Prepared by:
AECOM
300 – 300 Town Centre Boulevard 905 477 8400 tel
Markham, ON, Canada L3R 5Z6 905 477 1456 fax
www.aecom.com
Project Number:
60155032
Date:
February, 2013
Jericho Wind, Inc.
Final Decommissioning Plan Report – Jericho Wind Energy Centre
![Page 2: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/2.jpg)
![Page 3: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/3.jpg)
AECOM Jericho Wind, Inc. Final Decommissioning Plan Report – Jericho Wind Energy Centre
01ra_2013-02-11_FINAL_Jericho Decommissioning Rpt_60155032.Docx
Table of Contents
page
1. Introduction .................................................................................................................................. 1
1.1 Summary of Decommissioning Report Requirements ........................................................................ 1 1.2 The Proponent ..................................................................................................................................... 1 1.3 Project Study Area ............................................................................................................................... 2
2. Decommissioning Plan Overview ............................................................................................... 4
2.1 Decommissioning During Construction ............................................................................................... 4 2.2 Decommissioning After Ceasing Operations ....................................................................................... 4
2.2.1 Wind Turbines ......................................................................................................................... 5 2.2.2 Wind Turbine Foundations ..................................................................................................... 5 2.2.3 Access Road Removal ........................................................................................................... 5 2.2.4 Cable Wire Decommissioning ................................................................................................ 5 2.2.5 Electrical Substation Decommissioning.................................................................................. 5 2.2.6 Crane Pad Decommissioning ................................................................................................. 5 2.2.7 Overhead Collector System and Transmission Lines ............................................................ 5
2.3 Procedures for Decommissioning ........................................................................................................ 6 2.4 Land Restoration Activities .................................................................................................................. 6 2.5 Procedures for Managing Waste Generated ....................................................................................... 7 2.6 Emergency Response and Communications Plan .............................................................................. 7 2.7 Decommissioning Notification ............................................................................................................. 7 2.8 Other Approvals ................................................................................................................................... 8 2.9 Conditions of Approval......................................................................................................................... 8
3. Summary and Conclusions ......................................................................................................... 8
List of Figures
Figure 1-1 Project Location.......................................................................................................................................... 3
List of Tables
Table 1-1 Adherence to Decommissioning Plan Report Requirements ..................................................................... 1
Appendices
Appendix A. Parkhill Interconnect Renewable Energy Approval Application Decommissioning Plan Report (GLGH, 2013)
Glossary of Terms
GE ...................... General Electric
MOE ................... Ontario Ministry of the Environment
MNR ................... Ontario Ministry of Natural Resources
MTCS ................. Ontario Ministry of Tourism, Culture and Sport
MW ..................... Megawatt
NextEra ............... NextEra Energy Canada, ULC
O. Reg. 359/09.... Ontario Regulation 359/09
The Project ......... Jericho Wind Energy Centre
REA .................... Renewable Energy Approval
![Page 4: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/4.jpg)
![Page 5: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/5.jpg)
AECOM Jericho Wind, Inc. Final Decommissioning Plan Report – Jericho Wind Energy Centre
01ra_2013-02-11_FINAL_Jericho Decommissioning Rpt_60155032.Docx 1
1. Introduction
Jericho Wind, Inc., a wholly owned subsidiary of NextEra Energy Canada, ULC, (NextEra) is proposing to construct
a wind energy project in the Municipality of Lambton Shores and the Township of Warwick, in Lambton County,
Ontario and in the Municipality of North Middlesex, in Middlesex County, Ontario. The Project is referred to as the
Jericho Wind Energy Centre (the “Project”). All turbines will be located on private lands.
This Decommissioning Plan Report was prepared in accordance with the requirements of Ontario Regulation 359/09
(O. Reg. 359/09) and the Technical Guide to Renewable Energy Approvals (Ontario Ministry of the Environment
(MOE), 2011). At the time of decommissioning, the Decommissioning Plan will be reviewed in accordance with
applicable regulations.
The following sections outline the process of the Project’s decommissioning phase.
1.1 Summary of Decommissioning Report Requirements
The requirements for the Decommissioning Plan Report defined under O.Reg. 359/09 are provided in the following
table (Table 1-1).
Table 1-1 Adherence to Decommissioning Plan Report Requirements
Requirement Completed Corresponding Section
Description of Decommissioning Activities Yes 2.3
Site Restoration Yes 2.4
Managing Excess Materials and Waste Yes 2.5
Other Approvals Yes 2.8
1.2 The Proponent
The Project will be owned and operated by Jericho Wind, Inc., a subsidiary of NextEra. NextEra Energy Canada’s
indirect parent company is NextEra Energy Resources, LLC, a global leader in wind energy generation with a current
operating portfolio of over 100 wind energy projects in North America. Wind farms currently owned and operated by
NextEra Energy Canada include: Mount Copper and Mount Miller (both 54 megawatt (MW)), located in Murdochville,
Quebec; Pubnico Point, (31 MW) located near Yarmouth, Nova Scotia; Ghost Pine (82 MW), located in Kneehill
County, Alberta; and Conestogo (23 MW) located in Wellington County, Ontario.
The primary contacts for the Project are as follows:
Project Proponent Project Consultant
Ross D. Groffman
Project Director
NextEra Energy Canada, ULC
390 Bay Street, Suite 1720
Toronto, Ontario, M5H 2Y2
Phone: ..... 416.364.9714
Email: ...... [email protected]
Website: .. www.NextEraEnergyCanada.com
Marc Rose
Senior Environmental Planner
AECOM
300-300 Town Centre Blvd.
