, to guarantee that the accuracy of data is sufficient enough for strategic analysis.
Traditionally, reliability calculation has concentrated on the analysis of the medium-voltage
network, as 80–90 % of the outages experienced by customers originate from the medium-
voltage network.
The present practices concerning compilation of outage statistics support the above feeder
approach. Data from the distribution transformers and low-voltage networks are gathered and
allocated to the respective medium-voltage feeder. Distribution transformers are not treated as
single components but they and their end-customers always belong to some medium-voltage
feeder as shown in Figure 4.17.
Maa-kaapeli
Kauko-ohjatut erottimet
Manuaali-set erottimet
Pylväs-muuntamot
Puisto-muuntamot PJ-verkkopituus [km] Asiakkaiden lukumäärät ryhmittäin
Asema Johtolähtö [km] Yht. Metsä Pelto Tienvarsi Yht. Metsä Pelto Tienvarsi [km] Runko Thaara Phaara Määrä [kpl] Määrä [kpl] [kpl] [kpl] Avojohto AMKA Maakaapeli Kotitalous Vapaa-ajan as.
YHTEENSÄ: 413.2 306.8 119.4 159.3 28.1 53.1 18.6 26.9 7.6 53.3 21 252 406 67 47 1 146 158 10 828 0
Kallbäck KLB_J07 INGMAN30.455 19.742 7.5 8.4 3.8 5.217 0.821 2.8223 1.57365 5.496 76 22 2 2 28 1 0 34 4 1.06 345.1 25.507 1 430 0
Kallbäck KLB_J08 KALKSRAND13.747 10.49 8.7 1.1 0.7 2.936 2.0318 0.9042 0 0.321 60 40 0 0 7 1 0 18 1 5.541 53.7 1.779 532 0
Kallbäck KLB_J09 SÖDERKULLA6.263 1.695 0.8 0.2 0.7 2.341 0 2.341 0 2.227 90 10 0 0 9 1 0 6 3 1.605 7.8 1.919 105 0
Kallbäck KLB_J10 GUMBOSTRAND28.851 20.277 17.6 2.7 0.0 1.546 1.546 0 0 7.028 42 53 5 3 9 1 0 27 4 5.265 92.6 9.996 767 0
Kallbäck KLB_J11 BOX17.115 16.919 2.8 12.3 1.9 0.171 0 0.171 0 0.025 32 60 8 1 8 1 0 20 1 1.373 42.8 1.266 338 0
Kallbäck KLB_J12 GALTHAGEN4.544 2.312 0.5 0.5 1.3 1.1 0 0.682 0.418 1.132 42 58 0 0 5 1 0 4 3 0.296 11.4 3.346 282 0
AsiakastiedotPJ-muuntopiirit
1
Lähdöllä pylväs-katkaisija?
Johto-lähdön yhteis-pituus
Johtotiedot
Avojohto [km] Päällystetty avojohto [km]
Erottimet ja pylväskatkaisimet
Jako käyttötarkoituksen perusteella [%]
EiKyllä
Ei
Ei
Ei
Ei
Ei
Ei
Low-voltage networks- Customer numbers- Customer groups- Annual energy- Network information
z
z
20 kV
110/20 kV
Distribution substations
- Distribution transformer and substation information
- Age and condition information
Medium-voltage networks- Line structure- Line lengths- Switchgear - Interruption statistics
Switches- Structural and functioning
principles- Operation times
Feeder 1
Feeder 2
Figure 4.17. Principle of the network structure applied in the asset management system and an extract of
the initial data table.
97
In reality, for instance because of different amount of backup connections and network
automation systems, the supply areas of distribution transformers of the medium-voltage feeder
do not experience supply outages of equal length. In the strategic analysis, however, it is
possible to apply simplified and average estimates of fault durations at a feeder level. Figure
4.18 illustrates the background information and calculation systems used in the network
analyses.
Assessment of load
development
Network data
Power flow calculation (peak powers, losses), compensation considerations
Outage statistics, normally open points, operating times
Number of customers, kWh data, consumer group data, development of energy consumption
Network age and condition data
Reliability + major storm
analyses
Network unit costs, work costs, development of the operating area (land use planning etc.)
Development needs for transmission and
transformation capacity
SAIFI, SAIDI, MAIFI, outage costs
Present and replacement value of the network
Determination of network investment
history and value
Strategy alternatives
Network operation and maintenance costs
Network information system
Distribution management and operation control systems
Customer information system
Maintenance system
Other sources
SAIFI, SAIDI, outage costs, distribution fee, profit of owner, depreciations etc.
Figure 4.18. Information flows related to the strategy process. All the elements required in the process are
not included in detail in the illustration.
A detailed list of initial data collected into the system is presented in Table 4.3.
98
Table 4.3. Detailed list of initial data collected into the system.
Network data
Low-voltage network: lines, transformers, distribution substations, protection equipment, distribution cabinets
Medium-voltage network: lines, disconnectors, switches
Primary substations: main transformers, switchgear and controlgear, compensation equipment, automation
Others: other network assets (e.g. information systems, kWh meters)
Customer data
Consumption of electrical energy
Customer group information (households, agriculture, public, services, industry)
Cost data
Unit prices of network components (EMA)
Costs of losses
Outage cost parameters for different fault types and customer groups (EMA)
Maintenance costs
Fault repair costs
Fault statistics for different network structures
Long supply interruptions
Planned outages
High-speed and delayed autoreclosings
Age and condition information of network components
Operation times
Switching times of disconnectors (manual/remote-controlled)
Fault repair time and duration of a planned maintenance action for different network structures (overhead line,
cable, covered overhead line)
Calculation parameters
Lifetimes (network components)
Work costs (maintenance, fault repair)
Interest rate
Reference period
Load growth (area-specific)
99
4.4.3. Calculation operations of the asset management system
As described above, the asset management tool developed in this work utilises partly the results
produced by other systems. The reason for doing so is that there has been no need to introduce
such subfunctions to the asset management system that are already well established in the
present distribution network applications. Such are for instance the calculation results related to
load flow calculation (loads on lines and transformers, network losses, voltage drops,
compensation considerations) and calculations based on fault current calculation. The most
essential calculation functions of the developed asset management system are listed below.
- Calculation of reliability indices (SAIFI, SAIDI, MAIFI)
- Outage cost calculation (average and customer group weighted)
- Operation and maintenance cost calculation
- Evaluation of the development of loss costs in different network structures
- Calculation of the replacement value of the network
- Calculation of the present value of the network
- Effects of different development options on the distribution fee
- Definition of the techno-economic feasibility range of a circuit recloser
- Definition of the techno-economic feasibility range of underground cabling of medium-
voltage network, a covered overhead line, and transfer of lines to roadsides
- Determination of the investment history
- Assessment of future annual investment needs based on the investment history
The key reason for developing the asset management system has been the arising need for
flexible treatment of large network entities. Load flow and fault current calculations as such do
not assist in evaluating the cost and reliability effects of strategic network decisions. The asset
management system developed in this work makes it possible to consider the effects of different
strategic policy lines on large network entities. The background data gathered into the system
are used in various subapplications, such as in distribution system reliability calculation and
determination of the network value.
100
4.4.4. Determination of the network value
From the company’s business perspective, one of the key targets is to determine the value of the
electricity distribution infrastructure and its development in an appropriate way. The importance
of this target is emphasised by the fact that the calculation of the allowed return on capital by
the Energy Market Authority has been based on the determination of the network value. The
asset management system takes into account both the replacement value and the present value
of the network. The replacement value is the value of an asset when replacing an existing asset
with the same quality of construction. Correspondingly, replacement value of the distribution
network is the construction cost of the distribution network at the current level of costs.
Determination of the replacement value is based on the network component quantity data
submitted by the company and the network component unit price data defined by the Energy
Market Authority as shown in Table 4.4.
Table 4.4. Example of network component unit prices by the Energy Market Authority (EMA, 2009a).
Distribution substations Unit price [€/pcs.]
1-pole-mounted distribution substation 4 8502-pole-mounted distribution substation 6 6304-pole-mounted distribution substation 7 220Pad-mounted, type 1 (outside maintained) 27 490Pad-mounted, type 2 (inside maintained) 35 010Building-mounted distribution substation 47 620Special distribution substations 80 990Satellite-type distribution substations 16 800
Figure 4.19 illustrates the distribution of capital by component groups in an example
distribution company. The figure shows that a significant proportion (almost 70 %) of the
network assets (replacement value) is tied up in low- and medium-voltage networks. Hence,
approaches focusing on these component groups in the long-term development will have a
strong influence on the total value of the network and thereby the development of the business.
In addition to the formation of the network value, all component groups have an effect on the
accumulation of the operational and outage costs.
101
110/20 kV primary substation
10 %
110 kV lines6 %
20/0.4 kV distribution substations
15 %
20 kV medium-vo ltage lines26 %
0.4 kV low-voltage lines43 %
- Aerial bundled cables (AMKA)- Underground cables- Bare overhead lines- Distribution cabinets
- Distribution substation structures- Distribution transformers- Transformer disconnectors
- Bare overhead lines- Covered conductors- Line disconnectors- Underground cables- Cable joints and terminations
- Primary transformers- 110 kV equipment- 20 kV equipment- Earth fault arc suppression coils
Figure 4.19. Value of the network assets by component groups for an example company.
For a distribution company, besides compilation of network component quantity data, a more
challenging task has been to determine the ages of the network components. These age data are
used as the basis for the determination of the present value of the distribution network. The
present value in turn plays a key role in the calculation of allowed return on capital. Present
value is determined by the current ages and lifetimes of the network components (Eq. (4.10)).
RVPV ⋅
−=
timelife
age1 (4.10)
PV = present value of the network
age = average age of the network
lifetime = techno-economical lifetime of the network
RV = replacement value of the network
Considering the allowed return, it is desirable that the network age remains low, in other words,
the present value stays high. If no investments are made in the network, the network will
continue ageing and the company’s allowed return becomes lower. To avoid reduction in the
present network value, the annual investment level of the distribution company has to be at least
equal to the depreciation level defined from the network replacement value. Investments made
in the network can be categorised into new or replacement investments depending on whether
the investments increase the volume of the network or old components are just replaced by new
ones. Unlike in the determination of replacement value, in regard to calculation of the present
network value, all investments are equal, and it is not necessary to classify them into new or
102
replacement investments in advance. If needed, the classification can be made afterwards by
investigating the network component data recorded in the network information system. An
increase in the quantity of network components and thus in the network replacement value
compared with the previous year indicates that new investments have been made in the
network. By calculating the difference between the replacement value of the reference year and
the preceding year and by taking into account possible changes in the unit prices of network
components, we obtain a rough estimate of the proportion of new investments in the net
investments. In the calculation model, the present value of the network is obtained according to
Eq. (4.11).
T
RVINVPVPV n
nnn
11
−
− −+= (4.11)
PVn = present value of the network in the current year
PVn-1 = present value of the network from the previous year
INVn = investments on current year
RVn-1 = replacement value of the network from the previous year
T = average depreciation period
Depreciations on the distribution network are computed as straight-line depreciations from the
network replacement value. When the depreciations are calculated from the network
replacement value during the depreciation period, an average lifetime of network, computed
based on the techno-economic lifetimes of the network components, is used in the calculations.
Thus, component lifetimes play a key role in the determination of the present value of the
network and in the methods for determining depreciations of network investments. The
component lifetimes are based on surveys compiled by the Energy Market Authority (Partanen
et al., 2002). From the lifetime range provided by the authority, the distribution companies may
select such a value that best describes the company’s area of operation and demand for network
renovation. Essential factors that have an impact on the component lifetimes are the load
growth and development of the infrastructure in the area. In areas of intensive growth, the
techno-economic lifetimes are notably shorter than what the actual technical age of the
components would allow, because components have to be replaced by new ones for reasons
other than reaching the end of the technical lifetime. If the growth in electricity consumption
remains stable or the growth is slow, the techno-economic lifetimes of network components are
close to the technical lifetimes of the components. In terms of national economy, it is profitable
to keep the components in the network as long as they are still in order and operating.
103
In the calculation system developed, the age and lifetime data of the network can be taken into
account by component groups. Component-group-specific age data enable the presentation of
the investment history as shown in Figure 4.20. The figure shows how much has been invested
in different components in the course of time in the company history. In the example figure, the
component groups have been limited to low-voltage network components.
0
100 000
200 000
300 000
400 000
500 000
600 000
700 000
1957 1959 1961 1963 1965 1967 1969 1971 1973 1975 1977 1979 1981 1983 1985 1987 1989 1991 1993 1995 1997 1999 2001 2003 2005 2007 2009
Jälle
enha
nkin
ta-a
rvo
[€]
Pj-ilmajohdot
Pj-kaapelit
Muuntajat
Muuntamot
30 - 40 a> 40 a
Rep
lace
men
t val
ue [€
]
Low-voltage lines
Low-voltage underground cables
Distribution transformers
Distribution substations
Figure 4.20. Investment history of the example company; the low-voltage network.
When a component reaches its techno-economic lifetime, the present value of the network
component reduces to zero, and it no longer has an impact on the calculation of allowed profit.
Thus, the mechanism provides an incentive to renew the oldest network sections as they reach
their lifetime.
