Job Safety Analysis Annexure-I Job: False ceiling works Date: 25.06.2014 Analysis by: Engg Dept. Supervisor: Shankar Department: Projects Section: GMP Lab Required/Recommended PPE: Safety Shoes, safety Helmet, Safety Goggles, Nose Mask, Appropriate hand glo Sequence of Basic Job Steps Potential Hazards What Could Go Wrong 1. Material Shifting . Integrated Product Development Job Safety Analysis JSA No: 01 Title of employee doing job: M/s Shrusti projects Recommended Safe Job Procedure 1. Manual Handling 2. Slips/Trips. 3. Falling material during shifting process . 1. Wear recommended & healthy PPE's . 2. Ensure the correct lifting methods . 3. Remove trip hazards before carrying the materials. 1. Workmen may get injured in his hand fingers. 2. Material may fall on the foot of the workmen . 3. Person may fall on the ground .

Upload: javed

Post on 28-Jan-2016

1.171 views

Category:

Documents


129 download

DESCRIPTION

Job safety analysis for false ceiling

TRANSCRIPT

Page 1: JSA for False Ceiling

Job Safety Analysis

Annexure-IJob: False ceiling works Date: 25.06.2014 Analysis by: Engg Dept. Reviewed by:

Supervisor: Shankar Department: Projects Section: GMP Lab Approved by:

Required/Recommended PPE: Safety Shoes, safety Helmet, Safety Goggles, Nose Mask, Appropriate hand gloves, Aluminum Ladders.

Sequence of Basic Job Steps Potential Hazards What Could Go Wrong Corrective Action

1. Material Shifting .

Integrated Product Development

Job Safety Analysis

JSA No: 01Title of employee doing job:M/s Shrusti projects

Recommended Safe Job Procedure

1. Manual Handling

2. Slips/Trips.

3. Falling material during shifting process .

1. Wear recommended & healthy PPE's .2. Ensure the correct lifting methods .3. Remove trip hazards before carrying the materials.

1. Workmen may get injured in his hand fingers.2. Material may fall on the foot of the workmen .3. Person may fall on the ground .

1. PPE's must be used by the workmen .2. Minimum weight should be lifted ,if more weight Wheel barrows should be used for shifting .3. Work area & walk way should be clear from materials .

Page 2: JSA for False Ceiling

2. Alignment of false ceiling and gypsum board fixing

1. Electrical Shock2.Cuts 3. Slips / Trips .4. Fall of person from ladder

1. Certified portable cutting machine should be used.2 . All connections to be switched off prior to commencement of work (LOTO).3. Wear recommended & healthy PPE's . 4. Use of Proper Tools.5.Maintain 3 points contact on the ladder .

1. Person working in that area will receive shock.2. Work men get bruises on their body .3. Workmen may fall on the material and get injured .4 .Workmen may get severe injury in his back /Spinal cord .

1.LOTO to be followed & checked prior to commencement of work. 2. Proper PPE must be used without fail.3. Work area should be clear from materials .4. Ladder should be free from bends and dents .