Markham, Ontario, L3R 5Z6
Phone: .... 905.477.8400 x388
Email: ...... [email protected]
![Page 6: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/6.jpg)
AECOM Jericho Wind, Inc. Final Decommissioning Plan Report – Jericho Wind Energy Centre
01ra_2013-02-11_FINAL_Jericho Decommissioning Rpt_60155032.Docx 2
1.3 Project Study Area
The proposed Project is located in the Municipality of Lambton Shores and the Township of Warwick, in Lambton
County, Ontario and in the Municipality of North Middlesex, in Middlesex County, Ontario. The Project Study Area
consists of the areas being studied for the wind energy component (Wind Energy Centre Study Area), as well as for
the interconnection route (i.e., the area being studied for transmission lines to connect the Project to the electrical
grid) (Transmission Line Study Area). The Wind Energy Centre Study Area is generally bounded by Lakeshore
Road/Bog Line to the north, Egremont Road to the south, the Lambton Shores/North Middlesex municipal boundary
to the east and Rawlings Road/Elarton Road to the west, in Lambton County. The Transmission Line Study Area is
generally bounded by Kennedy Line, Parkhill Drive and Elginfield Road to the north, Jura Line, Elm Tree Drive and
Poplar Hill Road to the south, Fernhill Drive to the east, and the Jericho Road to the west, in Lambton and Middlesex
Counties.
The location of the Project Study Area was defined early in the planning process for the proposed wind energy
facility, based on the availability of wind resources, approximate area required for the proposed project, and
availability of existing infrastructure for connection to the electrical grid. The Project Study Area was used to
facilitate information collection.
Figure 1-1 shows the Project Location.
![Page 7: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/7.jpg)
Map Document: (N:\projects\0-aecom\60155032\2010\Final\GISSpatial\MXDs\ReportMXDs\NHA_Mapping\Jericho\60155032_Jericho_ProjectLocation.mxd)6/13/2012 -- 9:30:48 AM
N o r t h M i d d l e s e x
W a r w i c k
L a m b t o n S h o r e s
A d e l a i d e M e t c a l f e
M i d d l e s e xC e n t r e
K e t t l e P o i n t 4 4
5
6218
4
3
9
7
97
96
39
47
17
40
71
74
80
8662
85
15
83
43
73
32
46
29
50
3541
42
52
67
769291
12
33
1911
30
31
44
84
65
70
68
69
60
6154
90
6364
82
25
21
20
10
56
37
59
27
24
49
58
22
94
89
14
36
72
51
13
23
78
45
77
28
88
79
16
75
66
57
38
48
81
53
26
34
105
102
103
Re fer to Parkh i l l In terconnect Pro ject Appendix
Lake Huron
Ark
ona
Roa
d
Nairn Road
Townsend Line
Cen
tre
Roa
d
Coldstream Road
Egremont Drive
Zion Line
Birnam Line
WestCorner Drive
Ker
woo
d R
oad
Egremont Road
Bornish Drive
Petty S
treet
Brick Yard Line
Thomson Line
Argyle
Street
Jura Line
Sylv
an R
oad
Cuddy Drive
Elm Tree Drive
Fernhill
Drive
Jeric
ho R
oad
Cedar Point Line
Cassidy R
oad
Nau
voo
Roa
d
Mcewen
Driv
e
Mullifarry Drive
Poplar Hill Road
Bet
hel R
oad
Elar
ton
Roa
d
Parkhill Drive
Sext
on R
oad
Arm
y C
amp
Roa
d
Elliot Drive
Seed
Roa
d
Firs
t Sch
ool R
oad
Ridge Road
Maguire R
oad
Ausable Drive
Gor
don
Roa
d
Greyste
ad D
rive
New Ontario Road
Sprin
gban
k R
oad
Charlton D
rive
Proof Line
Nor
thvi
lle R
oad
Rod
dick
Roa
d
Scho
ol R
oad
Bog Line
Mooresville Drive
Elginfield Road
Hickory Creek Line
Kin
naird
Roa
d
Chalk Line
Hedley
Driv
e
Fulle
r Roa
d
Wis
beac
h R
oad
Wils
on R
oad
War
wic
k Vi
llage
Roa
d
Lond
on L
ine
Ivan D
rive
Mcgillivray Drive
Ildert
on Road
Fort
Ros
e R
oad
Pete
Seb
e R
oad
Ravenswood Line
Has
kett
Roa
d
Bear Creek Road
Langan Drive
Mci
nnis
Roa
d
Glasgow Street
Wood Road
River Drive
Amiens Road
Gra
nd B
end
Roa
d
Mcguffin Hills Drive
Hickory
Drive
Brinsley R
oad
Mcl
ean
Roa
d
Pran
ce R
oad
Decker Road
Farmers Line
God
kin
Roa
d
Wya
tt R
oad
New
ell R
oad
Ipperwash Road
Lieury Road
Komoka Road
Sinclair D
rive
Rob
otha
m R
oad
Haig Line
Crathie Drive
Grie
ves
Roa
d
Cream
ery Road
Widder Road
Ellio
t Roa
d
Second Street
Que
en S
tree
t
Mark Settlement Drive
Salem R
oad
Glengyle
Driv
e
Outer Drive
Wardell Drive
Avenue DriveKennedy Line
Han
sfor
d R
oad
Mccubbin Road
Indian Lane
Cen
tre
Side
road
Main Street
Lakeshore Road
Isla
nd R
oad
Scou
t Roa
d
Sitter Road
Cha
rlton
Roa
d
Ausable Road
Clandeboye Drive
Wes
t-Ipp
erw
ash
Roa
d
Fore
st R
oad
Petticoat Line
Walker Road
Bruce Scott Road
Willsie Line
Skinner
Drive
Middle Sideroad
Har
mon
y R
oad
Mci
ntyr
e R
oad
Boo
t Hill
Roa
d
Hod
gins
Roa
d
Don
nelly
Roa
d
Lamon Drive
Bro
wn
Roa
d
Port Franks Road
Sand
y Tr
ail
Ever
gree
n R
oad
Tamarack Line
King Street
Bet
hesd
a R
oad
Und
erpa
ss R
oad
Dru
mm
ond
Roa
d
Cedar Sw
amp R
oad
Hag
mie
r Roa
d
Park
hill
Mai
n St
reet
Rock Glen Road
Pow
er R
oad
Pedd
en R
oad
Bullock R
oad