Based on the investment history and the chosen component lifetimes, it is possible to determine
the future investment needs in a distribution company. Figure 4.21 shows how much the
company should invest in the network in years to come, if the outdated components are to be
replaced by new ones as they reach their lifetime. Often, there are also such components on the
network that are outside the techno-economic lifetimes defined by the authority. In the case
illustrated in Figure 4.20, these components exceeding the official lifetimes are planned to be
replaced at an even rate during the first ten years. After this, there are no longer any such
components on the network that would not have lifetime (and present value) left. The figure
also depicts the level of straight-line depreciations determined on the basis of the network
104
replacement value and average lifetime. This level represents the amount of money that has to
be invested in network renovation in order to keep the value of the network at the present level.
The figure shows also that in some years, the investment level is lower than the calculated
straight-line depreciation (the replacement value decreases) while in some years, the investment
level is higher than the straight-line depreciation (the present value increases). The actual age
data of the component groups based on component installation years are used as background
information in the analysis.
0
100 000
200 000
300 000
400 000
500 000
600 000
2010 2012 2014 2016 2018 2020 2022 2024 2026 2028 2030
Sa
ne
era
usi
nve
sto
inn
it [€
/a]
0,4 kV maakaapelit(asennus)0,4 kV ilmajohdot
Muuntajat
Muuntamot
DEPRECIATION LEVEL
Ren
ovat
ion
inve
stm
ents
[€/a
]
Low-voltage underground cables
Low-voltage lines
Distribution transformers
Distribution substations
Figure 4.21. Future investment needs based on the historic data of the example company.
By investigating the investment history of all network component groups, it is possible to
determine the present value of the entire distribution network and its development in the future.
Figure 4.22 depicts an alternative of the development of the network present value. In the
example, it is assumed that the company replaces the components by new ones as they reach
their techno-economic lifetime. In the initial situation, the average age of the network is slightly
above half of the average lifetime (present value percent is 46 %). The dashed line in the figure
depicts the annual investment need resulting from replacement of components. The calculations
are based on age and lifetime data of the components. The need for replacement of components
is based on the investment history, where investments documented for different years may vary
considerably. In practice, the target is usually to schedule any large-scale renovation actions to
span several years in order to evenly distribute the annual investment costs among the years.
105
34 %
36 %
38 %
40 %
42 %
44 %
46 %
48 %
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Nyk
ykäy
ttöar
vopr
osen
tti
0
200 000
400 000
600 000
800 000
1 000 000
1 200 000
1 400 000
Inve
stoi
nnit
Pre
sent
val
ue o
f th
e ne
twor
k [%
]
Inve
stm
ents
[€/a
]
Investments
Present value
Figure 4.22. Development of the present value of the example company.
4.4.5. Reliability calculation
Reliability calculation and network outage costs play a key role in the asset management system
developed in this work. Determination of outage costs is based on the fault rate of different
network structures, valuation of harm caused by outages (outage costs) and on the company
personnel’s ability to react to and recover from fault situations (amount of network automation,
switching speeds and repair times). In outage cost calculation, both short and long supply
interruptions are taken into account. In addition to faults, planned outages (such as network
maintenance) are taken into consideration in the calculation. Besides determination of outage
costs, the system calculates various technical (quality) indices based on the above (e.g. SAIFI,
SAIDI, MAIFI). Reliability calculation of an electricity distribution system is based on a large
amount of background information and different calculation parameters. The equations applied
in outage cost and quality index calculation are presented in section 4.5.4.
As groundwork for development alternatives, certain reference costs have to be determined for
outages, in other words, the present outage cost level of the network has to be defined. To
determine this reference level, the reliability calculation is first performed for the present
network structure and topology. After this, the structural data of the network are altered for
106
instance by converting overhead line sections into underground cables or by adding network
automation devices to the network. After the changes, the reliability analysis is carried out again
for the new network structure. If the operation and outage cost benefit is now higher than the
investment cost difference between these two alternatives, then it is economically justifiable to
include the chosen development alternative in the network strategy. The differences in the
operating conditions within the company’s area of operation lead to diverging solutions in the
outage cost considerations. To this end, the analysis tool provides an opportunity to analyse
large network entities simultaneously. The present network information systems do not include
this option; in these systems, calculations have to be made for each node section individually.
The results obtained from outage cost calculation can be utilised at least from two viewpoints;
for operative purposes, the outage costs can be determined for different fault types for instance
according to a distribution substation or a feeder. This way, the network operation can be
directed towards a state where the total outage costs caused by a fault are minimised. In practice
this means that customer groups that have a high outage cost value (such as a public load and
industry) are separated from network sections that are vulnerable to faults, or restoration of
supply is guaranteed as soon as possible. Figure 4.23a shows the outage costs by distribution
substations for one-hour outages in an example distribution company. Figure 4.23b presents the
outage costs by feeders.
107
Feeder 7Long interruption: 284 € + 2 955 €/hHSAR: 142 €/pcsDAR: 361 €/pcs
Feeder 2Long interruption: 930 € + 8 854 €/hHSAR: 512 €/pcsDAR: 995 €/pcs
Feeder 3Long interruption: 1 589 € + 14 366 €/hHSAR: 992 €/pcsDAR: 1 693 €/pcs
Feeder 1Long interruption: 1 242 € + 12 343 €/hHSAR: 704 €/pcsDAR: 1 333 €/pcs
Feeder 6Long interruption: 4 858 € + 52 013 €/hHSAR: 2 625 €/pcsDAR: 4 826 €/pcs
Feeder 4Long interruption: 399 € + 3 690 €/hHSAR: 229 €/pcsDAR: 465 €/pcs
Feeder 5Long interruption: 148 € + 1 646 €/hHSAR: 60 €/pcsDAR: 194 €/pcs
110/20 kV substationLong interruption: 9 450 € + 95 868 €/h
110/20 kV
Squares: Outage cost in distribution substation in 1-hour interruption:< 100 €/h100 – 500 €/h500 – 1000 €/h1000 – 2000 €/h> 2000 €/h
Lines: Installation year of the cable:< 19701970 – 1980 1980 – 19901990 – 2000> 2000
a) b)
Figure 4.23. Example of a) outage costs by distribution substations for a one-hour fault and b) outage cost
caused by different fault outages according to the number and duration of the outage.
The figure shows such distribution substations and feeders that are particularly vulnerable to
faults and require special attention, and where restoration of electricity supply in the occurrence
of a fault in the medium-voltage network has to be guaranteed as fast as possible.
Figure 4.24 illustrates the value of economic harm (outage cost) of a one-hour outage for the
distribution substations of the previous example. The figure shows for instance how a one-hour
fault occurring in the medium-voltage network may result in outage costs of thousands of euros
in certain supply areas of the distribution transformers. On the other hand, the figure illustrates
such supply areas of the distribution transformers that, in the occurrence of a fault in the
distribution substation itself, cause high outage costs in the supply area of the distribution
transformer in question. Thus, by taking into account this and the high ages of the distribution
substations (a higher risk of failure), the order in which the distribution substations are
renovated can be optimised. In the case of distribution substations, in addition to age, the risk of
failure depends on load rate and number and duration of possible overload situations. Constant
overloading weakens the transformer’s insulating capacity and increases the risk of failure.
108
Hence, actual load information together with age data has to be taken into account when
planning the renovation order.
0
10 000
20 000
30 000
40 000
50 000
60 000
0 10 20 30 40 50
Age of transformer [a]
Out
age
cost
s fo
r di
strib
utio
n su
bsta
tion
in th
e ca
se o
f a o
ne-h
our
faul
t [€/
h]
Figure 4.24. Example of outage costs for distribution substations in the case of a one-hour fault. In the
occurrence of a fault in the medium-voltage network, the outage costs will be particularly high in the
circled distribution substation. Owing to its high age, the distribution substation itself is susceptible to
faults.
Yet another aspect in the reliability calculation and renovation planning is the network
approach. Now, such line sections are determined on the network that are most prone to faults
and that, in the occurrence of a fault, cause significant outage costs. In this approach, the
investments can be directed to targets where their effect on the total outage costs of the network
is at highest. Such targets can be for instance overhead line sections close to urban areas.
Replacing overhead lines with underground cables or separating overhead lines as protection
zones of their own by network automation improves the reliability of supply for the customers
belonging to the same supply circuit. Figure 4.25 provides an example of such a case.
Considering the reliability of supply for the customers at the substation end of the feeder, both
renovation alternatives presented above bring the same outcome. Underground cabling
decreases the probability of a failure, while automation provides a means to restrict the fault to
a certain network section so that the fault is not seen outside this section. In the example case,
for the customers at the far end of the feeder, network automation is of no help, as in the
occurrence of a fault, they belong to the network section that is separated from the supply. The
109
reliability of supply for the customers at the far end of the feeder can be improved only by
reducing the absolute number of faults, for instance by underground cabling, or by otherwise
cutting down the number of faults occurring in the forest section of the feeder. Another option
is to arrange a backup connection for the customers at the far end of the feeder and to add
network automation between the risky (vulnerable) network section and customer at the far end
of the feeder.
z
z
110/20 kVFeeder 1
Feeder 2
a) b)
Figure 4.25. a) Separating a network section that is vulnerable to faults and causes significant outage costs
to constitute a protection zone of its own or b) replacing the line section with an underground cable.
In reliability considerations, special attention has to be paid to cross-effects of different
reliability investments. Underground cabling that was initially found to be techno-economically
feasible, may turn unprofitable if sufficient amount of network automation is added to the
network, and vice versa. Thus, investments are not independent of each other. On the other
hand, solutions may not necessarily rule each other out, if the outage cost level on the feeder is
very high. Hence, an optimum solution is often reached by combining different network
technologies. In the asset management system developed in this work, several development
alternatives can be taken into account simultaneously. The structure of the feeder can be
adjusted according to the needs for instance by replacing a traditional overhead line with a
covered conductor or an underground cable, or by adding manually or remotely controlled
disconnectors and circuit reclosers.
110
4.4.6. Determination of long-term costs in distribution system operation
A key target in the research has been to develop a system concept capable of determining long-
term costs of distribution system operation. The costs of a distribution system comprise costs
related to the capital costs, network operation and maintenance costs, and loss and outage costs
(listed as follows):
1) Investment costs
2) Loss costs
3) Outage costs
4) Repair and maintenance costs
5) Financing costs
These types of cost are made commensurate with each other by means of cost accounting in
order to be able to assess and compare the profitability of different network solutions in actual
situations. Alternatives are to determine the annual amount of lump-sum costs by applying the
annuity method, or to calculate the amount of annual recurrent costs (such as losses) by the
discounting method for the whole reference period.
A majority of the fixed annual costs in distribution networks consist of the capital costs of
transformers, lines and other components. Capital costs are further divided into financing costs
and costs caused by depreciations on investments (annual depreciations). Network investment
costs include labour, material and transport costs and other costs directly related to network
construction. Investment and financing costs are of significant weight in total costs of the
network. In addition to capital costs, fixed costs include network upkeep and maintenance costs.
Local conditions have an influence on the costs of the distribution network; network planning is
based on amounts and locations of loads on the network. Further, land use, the target level for
reliability and environmental aspects all have an impact on the network topology. In addition to
111
these, the value of the distribution network is affected by company-specific planning principles.
The distribution company has little power over environmental conditions; limitations related to
land use, such as land use planning, can be considered to belong to these. Environmental
conditions cause costs in network construction for instance in terms of compensations paid for
land use for line construction. During the lifetime of the network, the environmental effects are
mainly shown in the network maintenance and outage costs.
In addition to the general interest rate level, capital costs are affected by the network lifetime
and the age of the existing network at the moment of renovation. If it is necessary to renovate
an existing network before its calculated lifetime has been reached, the company balance sheet
will include depreciations on the old network that is out of operation but also investments in the
new network structures. Therefore, correct timing of renovations is of utmost importance in
network construction.
Besides the outage costs discussed in the reliability calculation section, costs of quality of
supply realised in the distribution company include standard compensations paid to customers if
an outage exceeds 12 hours. This blackout cost component is a useful tool in analysing the
ability of different investment strategies to manage blackouts. Empirical data gathered from
previous blackouts can be efficiently utilised when estimating future blackout costs.
Figure 4.26 depicts the results of long-term cost calculation for the present state in the network
and for a development alternative in an example case. The outage costs are presented together
with investment, financing, major storm costs and operational costs of two different network
technologies. The cost components have been calculated according to the principles presented
above. When comparing the sizes of the bars, we can see that in the development alternative,
special attention is paid to the reliability of networks. Furthermore, the development alternative
seems to reduce the network’s vulnerability to blackouts. The plan made for the target area
applies such network solutions that have a positive effect on the outage costs but are
simultaneously slightly less expensive than the traditional structural solutions.
112
0
10 000
20 000
30 000
40 000
50 000
60 000
70 000
80 000
90 000
1 2
Development strategy
Co
sts
of t
he
str
ate
gy
[k€
] Opex
Outages
Major storms
Financing
Investments
Figure 4.26. Total long-term costs of two network solutions.
In the strategic decision-making, outage costs constitute part of the total costs. Depending on
the network technology applied, fault frequencies and the area under consideration, these costs
may play a very significant role. Distribution of outage costs into the categories of short and
long outages as well as planned and unplanned outages of network alternatives is illustrated in
Figure 4.27.
