Copyright 2011, JICA’s Contribution towards Rebuilding Iraq Dr. Junichi Yamada Director General Middle East & Europe Department 1

Upload: others

Post on 29-May-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

Copyright 2011,

JICA’s Contribution

towards Rebuilding Iraq

Dr. Junichi Yamada

Director General

Middle East & Europe Department

1

Page 2: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

When the institutional framework of post conflict/vulnerable countries is largely impaired and governance is inefficient, how can donors respond to

the overwhelming needs?

2

Page 3: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

Copyright 2011,

1. A Brief Overview:

Our Assistance in Iraq

3

Page 4: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

Madrid Conference Commitments Grant Emergency

assistance USD 1. 5 billion

Complete

ODA loan Mid-term Reconstruction and Development

USD 3.28 billion USD 0.75 billion

Until Jan 2010 Starting Nov 2011

Technical Assistance

Training in Japan and neighboring countries

In kind assistance

By Mar 2011 over 4,200 participants By Aug 2011 4 Japanese Long-term Experts

4

Assis

tan

ce b

y t

he G

ove

rnm

ent of Japan

sin

ce

200

3

Page 5: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

Basic Infrastructure

• Water Supply & Sewage

• Agriculture

Activation of Private Sector

• Electricity

• Transport & ICT

Strengthening Foundation for

Economic Growth

• Oil & Gas

• Petrochemicals

Substituting private

finance

Promoting private

sector-led projects

(PPP scheme)

Improving business

environment

Providing investment

promotion opportunities

Governance

Development

5

JICA’s Priorities for Iraq

Improving living

conditions

Developing non-oil

sector to create jobs

Page 6: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

Grant Assistance Projects

6

Main Projects of Emergency Grant Aid

(a) Electricity Provision of 23 mobile substations throughout Iraq $ 70 million

Rehabilitation of Taji Gas Turbine Power Station (Unit No. 2,3 & 5) $ 66 million

Rehabilitation of Mosul Gas Turbine Power Station (Unit No. 1 & 3) $ 42 million

Rehabilitation of Mosul Hydroelectric Power Station $ 52 million

Construction of a diesel power station (60 MW) in Al-Samawah $ 118 million

(b) Health / Medical care Rehabilitation of and provision of equipment to 4 general hospitals in the South (Nasiriyah, Najaf, Diwaniyah, and Samawah) $ 51million

Rehabilitation of and provision of equipment to 4 general hospitals in the North (Kirkuk, Arbil, Mosul, Dahuk) $ 68 million

Rehabilitation of and provision of equipment to 3 general hospitals in the Central Region (Baghdad, Amarah and Kut) $ 46 million

Provision of 700 ambulances nationwide $ 53 million

Provision of medical equipment to 32 primary health centers in Al-Muthanna Governorate $ 8 million

(c) Water / Sanitation Provision of compact units to the city of Baghdad $ 55 million

Provision of special vehicles for garbage disposal and sewage cleaning throughout Iraq $ 57 million

Provision of equipment for solid waste management such as garbage collection vehicles and containers to the city of Samawah $ 6 million

(d) Employment / Infrastructure Improvement of trunk communications network $ 65 million

Improvement of transit switches for telecommunication $ 33 million

(e) Security (approximately $ 100 million) Provision of police vehicles $ 25 million

Provision of 20 armored vehicles to Baghdad and Al-Muthanna Governorate $ 5 million

Provision of 150 police buses and 500 police motorcycles $ 24 million

Provision of fire-trucks to Baghdad, Al-Basra and Al-Muthanna Governorate $ 20 million

Program for the police training in Al-Muthanna Governorate $ 4 million

Page 7: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

Ongoing Loan

Projects

15 Strategic Projects (USD 3.28 billion) for:

• Economic Growth – oil & gas

• Private Investment Opportunities – power generation

• Improved Living Conditions – water supply

(Projects are situated throughout the country to ensure regional balance)

7 7 7

Irrigation Sector Loan

[JP¥ 9.5 bil/ US$ 86 mil]