Douglas Line
Fisher Line
Cam
eron
Roa
d
Bro
ken
Fron
t Roa
d
Ross Road
Prince William Street
Northville
Crescent
Queen Street West
Macdonald Drive
Fletcher Road
Quaker Lane
Win
dsor
Roa
d
Raw
lings
Roa
d
21 Sideroad
Vernon Road
Sulli
van
Roa
d
Kin
g St
reet
Elginfield Road
Elginfield Road
Hedley
Driv
e
Nor
thvi
lle R
oad
Queen Street
Mcgillivray Drive
Gor
don
Roa
d
Kennedy Line
402
UTM Zone 17N, NAD 83
Project Location
Figure 1-1
February 2013Project 60155032
Jericho Wind Energy CentreDecommissioning Plan Report
1:50,000
LegendWind Energy Centre Study AreaTransmission Line Study Area120m Area of InvestigationMunicipal DivisionFreewayExpressway / HighwayMajor RoadLocal RoadRampRailway
Natural FeatureWatercourse (ABCA, SCRCA)Watercourse (MNR)WaterbodyCartographic WetlandWooded Area
Project LocationGE TurbinePermanent Meterological TowerAccess RoadCollection LineCrane PathTransmission LineSubstation & Laydown AreaDisturbance AreasExisting 500kV Transmission Line Bornish Switchyard
Parkhill Interconnect Infrastructure (See Addendum)
Parkhill Transformer Substation and Point of InterconnectionProposed Transmission line from Bornish Switchyard to Parkhill TS
Produced by AECOM under licence from Ontario Ministry of Natural Resources, Copyright © Queens Printer 2012
0 400 800 1,200 1,600200
Metres
This drawing has been prepared for the use of AECOM’s client and may not be used, reproduced or relied upon by third parties,except as agreed by AECOM and its client, as required by law or for use by governmental reviewing agencies. AECOM accepts no responsibility, and denies any liability whatsoever, to any partythat modifies this drawing without AECOM’s express written consent.
![Page 8: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/8.jpg)
![Page 9: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/9.jpg)
AECOM Jericho Wind, Inc. Final Decommissioning Plan Report – Jericho Wind Energy Centre
01ra_2013-02-11_FINAL_Jericho Decommissioning Rpt_60155032.Docx 4
2. Decommissioning Plan Overview
The anticipated life of the Project is estimated to be at least 30 years. The following sections describe how the
proposed Project will be dismantled either during construction (although unlikely) or following the operations phase
of the Project. The wind turbine decommissioning process will be initiated upon the termination of the leases with the
landowners. The decommissioning process will involve removing the wind turbine, including the tower, generator,
auxiliary equipment, above ground cables/poles, fixtures, all other personal property and otherwise restoring the
premises to its original condition. If it is agreed upon with the landowner, access roads and underground cables may
be left in place. Foundations shall be removed to original soil depth or approximately 1 metre (m) below grade,
whichever is the lesser, and replaced with topsoil. Within 12 months of initiating the decommissioning process, the
Project owner will have removed the relevant components from the leased land.
The decommissioning of the Jericho Wind Energy Centre will be undertaken in compliance with this Decommissioning
Plan and the Ontario Occupational Health and Safety Act along with any other applicable regulatory requirements and
standards, including those from the Ontario Ministry of Natural Resources (MNR), Conservation Authorities or Ontario
Ministry of Tourism, Culture and Sport (MTCS). As with construction, a manager responsible for safety will be present
on site for the duration of the work.
Reference should be made to Appendix A for the associated Parkhill Interconnect Renewable Energy Approval
Application Decommissioning Plan Report (GLGH, 2013).
2.1 Decommissioning During Construction
Although it is unlikely that the Project would be decommissioned before the operations phase, should this occur, the
actual procedures for dismantling the Project would depend upon the state of construction. Dismantling would follow
the steps outlined in Section 2.3 of this report and any exposed soils would be re-seeded in consultation with the
landowner. Mitigation measures as described in the Environmental Effects Management Plan (part of the Design
and Operations Report, AECOM 2013) would also be implemented.
2.2 Decommissioning After Ceasing Operations
Properly maintained wind turbines have an expected life of at least 30 years. At the end of the project life, depending
on market conditions and project viability, the wind turbines may be ‘re-powered’ with new nacelles, towers, and/or
blades, thus extending the useful life of the Project and delaying any decommissioning activities. Alternatively, the
wind turbines may be decommissioned.
