JMB MEETING UPDATES 19 th January 2019

Upload: others

Post on 28-Feb-2021

7 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: JMB MEETING UPDATES - MyCommunity...311 (13.3%) CURRENT DEFECTS RECTIFICATION WORK PROGRESS 01 DECEMBER 2018 - 31 DECEMBER 2018 S T S T S T S T S T S T S T S T S T S T 9 D 250 255

JMB MEETING UPDATES19th January 2019

Page 2: JMB MEETING UPDATES - MyCommunity...311 (13.3%) CURRENT DEFECTS RECTIFICATION WORK PROGRESS 01 DECEMBER 2018 - 31 DECEMBER 2018 S T S T S T S T S T S T S T S T S T S T 9 D 250 255

STATUS UPDATE

NO UPGRADING ITEM STATUS DATELINE

Other upgrading;

Badminton/Basketball court

3. Ventilation – Installation of Exhaust Fan Completed -

4. Benches Completed -

Signages

5. Tower A exit to Jalan Laksamana Boulevard- To add exit signage

Completed -

6. Installation of 2nos of Electric Charging Point for hybrid car

Completed -

NO UPGRADING ITEM STATUS DATELINE

Suites

1. Propose Suites Upgrading – Installation of Big 10 ft fan

Completed

2. Propose Suites Upgrading - Loading/unloading bay path way

Awarded. Included in signages contract.

-

Page 3: JMB MEETING UPDATES - MyCommunity...311 (13.3%) CURRENT DEFECTS RECTIFICATION WORK PROGRESS 01 DECEMBER 2018 - 31 DECEMBER 2018 S T S T S T S T S T S T S T S T S T S T 9 D 250 255

STATUS UPDATE

13. WIFI Service in Common Area and Lifts Others are completed.Pending installation in Cabana Lift only.

June 2018

10. WIFI Service in Common Area and Lifts Completed. Aug 2018

11. Water dispenser Delivered. -

12. Mosquito repellant bulb Delivered. July 2018

13. Missing Links Roof at E-deck Completed. Jan 2019

14. Child care and multipurpose room furnishings Pending handover to JMB. 22 Jan 2019

15. Upgrading of fencing 100% Completion with additional works added. Pending small openings.

Feb 2019

16. Signages Upgrading Awarded – 90 % complete 31 Jan 2019

17. Security Upgrading Awarded. 31 Jan 2019

NO UPGRADING ITEM STATUS DATELINE

Changing Room

7. Installation of Changing Room Fittings(hanger, towel racks and locker)

Completed. July 2018

9. Benches Completed. -

Page 4: JMB MEETING UPDATES - MyCommunity...311 (13.3%) CURRENT DEFECTS RECTIFICATION WORK PROGRESS 01 DECEMBER 2018 - 31 DECEMBER 2018 S T S T S T S T S T S T S T S T S T S T 9 D 250 255

OFFICE TOWER SIGNAGE

To be installed in 3rd week of January 2019.

Page 5: JMB MEETING UPDATES - MyCommunity...311 (13.3%) CURRENT DEFECTS RECTIFICATION WORK PROGRESS 01 DECEMBER 2018 - 31 DECEMBER 2018 S T S T S T S T S T S T S T S T S T S T 9 D 250 255

FIT-OUT WORKS

• Items included under this project are as follows;No. Location Item

1. Fit-out for childcare centre • Indoor Play area• Reading nook(Please refer to Perspective)

2. Cabana Lobby • Arm chair and coffee table

3. Games Room • Storage Cabinet to be fixed

4. Multipurpose Room / Function Room (E-deck Tower A & B)

• Foldable rectangular table• Block Curtain• Additional Banquet Chair

5. Pantry at Multipurpose / Function Room (Sky-lounge Tower A, B & Suites)

• Cabinet and wash basin

6. Mailroom at Suites • To provide metal strips at corner to avoid crack/damages to the glass.

Page 6: JMB MEETING UPDATES - MyCommunity...311 (13.3%) CURRENT DEFECTS RECTIFICATION WORK PROGRESS 01 DECEMBER 2018 - 31 DECEMBER 2018 S T S T S T S T S T S T S T S T S T S T 9 D 250 255

FIT-OUT FOR CHILDCARE CENTRE Proposal for Childcare Fit-out concept – COMPLETED. HANDOVER TO JMB ON 3RD WEEK OF JAN 2019.

