August 15, 2018 | Information Session
JFK Development Site RFP
Site Location
Goals
Development Parameters
Selection Criteria
Proposal Requirements
Questions & Answers
2August 15, 2018
Agenda Networking
Businesses
Developers
Consultants
JFK Development Site RFP
Springfield Gardens, Queens
182,000 square feet (4.18 acres)
Rockaway Boulevard provides rapid
access to North and South Conduit
Boulevard, the Van Wyck
Expressway, and Long Island
Dedicated turning lane and signal
from Rockaway Boulevard to
Eastern Road
Visibility from roadway
3August 15, 2018
Site Location
JFK Runway
Terminus and
Safety Area
JFK Fire Rescue
Training Facility
Port Authority
Tow Pound
Goals
A competitive proposal must accomplish the following goals:
- Develop a distribution, manufacturing, and/or commercial facility that supports
JFK activities and/or contributes to a resilient supply chain;
- Maximize the development of the Site in a thoughtful manner, including
incorporating green building and operating practices;
- Responsibly develop the Site by delivering on a comprehensive hiring and wage
program that helps create quality local job opportunities; and
- Plan and execute a feasible development that ensures the above project goals will
be achieved.
4August 15, 2018
NYCEDC seeks proposals that take advantage of the Site’s unique location to
construct a logistics, distribution, and/or freight-related airport-compatible facility.
Development Parameters
Sewer pipes bisect the site
No permanent construction can be
erected over sewer or an adjacent buffer
area without written approval from
appropriate City agencies and/or the Port
Authority of New York and New Jersey
Paving is typically not considered
permanent
5August 15, 2018
Sewer
Development Parameters
Site is subject to height limits pursuant to
the Federal Aviation Administration (“FAA”)
FAA height limits are approximately 30 feet
at the lowest point
FAA Form 7460-1 Notice of Proposed
Construction or Alteration is required to be
filed with the FAA prior to any development
on the Site
6August 15, 2018
Flight Path
Development Parameters
M1-1 zoning
1.0 FAR for
industrial/manufacturing uses
1.0 FAR for commercial uses
2.4 FAR for community facility
uses
7August 15, 2018
Zoning and Land Use
Development Parameters
Utilities
- Electrical and gas service are located across from the site on the north side of
Rockaway Boulevard via Con Ed
- Pursuant to the JFK Lease, the Port Authority will cooperate with the Developer to
assess feasibility of making a connection at JFK and will not charge greater than
standard rates for on-airport tenants
Vehicle Traffic
- Curb cut provides direct access for approximately 45 cars per hours during
business hours
- Developer can prepare a study for the Port Authority to review to accommodate
more capacity
8August 15, 2018
Other
Selection Criteria
9August 15, 2018
Program and Design
Financial and Schedule Feasibility
Adherence to Hiring and Workforce Programs
Qualifications
Economic Impact (Offer)
Proposal Requirements
1. Project Description
2. Respondent Description
3. Consideration
4. Financial Information
a. Financial Model / Cash Flow
b. Project Financing
c. Tenant / Operator Interest
d. Financial Statement
5. Site Plan / Architectural Design
6. Construction Plan / Schedule
7. Hiring
a. M/WBE
b. HireNYC
c. Living Wage and Prevailing Wage
8. Statement of Agreement
9. NYCEDC Internal Background Investigation Questionnaire
10. Local Law 34 – Doing Business Data Form (in a separate envelope)
11. Supplemental Information, if applicable
10August 15, 2018
Checklist
Proposal Requirements
Amended and Restated Agreement of Lease of the Municipal Air Terminal from the City
to the Port Authority of New York and New Jersey dated as of November 24, 2004
First Amendment to the Amended and Restated Agreement of Lease of the Municipal Air
Terminals dated as of August 7, 2013
Drawing showing the metes and bounds of the Site prepared by Central Survey Group
in January, 2013
Boundary and Utility Survey prepared by Mercator Land Surveying, LLC, in November,
2014
Phase 1 Site investigation, prepared by TRC Environmental Corporation for NYCEDC,
August 16, 2007
11August 15, 2018
Site File
Proposal Requirements
Rolling Deadlines
- October 4, 2018
- December 6 2018
- February 7, 2019
Three copies and one (1) electronic version of the proposal electronically (e.g. on flash
drive) delivered to:
- “JFK Development Site RFP Response”
New York City Economic Development Corporation
110 William Street, 4th Floor Mail Room
New York, New York 10038
Attn: Maryann Catalano, Chief Contracting Officer, Contracts
12August 15, 2018
Submission
JFK Development Site RFP
August 15, 2018
Please sign-in and put a corresponding sticker on your name tag. Thanks!
Businesses
Developers
Consultants