The following activities for the removal of the components will be undertaken once decommissioning is initiated:
Remove above-ground collection and transmission system including substation and switchyard unless
the transmission facilities are to be used by another qualified utility;
Remove wind turbines;
Partial removal of wind turbine foundations;
Remove underground cables, if required by landowners; and
Remove turbine access roads, if required by landowners.
The following anticipated detailed Decommissioning Plan is based on current procedures and experience. The
specifics of these procedures may be adjusted to reflect additional decommissioning experience in the future.
![Page 10: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/10.jpg)
AECOM Jericho Wind, Inc. Final Decommissioning Plan Report – Jericho Wind Energy Centre
01ra_2013-02-11_FINAL_Jericho Decommissioning Rpt_60155032.Docx 5
2.2.1 Wind Turbines
The first stage of disassembly will include wiring crews disconnecting the tower from the collection system and
disconnecting the wiring between turbine sections. A disassembly crew will then use a crane to remove the blades,
the rotor, nacelle and then the towers section by section. The lubricating oil will be drained from the gearbox once it
has been placed on the ground, and the oil will be disposed of in accordance with applicable regulations. As the
turbine is being disassembled, the various components will be transported off-site.
2.2.2 Wind Turbine Foundations
Once all the turbine components have been cleared from a site, the top metre of overburden around the foundation
will be excavated and stockpiled. Once cleared, the top approximately 1 m of the foundation (or to bedrock) will be
demolished. The resulting concrete and reinforcing bar (rebar) will be hauled off-site and disposed of at a licensed
facility. Afterwards, the stockpiled soil will be used to replace the now cleared area. The disturbed area will be
feathered out and graded. No off-site soil is predicted to be needed.
2.2.3 Access Road Removal
Access roads will be left at the landowner’s request or graded to restore terrain profiles (as much as possible), and
vegetated.
2.2.4 Cable Wire Decommissioning
At the time of decommissioning, if appropriate and with the consent of the landowner, the underground cables will be
left in place. The lines will be cut and the ends buried to approximately 1 m below grade.
2.2.5 Electrical Substation Decommissioning
The substation electrical components will be either removed as a whole or disassembled, pending reuse or
recycling. Once cleared, the gravel around the yard will be reclaimed (unless the landowner wishes to keep the area
as is) and the fence removed. The substation foundation will be excavated and the top approximately 1 m of
concrete (or to bedrock) will be demolished and hauled off-site to be disposed of at a licensed facility. The excavated
area will then be filled in with native soil and re-graded. Any material that has been used as a sound attenuating
berm will be levelled and replanted to the requirements of the landowner.
2.2.6 Crane Pad Decommissioning
The crane pad aggregate will be removed and areas will be filled unless the landowner asks for it to remain.
2.2.7 Overhead Collector System and Transmission Lines
Overhead cables and transmission poles will be removed or sold to an acceptable Transmission/Distribution
Operator. Transmission pole holes will be filled with clean fill and disturbed areas will be reseeded with native
vegetation, where required. Overhead lines will be removed and recycled, reused, or disposed of in accordance with
regulatory requirements at the time of decommissioning.
![Page 11: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/11.jpg)
AECOM Jericho Wind, Inc. Final Decommissioning Plan Report – Jericho Wind Energy Centre
01ra_2013-02-11_FINAL_Jericho Decommissioning Rpt_60155032.Docx 6
2.3 Procedures for Decommissioning
Decommissioning procedures will be similar to the construction phase. The procedures, which will be finalized prior
to decommissioning in accordance with REA requirements, are anticipated to include:
1. The creation of temporary work areas. In order to provide sufficient area for the lay-down of the
disassembled wind turbine components and loading onto trucks, an approximately 122 m by 122 m
square must be cleared, levelled and made accessible to trucks. The topsoil will be removed and
some material may need to be added.
2. The creation of crane pads. The crane pads will typically be 15 m x 35 m in size and will be located
within the temporary work area around each wind turbine. The topsoil at the crane pad will be
removed and approximately 600 mm of compacted crushed gravel will be added. Once the turbine
disassembly is complete, the gravel area around each turbine will be removed and the area will be
restored to prior use using stockpiled topsoil.
3. The use of cranes to remove the blades, hub and tower segments.
4. The use of trucks for the removal of turbines, towers and associated equipment.
5. The removal of approximately the top 1 m of the turbine foundations and replacement with clean fill
and stockpiled topsoil. The fill and topsoil will be contoured to allow cultivation in the case of
agricultural lands.
6. Road bedding material will be removed and replaced with clean subsoil and topsoil for reuse by the
landowner for agricultural purposes. It is proposed to leave culverts in place following the operations
phase.
7. Cutting underground electrical lines, burying the ends to approximately 1 m below grade, and
leaving the lines in place with the consent of the landowner. Above-ground lines and poles that are
not shared with another Transmission/Distribution Operator will be removed and the holes will be
filled with clean fill.
8. The demolition of the substation and operations and maintenance building. These will be
decommissioned in a manner appropriate to and in accordance with the standards of the day. All
materials will be recycled, where possible, or disposed off-site at an approved and appropriate
facility.
2.4 Land Restoration Activities
Once all of the turbines and ancillary facilities are removed, the remaining decommissioning work will consist of
shaping and grading the areas to, as near as practicable, the original contours prior to construction of the wind
turbines and access roads. Existing agricultural capacity will be restored and the land graded to maintain proper
drainage. All areas, including the access roads, transformer pads and crane pads will be restored to, as near as
practical, their original condition with native soils and seeding. If there is insufficient material onsite, topsoil and/or
subsoil will be imported from a source acceptable to the landowner.