Electricity Sector Reconstruction Project (middle

and southern Iraq) [JP¥ 32.6 bil/ US$ 281 mil]

Baghdad Sewerage Facilities Improvement

Project (E/S) [JP¥ 2.1 bil / US$ 19 mil]

Electricity Sector Reconstruction

Project in Kurdistan Region

[JP¥ 14.7 bil / US$ 127 mil]

Basrah Water Supply Improvement

Project [JP¥ 43 bil / US$ 370 mil]

Al-Akkaz Gas Power Plant Construction

Project [JP¥ 29.6 bil / US$ 287 mil]

Baghdad Sewerage Facilities Improvement

Project (E/S) [JP¥ 2.1 bil / US$ 19 mil]

Baghdad Sewerage Facilities Improvement

Project (E/S) [JP¥ 2.1 bil / US$ 19 mil]

Baghdad Sewerage Facilities Improvement

Project (E/S) [JP¥ 2.1 bil / US$ 19 mil]

Basrah Water Supply Improvement

Project [JP¥ 43 bil / US$ 370 mil]

Baghdad Sewerage Facilities Improvement

Project (E/S) [JP¥ 2.1 bil / US$ 19 mil]

Basrah Water Supply Improvement

Project [JP¥ 43 bil / US$ 370 mil]

Baghdad Sewerage Facilities Improvement

Project (E/S) [JP¥ 2.1 bil / US$ 19 mil]

Basrah Water Supply Improvement

Project [JP¥ 43 bil / US$ 370 mil]

Baghdad Sewerage Facilities Improvement

Project (E/S) [JP¥ 2.1 bil / US$ 19 mil]

Basrah Water Supply Improvement

Project [JP¥ 43 bil / US$ 370 mil]

Baghdad Sewerage Facilities Improvement

Project (E/S) [JP¥ 2.1 bil / US$ 19 mil]

Basrah Water Supply Improvement

Project [JP¥ 43 bil / US$ 370 mil]

Baghdad Sewerage Facilities Improvement

Project (E/S) [JP¥ 2.1 bil / US$ 19 mil]

Al-Akkaz Gas Power Plant Construction

Project [JP¥ 29.6 bil / US$ 287 mil]

Basrah Water Supply Improvement

Project [JP¥ 43 bil / US$ 370 mil]

Baghdad Sewerage Facilities Improvement

Project (E/S) [JP¥ 2.1 bil / US$ 19 mil]

Al-Akkaz Gas Power Plant Construction

Project [JP¥ 29.6 bil / US$ 287 mil]

Basrah Water Supply Improvement

Project [JP¥ 43 bil / US$ 370 mil]

Basrah Refinery Upgrading Project

(E/S) [JP¥ 2.1 bil/ US$ 18 mil]

Baghdad Sewerage Facilities Improvement

Project (E/S) [JP¥ 2.1 bil / US$ 19 mil]

Deralok Hydropower Plant Construction

Project [JP¥ 17.0 bil / US$ 165 mil]

Water Sector Loan Project in Midwestern

Iraq [JP¥ 41.3 bil / US$ 401 mil]

Al-Akkaz Gas Power Plant Construction

Project [JP¥ 29.6 bil / US$ 287 mil]

Port Sector Rehabilitation Project

[JP¥ 30.2 bil / US$ 272 mil]

Crude Oil Export Facility Reconstruction

Project [JP¥ 50.1 bil/ US$ 432 mil]

Khor Al-Zubair Fertilizer Plant Rehabilitation

Project [JP¥ 18.1 bil/ US$ 156 mil]

Basrah Water Supply Improvement

Project [JP¥ 43 bil / US$ 370 mil]

Samawah Roads and Bridges Construction

Project [JP¥ 3.3 bil/ US$ 30 mil]

Al-Mussaib Thermal Power Plant Rehabilitation

Project [JP¥ 36.8 bil/ US$ 331 mil]

Baghdad Sewerage Facilities Improvement

Project (E/S) [JP¥ 2.1 bil / US$ 19 mil]

Water Supply Improvement Project in Kurdistan

Region [JP¥ 34.3 bil / US$ 303 mil]

Page 8: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

Outline of Ongoing Projects

8

No. Amount

($ Mil.)