Actual On-Site Images

Page 7: JMB MEETING UPDATES - MyCommunity...311 (13.3%) CURRENT DEFECTS RECTIFICATION WORK PROGRESS 01 DECEMBER 2018 - 31 DECEMBER 2018 S T S T S T S T S T S T S T S T S T S T 9 D 250 255

OTHER UPGRADING;No. ITEMS/UPGRADES STATUS1. Cleaning of external Facade Yes Tower started. External perimeter

to be conducted in November

2018.2. E-Deck

2.1 Door upgrade Yes Doors delivered on 14th

September 2018. Installation

pending BOMBA certificate to

obtained by 14th October 2018

(1month)

Doors currently pending

installation by workers. Target

installation on 4th Week of Jan 19.

Page 8: JMB MEETING UPDATES - MyCommunity...311 (13.3%) CURRENT DEFECTS RECTIFICATION WORK PROGRESS 01 DECEMBER 2018 - 31 DECEMBER 2018 S T S T S T S T S T S T S T S T S T S T 9 D 250 255

OTHER UPGRADING;No. ITEMS/UPGRADES STATUS

SUITES3. Car Park Gantry repositioning Yes Awarded. Completed.4. Loading Bay Pending award.

5. Mailroom – mirror to be changed

to stainless steel

Yes Completed

6. Wheelchair friendly at entrance Yes Completed.7. Fire Doors to include vision panel

(glass) (Edeck)

Yes Same as no. 2

8. Car Stopper to be painted to

prevent tripping near lift

entrance.

Completed.

Page 9: JMB MEETING UPDATES - MyCommunity...311 (13.3%) CURRENT DEFECTS RECTIFICATION WORK PROGRESS 01 DECEMBER 2018 - 31 DECEMBER 2018 S T S T S T S T S T S T S T S T S T S T 9 D 250 255

OTHER UPGRADING;No. ITEMS/UPGRADES STATUS

RESIDENCES

14. Fire Doors to include vision panel

(glass) (Edeck)

Yes Same as No.3

15. Corridor to badminton court – Better

lighting and signages required

Yes Completed.

Page 10: JMB MEETING UPDATES - MyCommunity...311 (13.3%) CURRENT DEFECTS RECTIFICATION WORK PROGRESS 01 DECEMBER 2018 - 31 DECEMBER 2018 S T S T S T S T S T S T S T S T S T S T 9 D 250 255

COMMON AREA DEFECTS UPDATE

Note : The defects lodged into the Novade will be deleted/rejected due to the following reason : (1) Duplicate case (2) Lodged without photo evidence (3) Lodged with wrongly location.

OVERALL PROGRESS

CLOSED/ COMPLETED

1878(83.7%)

WIP/ NEW

367(16.3%)

PREVIOUS DEFFECT RECTIFICATION WORK PROGRESS

01 NOVEMBER 2018 - 30 NOVEMBER 2018

CLOSED/ COMPLETED

2027(86.7%)

WIP/ NEW

311(13.3%)

CURRENT DEFECTS RECTIFICATION WORK PROGRESS

01 DECEMBER 2018 - 31 DECEMBER 2018

PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT

Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19

CLOSED/

COMPLETED250 255 603 620 190 206 282 307 21 21 439 446 21 27 47 120 25 25 1878 2027

WIP/ NEW 9 9 21 13 122 108 136 118 2 2 26 20 27 21 15 11 9 9 367 311

LODGED 259 264 624 633 312 314 418 425 23 23 465 466 48 48 62 131 34 34 2245 2338

DEFECTS RECTIFICATION WORK RECORD

DESCRIPTION

TEEGA TOWER

(OFFICE)TEEGA SUITE TOWER A TOWER B CABANA CAR PARK

CONDOMINIUM

E-DECKRETAIL

SERVICE

APARTMENT

E-DECK

TOTAL

DEFECTS

Page 11: JMB MEETING UPDATES - MyCommunity...311 (13.3%) CURRENT DEFECTS RECTIFICATION WORK PROGRESS 01 DECEMBER 2018 - 31 DECEMBER 2018 S T S T S T S T S T S T S T S T S T S T 9 D 250 255

COMMON AREA DEFECTS UPDATE

Note : The defects lodged into the Novade will be deleted/rejected due to the following reason : (1) Duplicate case (2) Lodged without photo evidence (3) Lodged with wrongly location.

