A Practical Way to Sustainability “Finding the Energy Savings”
Evaluate Energy Usage
Evaluate Energy Purchases
Energy Savings Implementation
Plan Evaluate
Interactive Effects
Energy Analysis
� Evaluate Energy Usage: Disaggregation ¡ By Facility Type and Occupancy ¡ Energy Usage Pattern (Hourly, DOW, Month) ¡ Compare Usage in Similar Campus Buildings
� The Key factors ¡ Existing equipment usage ¡ Existing equipment schedules ¡ Existing occupancy schedule
� Develop Energy Usage Index targets by building type
Look for Mismatch
Energy Usage Index (/sqft)
Building Type à Admin Admin Admin Admin Dorm Dorm
Pre Post Pre Post Pre Post
System Type kWh kWh Therm Therm Therm Therm
Steam Heat (No A/C) 1-3 1 70 50 190 110
Hydronic Heat (No A/C) 5-8 4-6 80 45 140 80
Air Distribution Heat (No A/C) 10-12 7-9 80 45 140 90
Hydronic Heat Central A/C 14-18 9-12 80 45 140 90
Air Distribution for Heat with A/C 15-12 12-15 80 45 140 90
Evaluate Energy Purchases
� Energy Cost Profile ¡ Electricity – Evaluate rate schedule and how it affects cost ¡ Fuel – What happens over the course of the year?
� Current energy rates ¡ Determine the best applicable energy rate for existing systems ¡ Determine the best rate upon completion of the energy project
Reduce and Control Energy Usage q Weatherization and Air Sealing q Heating and Cooling Plant Optimization q Heating and Cooling Centralized Control (EMS) q Lighting and Lighting Controls q Cloud Computing - Data Center Consolidation
Generate New Sources of Localized Energy Production q Combined Heat and Power q Wind Turbine q Solar Thermal and PV q Ground Source Heat Pump (aka Geothermal Energy)
Occupant Behavioral Awareness and Change q Kinetic Energy Gym Equipment q Dormitory Energy Challenges
Pathway to Net Zero
Final ECM Selection
Site Conditions Investment
Interacted Savings
Site-Specific Model Generates ECM Shortlist
20 Technology Categories- Multiple Energy Conservation Measures (ECMs)
Measure Selection Process
Geographic Location of Building (Weather Conditions) Utility Incentive Programs
Utility Rate Structures
ECM ECM
ECM ECM ECM
ECM ECM
ECM ECM
Page 8
Longer Project Term allows for bundling of ECMs
ENERGY & O&M
SAVINGS
INTEREST RATE
CONTRACT TERM
PROJECT COST
ENERGY & O&M
SAVINGS
CONTRACT TERM
INTEREST RATE
PROJECT COST
Final Implementation Plan is dictated by the Plan Architects
Balance the ECMs, financing term, interest rates and Cash Flow
ENERGY & O&M
SAVINGS
INTEREST RATE
CONTRACT TERM
PROJECT COST
Self Funded Energy Program
ADI Energy Dashboard™ ADI develops proprietary interactive ECM selection. See www.ad-institute.com/DCAM.html
� 4 Step Evaluation Process � Very Interactive Selection � There are Tools Available to Facilitate the Process
� Next presenters: � Discuss Project Examples in Campus Settings � DCAMM’s Accelerated Energy Program