0
2 000
4 000
6 000
8 000
10 000
12 000
Strategy 1 Strategy 2
Out
age
cost
s [k
€]
Delayed autoreclosings
High-speed autoreclosings
Planned interruptions
Long interruptions
Figure 4.27. Long-term outage costs of two network solutions.
113
4.5. Background information required in the process
Background information plays a crucial role in the network strategy process. Erroneous or
deficient initial data hamper the strategy work and may lead to wrong decisions. Here, the term
‘background information’ refers both to various statistical data and different subcalculation
results as shown in Figure 4.28.
Load flow calculation
Background information and parameters for
strategy analyses
- Voltage and power losses and operational costs
- Transmission and transforming capacity� development needs
Fault current calculation
- Fault-prone line sections� Reinforcement needs
Parameters
- Unit prices of components (EMA)- Price of losses- Outage cost parameters for different
interruptions and different customer groups (EMA)
- Fault rates- Repair and reconnection times- Life-times (network components)- Work costs (maintenance, fault repair) - Interest rate- Calculation period- Load growth
Statistics
- Fault statistics- Repair and reconnection times- Current measurements- Area-specific load forecasts- Network age and condition information
Figure 4.28. Background information required in the strategy process.
In the asset management, the network information system plays a central role. Network
information systems have traditionally been used in power flow and fault current calculations.
A network information system serves asset management also by providing various statistical
data. The determination of network asset and thereby assessment of allowed return is based on
component quantity and age data. These data are typically available from the network
information system. In addition to the network information system, other information systems
utilised in the strategy work are distribution management, condition monitoring and customer
information systems.
4.5.1. Power flow calculation
Development of electricity distribution business calls for comprehensive knowledge of the
various needs related to the task. A crucial boundary condition determining the development
comes from the present transmission and transforming capacity and the future load growth
forecasts on the network. A persistent and long-standing industry as it is, electricity distribution
114
requires long-term analyses, extending up to 20 years from the present. Regional load growth
forecasts require for instance detailed study of the land use planning in towns and other
municipalities.
From the very early days of information system applications in electricity distribution
companies, determination of losses and voltage drops, that is, load flow calculation, has been
considered to constitute one of the most essential calculation targets. The results of load flow
calculation are applied to asset management especially when estimating the sufficiency of
transmission and transforming capacity in the future, in other words, whether it is necessary to
build new primary substations in the company’s area of operation, or whether the demand for
power can be covered with the present network structures. As the weight of operational costs is
increasing in the official regulation, also the role of loss costs gains importance in asset
management. Load flow calculation provides background information for increasing
transforming and transmission capacity if for instance the risk of large outages increases as a
result of insufficient/limited capacity. Figure 4.29 lists the initial data in power flow calculation
and application targets for the calculation results.
ENERGY INFORMATION
-Energy information (billing, CIS)
-Load models (nationwide, customer-specific)
ENERGY INFORMATION
-Energy information (billing, CIS)
-Load models (nationwide, customer-specific)
NETWORK INFORMATION
-Primary transformers (110/20 kV)
-Medium-voltage network
-Distribution substations
-Disconnectors
-Low-voltage network
-Normally open points
NETWORK INFORMATION
-Primary transformers (110/20 kV)
-Medium-voltage network
-Distribution substations
-Disconnectors
-Low-voltage network
-Normally open points
MEASUREMENTS
-Primary transformers
-Medium-voltage feeders
-Distribution substations (peak current)
-Voltage measurements
MEASUREMENTS
-Primary transformers
-Medium-voltage feeders
-Distribution substations (peak current)
-Voltage measurements
CALCULATION PARAMETERS
-Voltage
-Load growth
CALCULATION PARAMETERS
-Voltage
-Load growth
Voltages and voltage dropsVoltages and voltage drops
Initial data for power flow calculations
Results and targets of power flow calculations
Load rate of conductorsLoad rate of conductors
Load rate of primary and distribution transformers
Load rate of primary and distribution transformers
Backup power analysesBackup power analyses
Optimisation of normally open points of the network, economic operation of the network
Optimisation of normally open points of the network, economic operation of the network
Investment of transmission and transformation capacity
Investment of transmission and transformation capacity
Relay settings of the networkRelay settings of the network
Outage cost calculationsOutage cost calculations
(CIS=customer information system)
Figure 4.29. Initial data and targets of power flow calculation.
115
The accuracy of the results of power flow calculation has a significant influence on the future
investment decisions. The reliability of results depends on the initial data used in the power
flow calculation; network and customer data and calculation parameters. Considering
calculation parameters, determining the regional development of load levels is one of the most
challenging tasks. Owing to the long lifetimes of network investments, an error in the estimate
for the annual development of the load level may significantly influence the calculation results.
The correctness and accuracy of the results of power flow calculation have to be checked and
assessed before the results can be applied to long-term network planning. This assessment stage
is critical always when large network investments or changes in the network structure or loads
are considered. Figure 4.30 depicts the initial data, the assessment process and further use of the
results.
RESULTS FROM POWER FLOW CALCULATION
RESULTS FROM POWER FLOW CALCULATION
MEASUREMENTS� Load rate of primary transformers� Load rate of feeders� Load rate of distribution transformers� Voltage levels at the end of feeders
MEASUREMENTS� Load rate of primary transformers� Load rate of feeders� Load rate of distribution transformers� Voltage levels at the end of feeders
ENERGY� kWh data
� Load models
ENERGY� kWh data
� Load models
NETWORK� Component data� Topology, supply areas
NETWORK� Component data� Topology, supply areas
COMPARISON
CHECK LIST� Customer energy information (reasonable kWh data)� Topology of the network (simulation vs. real situation)� Quality of load models � Remeasurements for feeders and distribution
substations
CHECK LIST� Customer energy information (reasonable kWh data)� Topology of the network (simulation vs. real situation)� Quality of load models � Remeasurements for feeders and distribution
substations
DIFFERENCE SIGNIFICANT BETWEEN SIMULATION AND MEASUREMENTS
RESULTS O
K
FURTHER PROCESSING OF POWER FLOW CALCULATION RESULTS
� Backup power analyses (primary substation faults, feeders)
� Increase in transmission and transformation capacity � Reliability calculations� Protection analyses and relay settings� Optimisation of normally open points of the network,
economic operation of the network
FURTHER PROCESSING OF POWER FLOW CALCULATION RESULTS
� Backup power analyses (primary substation faults, feeders)
� Increase in transmission and transformation capacity � Reliability calculations� Protection analyses and relay settings� Optimisation of normally open points of the network,
economic operation of the network
RECALCULATION OF POWER FLOW RECALCULATION OF POWER FLOW
RESULTS OK
DIFFERENCE SIGNIFICANT BETWEEN SIMULATION AND MEASUREMENTS
Figure 4.30. Assessment process of the power flow calculation results.
The results of power flow calculation are applied for instance to determine investment needs
from the perspective of transmission or transforming capacity and in loss and outage cost
calculation. Figure 4.31 illustrates an example of regional load growth estimates and
distribution of loads by primary substations.
116
+ 23.2
+13.6+ 0.5
+ 13.2
+1
+7.1
+8.1
+ 4.2
+1.6 +1.8
+ 1
+ 0.9
+ 1.9
+ 0.1
+ 1.1
+ 0.7
+ 0.6
+ 0.9
+ 0.6+ 0.6
+ 1
+ 13
+ 7
+2.2
+ 0.5
Load forecast 2007–2025 (maximum forecast)
PS 1
PS 2
PS 3
PS 4
PS 1 - 31.5 MVA2007: 20 MW2010: + 8 MW (max. + 10 MW)
2015: + 24 MW (29) *2020: + 43 MW (51) *2025: + 54 MW (64) *
PS 2 - 25 MVA2007: 13 MW2008: 5 MW2010: + 1 MW2015: + 2 MW2020: + 3 MW2025: + 5 MW
PS 3 - 20 MVA2007: 18 MW2010: + 2 MW (3)
2015: + 4 MW (5) *2020: + 7 MW (8) *2025: + 11 MW (13)*
PS 4 - 31.5 MVA2007: 0 MW2008: 8 MW2010: + 2 MW (3)
2015: + 8 MW (11)
2020: + 17 MW (22) *2025: + 37 MW (50) *
* = need to increase trasformer capacity
Load growth [MW]Substation 2010 2015 2020 2025PS 1 8 24 43 54PS 2 1 2 3 5PS 3 2 4 7 11PS 4 2 8 17 37
14 38 69 107
Load growth [MW]Substation 2010 2015 2020 2025PS 1 8 24 43 54PS 2 1 2 3 5PS 3 2 4 7 11PS 4 2 8 17 37
14 38 69 107
PS = 110/20 kV primary substation
Figure 4.31. Forecast for the increase in demand for electric power [MW] in the example area.
The results describing loading of the distribution network serve already as such in the long-term
development of the network. The results of power flow calculation may set a boundary
condition on the strategy work; even if the age or reliability of the network did not require
renovation, insufficient transmission capacity may compel certain actions. In such a case, an
increase in capacity is planned to be carried out so that it best serves also the other targets set in
the strategy.
4.5.2. Fault current calculation
Similarly as the results of load flow calculation, the results of fault current calculation carried
out by network information systems are applied to long-term development of the distribution
network. In the strategic planning, fault current calculation can be applied for instance to
guarantee that a primary substation construction project, which is found necessary based on
network reliability requirements, does not lead to excessive conductor replacement needs
117
because of increasing fault currents. The weight of short circuit current calculation has
nevertheless decreased in the past few decades. Previously, the medium-voltage network had to
be reinforced because of increased fault currents. This was the situation particularly in rural
areas, where the main transformer capacity at the primary substations had to be increased and
the mains of the medium-voltage networks had to be reinforced as the voltage drops were
increasing on the network. This led to a significant increase in fault currents and problems in
particular on branch lines with low power and small conductor cross-section. Figure 4.32
presents the initial data and application targets of the results of fault current calculation. A
successful short-circuit calculation requires extensive initial data of the lines, relays and the
supplying main grid.
POWER FLOW DATA
-MV network power flow
POWER FLOW DATA
-MV network power flow
NETWORK DATA
-Transmission network
-Primary transformers (110/20 kV)
-Protection relays
-Medium-voltage network
-Circuit breakers and reclosers
-Network topology
NETWORK DATA
-Transmission network
-Primary transformers (110/20 kV)
-Protection relays
-Medium-voltage network
-Circuit breakers and reclosers
-Network topology
CALCULATION PARAMETERS
-Calculation voltage
CALCULATION PARAMETERS
-Calculation voltage
Modification needs in relay settingsModification needs in relay settings
Initial data in short-circuit calculations Results and application targets of short-circuit calculation
Backup power analysesBackup power analyses
Effects of an increase in primary transformer capacity
Effects of an increase in primary transformer capacity
Line sections without short-circuit withstand capacity
Line sections without short-circuit withstand capacity
Figure 4.32. Initial data and application targets of short-circuit calculation.
From the perspective of electrical safety and reliability, earth fault calculation produces
valuable information for the long-term development. The expanding use of underground cabling
increases fault currents in the medium-voltage network. In poor earthing conditions, this may
mean facing the limits of electrical safety requirements and increased investments in earthing or
compensation of earth fault currents. As a single investment, compensation equipment is an
expensive one. The decreasing effect of the equipment on earth fault current has a positive
influence on the reliability of the network (reclosings). Thus, in the company’s investment
strategies, compensation equipment has to be regarded as an investment improving the
reliability of the network.
118
4.5.3. Network age and condition data
The age and condition of the network have a crucial impact on the company development plans,
in particular from the viewpoint of the development schedule. The prevailing situation in the
field is that the ages of networks are high and extensive renovations are required in the near
future. For the network strategy, a sufficiently detailed and extensive database for instance on
the age and mechanical condition of the wood poles in the overhead network is required. This
information together with the reliability statistics and loading of the network is applied to
allocate investments to targets requiring special attention. Figure 4.33 introduces some
principles of processing of the condition monitoring data.
INSPECTION DATA
INSPECTION DATA
NETWORK DATA� MV network� Distribution transformers� Circuit breakers, reclosers and disconnectors� Pole data
NETWORK DATA� MV network� Distribution transformers� Circuit breakers, reclosers and disconnectors� Pole data
CHECK-UP LIST� Repair of detected defects� Comparison with the previous inspection: have the
detected defects been repaired? Do the same defects occur repeatedly ath the same locations?
CHECK-UP LIST� Repair of detected defects� Comparison with the previous inspection: have the
detected defects been repaired? Do the same defects occur repeatedly ath the same locations?
OK (Nothing to repair)
CONDITION MONITORING DATA� Input of condition data into NIS or condition
monitoring system� Listing of targets critical with respect to age, condition
and loads� Renovation planning
CONDITION MONITORING DATA� Input of condition data into NIS or condition
monitoring system� Listing of targets critical with respect to age, condition
and loads� Renovation planning
INSPECTIONINSPECTION
DEVELOPMENT PLANNING� Linking the condition and age data and the list of critical
components to the planning process and network renovation
� Solutions to recurrent problems
DEVELOPMENT PLANNING� Linking the condition and age data and the list of critical
components to the planning process and network renovation
� Solutions to recurrent problems
DEFICIENCIES DETECTED IN INSPECTION
CRITERIA� Consistent, unambiguous and justifiable criteria and
procedures� Updating of the criteria
CRITERIA� Consistent, unambiguous and justifiable criteria and
procedures� Updating of the criteria
Figure 4.33. Processing of the condition monitoring data in asset management.
