Client Ramsay Healthcare Architect Phillips Smith Conwell Consultants Phillips Smith Conwell Project Size 2,500 m² Delivery Model Lump Sum Location Gold Coast, QLD Completed January, 2015 Duration 12 weeks JOHN FLYNN PRIVATE HOSPITAL PROJECT DELIVERABLES Time Critical Secure Environment JOHN FLYNN PRIVATE HOSPITAL, QLD ISIS delivered this project: - On time - With zero defects - With O&M manuals provided within one week of handover - Outstanding conduct maintained onsite at all times by ISIS and their contractors to eliminate disruption to the hospital staff, patients and visitors alike (the key client value)

Upload: isis-group-australia

Post on 07-Aug-2015

25 views

Category:

Health & Medicine


3 download

TRANSCRIPT

Page 1: John Flynn Private Hospital Project

ClientRamsay Healthcare

ArchitectPhillips Smith Conwell

ConsultantsPhillips Smith Conwell

Project Size2,500 m²

Delivery ModelLump Sum

LocationGold Coast, QLD

CompletedJanuary, 2015

Duration12 weeks

JOHN FLYNN PRIVATE HOSPITAL PROJECT DELIVERABLES

Time Critical Secure Environment

JOHN FLYNN PRIVATE HOSPITAL, QLD

ISIS delivered this project: - On time- With zero defects- With O&M manuals provided within one week of handover - Outstanding conduct maintained onsite at all times by ISIS and their contractors to eliminate disruption to the hospital staff, patients and visitors alike (the key client value)