WORK IN PROGRESS BY AGING

PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT PREVIOUS CURRENT

Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19 Nov-19 Dec-19

DEFECTS < 30

DAYS0 1 10 5 40 35 8 14 2 0 3 3 7 3 5 7 1 1 76 69

DEFECTS > 30

DAYS9 8 11 8 82 73 127 103 0 2 23 17 20 18 10 4 8 8 290 241

WORK IN PROGRESS (WIP) DEFECTS CATEGORY BY AGING

DEFECTS

AGING

TEEGA TOWER

(OFFICE)TEEGA SUITE TOWER A TOWER B CABANA CAR PARK

CONDOMINIUM

E-DECKRETAIL

SERVICE

APARTMENT

E-DECK

TOTAL

DEFECTS

Page 12: JMB MEETING UPDATES - MyCommunity...311 (13.3%) CURRENT DEFECTS RECTIFICATION WORK PROGRESS 01 DECEMBER 2018 - 31 DECEMBER 2018 S T S T S T S T S T S T S T S T S T S T 9 D 250 255

COMMON AREA DEFECTS UPDATE

423

678

8681000

1208

1454

1671

1831 1878

2027

11631045

901810

742641

466343 367

311

0

500

1000

1500

2000

2500

Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18

NU

MB

ER

OF

DE

FE

CT

S

MONTH

COMMON AREA DEFECTS RECTIFICATION WORK PROGRESSMARCH 2018 - DECEMBER 2018

Completed/Closed Work In progress (WIP)

Variance

, σClosed :

217

WIP : -

175

Variance

, σClosed :

246

WIP : -

101

Variance

, σClosed :

160

WIP : -

123Variance

, σClosed :

208

WIP : -68

Variance

, σClosed :

132

WIP : -91

Variance

, σClosed :

190

WIP : -

144

Variance

, σClosed :

225

WIP : -

118

Variance

, σClosed :

149

WIP : -56

Variance

, σClosed :

47

WIP : 24

Defects / Month Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18

Completed/Closed 423 678 868 1000 1208 1454 1671 1831 1878 2027

Work In progress (WIP) 1163 1045 901 810 742 641 466 343 367 311

Closed/Completed Variance, s - 255 190 132 208 246 217 160 47 149

Work in Progress (WIP), s - -118 -144 -91 -68 -101 -175 -123 24 -56

Page 13: JMB MEETING UPDATES - MyCommunity...311 (13.3%) CURRENT DEFECTS RECTIFICATION WORK PROGRESS 01 DECEMBER 2018 - 31 DECEMBER 2018 S T S T S T S T S T S T S T S T S T S T 9 D 250 255

ISKANDAR PUTERI CONNECTIVITYConnectivity – Current transport available in Puteri Harbour, Iskandar Puteri

FREE SHUTTLE SERVICE

• Complimentary shuttle service brought to you by UEM Sunrise & MediniIskandar Malaysia

• Current Status : 4 nos. of busses in operation.

• Timetable as per next page.