Figure 4.34a provides an example of the present state of a distribution network with the
installation year data of the wood poles. The figure shows that already the present state calls for
extensive investment in the renewal of the network. In the example case, almost a third of the
wood poles in the network have exceeded the 40 years’ lifetime. In addition, considering the
allowed return and the distribution business regulatory model, incentives for renovation are
significant. A high pole age alone does not tell whether the line requires instant renovation.
Figure 4.34b presents the results of a condition survey for the area in question. The figure
119
shows that the major problems are limited chiefly to the wood poles installed before the mid-
1970s.
0
100
200
300
400
500
600
< 5 5 - 10 11 - 15 16 - 20 21 - 25 26 - 30 31 - 35 36 - 40 41 - 45 46 - 50 51 - 55 > 55
Ikä
Num
ber
of p
oles
Age
26 % 29 %
1934 1951 1954 1957 1960 1964 1968 1971 1974 1977 1980 1983 1986 1989 1992 1995 1998 2001 2004
0
50
100
150
200
250
300
350
Pyl
väid
en m
äärä
[kp
l]
Kyllästysvuosi
LAHOA YLI 20 MM
LAHOA 10-20 MM
LAHOA 2-10 MM
LAHOA 0-2 MM
TERVE
Year of impregnation
Num
ber
of p
oles
Diameter of rot
Over 20 mm
10–20 mm
2–10 mm
0–2 mm
Healthy
a) b)
Figure 4.34. Example of the age and condition data of wood poles on medium-voltage lines.
By combining age and condition data, valuable information is obtained on network sections
requiring special attention. When considering only minimising of investment costs, it would be
advisable to replace the wood poles by new ones right when they reach their lifetime and the
limits of sufficient operating condition. This has been the common practice in Finland until the
turn of 2000s, and it is partly the reason why the present distribution network includes poles of
almost all ages, as shown in Figure 4.35.
> 40 years
30 – 39 years
20 – 29 years
10 – 19 years
< 10 years
Figure 4.35. Example of the age data of wood poles on medium-voltage lines.
Considering the reliability of the network, a problem in a pole renewal of this kind is that the
network topology and locations of the lines remain unchanged; the number of supply outages
caused by storms will not decrease if only the poles are replaced by new ones without
transferring the lines to safer areas, such as fields or roadsides.
120
4.5.4. Reliability calculation
Reliability calculation (outage cost calculation) plays a key role in the present network
strategies and distribution business (Sand et al., 2004). In the strategy work, reliability
calculation aims at analysing the large-scale effects of different network solutions on the indices
describing the reliability of distribution networks (such as SAIFI, SAIDI, MAIFI) and outage
costs. In reliability calculation, challenges are posed by different cross effects of actions; for
instance, network automation added to the medium-voltage network influences the economic
feasibility of underground cabling and vice versa. Network renovation usually consists of a
number of different structural renewals, and therefore, their mutual effects have to be known. In
this work, reliability issues have already been considered from the perspective of individual
technologies for instance for the case of a circuit recloser and the comparison underground
cable – overhead line in sections 4.2.2 and 4.2.3. Figure 4.36 provides some initial data needed
in the reliability calculation and the most relevant application targets of the calculation results in
the long-term network development.
POWER FLOW DATA
-MV network power flow
POWER FLOW DATA
-MV network power flow
NETWORK DATA
-MV network
-Distribution transformers
-Circuit breakers, reclosers and disconnectors
-Network structure and topology (forest, field, roadside)
NETWORK DATA
-MV network
-Distribution transformers
-Circuit breakers, reclosers and disconnectors
-Network structure and topology (forest, field, roadside)
CALCULATION PARAMETERS
-Outage cost parameters (€/kWh, €/kW)
-Fault frequencies
-Load growth
CALCULATION PARAMETERS
-Outage cost parameters (€/kWh, €/kW)
-Fault frequencies
-Load growth
Line sections critical with respect to reliability of supply
Line sections critical with respect to reliability of supply
Initial data in outage cost calculation Results and application targets of outage cost calculation
Reserve power analysisReserve power analysis
Optimisation of normally open points of feeders, economical operation of the network
Optimisation of normally open points of feeders, economical operation of the network
Need for an increase in transmission capacityNeed for an increase in transmission capacity
Protection relay settings on the networkProtection relay settings on the network
Assessment of the need for an increase in network automation
Assessment of the need for an increase in network automation
NETWORK OPERATION DATA
-Normally open points
-Fault disconnection time (manual/remote-controlled)
-Fault repair time
-Fault statistics
NETWORK OPERATION DATA
-Normally open points
-Fault disconnection time (manual/remote-controlled)
-Fault repair time
-Fault statistics
Outage costs by feeders and distribution districts
Outage costs by feeders and distribution districts
Figure 4.36. Initial data and application targets of reliability calculation.
The principles of reliability calculation in the asset management system are based on a radially
operated medium-voltage network. As most of the outages (80–90 %) of the outages
experienced by electricity consumers originate in the medium-voltage network, the faults
occurring in the low-voltage network are neglected in the calculation. The number of outages,
121
their duration and outage costs can be calculated by the following equations (Mäkinen et al.,
1990); the subscript j denotes electricity consumer and the subscript i network component from
the set of the components I.
Outage rate ∑∈
=Ii
ij ff (4.12)
Annual outage time ∑∈
⋅=Ii
ijij tfU (4.13)
Average outage duration
j
j
jf
Ut =
(4.14)
Non-distributed energy jjjj PtfE ∆⋅⋅= (4.15)
Outage costs [ ]∑∈
∆+=Ii
jijijjjij PttbafC )( (4.16)
The above equations can be used to calculate the indices that describe the reliability for each
electricity consumer. The first equation describes the total number of outages, which can be
calculated by determining the failure rates fi of the components i in the medium-voltage feeder.
For instance, if the total line length is 120 km, and the failure rate of the sustained faults on the
overhead lines is 5 faults/100 km per annum, each consumer experiences in average six faults in
a year, depending on the number of faults occurring on the lines.
The outage cost for each electricity consumer can be calculated with Eq. (4.16). The calculation
of costs is based on the approach of Eq. (4.13); that is, first, we determine the number and
duration of faults caused by each network component to a consumer. The outage costs
122
experienced by the electricity consumer depend on the number and duration of faults and the
power and type of the electricity consumer. The annual mean power is usually assumed as the
outage power. The outage costs are usually estimated by a constant term proportional to the
power (parameter a in Eq. (4.16)) and by a term proportional to the outage time (non-distributed
energy; parameter b in Eq. (4.16)). The amount of outage costs also depends strongly on the
type of the electricity consumer; for instance, an outage cost caused for instance to services is
manifold when compared with the costs caused to domestic customers (Järventausta et al.,
2003). Figure 4.37 depicts determination of outage costs for a single supply area of a
distribution transformer; this is a procedure used in the asset management system also.
Number of Mean power of Mean power Outages/customer, acustomers Energy [MWh] the group [kW] [kW/as] Outage time, planned 3.5 h
Domestic 2 25 2.9 1.43 Outage time, fault 1 hAgriculture 2 52 5.9 2.97 Number of outages, fault 5 pcsIndustry 1 80 9.1 9.13 Number of outages, planned 1 pcsPublic 1 11 1.3 1.26 High-speed automatic reclosings 10 pcsService 1 14 1.6 1.60 Delayed automatic reclosings 2 pcs
High-speed DelayedOutage cost values [€/kW] [€/kWh] AR [€/kW] AR [€/kW]
Domestic fault 0.36 4.29 0.11 0.48planned 0.19 2.21
Agriculturefault 0.45 9.38 0.2 0.62planned 0.23 4.8
Industry fault 3.52 24.45 2.19 2.87planned 1.38 11.47
Public fault 1.89 15.08 1.49 2.34planned 1.33 7.35
Service fault 2.65 29.89 1.31 2.44planned 0.22 22.82
Outage costsDomestic Agriculture Industry Public Service Sum Percentage
Outage time, planned 42.9 195.0 781.3 66.5 167.4 1253 62.7 %Outage time, fault 6.3 28.5 104.7 9.3 36.5 185 9.3 %Number of outages, fault 5.1 13.4 160.7 11.9 21.2 212 10.6 %Number of outages, planned 0.5 1.4 12.6 1.7 0.4 17 0.8 %High-speed automatic reclosings 3.1 11.9 199.9 18.8 21.0 255 12.7 %Delayed automatic reclosings 2.7 7.4 52.4 5.9 7.8 76 3.8 %
61 257 1312 114 254 1998 100.0 %
CENSOutage timeMean powerNumber of customersCost ⋅⋅⋅=
CENSOutage timeMean power of the customersCost ⋅⋅=
OR
Figure 4.37. Calculation of outage costs for the electricity consumers of a single supply area of a
distribution transformer (Järventausta et al., 2003).
Calculation of outage costs is affected by the parameters applied in the analyses; for instance, as
outage parameters, it is possible to use the common national values determined by the Energy
Market Authority, or company- or target-specific customer distribution can be used in the
reliability calculation, as shown in Figure 4.37.
There are various uncertainty factors related to the fault statistics, outage cost calculation and
selection of structural solutions. For instance, the network fault statistics and distribution
123
management systems involve a challenge; in the case of planned outage costs (work outage),
the distribution management system may record a single operation carried out in a certain target
as several work outages if more than one connections are made in the target for example in the
same day. From the viewpoint of a customer, this is correct when all individual outages and
restorations of supply and the actual time without supply are taken into account with an
accuracy given by the distribution management system. However, considering the assessment
of the reliability of a network structure, it is problematic that the same target can be recorded as
three to five separate work outages at worst. Therefore, in the strategy work, special attention
has to be paid to the determination of parameters used in the analyses.
Similarly as the adequate usability and reliability of the results of load flow calculations
constitute the basis for the strategy work, the results of the reliability calculation have to be
critically assessed before applying them to practice. To this end, sufficiently extensive and
versatile statistics on different network solutions are needed to be able to assess the initial data
and calculation results. Figure 4.38 presents the initial data, the assessment process and the
further use of the results.
OUTAGE COST CALCULATION AND RESULTS
OUTAGE COST CALCULATION AND RESULTS
POWER FLOW DATA� Power flow results for
the MV network
POWER FLOW DATA� Power flow results for
the MV network
NETWORK DATA� MV network� Distribution transformers� Circuit breakers, reclosers and
disconnectors� Network structure and topology
NETWORK DATA� MV network� Distribution transformers� Circuit breakers, reclosers and
disconnectors� Network structure and topology
CHECK-UP LIST� Does the network structure used in calculations correspond
with the actual situation (cabling rate of feeders etc.)?� Do the actual fault statistics cover a long-enough time span?
CHECK-UP LIST� Does the network structure used in calculations correspond
with the actual situation (cabling rate of feeders etc.)?� Do the actual fault statistics cover a long-enough time span?
SIGNIFICANT DIFFERENCE (between fault frequencies applied to calculations and actual values)
RESULTS OK(fault frequencies applied to calculations correspond with actual values)
FURTHER USE OF OUTAGE COST RESULTS� Assessment of outage costs� Line sections critical with respect to reliability of supply� Optimisation of normally open points of feeders, economical
operation of the network� Renovation planning� Protection settings of the distribution network � Assessment of the need for an increase in network automation
FURTHER USE OF OUTAGE COST RESULTS� Assessment of outage costs� Line sections critical with respect to reliability of supply� Optimisation of normally open points of feeders, economical
operation of the network� Renovation planning� Protection settings of the distribution network � Assessment of the need for an increase in network automation
NETWORK OPERATION DATA� Normally open points� Fault isolation time (manual, remote)� Fault repair time� Fault statistics
NETWORK OPERATION DATA� Normally open points� Fault isolation time (manual, remote)� Fault repair time� Fault statistics
ANALYSIS OF CALCULATED AND ACTUAL FAULT FREQUENCY
STATISTICS
ANALYSIS OF CALCULATED AND ACTUAL FAULT FREQUENCY
STATISTICS
DEVELOPMENT PLANNING� Add automation, modify the network structure, adjust
location of lines → adjust fault frequency in calculations� Perform outage cost calculation again
DEVELOPMENT PLANNING� Add automation, modify the network structure, adjust
location of lines → adjust fault frequency in calculations� Perform outage cost calculation again
OUTAGE COST PARAMETERS(€/kW,a and €/kWh)
Figure 4.38. Assessment process of the reliability of outage cost calculation.
124
125
5. Strategic decision-making
In this chapter, the target is to illustrate how the development strategies introduced in Chapter 4
and the concept approach presented in Figures 2.4 and 2.5 can be applied to the strategy work in
an actual distribution network environment (Figure 2.5 is repeated as Figure 5.1 for the
convenience of the reader). The results presented here are examples from actual distribution
networks; however, it is emphasised that the results cannot be generalised as such. In the
strategy process, the objective in the decision-making stage is to establish the models of
operation that have been found feasible in the network analyses and agreed upon in the
negotiations between the owner and the operative management of the distribution company.
Successful strategic decision-making calls for extensive surveys on the operating environment
and analyses of the potentials of different network technologies. The decision-making addresses
issues related to the scope and schedule of application of different technologies to the long-term
network planning; see Figure 5.1. The decision-making is based on cost and reliability analyses
of the strategies.