Although strict spill prevention procedures will be in place, there is the potential through the decommissioning
process for small spills of solvents or fuels. The soil conditions of the turbine areas will be surveyed to determine if
any effects have occurred. Should soil effects be noted, the affected soils will be identified, excavated, and removed
to the applicable standards from the site for disposal at an approved and appropriate facility. The removed soils will
be replaced with stockpiled subsoil and topsoil, if available. If none are available, clean fill and topsoil will be
imported.
![Page 12: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/12.jpg)
AECOM Jericho Wind, Inc. Final Decommissioning Plan Report – Jericho Wind Energy Centre
01ra_2013-02-11_FINAL_Jericho Decommissioning Rpt_60155032.Docx 7
Decommissioning may temporarily affect the agricultural practices directly around the access roads, substation and
turbine locations, but only during their removal. Similar to the construction phase, decommissioning will follow a
stormwater protection plan that will ensure proper steps are followed to mitigate erosion and silt/sediment runoff.
As with the Project’s construction, noise levels around the decommissioning work may be higher than average.
Proper steps will be followed to minimize this disturbance, such as avoiding work outside of daylight hours where
possible. All decommissioning project activities will conform to applicable local municipal noise by-laws. Also, as with
the Project’s construction, road traffic in the area will increase temporarily due to crews and heavy equipment
movements. If required, a traffic management plan will be prepared to mitigate the effects of increased road traffic, in
consultation with the local municipality.
2.5 Procedures for Managing Waste Generated
As discussed above, the waste generated by the decommissioning of the Project is minimal, and there are
anticipated to be no toxic residues. Any waste generated will be disposed of according to the applicable standards
with the emphasis on recycling materials whenever possible.
The major components of the wind turbines (tower, nacelle, blades) are modular items that allow for ease of
construction and disassembly of the wind turbines during replacement or decommissioning. Dismantled wind
turbines have a high salvage value due to the steel and copper components. These components are easily
recyclable and there is a ready market for scrap metals. Transformers and transmission lines are typically designed
for a 50 year lifespan so these items could be refurbished and sold for reuse.
Based on the construction details for the GE wind turbines and associated tower and components, it is assumed that
both the tower and nacelle will yield approximately 80% salvageable materials. Since the hub assembly and
bedplate is manufactured steel, it is anticipated that the hub will yield 100% salvageable metallic materials. Copper
salvage estimates were derived by assuming 5% of the total tower and nacelle weight consists of salvageable
copper bearing materials. Since the rotor/blades are constructed of predominantly non-metallic materials (fiberglass
reinforced epoxy and carbon fibres), no salvage for the rotor or blades is currently assumed.
It is assumed that 75% of the aggregate material from the decommissioning of the crane pads can be salvaged for
future use as aggregate base course. The remaining materials would be viable for general fill on non-structural fill
areas. The geotextile fabric cannot be salvaged.
2.6 Emergency Response and Communications Plan
The Emergency Response and Communications Plan is included in the Design and Operations Report (AECOM,
2013) prepared as part of the REA application for the proposed Jericho Wind Energy Centre.
2.7 Decommissioning Notification
The process for notification of decommissioning activities will be the same as the process for notification of
construction activities and is detailed in Section 5 of the Emergency Response and Communications Plan in the
Design and Operations Report (AECOM, 2013).
![Page 13: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/13.jpg)
AECOM Jericho Wind, Inc. Final Decommissioning Plan Report – Jericho Wind Energy Centre
01ra_2013-02-11_FINAL_Jericho Decommissioning Rpt_60155032.Docx 8
2.8 Other Approvals
The Project owners will ensure that all of the required approvals at the time of decommissioning of the proposed
facility are adhered to.
2.9 Conditions of Approval
The Project owner will ensure that the decommissioning stage of the proposed Project is carried out in accordance
with REA requirements and the measures/practices as described in this report as well as any conditions imposed in
the REA approval.
3. Summary and Conclusions
This Decommissioning Plan Report has been completed to assist the Project owner in fulfilling regulatory
requirements for the decommissioning of the Jericho Wind Energy Centre project. This report is consistent with the
provisions of Ontario Regulation 359/09 for a Class 4 Wind Farm facility.
![Page 14: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/14.jpg)
![Page 15: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/15.jpg)
01ra_2013-02-06_Tps - Decomm_60155032.Docx
Appendix A
Parkhill Interconnect Renewable Energy Approval Application Decommissioning Plan Report (GLGH, 2013)
![Page 16: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/16.jpg)
![Page 17: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/17.jpg)
PARKHILL INTERCONNECT
RENEWABLE ENERGY APPROVAL APPLICATION
DECOMMISSIONING PLAN REPORT
February 2013
![Page 18: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/18.jpg)
![Page 19: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/19.jpg)
RENEWABLE ENERGY APPROVAL APPLICATION
PARKHILL INTERCONNECT
DECOMMISSIONING PLAN REPORT
Client Jericho Wind, Inc. Contact Ross Groffman Document No 800253-CAMO-R-01 Issue B Status Final Classification Client’s Discretion Date 07 February 2013
Author: G. Constantin
Checked by: -
Approved by: N. O’Blenes
![Page 20: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/20.jpg)
IMPORTANT NOTICE AND DISCLAIMER
1. Acceptance of this document by the Client is on the basis that GL Garrad Hassan Canada, Inc. (hereafter ‘‘GL GH’’), a GL Group member traded as GL Garrad Hassan, is not in any way to be held responsible for the application or use made of the findings or results of the analysis and that such responsibility remains with the Client.