Note:-

• Timing for the public bus are base on the operator schedule (available in mobile apps HUGO)

Page 14: JMB MEETING UPDATES - MyCommunity...311 (13.3%) CURRENT DEFECTS RECTIFICATION WORK PROGRESS 01 DECEMBER 2018 - 31 DECEMBER 2018 S T S T S T S T S T S T S T S T S T S T 9 D 250 255

ISKANDAR PUTERI BUS SCHEDULE

Note:-

• Timing for the public bus are base on the operator schedule (available in mobile apps HUGO)

Page 15: JMB MEETING UPDATES - MyCommunity...311 (13.3%) CURRENT DEFECTS RECTIFICATION WORK PROGRESS 01 DECEMBER 2018 - 31 DECEMBER 2018 S T S T S T S T S T S T S T S T S T S T 9 D 250 255

ISKANDAR PUTERI BUS SCHEDULE

Page 16: JMB MEETING UPDATES - MyCommunity...311 (13.3%) CURRENT DEFECTS RECTIFICATION WORK PROGRESS 01 DECEMBER 2018 - 31 DECEMBER 2018 S T S T S T S T S T S T S T S T S T S T 9 D 250 255

ISKANDAR PUTERI CONNECTIVITY• Proposed Route - Phase 2 Community Shuttle

M6/M7

Rumah Iskandar

Malaysia (RIM) –

Gelang Patah

Bukit Indah

Taman

Nusa Perdana

- Afinit Medini

- Somerset Medini

- 1 Medini

- Sunway Iskandar

- Sunway

International

School

- Imperia

- Teega

- Puteri Cove

- Ledang

Clubhouse

- Ujana

- Nusajaya Center

- Tesco

Iskandar Puteri Community

Shuttle Service

Route Operation Time

Route 1 (Morning & Evening only)

RIM - PHIFT

7:00am –7:00pm

Route 2 Edu City -PHIFT

Route 3(existing)

Terminal Larkin -PHIFT

6:30am –7:00pm

Route 4 Bukit Indah 6:45am –7:00pm

Note:-

• Awaiting permit approval from Land Public Transport Commission (SPAD) on the proposed route

Page 17: JMB MEETING UPDATES - MyCommunity...311 (13.3%) CURRENT DEFECTS RECTIFICATION WORK PROGRESS 01 DECEMBER 2018 - 31 DECEMBER 2018 S T S T S T S T S T S T S T S T S T S T 9 D 250 255

ISKANDAR PUTERI CONNECTIVITYStarex Operation (3 nos)• Operation will start on 1st September 2018.• The trips will be increased from 4 trips per day to 6 trips per

day.• New time slot will be proposed as late as 10:30am from Teega

and 3:30pm from Jurong East• There will be 3 timing in the morning (Poster as per next

page)• Starex routing as follows;

TeegaEast

LedangJurong

East

Page 18: JMB MEETING UPDATES - MyCommunity...311 (13.3%) CURRENT DEFECTS RECTIFICATION WORK PROGRESS 01 DECEMBER 2018 - 31 DECEMBER 2018 S T S T S T S T S T S T S T S T S T S T 9 D 250 255

ISKANDAR PUTERI CONNECTIVITY

Page 19: JMB MEETING UPDATES - MyCommunity...311 (13.3%) CURRENT DEFECTS RECTIFICATION WORK PROGRESS 01 DECEMBER 2018 - 31 DECEMBER 2018 S T S T S T S T S T S T S T S T S T S T 9 D 250 255

BUS STOP IN FRONT OF TEEGA BUS STOP

1. Bus stop tensile roof completed.

2. Sitting area completed.

Proposed sitting design

Page 20: JMB MEETING UPDATES - MyCommunity...311 (13.3%) CURRENT DEFECTS RECTIFICATION WORK PROGRESS 01 DECEMBER 2018 - 31 DECEMBER 2018 S T S T S T S T S T S T S T S T S T S T 9 D 250 255

TEEGA RETAIL LOTS

GROUND LEVEL

LOWER GROUND

Teega Handover Office

Tribus Café SUTL Sales Gallery

Note: 1. Occupied unit delineated in green2. Units in negotiation delineated in yellow3. Vacant unit delineated in red

SUTL-One Degree 15 Marina Puteri HarbourTarget to open: 1 October 2018

YSL FreshmartTarget to open: 1 December 2018The Tribus

Target to open: 1

December 2018

Page 21: JMB MEETING UPDATES - MyCommunity...311 (13.3%) CURRENT DEFECTS RECTIFICATION WORK PROGRESS 01 DECEMBER 2018 - 31 DECEMBER 2018 S T S T S T S T S T S T S T S T S T S T 9 D 250 255

Thank you