Strategic analyses
Long-term plan
Implementation of strategic decisions
Potential use of technologies (%)- Transfer of overhead lines to roadsides (25 %)- Underground cabling (10 %)- Remote-controlled disconnector substations, circuit
reclosers (1 pcs/feeder)- 1000 V technology (30 %)
Cost effects of the technologies- Transfer of overhead lines to roadsides (50 km/a, 1 M€/a)- Underground cabling (5 km/a, 250 k€/a)- Remote-controlled disconnector substations, circuit
reclosers (20 pcs/a = 250 k€/a)- 1000 V technology (50 km/a, 1 M€/a)
A long-term plan for the example area and the whole distribution company taking into account the strategic decisions made in the process.
How a single development technology e.g. underground cabling is implemented in practice?
- Underground cabling: starting from the feeder sections most vulnerable to faults, or from the oldest sections, or by proceeding from the substation downstream from the feeder
- Network automation:…
What are the effects of different development methods?
- Costs, reliability, distribution fee, allowed return
Strategic decisions
Reliability effects of the technologies fault duration rate reclosings
- Transfer of overhead lines to roadsides (x) x x- Underground cabling (x) x x- Remote-controlled disconnector
substations, circuit reclosers x/x -/x -/x- 1000 V technology (x) x x
Owners’ objectives- Reduction in SAIDI 20–40 %- Increase in the present value of the network from 45 to 50 %
Calculation parameters- Unit costs: x €/km, y €/pcs- Losses: 50 €/MWh- Outage cost values: EMA- Interest rate: 5 %- Lifetime: limits set by EMA (maximum)- Load growth: 1–3 %/a (by regions)- Fault rates: x pcs/100km,a (overhead line)…- Switching times: 60 min (manual), 10 min (remote) - Repair times: 4 h (cable), 2 h (overhead line)…
- Main technologies- Owner’s perspectives
(amount and schedule of investments)
Figure 5.1. (Figure 2.5 repeated) Network strategy process: from strategic decisions to a long-term plan.
126
The electrotechnical state, reliability, age and condition of the distribution networks have to be
taken into account in the strategic decision-making; these factors significantly affect the
strategic planning. For instance, new primary substations added to the network to increase the
transmission capacity will reduce the need for network automation, which is otherwise found
profitable in the strategy work. Cross effects are significant in network development, and they
have to be taken into account regularly in the strategy work (Grünig and Kühn, 2006, p. 85). In
the decision-making stage, the calculation principles and parameters as well as their mutual
effects have to be recognised and understood by the parties involved in the process.
Furthermore, it is necessary to assess and understand what kind of large-scale effects the results
obtained in the potential surveys of different network technologies may have on the company
business. For example, a network technology, which has obtained a 5 % application potential in
the feasibility study (e.g. 1000 V technology) may turn out to have a 30 % potential if the initial
data such as costs and calculation parameters are varied in the analyses. A need for variation
may arise from internal needs, such as changes in cost structures, or outside the company, such
as changes in the outage cost parameters in the regulatory model. Thus, in order to be viable,
strategic decision-making has to be based on various sensitivity analyses.
5.1. Strategy analyses
In the strategy work, a survey on the operating environment of the distribution company
together with an analysis of alternative development technologies draws the focus on those
issues that have the strongest influence on the company business in the future. There may be a
vast number of network development options available, and therefore, these choices have to be
limited by strategic decisions before introducing the options into the actual development
process. The decision-making is supported and facilitated by the cost and reliability analyses
introduced in Chapter 4; such tools are selected that best contribute to reaching the objectives
set by the distribution company. The cost analysis of different development alternatives is based
on the principles presented in section 4.4.6. Lump-sum investment costs are scheduled for
instance by applying the annuity method for the whole network lifetime, or alternatively, the
periodic costs such as operation and maintenance costs are converted to the present value to
enable comparison.
127
A development strategy may comprise several different network technologies. The development
strategy, the total costs of which are the lowest, may include for instance underground cabling
of the medium-voltage network and transfer of overhead lines to roadsides, network automation
and 1000 V low-voltage technology. The development strategies may vary considerably
between different distribution companies. For instance, considering the 1000 V technology, the
geographic conditions and location of a distribution company significantly affect the feasibility
of the technology. Figure 5.2 illustrates the proportion of low-loaded branch lines suitable for
1000 V technology in the entire distribution network in some example companies. The figure
shows that differences between companies may be considerable in the feasibility of the
technology, and consequently, the contents of the development strategy may vary substantially
among companies. For company 1, in the strategic sense, the 1000 V has a marginal role as a
replacement of the medium-voltage network, as only 8 % of the present medium-voltage
network includes low-loaded branch lines suitable for 1000 V technology. In companies 2 and 5
instead, the proportion of suitable branch lines is about 40 % of the total medium-voltage
network. Although this figure only gives an indication of the theoretical maximum
exploitability of the technology, the proportion of network suitable for the development
alternative in question is so large that the issue has to be considered in the strategy process.
0 %
10 %
20 %
30 %
40 %
50 %
60 %
70 %
80 %
90 %
100 %
Company 1 Company 2 Company 3 Company 4 Company 5
Low -loaded branchlines
Heavy-loaded branchlines
Main trunks
Figure 5.2. Exploitability of the 1000 V technology in the example distribution companies.
The contents of the strategy are not necessarily the same for the entire operating area of the
distribution company but the composition and application of the strategy may vary depending
128
on the network technologies applicable in practice. For instance the issue of underground
cabling is strongly dependent on soil properties and opportunities to apply cost-efficient
ploughing technology. In some other network targets, the selection of network development
technologies and other technical decisions may be directed by a strong load growth and severe
weather phenomena in the area. Figure 5.3 illustrates an example calculation result of the long-
term costs of different network development alternatives in an example distribution company.
The costs have been calculated for the whole network lifetime, in this case for 40 years.
0
10 000
20 000
30 000
40 000
50 000
60 000
70 000
80 000
1 2 3 4 5 6Network Strategy
To
tal
cost
s o
f th
e st
rate
gy
[k€
]
OPEX
OUTAGE
FINANCING
INVESTMENTS
Development strategy
Tot
al c
osts
of
the
stra
tegy
[k€]
Figure 5.3. Annual costs of the investment strategies divided into investment, operational and outage costs.
Based on the owners’ objectives and development prospects in the operating environment, a
distribution company can emphasise certain cost components, or alternatively, omit them from
the strategic consideration altogether. The major single uncertainties related to the cost
components presented in the above figure concentrate on reliability and blackout costs.
Moreover, attention has to be paid to environmental factors presented in Chapter 3 in particular
when the operating environment of the distribution company is susceptible to the effects of
climate change. From the perspective of network operation, the annual variation in adverse
weather phenomena may be large, and estimating the scope of climate change for instance 20
years ahead will be extremely challenging. Severe and frequently occurring blackouts may have
a decisive effect on the total long-term costs of overhead line solutions.
129
Generally speaking, the role of outage costs is significant and will gain further importance in
the long term. Along with the general development in society, the requirements for higher
reliability will be emphasised; this will show particularly in weighting of outage cost
parameters. Therefore, considering reliability parameters, it is necessary to carry out different
sensitivity analyses to get as comprehensive overall picture as possible. Figure 5.4 illustrates
how a change in outage parameters affects the costs of alternative development methods in an
example network area. The present level of outage cost (100 %) depicts the situation before the
update of outage cost values at the turn of year 2006. The new outage cost values have nearly
doubled compared with the values ten years ago.
0
20 000 000
40 000 000
60 000 000
80 000 000
100 000 000
120 000 000
140 000 000
160 000 000
180 000 000
100%200%
300%400%
500%600%
700%800%
900%1000%
1100%1200%
1300%140
0%150
0%
Keskeytyskustannusparametrien arvostuksen muutos
Total costs
of the strategy [€]
Valuation of outage costs (100 % = present valuation level)
Renovation with the present technology
Transfer to roadsides
Lines next to road + 1 kV technology
Underground cabling
Lines next to road with covered conductors + 1 kV
Figure 5.4. Effect of changes in the valuation of outage costs on the total costs of different investment
strategies. 100 % refers to the situation before the update of outage cost values at the turn of year 2006
(Matikainen, 2006) and (Lassila et al., 2007b).
The above figure emphasises the importance of the sensitivity analyses made as part of strategic
calculations. Development in the operating environment and initial data may have a crucial
effect on the strategic decisions. In addition to the sensitivity analysis of outage cost parameters,
it is advisable to vary for instance the unit prices of network components, load growth forecasts
and fault frequencies in the strategic calculation. By sensitivity analyses, it is possible to better
take into account such uncertain initial data, which, when changing, would strongly affect the
strategic choices. The example illustrated in the above figure shows for instance that if the case
network is renovated with the present technology, an optimum level in costs will not be reached
at any time. On the other hand, construction of a full-scale underground cable network would be
reasonable and justified, if the valuation of outage costs were four- to fivefold compared with
the latest outage cost values. For this case network an optimal solution is reached by applying
130
several different technologies in the development of the distribution network. It is also worth
pointing out here that the cost analysis of network strategies presented is not universal but the
analysis has to be made for each case individually. In any case, it is advisable to consider
whether the best results can be reached by putting emphasis on network automation or by
concentrating on the development and utilisation of the primary technology.
5.2. Strategic decisions
As a result, the strategy analyses produce the main technology choices for long-term
distribution network development. The strategic decisions call for guidelines from the owners
concerning annual investment appropriations, objectives for reliability, and development targets
set for distribution fees and return. The methodology presented in the dissertation has been
applied in an actual distribution network environment. In one of the case companies, the
strategy process produced for instance the following guidelines and principles concerning the
network technologies:
- Underground cabling of the medium-voltage network will be applied only to urban
environments.
- The overhead lines in rural areas will be renovated to the roadsides either as overhead
lines or underground cables at a rate based on the natural ageing of the lines.
- The network automation rate will be increased by adding remote-controlled disconnectors
and circuit reclosers to the network. Network automation will be concentrated on those
targets where, according to the reliability calculation, the investments are the most
profitable.
- 1000 V technology is applied to the renovation of low-voltage networks and low-loaded
medium-voltage branch lines.
In particular, the above technologies will be applied to the renovation of those targets where
investments are required owing to the electrotechnical state, ageing, mechanical condition or
reliability of the distribution network. The principles of prioritisation are discussed in detail in
the following section.
131
5.3. Implementation of strategic decisions
When a distribution company has, after comprehensive analyses, decided upon a certain set of
network technologies, the next task is to address various questions related to the practical
implementation of the network development, such as where or at what kinds of targets to start
the renovation, how much is invested at an annual level, and what are the eventual effects for
instance on reliability indices and distribution fees. Selection of development targets, in other
words, prioritisation, can be based for instance on age and condition data of the network,
electrotechnical calculations or reliability statistics as shown in Figure 5.5.
KALLBÄCK
BoxGalthagen
> 40 years
30 – 39 years
20 – 29 years
10 – 19 years
< 10 years
> 8 points
7 – 8 points
5 – 6 points
3 – 4 points
< 3 points
Age
1934 1951 1954 1957 1960 1964 1968 1971 1974 1977 1980 1983 1986 1989 1992 1995 1998 2001 2004
0
50
100
150
200
250
300
350
Pyl
väid
en m
äärä
[kp
l]
Kyllästysvuosi
Mechanical condition
Reliability
Transmission capacity
MASSBY
KALLBÄCK
Box
Masby:
Söderkulla5.9 MW2.8 %
Masby:
Hitå7.6 MW5.2 %
PSS:
1 MW
PSS:
0.5 MW
Gumbostrand
Galthagen
Ingman
OLD OVERHEAD LINE
Load and line layout
INVESTMENT ORDER
Figure 5.5. Prioritisation of targets based on initial data.
Reliable and extensive initial data on the distribution network facilitate the prioritisation of
development targets (Brown et al., 2005). However, applying several initial data at a time
involves a challenge of how to weight different factors in decision-making and selection of
technologies. All the initial data cannot be converted into commensurate cost components
presented in euros; therefore, various ranking systems have to be developed to assign scores to
the compared cost parameters in order to support the decision-making. If the network
132
renovation has been postponed for a long time already, a cost-efficient renovation order can be
found reliably by concentrating first on the aged feeders. The prioritisation of targets may prove
challenging if the network sections do not essentially differ from each other with respect to the
initial data and development criteria. An example of background feeder data for prioritisation of
development targets is given in Table 5.1.
Table 5.1. Background feeder data for prioritisation of development targets.