Project Description

1 272 Port Sector Rehabilitation

Project Reconstruction of the Port of Umm-Qasr and surrounding areas by dredging the shipping lanes, removing wrecked ships, and

rehabilitating the port facilities, as well as providing equipment and materials such as dredgers and other related items.

2 86 Irrigation Sector Loan Provision of irrigation drainage pumps, and equipment and materials for maintaining the operation of irrigation channels in the

areas where agriculture is important including the Governorate of Al- Muthanna.

3 331 Al-Mussaib Thermal Power

Plant Rehabilitation Project Rehabilitation of the existing unit 1 and unit 3 Al-Mussaib thermal power plants, located in the suburbs of Baghdad.

4 30 Samawah Bridges and Roads

Construction Project Construction and rebuilding of bridges to cross over the Euphrates River and construction of their connecting roads in Al-

Samawah and its vicinity.

5 18 Basrah Refinery Upgrading

Project (Eng. Services) Engineering Services for construction of a new plant which will contribute to increasing the productivity of the refinement of

gasoline and other oil products in the existing refinery located in Basrah Governorate in Southern Iraq.

6 156 Khor Al-Zubair Fertilizer Plant

Rehabilitation Project Supply of urgently needed machinery for Kohr Al-Zubair Fertilizer Plant located in Basrah Governorate in Southern Iraq.

7 432 Crude Oil Export Facility

Reconstruction Project Construction of an on-shore/off-shore pipeline to export oil and installation of off-shore loading facilities in Al-Fao, Basra in

Southern Iraq.

8 281 Electricity Sector

Reconstruction Project Supply of machinery and materials for the transformation of the power supply and distribution section to stabilize the power

supply - mainly targeting the areas with high priority.

9 370 Basrah Water Supply

Improvement Project Improvement of the water supply facilities in Basrah City and its vicinity.

10 127 Electricity Sector

Reconstruction Project in

Kurdistan Region

Supply of machinery and materials for the power transformation and distribution system in Kurdistan Region (Governorates of

Dohuk, Erbil and Sulaimaniya).

11 303 Water Supply Improvement in

Kurdistan Region Improvement of the quantity and quality of the water supply in several municipal areas in the KRG region (incl. Harabja town)

through improvement of water supply facilities such as water treatment plant, water transmission facility, distribution network,

etc.

12 19 Baghdad Sewerage Facilities

Improvement (Eng. Services) Engineering Services for improving the living environment in Baghdad and water quality of the Tigris River by expanding the

Karkh sewage treatment plant and rehabilitating major pump stations in Baghdad.

13 401 Water Supply Sector Loan

Project in Mid-Western Iraq Rehabilitation and improvement of water supply facilities, such as water treatment plant, water transmission facility, distribution

network to improve the quantity and quality of the water supply in Mid-Western Iraq (Anbar, Salah al-Din, Ninewa)

14 287 Al-Akkaz Gas Power Plant

Construction Project Construction of a new gas-fired power plant and related facilities in Anbar to improve the electricity supply situation.

15 165 Deralok Hydropower Plant

Construction Project Construction of a new hydropower plant and related facilities in Duhok governorate to improve the electricity supply situation in

Kurdistan region.

Page 9: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

Japan’s ODA loan commitments for new projects after November 2011:

• Basrah Refinery Upgrading Project (42.4 billion Yen; 478.9 million USD)

• Baiji Refinery Upgrading Project (E/S) (2.1 billion Yen; 23.7 million USD)

• Communications Network Development Project for Major Cities (11.7 billion Yen; 132.2 million USD)

• Health Sector Reconstruction Project (10.2 billion Yen; 115.2 million USD)

Total: 4 projects

(66.4 billion Yen; 750 million USD)