This Report shall be for the sole use of the Client for whom the Report is prepared. The document is subject to the terms of the Agreement between the Client and GL GH and should not be relied on by third parties for any use whatsoever without the express written authority of GL GH. The Report may only be reproduced and circulated in accordance with the Document Classification and associated conditions stipulated in the Agreement, and may not be disclosed in any offering memorandum without the express written consent of GL GH.
GL GH does not provide legal, regulatory, insurance, tax or accounting advice. The recipient must make its own arrangements for consulting in these areas.
This document has been produced from information at the date of this document and, where applicable, information relating to dates and periods referred to in this document. The Report is subject to change without notice and for any reason including, but not limited to, changes in information, conclusion and directions from the Client.
2. This report has been produced from information relating to dates and periods referred to in this report. The
report does not imply that any information is not subject to change.
![Page 21: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/21.jpg)
KEY TO DOCUMENT CLASSIFICATION
Strictly Confidential For disclosure only to named individuals within the Client’s organization
Private and Confidential
For disclosure only to individuals directly concerned with the subject matter of the Report within the Client’s organization
Commercial in Confidence Not to be disclosed outside the Client’s organization
GL GH only Not to be disclosed to non-GL GH staff
Client’s Discretion
Distribution for information only at the discretion of the Client (subject to the above Important Notice and Disclaimer)
Published Available for information only to the general public (subject to the above Important Notice and Disclaimer)
© 2013 GL Garrad Hassan Canada, Inc.
![Page 22: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/22.jpg)
Document No.: 800253-CAMO-R-01
Renewable Energy Approval Application – Decommissioning Plan Report – Parkhill Interconnect
Issue: B Final
GL Garrad Hassan Canada, Inc.
i
REVISION HISTORY
Issue Issue Date Summary
A
B
05 November 2012 07 February 2013
Initial version Reference to the Operation and Maintenance Building
![Page 23: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/23.jpg)
Document No.: 800253-CAMO-R-01
Renewable Energy Approval Application – Decommissioning Plan Report – Parkhill Interconnect
Issue: B Final
GL Garrad Hassan Canada, Inc.
ii
TABLE OF CONTENTS
1 PREAMBLE 1 1.1 General Project Description 1 1.2 Contact Information 4
Project Proponent 4 1.2.1 Project Consultant 4
2 DECOMMISSIONING 5 2.1 Decommissioning During Construction 5 2.2 Decommissioning After Ceasing Operations 5 2.3 Procedures for Dismantling 5 2.4 Restoration of Land 5
2.4.1 Land Restoration Activities 6 2.5 Waste Generated 6
3 EMERGENCY RESPONSE AND COMMUNICATIONS PLANS 7
4 PUBLIC, MUNICIPAL AND ABORIGINAL COMMUNITY NOTIFICATION 7
5 OTHER APPROVALS 7
6 SUMMARY 7
7 REFERENCES 9
![Page 24: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/24.jpg)
![Page 25: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/25.jpg)
Document No.: 800253-CAMO-R-01
Renewable Energy Approval Application – Decommissioning Plan Report – Parkhill Interconnect
Issue: B Final
GL Garrad Hassan Canada, Inc.
1
1 PREAMBLE
Jericho Wind, Inc. is proposing to develop the Jericho Wind Energy Centre and the Parkhill Interconnect Project (‘’Parkhill Interconnect”), which are subject to Ontario Regulation 359/09 (Renewable Energy Approvals (REA) under Part V.0.1 of the Ontario Environmental Protection Act (EPA)) [1]. Jericho Wind, Inc. is seeking a Renewable Energy Approval from the Ontario Ministry of the Environment (MOE) for the Jericho Wind Energy Centre and its related Parkhill Interconnect Project. The Parkhill Interconnect will consist of a switchyard, approximately 11.5 km of 115 kV transmission line and a substation. The substation will consist of two (2) 135/225 MVA transformers. The 115 kV line will run from the Parkhill Interconnect’s switchyard, known as the Bornish Switchyard, to the Parkhill Interconnect’s substation, known as the Parkhill Substation. The Parkhill Substation will then be interconnected to a Hydro One-owned switchyard, known as the Evergreen Switchyard, and to an existing Hydro One 500 kV transmission line that is common to the Jericho Wind Energy Centre, the Adelaide Wind Energy Centre (owned by Kerwood Wind, Inc.), and the Bornish Wind Energy Centre (owned by Bornish Wind, LP). The Point of Common Coupling will be the interface between the Parkhill Substation and Hydro One’s Evergreen Switchyard. The Parkhill Interconnect will be owned by Bornish Wind LP, Kerwood Wind, Inc., and Jericho Wind, Inc. These three companies are wholly-owned subsidiaries of NextEra Energy Canada, ULC (“NextEra”). This Decommissioning Plan Report has been prepared in accordance with section 54.1 of O. Reg. 359/09 and the MOE’s “Draft Technical Guide to Renewable Energy Approvals”(2012) [3]. 1.1 General Project Description
The proposed Parkhill Interconnect is located in the Municipality of North Middlesex, Middlesex County, Ontario (please refer to Figure 1-1). The Study Area comprises a 115 kV transmission line from the Bornish Switchyard to the Point of Common Coupling (PCC) on Hydro One’s 500 kV transmission line. The electricity generated from the Adelaide, Bornish and Jericho Wind Energy Centres will converge at the Bornish Switchyard. From this point, the proposed 115 kV line will carry electricity generated by all three projects to the Parkhill Substation then to a second Hydro One-owned Switchyard on to an existing Hydro One 500 kV transmission line. Approximately 11.5 km in length, the transmission line is proposed to be mounted on new hydro poles within the road rights-of-way along Kerwood, Elginfield and Nairn Roads. There may be occasional locations where the transmission is below ground for technical reasons.