MV networks (20 kV) LV networks (0.4 kV) Customers Energy Peak power Wood poles Outages
Total [km] UG [km] Substations Length [km] [GWh/a] [kW] Number Age [faults/100km,a] Costs [€/a]
Feeder 1 30.5 5.5 38 370.7 1 486 20.2 6 000 374 29 4.6 39 737
Feeder 2 13.7 0.3 19 55.5 538 10.3 3 200 201 28 7.8 57 345
Feeder 3 6.3 2.2 9 9.7 112 4.8 2 300 61 29 3.0 3 971
Feeder 4 28.9 7.0 31 102.5 781 6.1 2 100 327 35 5.8 24 572
Feeder 5 17.1 0.0 21 44.1 353 5.4 1 700 256 33 3.9 10 070
Feeder 6 4.5 1.1 7 14.8 287 3.2 1 100 51 30 4.1 2 426
Feeder 7 59.1 18.3 42 110.7 1 010 7.1 2 400 612 34 5.4 21 215
Feeder 8 0.3 0.3 5 0.0 1 22.8 3 800 0 20 1.0 473
Feeder 9 19.2 12.3 11 30.7 292 6.6 4 800 104 25 4.7 6 879
Feeder 10 36.3 6.8 48 106.6 956 16.5 5 400 441 28 6.9 52 617
Feeder 11 20.9 7.5 38 77.6 2 278 36.2 8 800 200 34 2.3 50 873 Figure 5.6 illustrates a case where the renovation criterion and the technology choice have been
the fault rate on the feeder, the feeder length and the network structure (overhead
line/underground cable), respectively, in an example distribution company. In this reliability-
oriented renovation example, short, already partly underground-cabled medium-voltage feeders
in urban areas are laid underground altogether, and network automation is added to long feeders
in rural areas to cut the outage costs. This kind of an approach may be adopted for instance in a
network where the reliability of supply poses a challenge but the network age does not call for
renovation yet. If, in addition to reliability, also the network age calls for actions, adding
automation to the network does not abolish the need for renovation. Now, besides adding
network automation to the network, the lines have to be renewed by replacing the poles by new
ones and by transferring the lines to the roadsides, and by applying covered overhead
conductors or underground cables.
133
0
2
4
6
8
10
12
14
16
18
0 10 20 30 40 50 60 70
Johtolähdön pituus [km]
Vik
ataa
juus
[kpl
/100
km,a
]
Feeder 2 (39 %)
Feeder 1 (44 %)
Feeder 5 (5 %)
Feeder 4 (3 %)
Feeder 3 (11 %)
Feeder 6 (1 %)
CABLING
NETWORK AUTOMATION
Feeder name (underground cabling rate,%)F
ault
rat
e [f
ault
s/10
0km
,a]
Length of the feeder [km]
Figure 5.6. Allocation of reliability investments to different feeders.
The distribution company’s investment strategy includes analyses of the actual implementation
of different network technologies (how the technologies are applied, and in which order). For
instance, implementation of underground cabling can be carried out by starting from those
feeder sections that are most vulnerable to faults, or by proceeding from the substation
downstream. Figure 5.7 illustrates an example result of an analysis in which the reliability
effects of different cabling techniques on a feeder are presented as a function of time.
0,00
0,50
1,00
1,50
2,00
2,50
0 5 10 15 20 25 30 35 40
Fault rate [faults/customer,a]
Year
Cabling-B
Cabling-A = cabling starting from the feeder sections most vulnerable to faults
Cabling-B = cabling proceeding from the substation downstream towards the end of the feeder
Cabling-C = pole-mounted circuit recloser at the beginning of a long branch line + cabling proceeding from the substation downstream towards the end of the feeder
Cabling-A
Cabling-C
Figure 5.7. Development of fault (outage) rate (SAIFI) in different cabling strategies. Forest rate 10 %,
investment costs (€) of all alternatives are the same (adapted from Haakana et al., 2009).
134
Prioritisation of targets may also be based on the progress in locations of loads. Figure 5.8
depicts the locations of loads on a rural feeder away from the line route, along the roads. The
rather straightforward choices made in route planning for overhead lines were based on material
savings targets in the past decades. The development of built-up areas and loads on the network
is mainly concentrated along roadsides. In the large-scale network renovation, it is necessary to
consider on which principles the choices for line routes are based. If the feeder renovation is
carried out by underground cabling or by transferring the line to the roadside, the distribution
system simultaneously shifts closer to the point at which the loads are actually concentrated.
110/20 kVPrimary substation
OLD OVERHEAD LINE
= Customer
= 20/0.4 kV distribution substation
Figure 5.8. Renovation of an old overhead line by shifting the line closer to the area in which the loads are
concentrated.
After the completion of the prioritisation process, potential feeders that meet different
renovation criteria are investigated; cost and reliability analyses are performed for the feeders
starting from the oldest network sections. Now it is time also to make decisions on the schedule
of renovations, that is, whether it is desirable or necessary to renew the network for instance in
10, 20 or 30 years. The timetable depends strongly on the owners’ desires, financing
arrangements and renovation resources. Figure 5.9 illustrates the first four years of the feeder
renovation scheme implemented by underground cabling on the example feeder. The renovation
is planned to be carried out in 20 years.
135
Figure 5.9. Example of a feeder renovation scheme; the first four years.
5.4. Impacts of implementation
Figure 5.10 depicts the development of reliability indices of the example feeder and the annual
investments required in the medium-voltage network. The background with diagonal lines
illustrates the first four years of renovation related to Figure 5.9.
0
50 000
100 000
150 000
200 000
250 000
300 000
350 000
400 000
450 000
500 000
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Year
Inve
stm
ent [
€/a
]
0 %
10 %
20 %
30 %
40 %
50 %
60 %
70 %
80 %
90 %
100 %
Cha
nge
in re
liabi
lity
indi
ces
Investment SAIFI SAIDI MAIFI
SAIDI
SAIFI
MAIFI
Cha
nge
in r
elia
bili
ty in
dice
s
100 %
Figure 5.10. Investments in the example feeder and the development of reliability indices as the renovation
proceeds.
136
Figure 5.10 shows that the effects of underground cabling on reliability indices are substantial;
SAIFI reduces by 72 % and SAIDI by 63 % in the case feeder. There are no autoreclosings at
all on the network at the end of the renovation schedule. Figure 5.11 depicts the effects of the
renovation scheme on maintenance, fault repair and outage costs; the outage costs decrease by
77 %.
0
5 000
10 000
15 000
20 000
25 000
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Year
Cos
ts [€
/a]
Outage costs
Maintenance
Fault repair
Figure 5.11. Development of costs occurring on the example feeder as the renovation proceeds.
The question of renovation schedule is strongly linked with the development of the
replacement and present value of the network, as well as the network components removed in
the renovation from the network before they reach their lifetime. Figure 5.12 shows how the
above renovation affects the replacement and present value of the network on the case feeder.
The figure shows that the replacement value of the medium-voltage network nearly doubles
when changing over to the underground cabling. Simultaneously, the network age is reduced
from the initial 30 years so that the present value of the network when approaching the end of
the renovation period is about 75 %. The figure also depicts the financial value of wood poles
removed from the network before the end of their lifetime, proportioned to the total network
length. The renovation has to be carried out for complete sections, and therefore, owing to the
age structure of the line, substantial amounts of network sections that still have some techno-
economical lifetime left may be removed from the network. For the example feeder, the value
of the removed feeder sections is on average 2 000 €/km. This is about 5 % when proportioned
to the total costs of underground cabling. The renovation schedule has a strong impact on the
value and amount of removal; if the renovation schedule is tight, the number of removed
network components with some lifetime left will increase. On the other hand, if the renovation
137
schedule can be extended, the amount of removed components can be minimised. In the plan
made for the example feeder, extending the renovation schedule to 30 years (Figure 5.13) will
significantly reduce the amount of annually removed pole assets that have some lifetime left,
the value of removal being less than 500 €/km. On the other hand, if the schedule can be
stretched, the amount of removals can be minimised. Halving the renovation period planned for
the example feeder to ten years doubled the amount of removals. In reality, this removal is not
necessarily shown in the financial performance of the distribution company, since the existing
network assets have probably been depreciated during the first 20–25 years. A typical lifetime
for an overhead medium-voltage line in rural areas is 40–50 years.
0
1 000
2 000
3 000
4 000
5 000
6 000
7 000
8 000
9 000
10 000
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Year
Lost
ass
et o
f woo
d po
les
[€/k
m]
0 %
20 %
40 %
60 %
80 %
100 %
120 %
140 %
160 %
180 %
200 %
Ne
t pre
sen
t an
d r
ep
lace
me
nt v
alu
e
Replacement value
Present value
Removed asset of wood poles Removed asset of wood poles [€/km]
Figure 5.12. Development of the replacement and present value of the example feeder and the amount of
pole assets having some lifetime left, proportioned to the total line length. Reinvestment schedule 20 a.
0
1 000
2 000
3 000
4 000
5 000
6 000
7 000
8 000
9 000
10 000
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Year
Lost
ass
et o
f w
ood
pole
s [€
/km
]
0 %
20 %
40 %
60 %
80 %
100 %
120 %
140 %
160 %
180 %
200 %
Net
pre
sent
and
rep
lace
men
t val
ue .
Replacement value
Present value
Removed asset of wood poles
Removed asset of wood poles [€/km]
Figure 5.13. Development of the replacement and present value of the example feeder and the amount of
pole assets having some lifetime left, proportioned to the total line length. Reinvestment schedule 30 a.
138
Deviating from the previous consideration presented in Figure 5.14 for a single feeder, the focus
is now on a larger network section covering the whole area of a primary substation. The
network section under consideration is ten times as large as in the case of an example feeder.
The figure shows, according to different investment schedules, what is the proportion of those
wood poles removed from the network that have reached their lifetime (in this case 40 years).
The amount of renovation is evenly distributed to different years according to the length of the
reference period so that at the end of the renovation program, the present overhead network is
fully replaced by underground cabling. The figure shows that with the shortest ten-year
investment schedule, in the first five years, the renovation can be targeted to poles that no
longer have present value. After the sixth year of the investment schedule, the proportion of
wood poles with some lifetime left in the renovated network sections increases significantly.
The percentage describes the proportion of “zero-years-old” equivalent poles having full
present value in the renovation. For instance, in the tenth year, about 65 % of the pole asset to
be renovated still has full present value. The proportion of these poles decreases significantly
when the renovation schedule is extended to 20 or 30 years. The consideration for the larger
network section, that is, the whole area of a primary substation, is based on a theoretical
analysis of the pole asset mass, in other words, there is no actual target-specific renovation plan
as in the case of the example feeder in Figure 5.9.
0 %
20 %
40 %
60 %
80 %
100 %
120 %
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30
Year
Am
ou
nt o
f wo
od
po
les
wh
ich
ha
ve b
ee
n
rem
ove
d a
t fu
ll a
ge
fro
m th
e n
etw
ork
30 a schedule
20 a schedule
10 a schedule
Figure 5.14. Amount of wood poles having reached their lifetime at the moment of removal from the
network in the 10, 20 and 30 year renovation schedule.
139
In the strategy work, also the effects of the development alternative on the distribution fees are
of interest. The analysis of these effects is based on the cost difference between a traditional
development solution and an alternative network technology. Based on the above example
network, the underground cabling strategy is compared with an alternative where an overhead
line is renovated to the roadside (in practice, a completely new line was built). In the example,
the renovation cost is here divided by the distributed energy on the average feeder (107
MWh/km). The renovation costs are calculated for a 20 year renovation schedule. The
renovation costs of cabling per energy transferred are 0.84 cent/kWh higher than in overhead
line alternative (Figure 5.15) in the example case. If the OPEX benefit is taken into account
(reduction in maintenance and fault repair costs), the renovation cost is 0.80 cent/kWh higher
than in overhead line alternative. The future target price level of underground cabling, derived
in the determination of the operating environment, has been used as the unit price of cabling in
the analysis of the example case.
Comparison: transfer of the cable to the roadside vs. transfer of the overhead line to the roadside
(0.80 cent/kWh with the OPEX benefit)
���� 0.84 cent/kWhCosts
Investments (cable) 1 946 255Investments (overhead line) 1 144 000Saving in customer outage cost (40 a) 291 330Maintenance (40 a) 100 918Fault repair (40 a) 9 925
Figure 5.15. Comparison of costs of different investment strategies and effects on the distribution fee.
The principle of the comparison method has a strong influence on the final costs of a strategy. If
in the example case, as an alternative to underground cabling, the old overhead line is renovated
in the existing line path in connection of pole renovation, the additional cost of cable renovation
per transferred energy would be 1.42 cent/kWh and 1.35 cent/kWh taking the OPEX into
account. In that case, it is assumed that the conductors and cross-arms can still be used on the
renovated line. The higher difference in costs is explained by the cost difference between a
completely new overhead line and pole renovation.
The above example shows that the network renovation schedule has a significant influence on
the costs. Considering the investment costs alone, pole renovation based on the lifetime of poles
would be the most beneficial option from the perspective of national economy. The benefits of
this alternative are further emphasised if the selection of renovation targets is based on the
140
different models developed in the recent years for pole ageing (Datla and Pandey, 2006),
(Hilber et al., 2005). Optimisation of the pole replacement schedule alone cannot provide an
answer to the challenges posed for instance by increasing labour costs, or the need to develop
network reliability. Development of the operating environment increasingly drives to such
network structural solutions that are immune to various weather events and that are cost-
efficient with respect to maintenance.
5.5. Conclusions on strategic decisions
There is a large variety of network technologies applicable to the strategy. The palette of
technologies available depends strongly on the boundary conditions set by the operating
environment and the objectives of the company owners. If the main target in the development
strategy is to make the network immune to environmental disturbances as soon as possible, the
outcome of the strategy from the viewpoint of technologies and the investment schedule is
different than if the target is only moderate renovation of the oldest network sections in order to
increase the present value of the network. The purpose of the example calculations and results
presented in this section is to illustrate how the methodology can actually be applied to the
strategic development of the network. Nevertheless, it is pointed out that the results cannot be
generalised as such, but each distribution network has to considered individually.