9

Baiji

Basrah

Mosul

Reconstruction for

Sustainable

Development

Page 10: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

Supervising and Monitoring Project

Implementation

Strengthening Supervision in Iraq

• Baghdad Office (2003, 7 Japanese Staff since 2011)

• Erbil Office (2009)

ODA Monitoring Committee

• Meets every quarter in Baghdad

• Chaired by Dr. Thamir Al-Ghadban, of Prime Minister’s Advisory Committee

• Includes responsible officers from all projects, Ministry of Finance, Ministry of Planning, JICA Iraq Office, JICA Headquarters and Embassy of Japan in Iraq

10

Page 11: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

Copyright 2011,

2. Challenges and

Countermeasures in

Assistance to Fragile States

Page 12: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

12

Low Institutional Capacity • New Government

• Loss of Human Resources

• Minimal Experience in International Business

Challenges to Operations in Iraq

Our Approach to these

Challenges

Deteriorating Security • Limited Access to Project Sites

• Poor Transparency in Implementation

Page 13: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

(1) Human Resources Development in Japan or Neighboring Countries

13 Management of container terminal at Hakata Bay

Capacity development for 4,226 Iraqi governmental officers (JFY2003-2010)

Field visit to a hydropower plant in Japan

Energy

984

Agriculture

862

Public Works &

Utility

800

Health

652

Planning

&

Governance

639

Human

Resources

181 Others

241

Page 14: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

Program for Good Governance

National reconciliation and democratization assistance

Iraq-Japan Knowledge Sharing Seminar (Secretariat for the National Diet)

Training for administrative officials

Seminar for Iraqi Government Officials (Presidency Council/ Prime Minister’s Office)

ODA seminar (Project Managers of Japanese ODA Loans)

WTO(Ministry of Planning and International Cooperation/Ministry of Trade/Ministry of Finance and others)

Training for Security Authorities

Police Officers (Ministry of Interior)

Law Enforcement Body in Basrah (Ministry of Interior and others)

14

Page 15: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

(2) Transparency in Procurement

15

Pre-Qualification

J

I

C

A

Review

and

Concurrence

• International standards (JICA’s Guidelines) are applied. • While the Iraqi side maintains ownership, transparency is assured by

JICA’s review and concurrence.

Tender documents

Tender

Evaluation of bids

Award

Contract signing

Contract documents

I

R

A

Q

Page 16: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

16

JICA and UNDP

Monitoring

on PMT Activities

(daily basis)

Monitoring Committee (M/C): Government of Iraq/Government of Japan/JICA

(quarterly basis)

(3) Rigorous Monitoring System

Procurement Management

Financial Management

Contract Monitoring

Report Monitor

Recommend Actions for

Institutional/Systematical

Development

Capacity Building

to Reduce Bottlenecks

• Periodic monitoring at high level with clear criteria. • Close monitoring of PMT activities to find actual/potential

bottlenecks to project implementation • Capacity Building/Institutional Development based on the results of

monitoring.

PMT PMT PMT PMT

Page 17: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

(4) Collaboration with UNDP

17

Oct. 2009: JICA and UNDP signed a partnership agreement to jointly monitor project implementation.

Limited Access to Project Site

• UNDP has established field offices over the country with capable Iraqi staff.

Poor Transparency

• UNDP conducts fiduciary monitoring on implementation.

Independent Third Party

• UNDP, as an independent third party, monitors the performance of PMTs and JICA in project implementation.

• Collaboration with partners to overcome challenges amidst deteriorating security. • Independent monitoring offers benefits for both donor and recipient.

Page 18: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

18

(5) Long-Distance Supervision

Case: Samawah 60 MW Diesel Power Station

Emergency Grant extended by GoJ in 2005 (JPY 12.7 billion; USD 143.5 million)

Supervision via web camera and mobile phone

Comprehensive instruction & work manuals

Page 19: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

Results 1) Analysis of Procurement Process

19

35

127

80 78

20

67 64

113

19

139

107

0

20

40

60

80

100

120

140

160

JICA's

Concurrence of

PQ Document

PQ Evaluation Bid Evaluation Contract

Negotiation

Till 2009 2010 2011

Needs

Improvement

Needs Improvement

Days

Page 20: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

20

Results 2) Analysis of Disbursement Rates

Billion JPY

4

14.9

25.1

0

5

10

15

20

25

30

2009 FY 2010 FY 2011 FY (Up to Jan.2012)

Page 21: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

Copyright 2011,

3. Implications for Post-Conflict/Vulnerable Countries

Page 22: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

3. Implications for Post-Conflict/ Vulnerable

Countries

Security and governance can be strengthened through various mechanisms.