![Page 26: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/26.jpg)
Document No.: 800253-CAMO-R-01
Renewable Energy Approval Application – Decommissioning Plan Report – Parkhill Interconnect
Issue: B Final
GL Garrad Hassan Canada, Inc.
2
Table 1-1: Geographic coordinates of the Transmission Line Study Area
Site Easting Northing
Northwest corner 441 165 4 780 749
Northeast corner 458 588 4 777 297
Southwest corner 438 585 4 771 264
Southeast corner 458 588 4 766 303
The location of the Transmission Line Study Area was defined early in the planning process for the proposed wind energy facility, based on the availability of existing infrastructure for connection to the electrical grid. The Transmission Line Study Area was used to facilitate information collection and Records Review.
![Page 27: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/27.jpg)
Document No.: 800253-CAMO-R-01
Renewable Energy Approval Application – Decommissioning Plan Report – Parkhill Interconnect
Issue: B Final
GL Garrad Hassan Canada, Inc.
3
Figure 1-1: Transmission Line Study Area
![Page 28: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/28.jpg)
Document No.: 800253-CAMO-R-01
Renewable Energy Approval Application – Decommissioning Plan Report –Parkhill Interconnect
Issue: B Final
GL Garrad Hassan Canada, Inc.
4
1.2 Contact Information
Project Proponent
Jericho Wind, Inc., a wholly owned subsidiary of NextEra Energy Canada, ULC, is the proponent for the Parkhill Interconnect. The primary contact for Jericho Wind, Inc. is: Derek Dudek Community Relations Consultant NextEra Energy Canada, ULC 390 Bay Street, Suite 1720 Toronto, ON M5H 2Y2 Canada Phone: 1-877-257-7330 Email: [email protected] Website: www.NextEraEnergyCanada.com 1.2.1 Project Consultant
GL Garrad Hassan Canada, Inc., a member of the GL Group and part of the GL Garrad Hassan brand, (hereafter referred to as “GL GH”), has been retained to lead the REA Process for the Parkhill Interconnect Project. The Environmental and Permitting Services team of GL GH has completed mandates throughout Canada, the United States and in many other parts of the world. These mandates include permitting management, permit applications, environmental impact assessment, and various environmental studies for more than 15,000 MW of wind and solar-PV projects. GL GH’s environmental team is composed of over 20 environmental professionals, including environmental impact specialists, planners, GIS, technicians and engineers. GL GH has no equity stake in any device or project. This rule of operation is central to its philosophy, distinguishing it from many other players and underscoring its independence. GL GH’s contact information is as follows: Nancy O’Blenes GL Garrad Hassan Canada, Inc. Uxbridge, ON L9P 1A5 Tel.: (416) 801-6822 nancy.o’[email protected] Further information about GL GH can be found at: www.gl-garradhassan.com.
![Page 29: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/29.jpg)
Document No.: 800253-CAMO-R-01
Renewable Energy Approval Application – Decommissioning Plan Report –Parkhill Interconnect
Issue: B Final
GL Garrad Hassan Canada, Inc.
5
2 DECOMMISSIONING
The anticipated life of the Parkhill Interconnect is estimated to be a minimum of 30 years. The following sections describe how the Parkhill Interconnect will be dismantled either during construction (although unlikely) or following the operations phase of the Parkhill Interconnect Project. 2.1 Decommissioning During Construction
Although it is unlikely that the Parkhill Interconnect would be decommissioned prior to the operations phase, should this occur, the actual procedures for dismantling Parkhill Interconnect would depend upon the state of construction activities. Dismantling would follow the steps outlined in the Section “Procedures for Dismantling” below and any exposed soils would be re-seeded in consultation with the landowner. 2.2 Decommissioning After Ceasing Operations
Should it be decided to not repower the Parkhill Interconnect at the end of its service life, the steps outlined in the Section “Procedures for Dismantling” would be taken to dismantle the various Parkhill Interconnect components. 2.3 Procedures for Dismantling
If the facility is to be decommissioned and components are to be removed at the end of its service life or during construction, the procedures will be similar to the construction phase, but in reverse sequence. The procedures will include:
1 Roads and culverts, if required, will be removed unless the landowner requests that they be left in place. Road bedding material will be removed and replaced with clean subsoil and topsoil for reuse by the landowner for agricultural purposes. If requested by the landowner and subject to approval by the ABCA and the MNR, the culverts will be removed and the land will be contoured to maintain the current drainage patterns.
2 Overhead lines and poles, unless required to be left in place, will be removed and the holes will be filled with clean fill.
3 The substation, switchyard and operations building will be dismantled. These will be decommissioned in an appropriate manner and in accordance with the standards of the day. All materials will be recycled, where possible, or disposed off site at an approved and appropriate facility.
2.4 Restoration of Land
Abandonment of Parkhill Interconnect will not result in any impacts to surface or groundwater quality. After the abandonment process is completed the land will be returned to previous agricultural conditions, in consultation with the landowner.