From the perspective of cost optimisation, the strong interactions between different
technologies have to be recognised and taken into account. The techno-economic feasibility of a
single network technology depends on whether the technology in question is used alone in
network development, or some other technologies are used in parallel in the process. Further,
the mutual order of investments in different technologies has an impact on the final result. For
instance, adoption of network automation before large-scale network renovation will reduce the
outage cost benefits of technologies applied later in the network. This is an issue that has to be
taken into account in the long-term network planning at the latest.
The strategy process has shown the importance of the operating environment in the electricity
distribution business. During this research work, the technology development and changes in
cost components in particular related to underground cabling technology have raised a question
141
of extensive underground cabling in rural areas. We may thus conclude that in the strategy
work, it is of paramount importance to reflect on the company targets with respect to the
general development in society and update the company strategies. In other words, strategy
work is an ongoing process. The owners’ objectives may eventually have a significant influence
on the investment strategy. The presence of owners directs the strategy work towards an
iterative, conversational process.
142
143
6. Conclusions
Over the past years, electricity distribution business has faced numerous challenges.
Simultaneously as the climate change and ageing networks have put pressure on developing the
distribution networks, the regulation of the distribution business has increased thereby
compelling the companies to improve the cost-efficiency of their operations. The growing
challenges have forced to find new and more efficient solutions in network development. To
this end, methodology has been developed to support strategic decision-making in electricity
distribution networks. The main contribution of this doctoral dissertation is in the analysis and
development of the strategy process of the long-term planning of electricity distribution
networks. The scientific contributions of the dissertation are the analysis and development of
the concept for strategy process, the calculation and analysis methodology developed into the
concept, and assurance of the functioning of the concept.
The concept of strategy process proposed in this doctoral dissertation can well be utilised in the
long-term development of electricity distribution networks. Furthermore, this is the first time
that strategy-level network planning methodology is presented as extensively and as a single
entity for rural distribution networks. The results of this work can be considered internationally
applicable, yet it is emphasised that diverging regulatory models in different countries call for
specific, detailed methodology in each country. The concept introduced in this work facilitates
the distribution companies to recognise and prepare for factors that have an impact on the
strategic development of distribution networks. The methodology presented in the dissertation
assists in discerning how various changes in the operating environment may affect the
investment decisions.
The most essential findings of the doctoral dissertation are concretised in the following:
- The planning concept and methods for strategic planning presented in this work (which
take into account the network age, reliability, electrotechnical and mechanical condition of
the network and environmental factors) are applicable to practice.
- The need for strategic planning has increased for instance as a result of more focused
owner policy and intensified economic regulation. Success in the distribution business
144
calls for an ability to anticipate and react to changes in the operating environment.
Electricity distribution network business, similarly as any business or investment target,
should be profitable. The most profitable solutions that best serve the owners interests can
be found when there is comprehensive knowledge on the business in the field, and the role
of the strategy process in decision-making is understood in full.
- There is no single universal model to be applied to strategic decision-making, but each
development task has to be carried out case by case. This is due to the different operating
environments and diverging targets set by the owners of the distribution companies;
moreover, these are issues that have a strong influence on the outlines and progress of the
strategy process.
- All the essential information on the distribution network (e.g. reliability, age and condition
data, information on the electrotechnical state of the network) and information on the
operating environment of the business have to be available for the strategic planning.
Should all these necessary data be not at hand for decision-making, the best results may
not be reached in minimisation of the total costs. The importance of analysing several
information sources simultaneously was accentuated for instance in section 5.3. However,
it is the strategy process that determines which of the network renovation criteria is the
most decisive one in the distribution company in question.
- The strategy process has to be updated from time to time. For instance, the entry of
electric vehicles into the market may have an influence on distribution network design in
the future. Moreover, the changing and evolving objectives and requirements of society
together with the general technological development necessitate up-to-date information in
strategic decision-making.
- Outage costs constitute an important part of the economic regulation of the electricity
distribution business, and reliability is a key driver in network planning. This results from
the constant development of society and intensified requirements for reliable supply of
electricity associated with it. The significant role of outage costs is discussed for instance
in sections 3.2 and 3.3.
145
- The high average age of distribution networks and the high renovation needs in the near
future constitute a challenge but also an opportunity. In Finland, electrification of rural
areas took place almost simultaneously in most parts of the country, and consequently, the
renovation needs are not restricted to single distribution companies. Large-scale
renovation needs, on the other hand, enable cost-efficient adoption of new network
structures and construction methods (large-scale transfer of overhead lines to roadsides
and underground cabling serving as examples).
Based on the strategy analyses and analyses on the operating environment, we may conclude
that under the conditions prevailing in Finland, in the network development work, even large
network-technological changes could be considered in the distribution system. This conclusion
is supported by the experiences obtained from the actual distribution companies during the
strategy process.
The changes taking place both in the operating environment and network technologies call for
further development of the strategy process proposed in this doctoral dissertation. Among
others, the role of distributed generation and smart grids in the network development will grow.
In order to be able to reliably embed such significant topics in the strategy process, intensive
research on these topics is required in the future also. To a certain degree, these issues will be
addressed in various national and international research projects already launched on the theme.
146
147
References
Adato. 2009. Age distribution of personnel in electricity distribution and district heating
companies in 2001–2007. Unpublished document.
ASCE. 2009. The 2009 Report Card for America's Infrastructure – Executive Summary.
American Society of Civil Engineers. Accessed 11 Oct. 2009.
www.infrastructurereportcard.org/sites/default/files/RC2009_full_report.pdf
Billinton, R. and Grover, M.S. 1975. “Reliability evaluation in transmission and distribution
systems”. In Proc. IEE 1975, pp.517–523.
Billinton, R. and Pan, Z. 2002. “Incorporating Reliability Index Probability Distribution in
Performance Based Regulation.” In Proceedings of the IEEE Canadian
Conference on Electrical & Computer Engineering. Vol. 1, May 2002, pp.
12–17.
Birtwhistle, D., Gilbert, R., Oyegoke, B., Lyall, J., Powell, L. and Saha, T. 2006. “Asset
Management of Medium Voltage Cable Networks”. In Proceedings of the
WCEAM 2006, World Congress of Engineering Asset Management.
Bouford, J. and Willis, L. 2005. “Managing Aging and Sustainable Use of T&D
Infrastructures.” Power Engineering Society General Meeting, 2005. IEEE,
pp. 2608–2609 Vol. 3.
Brown, R.E. 2009. Electric Power Distribution Reliability. Boca Raton, FL: SRS Press, Taylor
& Francis Group.
Brown, R.E., Engel, M.V. and Spare, J.H. 2005. “Making Sense of Worst-Performing Feeders.”
IEEE Transactions on Power Systems, Vol. 20, No. 2, May 2005.
Brown, R.E. and Humphrey, B.G. 2005. “Asset Management for Transmission and
Distribution.” Power and Energy Magazine, IEEE. Volume 3, Issue 3, May-
June 2005, pp. 39–45.
Brown, R.E. and Willis, H.L. 2006. “The Economics of Aging Infrastructure.” Power and
Energy Magazine, IEEE. Volume 4, Issue 3, May-June 2006, pp. 36–43.
148
Brådd, A., Lassila, J. and Partanen, J. 2006. “The Challenges of the Network Operation in the
Nordic Electricity Distribution Business Heading for 2030.” IASTED
Conference, Botswana.
CEER. 2005. 3rd Benchmarking Report on Quality of Electricity Supply 2005. Council of
European Energy Regulators ASBL. 28 rue le Titien, 1000 Bruxelles.
Arrondissement judiciaire de Bruxelles. RPM 0861.035.445.
CEER. 2008. 4th Benchmarking Report on Quality of Electricity Supply 2008. Council of
European Energy Regulators ASBL. 28 rue le Titien, 1000 Bruxelles.
Arrondissement judiciaire de Bruxelles. RPM 0861.035.445.
CIBC World Markets. Capitalizing on the Upcoming Infrastructure Stimulus. Occasional
Report #66, January 26, 2009. Accessed 11 Oct. 2009.
http://research.cibcwm.com/economic_public/download/occrept66.pdf
Civil Infrastructure Systems Technology Road Map 2003-2013. Centre for Advancement of
Trenchless Technologies, University of Waterloo, June 2003. Accessed 11
Oct. 2009. www.engineerscanada.ca/files/w_TRMReporteng.pdf .
Datla, S.V. and Pandey, M.D. 2006. “Estimation of life expectancy of wood poles in electrical
distribution networks.” Structural Safety 28 (2006) pp. 304–319.
Electricity Market Act (386/1995; amendments up to 1172/2004 included). Unofficial
translation. Ministry of Trade and Industry. Helsinki, Finland. Accessed 11
Oct. 2009. www.emvi.fi/files/electricity_market_act_20050128.pdf
Energy Market Authority (EMA) 2001. Summary: Considerations of efficiency in the
assessment of the reasonableness of electricity distribution pricing. The
Finnish Energy Market Authority’s Publications. Accessed 16 Nov. 2009.
www.energiamarkkinavirasto.fi/data.asp?articleid=253&pgid=133
Energy Market Authority (EMA) 2009a. Sähkönjakeluverkon komponenttien yksikköhinnat
vuodelle 2009. [Unit price list of network components for 2009.] In Finnish.
Accessed 11 Oct. 2009.
www.energiamarkkinavirasto.fi/data.asp?articleid=1615&pgid=195.
149
Energy Market Authority (EMA) 2009b. Sähköverkkotoiminnan tunnusluvut vuodelta 2008.
[Key parameters of electricity distribution networks.] In Finnish. Accessed 11
Oct. 2009. www.energiamarkkinavirasto.fi/data.asp?articleid=1760&pgid=69.
European Commission. Environment fact sheet: climate change. August 2005. Accessed 4 Nov.
2009. http://ec.europa.eu/environment/climat/pdf/cc_factsheet_aug2005.pdf.
European Commission. European SmartGrids Technology Platform. Vision and Strategy for
Europe’s Electricity Networks of the Future. 2006. EUR 22040. Accessed 11
Oct. 2009. http://ec.europa.eu/research/energy/pdf/smartgrids_en.pdf.
European Council. Presidency Conclusions of the Brussels European Council (March 2007).
Accessed 11 Oct. 2009.
www.consilium.europa.eu/ueDocs/cms_Data/docs/pressData/en/ec/93135.pdf.
EU Directive 2006/32/EC of the European Parliament and of the Council. Official Journal of
the European Union.
Finnish Energy Industries (ET) 2009. Keskeytystilasto 2008. [Outage statistics 2008.] Finnish
Energy Industries ET, Helsinki. Version 2009-06-03. In Finnish.
Fletcher, R.H. and Strunz, K. 2007. “Optimal Distribution System Horizon Planning–Part I:
Formulation.” IEEE Transactions On Power Systems, Vol. 22, No. 2, May
2007. pp. 791–799.
Finnish Meteorological Institute (FMI) 2009a. Miten Suomen ilmasto muuttuu? [How will the
climate change in Finland?] In Finnish. Accessed 16 Nov. 2009.
www.fmi.fi/ilmastonmuutos/suomessa.html.
Finnish Meteorological Institute (FMI) 2009b. Suomen ilmaston tulevat muutokset mallitulosten
perusteella. [Future changes in the climate in Finland based on model results].
In Finnish. Accessed 16 Nov. 2009.
www.fmi.fi/ilmastonmuutos/suomessa_18.html.
Fumagalli, E., Schiavo, L. and Delestre, F. 2007. Service Quality Regulation in Electricity
Distribution and Retail. Berlin and New York: Springer.
Grünig, R. and Kühn, R. 2006. Process-based Strategic Planning. Berlin and New York:
Springer.
150
Haakana, J., Lassila, J., Kaipia, T. and Partanen, J. 2009. ”Underground Cabling Strategies in a
Rural Area Electricity Distribution Network.” CIRED, International
Conference on Electricity Distribution. Prague, Czech Republic.
Hampson, J. 2001. “Urban network development.” Power Engineering Journal. Volume 15,
Issue 5, Oct. 2001, pp. 224–232.
Hilber, P., Hällgren, B. and Bertling, L. 2005. “Optimizing the Replacement of Overhead
Lines in Rural Distribution Systems with Respect to Reliability and Customer
Value.” CIRED, 18th International Conference on Electricity Distribution.
Turin, Italy.
Honkapuro, S. 2008. Performance benchmarking and incentive regulation- considerations of
directing signals for electricity distribution companies. Dissertation,
Lappeenranta University of Technology, Acta Universitatis Lappeenrantaensis
309, Lappeenranta.
Hoskins, R.P., Brint, A.T. and Strbac, G. 1998. “A structured approach to Asset Management
within the electricity industry.” Utilities Policy 7 (1998) pp. 221–232.
Houseman, D. 2005. “Smart metering – The holy grail of demand-side energy management?”
Capgemini Energy Utilities and Chemicals. September/October 2005.
Hänninen, M. 2008. Verkonhaltijoiden raportoimien teknisten valvontatietojen seuranta.