• Capacity can be developed through the implementation of in-country projects as well as personnel training in neighboring countries.

• Anti-corruption and transparency can be achieved through adherence to international rules.

Some projects can be implemented through remote systems. • Iraq’s experience can be transferred to other fragile countries like

Yemen, Syria and Libya.

22

Page 23: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

Copyright 2011,

4. Projects

Page 24: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

24

ABOT: Al-Basrah Oil Terminal

Location: 50km offshore from Fao (2.5 hours from Umm Qasr Port)

Size: Length: 1km, Width: 80m, Max 4 oil tankers can moor

Project Input: Loan for Construction of 1 New Pipeline, SPM (Single Point Mooring)

Technical Assistance for Establishment of Oil Spill Response Plan

Current Export Amount: about 1.6 million bpd (approx. 80% of Iraqi total exports)

>>> The Project will expand that capacity to 3.2 million bpd

Case 1: Crude Oil Export Facility Reconstruction

Project

Page 25: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

• Improve productivity of existing Basrah Refinery by installing a FCC plant

• Existing Capacity

• 1st Train (Czech): Operations started in 1974, 70 thousand bpd

• 2nd Train (Japanese): Operations started in 1979 (damaged by Iranian War in 1980, operations re-started in 1991), 70 thousand bpd

25

Case 2: Basrah Refinery Upgrading Project

• Iraq is an importing country for gasoline and other petroleum products. Approximately USD 1.27 billion is spent annually to import petroleum products.

• An increase of 20 million bl in gasoline is expected upon completion of the FCC plant. However, the supply/demand gap of gasoline was 40 million bl in 2009.

Page 26: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

• Emergency grant assistance in 2003

• Grant assistance through UNDP in 2005

• ODA loan project since 2008

• Technical cooperation (training) for port management and dredging

26

Case 3: Port Reconstruction

Rehabilitation of Port

• Shipwreck removal

• Maintenance dredging

• Improvement of Port Facilities

Page 27: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

Umm Qasr Port Dredging (2003 – 2010)

27

2003

Emergency

Grant Assistance

Old Port (South)

2005

Grant Assistance

through UNDP

Gulf to Port (85km) 2010

ODA Loan

New Port (North)

Page 28: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

28

1. Significance of Agriculture Development

• Large potential for development / investment

• Economic diversification

• (main industry in non-petroleum sector)

• Effect on job creation

2. Achievements and Future Direction • ODA Loan

• Irrigation Sector Loan: (USD 86 million) • Provision of irrigation drainage pumps, equipment and materials for

maintaining the operation of irrigation channels

• Khor Al-Zubair Fertilizer Plant Rehabilitation Project: (USD 156 million)

• Supply of urgently needed machinery to produce Kohr Al-Zubair Fertilizer

• Technical Cooperation: 4 Japanese Experts

• Agriculture Policy Advisor for Kurdistan Regional Government

• Project on Horticulture Technology Improvement and Extension: Expansion of horticulture technology suitable for local conditions and market needs

• Wheat Productivity Improvement Project for Food Self-Sufficiency:

• Technology/Knowledge Transfer on wheat seed selection, cultivation and irrigation suited for the region

Case 4: Agriculture Development

Page 29: JICA’s Contribution...Al-Akkaz Gas Power Plant Construction Project [JP¥ bil / US$ 287 mil] Port Sector Rehabilitation Project [JP¥ 30.2 bil / US$ 272 mil] Crude Oil Export Facility

Copyright 2011,

جزيل شكرا Thank you for your kind attention!