![Page 30: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/30.jpg)
Document No.: 800253-CAMO-R-01
Renewable Energy Approval Application – Decommissioning Plan Report –Parkhill Interconnect
Issue: B Final
GL Garrad Hassan Canada, Inc. 6
2.4.1 Land Restoration Activities
Once the equipment has been removed, the land will be restored to its previous agricultural capacity in consultation with the landowner. This will be accomplished by removing the granular material from roadways and culverts, depending on the landowner preference. Agricultural capacity will be restored and the land re-contoured to maintain proper drainage. Preferably, this will be accomplished using stockpiled subsoil and topsoil. If there is insufficient material onsite, topsoil and/or subsoil will be imported from a source acceptable to the landowner. Although strict spill prevention procedures will be in place, the potential for small spills of solvents or fuels exists through the routine maintenance and operation of the substation and/or decommissioning process. The soil conditions of the component areas will be surveyed per current standards to determine if any impacts have occurred. Should soil impacts be noted, the impacted soils will be delineated, excavated and removed, per applicable standards, from the site for disposal at an approved and appropriate facility. The removed soils will be replaced with stockpiled subsoil and topsoil, if available. If no subsoil or topsoil is available onsite, clean fill and topsoil will be imported. 2.5 Waste Generated
The waste generated by the installation, operation and decommissioning of the Parkhill Interconnect is minimal and there are no toxic residues. Any waste generated will be disposed of according to standards of the day with an emphasis on recycling materials whenever possible. Throughout the lifecycle of the Parkhill Interconnect Project, the Proponent will work with the Canadian Food Inspection Agency and its Provincial and municipal partners to ensure that any woody waste is disposed of in such a way that it does not contribute to the spread of the Emerald Ash Borer.
![Page 31: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/31.jpg)
Document No.: 800253-CAMO-R-01
Renewable Energy Approval Application – Decommissioning Plan Report –Parkhill Interconnect
Issue: B Final
GL Garrad Hassan Canada, Inc. 7
3 EMERGENCY RESPONSE AND COMMUNICATIONS PLANS
The Emergency Response and Communications Plans for Decommissioning are the same as the procedures found in more detail in the Design and Operations Report. 4 PUBLIC, MUNICIPAL AND ABORIGINAL COMMUNITY NOTIFICATION
Decommissioning activities may require notification to stakeholders given their potential to increase traffic, noise, and general disturbance. In the eventuality of the decommissioning of the Parkhill Interconnect, Jericho Wind, Inc. will update the list of stakeholders from the area to ensure that all new stakeholders are considered and are notified of the decommissioning activities. Local and provincial agencies will also be advised to discuss potential approvals required to engage in such activities. In accordance with the requirements of REA, the stakeholder update would occur approximately six months prior to the start of the decommissioning activities. 5 OTHER APPROVALS
It is expected that decommissioning activities will require certain permits, similar to those required for construction, given the use of heavy machinery, trucks and oversize loads, and the potential for impacts to the surrounding environment. Authorisations by the following agencies or entities may be required:
• County of Middlesex and the municipality of North Middlesex, Ontario;
• Municipal building or demolition permits;
• Local Conservation Authority (if potential disturbance to watercourses);
• Ministry of Natural Resources (Record of Site Condition); and
• Ministry of Environment (Record of Site Condition). Applications for the required approvals will be prepared prior to decommissioning and per the current regulations in place. 6 SUMMARY
This Decommissioning Plan Report has been prepared in accordance with regulatory requirements subject to Ontario Regulation 359/09 (Renewable Energy Approval (REA)) under Part V.0.1 of the Ontario Environmental Protection Act (EPA)). This report has provided procedures for decommissioning during construction and after ceasing operations. These procedures include above and below-ground decommissioning and equipment dismantling and removal.
![Page 32: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/32.jpg)
Document No.: 800253-CAMO-R-01
Renewable Energy Approval Application – Decommissioning Plan Report –Parkhill Interconnect
Issue: B Final
GL Garrad Hassan Canada, Inc. 8
Though site restoration has been discussed herein, it is expected that the Director will impose a condition that requires Jericho Wind, Inc. to generate an updated and more comprehensive decommissioning plan six months prior to commencement of decommissioning. This plan will provide more site-specific restoration strategies that will help return the site to pre-project conditions. Sections discussing emergency response, communications plans, and public, municipal, and aboriginal community notification have also been included as part of the complete Renewable Energy Approval Application.
![Page 33: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/33.jpg)
Document No.: 800253-CAMO-R-01
Renewable Energy Approval Application – Decommissioning Plan Report –Parkhill Interconnect
Issue: B Final
GL Garrad Hassan Canada, Inc. 9
7 REFERENCES
[1] Ontario Regulation 359/09, made under the Environmental Protection Act, Renewable Energy Approvals under Part 1.0 of the Act.
[2] Ontario Regulation 521/10, made under the Environmental Protection Act, Renewable Energy Approvals under Part 1.0 of the Act.
[3] DRAFT Technical Guide to Renewable Energy Approvals, Ontario Ministry of the Environment, April 2012.
![Page 34: Jericho Wind, Inc. Final Decommissioning Plan Report ......Prepared by: AECOM 300 – 300 Town Centre Boulevard 905 477 8400 tel Markham, ON, Canada L3R 5Z6 905 477 1456 fax Project](https://reader030.vdocuments.mx/reader030/viewer/2022041117/5f2d0729c0cf6509a942d769/html5/thumbnails/34.jpg)