[Surveillance of the technical regulation data submitted by the network
operators.] Discussions meeting held at the Energy Market Authority on 11
March 2008. In Finnish. Accessed 11 Oct. 2009.
www.energiamarkkinavirasto.fi/data.asp?articleid=1509&pgid=205.
IEEE 1366-2001. IEEE Guide for Electric Power Distribution Reliability Indices. Transmission
and Distribution Subcommittee, IEEE Power Engineering Society, USA.
Ipakchi, A. and Albuyeh, F. 2009. “Grid of the future.” Power and Energy Magazine, IEEE.
Volume 7, Issue 2, March–April 2009, pp. 52–62.
Järventausta, P., Mäkinen, A., Nikander, A., Kivikko, K., Partanen, J., Lassila, J., Viljainen, S.
and Honkapuro, S. 2003. The Role of Power Quality in Electricity
Distribution Business Regulation. Publications of Energy Market Authority
1/2003. In Finnish.
151
Kaipia, T. 2004. 1000 V sähkönjakelujärjestelmän teknistaloudellisen kannattavuuden
tarkastelu. [Economic efficiency of 1000 V electricity distribution system.]
Master's thesis. Lappeenranta University of Technology. In Finnish.
Kaipia, T., Lassila, J. and Partanen, J. 2007. “A Cost Analysis Method for Storm Caused
Extensive Outages in Distribution Networks.” CIRED, International
Conference on Electricity Distribution. Vienna, Austria.
Kaipia, T., Salonen, P., Lassila, J. and Partanen, J. 2006. “Possibilities of the low voltage DC
distribution systems.” Nordic Distribution and Asset Management Conference
NORDAC 2006, Stockholm, Sweden.
Kestopuu. 2009. Production of pressure impregnated wood in Finland in 1960–2007.
Unpublished document. Kestopuuteollisuus ry.
Kivikko, K., Antila, S., Järventausta, P., Mäkinen, A., Lassila, J., Viljainen, S., Tahvanainen,
K., Partanen, J., Mogstad, O. and Tapper, M. 2005. “Comparison Of
Interruption Statistics And Their Use In Network Business Regulation In
Nordic Countries.” CIRED, 18th International Conference on Electricity
Distribution. Turin, Italy.
Korhonen, P. and Syrjänen, M. and Tötterström, M. 2000. Sähkönjakeluverkkotoiminnan
kustannustehokkuuden mittaaminen DEA-menetelmällä. [Assesment of Cost
Efficiency in Finnish Electricity Distribution Using DEA.] Publications of
Energy Market Authority, 1/2000. Helsinki. Finland (In Finnish). Accessed 11
Oct. 2009. www.energiamarkkinavirasto.fi/data.asp?articleid=387&pgid=59
Lakervi, E. and Holmes, E. J. 1995. Electricity distribution network design. 2nd Edition. IEE
Power Engineering Series 21. England.
Langset, T., Trengereid, F., Samdal, K. and Heggset, J. 2001. “Quality adjusted revenue caps - a
model for quality of supply regulation.” CIRED, International Conference on
Electricity Distribution. Amsterdam, the Netherlands.
Lassila, J., Honkapuro, S. and Partanen, J. 2005a. “Economic Analysis of Outage Costs
Parameters and Their Implications on Investment Decisions.” IEEE PES
General Meeting. San Francisco, California.
152
Lassila, J., Honkapuro, S. and Partanen, J. 2006. “Distribution Network Investment Strategies in
the New Business Environment.” IEEE PES General Meeting, Montréal,
Québec Canada.
Lassila J., Honkapuro S., Viljainen S., Tahvanainen K., Partanen J., Kivikko, K., Antila, S.,
Mäkinen, A. and Järventausta, P. 2005b. “Power Quality Factors in Efficiency
Benchmarking.” CIRED, 18th International Conference on Electricity
Distribution. Turin, Italy.
Lassila, J., Kaipia, T., Haakana J., Partanen J., Järventausta, P., Rautiainen, A., Marttila, M. and
Auvinen, O. 2009a. “Electric Cars – Challenge or Opportunity for the
Electricity Distribution Infrastructure?” European Conference: Smart Grids
and Mobility. Würzburg, Germany.
Lassila, J., Kaipia, T., Haakana, J., Partanen, J. and Koivuranta, K. 2009b. “Potential and
Strategic Role of Power Electronics in Electricity Distribution Systems.”
CIRED, International Conference on Electricity Distribution. Prague, Czech
Republic.
Lassila J., Kaipia T., Partanen J., Järventausta, P., Verho, P., Mäkinen, A., Kivikko, K. and
Lohjala, J. 2007a. “A Comparison of the Electricity Distribution Investment
Strategies.” CIRED, International Conference on Electricity Distribution.
Vienna, Austria.
Lassila, J., Kaipia, T., Partanen, J. and Lohjala, J. 2007b. “New Investment Strategies in the
Modern Electricity Distribution Business - Reliability in the Long-Term
Planning.” IEEE PES General Meeting, Tampa, USA.
Lassila, J., Tanskanen, A., Partanen J. and Lohjala, J. 2009c. “Unbundling of Operation and
Network Development Activities in Electricity Distribution.” International
Journal of Energy Sector Management. Volume 3, No. 4, 2009, pp. 383–405.
Lassila, J., Viljainen, S., Honkapuro, S. and Partanen, J. 2003a. Verkkoliiketoiminnan
tehokkuusmittauksen kehittäminen. [Development of benchmarking of
distribution business]. In Finnish.
Lassila, J., Viljainen, S. and Partanen, J. 2002. “Analysis of the benchmarking results of the
electricity distribution companies in Finland.” IEEE Postgraduate Conference
on Electric Power Systems. Budapest, Hungary.
153
Lassila, J., Viljainen, S. and Partanen, J. 2003b. “Data Envelopment Analysis in the
benchmarking of electricity distribution companies.” CIRED, International
Conference on Electricity Distribution. Barcelona, Spain.
Lave, L.B., Ashworth, M. and Gellings, C. 2007. “The Aging Workforce: Electricity Industry
Challenges and Solutions.” The Electricity Journal. Volume 20, Issue 2,
March 2007, pp. 71–80.
Lemström, B. and Lehtonen, M. 1994. Costs of Electricity Supply Outages. VTT Energy,
Energy and Power Systems. Report 2-94.
Li, Z. and Guo, J. 2006. “Wisdom About Age.” Power and Energy Magazine. IEEE Volume 4,
Issue 3, May–June 2006, pp. 44–51.
Lohjala, J. 2005. Development of rural area electricity distribution system – potentiality of
using 1000 V supply voltage. Dissertation. Lappeenranta University of
Technology. Acta Universitatis Lappeenrantaensis 205. Lappeenranta.
Lohjala, J. 2009. Age distribution of wood poles in medium-voltage networks. Unpublished
document. Järvi-Suomen Energia Oy.
Lohjala, J., Kaipia, T., Lassila, J. and Partanen, J. 2004. “Overwiev to economical efficiency of
1000 V low voltage distribution.” Nordic Distribution and Asset Management
Conference NORDAC Espoo, Finland.
Lohjala, J., Kaipia, T., Lassila, J. and Partanen, J. 2005. “Potentiality and effects of the 1 kV
low voltage distribution system.” The International Steering Committee of the
International Conference on Future Power Systems (FPS 2005), Amsterdam,
The Netherlands.
Losa, I. and Bertoldi, O. 2009. “Regulation of Continuity of Supply in the Electricity Sector and
Cost of Energy not Supplied.” IEW, International Energy Workshop. Venice.
Accessed 11 Oct. 2009. www.iccgov.org/iew2009/4-2-a-3.htm.
Martikainen, A. 2005. Ilmastonmuutoksen vaikutus sähköverkkoliiketoimintaan. [Impacts of
climate change on electricity network business.] Master's thesis. Lappeenranta
University of Technology. In Finnish.
154
Matikainen, M. 2006. Sähkönjakeluverkon kehittämissuunnitelma luotettavuuden näkökulmasta.
[Development of the electricity distribution system from aspect of reliability.]
Master's thesis. Lappeenranta University of Technology. In Finnish.
Mäkinen, A., Partanen, J. and Lakervi, E. 1990. “A Practical Approach for Estimating Future
Outage Costs in Power Distribution Networks.” IEEE Transactions on Power
Delivery, Vol. 5, No. 1, January 1990.
Norges vassdrags- og energidirektorat (NVE) 2009. Avbruddsstatistikk 2008. [Outage statistics
2008.] Pages: 96. Oslo 2009. Accessed 11 Oct. 2009.
www.nve.no/Global/Energi/Avbruddstatistikk/Rapport-Avbruddstatistikk-
2008.pdf.
Northcote-Green, J. and Wilson, R. 2006. Control and Automation of Electrical Power
Distribution Systems. Boca Raton, FL USA: SRS Press, Taylor & Francis
Group.
Paananen, A. 2008. Sähköverkkotoiminnan hinnoittelun valvonnan valvontamalli vuosille 2008-
2011 ja valvonnan jatkokehittäminen. [Regulatory model 2008–2011 for the
electricity distribution business and further development of regulation].
Discussions meeting held at the Energy Market Authority on 11 March 2008.
In Finnish. Accessed 11 Oct. 2009.
www.energiamarkkinavirasto.fi/data.asp?articleid=1509&pgid=205.
Partanen, J., Lassila, J. and Viljainen, S. 2002. Investoinnit sähkön siirron hinnoittelun
arvioinnissa. [Investments in the assessment of electricity distribution
pricing]. Publications of the Energy Market Authority 1/2002. In Finnish.
Partanen, J., Lassila, J., Viljainen, S., Honkapuro, S., and Tahvanainen, K. 2004. Investoinnit
verkkoliiketoiminnan valvonnassa – erityisesti tehokkuusmittauksessa.
[Investments in regulation – especially in efficiency benchmarking].
Publications of the Energy Market Authority, 1/2004. Helsinki, Finland. In
Finnish.
Pöyhönen, O. W., ed. 1978. Sähkötekniikan käsikirja [Electrical engineering handbook]. 5th
edition. Helsinki: Tammi. pp. 522–523.
155
Salonen, P. 2006. Tasasähkön hyödyntämismahdollisuudet sähkönjakelussa. [Exploitation
possibilities of DC in electricity distribution.]. Master's thesis. Lappeenranta
University of Technology. In Finnish.
Sand, S., Samdal, K. and Seljeseth, H. 2004. “Quality of Supply Regulation – Status and
Trends.” Nordic Distribution and Asset Management Conference NORDAC
Espoo, Finland.
Schneider, J., Gaul, A.J., Neumann, C., Hogräfer, J., Wellßow, W., Schwan, M. and
Schnettler, A. 2006. “Asset management techniques.“ Electrical Power and
Energy Systems 28 (2006) pp. 643–654.
Silvast, A., Heine, P., Lehtonen, M., Kivikko, K., Mäkinen, A. and Järventausta, P. 2005.
Sähkönjakelun keskeytyksestä aiheutuva haitta. [Outage costs in electrical
distribution networks.] Espoo: TKK.
Statistics Finland, 2009. Development of building cost index in 2000–2009. Accessed 11 Oct.
2009. www.stat.fi/
Sähköntuottajien yhteistyövaltuuskunta (STYV) 1979. Selvitys toimittamatta jääneen sähkön
arvosta (TJSA). [Report on the Value of Non-Distributed Energy, English
summary of report 1/79]. The Finnish Power Producers Coordinating Council,
Planning Committee STYV-S, August 1979.
Van Geert, E. 1997. “Towards new challenges for distribution system planners.” Electricity
Distribution. Part 1: Contributions. CIRED. 14th International Conference
and Exhibition on (IEE Conf. Publ. No. 438) Volume 6, June 1997.
Viljainen, S., Lassila, J., Honkapuro, S. and Partanen, J. 2004. ”The role of investments in the
regulated electricity distribution business in Finland.” The 2nd International
Conference on Electricity Utility Deregulation, Restructuring and Power
Technologies, Hong Kong , April 2004.
Warren, C., Ammon, R. and Welch. G. 1999. “A Survey of Distribution Reliability
Measurement Practices in the U.S.” IEEE/PES Working group. IEEE
Transactions on Power Delivery, Vol. 14, No. 1, January 1999, pp. 250–257.
156
Watson, A.S., McDonald, J.R., Burt, G.M. Ferguson, A.G. and Hill, A.C. 2001. “Challenges
and opportunities facing electricity distribution utilities.” Power Engineering,
2001. LESCOPE '01. 2001 Large Engineering Systems Conference on 11–13
July 2001, pp. 167–171.
Welch, G.V. 2001. “A Case for Managed Infrastructure Improvement.” Transmission and
Distribution Conference and Exposition, 2001 IEEE/PES Volume 2, 28 Oct.–
2 Nov. 2001, pp. 931–936.
Wijnia, Y.C., Korn, M.S., de Jager, S.Y. and Herder, P.M. 2006. “Long term optimization of
asset replacement in energy infrastructures.” Systems, Man and Cybernetics,
2006. SMC '06. IEEE International Conference on. Volume 3, Oct. 2006, pp.
2615–2621.
Willis, H.L. 2004. Power Distribution Planning Reference Book. New York: Marcel Dekker,
Inc.
Woodman, B. and Baker, P. 2008. “Regulatory frameworks for decentralized energy.” Energy
Policy Volume 36, 12/2008. pp. 4527–4531.