Page 1: Jordan High School Major Renovation Powerpoint

Long Beach Unified School District 1  

Jordan High School Major Renovation

David Starr Jordan High School Major Renovation

February 28, 2013 Community Meeting

Page 2: Jordan High School Major Renovation Powerpoint

Long Beach Unified School District 2  

Jordan High School Major Renovation Introduc)on  

Planning  Team/Collaborators  – High  School  Representa)ves  

• Principals  •  Jordan  HS  Teachers  • SLC  Directors  

– High  School  Office  

– District  Offices  – NTD  Architects  – McCarthy  Construc)on  

– Facili)es  Development  &  Planning  Branch  

Page 3: Jordan High School Major Renovation Powerpoint

Long Beach Unified School District 3  

Jordan High School Major Renovation Project  Goals  &  Objec)ves  

Facility  Master  Plan  1.  Crea)ng  Learning  Environments  to  meet  schools  for  the  next  genera)on  

•  Increase  classroom  size  to  meet  current  educa)onal  goals  •  Create  career  technical  educa)on  labs  

2.  Renova)on  and  replacing  aging  infrastructure  •  Modernize  building  systems  •  Improve  technology  infrastructure  •  Improve  energy  efficiency  

3.  Declining  Enrollment  &  Elimina)on  of  Portables  and  Bungalows  •  Remove  portables  

4.  Changing  the  size  and  types  of  high  schools  •  Consolidate  high  school  program  on  one  campus  •  Efficient  u)liza)on  of  a  small  site  

5.  Joint  Use  •  Collabora)on  with  the  City  of  Long  Beach  

6.  School  Safety  and  Security  •  Improve  parking  and  drop-­‐off  

Page 4: Jordan High School Major Renovation Powerpoint

Long Beach Unified School District 4  

Jordan High School Major Renovation

4

Exis)ng  School  Site  Plan  

Page 5: Jordan High School Major Renovation Powerpoint

Long Beach Unified School District 5  

Jordan High School Major Renovation

Page 6: Jordan High School Major Renovation Powerpoint

Long Beach Unified School District 6  

Jordan High School Major Renovation Exis)ng  Facili)es  

•  Exis)ng  facili)es  built  in  1930’s  &  1940’s  with  addi)ons  built  in  the  1950’s  -­‐1990’s  

•  26.9  acre  site  with  approx.  301,000  S.F.  of  permanent  buildings  and  addi)onal  31,680  S.F.  of  portable  structures  

•  104  Permanent  Classrooms,  32  Portable  Classrooms  

•  Exis)ng  Permanent  Capacity  is  3,640  •  2012-­‐2013  Enrollment  for  Jordan  High  School  and  Jordan  Plus  is  3,607  

Source: DecisionInsite 2013 Moderate Study

Page 7: Jordan High School Major Renovation Powerpoint

Long Beach Unified School District 7  

Jordan High School Major Renovation Campus  Master  Planning  Process  

1.  Facility  Needs  Assessment/Site  Evalua)on    

•  Survey  Condi)on  of  Facili)es  •  Iden)fy  Facili)es  Deficiencies  

and  Constraints  

2.  Demographic  Study    •  Declining  Enrollment  •  Neighborhood  school  with  

high  popula)on  of  9th  –  12th  grade  students:  

•  5,432  9-­‐12  students  currently  live  in  Jordan  HS  boundary  

•  94%  of  students  aeending  JHS  live  within  the  boundary  

•  3,122  current  2012-­‐2013  enrollment  (JHS  only)  

Source: DecisionInsite 2013 Moderate Study

Page 8: Jordan High School Major Renovation Powerpoint

Long Beach Unified School District 8  

Jordan High School Major Renovation Campus  Master  Planning  Process  

3.  Educa)onal  Specifica)ons  &  Facility  Design  Standards    •  Iden)fy  Program  /  

Curriculum  Needs  •  Regular  Mee)ngs  with  

Curriculum  Leaders  

5.  Campus  Program  Development    •  Determined  number  of  

classrooms  &  building  square  footage  

•  Determined  Special  Program  Needs  (Music,  Art,  Science)  

•  Determined  Support  Spaces  •  Determined  Athle)c  Program  

Needs  •  Joint  Use  Opportuni)es  

Page 9: Jordan High School Major Renovation Powerpoint

Long Beach Unified School District 9  

Jordan High School Major Renovation Findings  

•  Dense  campus  /  Urban  District    –  California  Dept.  of  Educa)on  Recommended  Site:  70.9  acres  vs.  

Exis)ng  Site:  26.9  acres  –  Similar  to  other  High  Schools  in  the  District  •  Undersized  classrooms:  68%  (88  out  of  128  classroom)  •  Lack  of  Small  Learning  Community  (SLC)  Iden)ty  •  Inadequate  spaces  for  career  technical  educa)on  labs  •  Insufficient  parking  •  Poor  vehicular  access  •  Poor  pedestrian  circula)on  •  Aging  facili)es  &  infrastructures  •  Insufficient  land  for  all  physical  educa)on  and  athle)c  programs  •  Lack  of  central  gathering  area  •  Lack  of  campus  entrance  iden)fica)on  •  Need  to  invoke  student  pride  and  campus  iden)ty  •  Need  for  beeer  security  and  supervision  

Page 10: Jordan High School Major Renovation Powerpoint

Long Beach Unified School District 10  

Jordan High School Major Renovation Exis)ng  Campus  Academies  

 8    Exis)ng  Campus  Academies  • Architecture,  Construc)on  &  Engineering  (ACE)  

• Aspira)ons  in  Medical  Services  (AIMS)  

• Business  and  Entertainment  School  of  Travel,  Trade  and  Tourism  (BESTT)  

• Excellence  Through  the  Arts  (ETA)  

• Jordan’s  Media  &  Communica)on  Learning  Community  (JMAC)  

• Jordan’s  Technical  Studies  (JTECH)  

• Panther  Academy  (PANTHER)  

• Interna)onal  Baccalaureate  (IB)  

Page 11: Jordan High School Major Renovation Powerpoint

Long Beach Unified School District 11  

Jordan High School Major Renovation Project  Constraints  &  Challenges  

•  Site  U)liza)on  –  Exis)ng  Buildings  –  Structural,  Mechanical  Capacity  –  Environmental  Remedia)on  Work  –  Geotechnical/Soil  Improvement  

•  Program    –  Teaching    Spaces  

•  U)li)es  Distribu)on  –  Aging  Infrastructure  –  Complex  maze  due  to  segmented  construc)on  of  Facili)es  over  )me  

•  Construc)on  Schedule    –  Mul)ple  Phases  of  Construc)on  (Es)mated  6  Phases)  –  Occupied  Campus  (Maintaining  school  opera)ons)  –  Interim  Housing  (Displacing  Physical  Educa)on  &  Athle)c  Facili)es)  

Page 12: Jordan High School Major Renovation Powerpoint

Long Beach Unified School District 12  

Jordan High School Major Renovation Project  Constraints  &  Challenges  

•  Budget  –  Construc)on  Target  Cost:  $135.6  Million  

–  Total  An)cipated  Project  Budget  including  sol  costs:  $185  Million  

•  Financing  –  Sale  of  Bonds  Con)ngent  on  Future  Assessed  Value  of  Housing  –  Cash  flow  impact  to  the  construc)on  schedule  and  phasing  

Page 13: Jordan High School Major Renovation Powerpoint

Long Beach Unified School District 13  

Jordan High School Major Renovation

13

•  Master Plan Capacity - 3,600 students, grades 9-12

•  6 Academies (Small Learning Communities) each with 2 universal/flexible lab spaces

•  142 Classrooms / Labs •  349,000 SF of total building area •  Visual & Performing Arts Facilities •  Science and Technical Labs •  Renovation of Existing Media Center •  Physical Education and Athletic

Facilities •  Special Needs Classroom Facilities •  Fire alarms, communications and

technology systems •  Cafeteria / Food Service Facilities •  Additional Parking and Drop-Off Area •  Landscaping, Site Utilities & Site

Improvements •  Construction Estimate: $135.6

million

PROPOSED MASTER PLAN

Page 14: Jordan High School Major Renovation Powerpoint

Long Beach Unified School District 14  

Jordan High School Major Renovation

Master Plan Proposed Buildings to be Demolished shown in RED

Page 15: Jordan High School Major Renovation Powerpoint

Long Beach Unified School District 15  

Jordan High School Major Renovation

15

PROPOSED CONSTRUCTION PHASING PLAN

Construc4on  Phasing   Start   Comple4on  Date  

•   Interim  Housing  Phase  1A  

–   Design   Sep  2012   Jul  2013  

–   Construc)on   Jan  2014   Jul  2014  

•   Phases  1B  &  1C  

–   Design   Jun  2012   Apr  2014  

–   Construc)on   Jul  2014   Jun  2018  

•   Phases  2  -­‐  6   TBD   TBD  

Phases   Building/Program  

1A   Interim  Housing  

1B/1C   Cafeteria,  ETA,  JMAC,  JTECH,  ACE,  BESTT  

2  -­‐  6   In  Development  (Subject  to  Change)  

Page 16: Jordan High School Major Renovation Powerpoint

Long Beach Unified School District 16  

Jordan High School Major Renovation

16

Interim Housing will displace practice fields

INTERIM HOUSING SITE PLAN

New Tennis Courts

Interim Housing Location

PHASE 1A Jan 2014 – Aug 2014

•  Installation of Temporary Portable classrooms

•  New Tennis Courts

Phase 1A includes:

Page 17: Jordan High School Major Renovation Powerpoint

Long Beach Unified School District 17  

Jordan High School Major Renovation

17

PHASE 1

•  New Permanent Classrooms

•  Cafeteria Building •  New Classrooms and Labs

for ETA, JMAC, JTECH, BESTT, and ACE

•  New Science Classrooms •  New Central Plant •  Additional Parking. •  Landscape improvements

PHASE 1B & 1C Aug 2014 – Jun 2018

Cafeteria

Bldgs “K” and “L” SLCs

Bldgs “M” and “N” SLCs

Phase 1B & 1C includes:

Page 18: Jordan High School Major Renovation Powerpoint

Long Beach Unified School District 18  

Jordan High School Major Renovation

18

Phase 6 includes: Phases 2-6

In development and is subject to change. Sequencing of buildings is under further review.

Page 19: Jordan High School Major Renovation Powerpoint

Long Beach Unified School District 19  

Jordan High School Major Renovation

Long Beach Unified School District 19

PROPOSED CAMPUS MASTER PLAN

Master Plan after construction of all Phases

Page 20: Jordan High School Major Renovation Powerpoint

Long Beach Unified School District 20  

Jordan High School Major Renovation On-­‐Going  Ac)vi)es  

•  Con)nue  design  development  for  Phase  1  

•  Review  and  analyze  sequencing  and  feasibility  of  Phases  2  -­‐  6  

•  Design  of  Interim  Housing  Plans  •  Target  Start  of  Construc)on  for  Interim  Housing  -­‐January  2014  

•  Target  Start  of  Construc)on  for  Phase  1  -­‐  Fall  2014  •  Board  Updates