Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD- 027 CUG Meeting June 3 – 5 Salt Lake City, UT

Upload: stuart-dunnell

Post on 01-Apr-2015

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

Jay LoockSR Compliance AuditorOperations & Planning

Audit Approach MOD-026 & MOD-027

CUG Meeting June 3 – 5Salt Lake City, UT

Page 2: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

2

• Brief history of MOD Standards• Applicability to registered functions• Timelines • Audit approach for each requirement

Agenda

Page 3: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

3

• On March 20, 2014, FERC approved:o MOD-025-2 (MOD-024-1 and MOD-025-1

merge) effective date – July 1, 2016o MOD-026-1 (New) effective date - July 1, 2014o MOD-027-1 (New) effective date - July 1, 2014o PRC-019-1 (New) effective date - July 1, 2016o PRC-024-1 (New) effective date - July 1, 2016

FERC did what?

Page 4: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

4

• Also on May 1, 2014 FERC approved:o MOD-032-1(New) - Effective date - July 1, 2015o MOD-033-1(New) - Effective date - July 1, 2017o MOD-010-0 and MOD-12-0 (retired)

What else did FERC do?

Page 5: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

5

MOD-026 and MOD-027

• These standards are applicable to Transmission Planners (TP) and Generator Owners (GO).

Page 6: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

6

What about those MODs?

• MOD-026 requires generator owners to verify that dynamic models of excitation controls are accurate and up-to-date;

• MOD-027 places the same requirements on dynamic models of governors and turbine controls.

Page 7: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

7

MOD-026 R1 (TP)

• R1 is intended to ensure that the TP provides information to the GO(s) necessary to ensure that they provide a useable model in an acceptable format (from an approved model list). This ensures that GOs can comply with Requirement R2.

Page 8: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

8

Within 90 days of a request from the GO the TP shall:• Provide a approved model list.• Provide data (model) being used historically

for the GO.

MOD-026 R1 - Audit approach

Page 9: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

9

• The purpose of R2 is to verify that the generator excitation control system or plant volt/var control function model and the model parameters used in dynamic simulations performed by the TP accurately represents the generator excitation control system or plant volt/var control function behavior when assessing BES reliability.

MOD-026 R2 (GO)

Page 10: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

10

Not auditable until July 1, 2018• July 1, 2018 - 30%• July 1, 2020 - 50%• July 1, 2024 - 100%

MOD-026 R2 - Audit approach

Page 11: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

11

• Individual generating unit greater than 75 MVA (gross nameplate rating).

• Individual generating plant consisting of multiple generating units that are directly connected at a common BES bus with total generation greater than 75 MVA (gross aggregate nameplate rating).

MOD-026 R2 MVA Requirement

Page 12: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

12

or….

A technically justified unit that meets NERC registry criteria but is not otherwise included in the above applicability and is requested by the Transmission Planner.

MOD-026 R2 MVA Requirment

Page 13: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

13

• R3 provides response requirements for a GO when it receives certain requests from the TP. This communication ensures that GOs have an obligation to respond in a timely fashion when there are demonstrated problems with a model that was provided by the GO.

MOD-026 R3 (GO)

Page 14: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

14

GO response to TP in 90 days when:• Model is unusable• Model has technical concerns• Model response concerns

• R3 details what should be in the GO response

MOD-026 R3 - Audit approach

Page 15: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

15

• R4 ensures that when a GO makes a change to an applicable unit that would affect the model provided in accordance with Requirement R2, the GO then has an obligation to determine whether there is an impact on the model and to provide the TP with revised model data or plans to perform model verification.

MOD-026 R4 (GO)

Page 16: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

16

• Were changes made to the units?• Were models updated?• Were timelines met?

MOD-026 R4 - Audit approach

Page 17: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

17

• R5 ensures that there is a process for TP to request a model review for technically justified units not specified in the standard applicability section but that meet or exceed the Registry Criteria unit MVA thresholds.

MOD-026 R5 (GO) Footnote 2

Page 18: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

18

• Did GO provide a written response to the TP within 90 days?

• Do the details of the response address the requirement?

MOD-026 R5 - Audit approach

Page 19: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

19

• R6 requires the TP to inform the GO within 90 calendar days whether a model is useable or not. The response from the TP verifies that the TP has sufficient information and ensures that the verification process is complete.

MOD-026 R6 (TP)

Page 20: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

20

• TP communicated to the GO(s) that the model is or is not useable.

• TP shall provide a technical description why the model is not usable.

MOD-026 R6 - Audit approach

Page 21: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

21

Its purpose is to verify that the turbine/governor and load control or active power/frequency control model and the model parameters, used in dynamic simulations that assess bulk electric system reliability, accurately represent generator unit real power response to system frequency variations.

MOD-027-1 Purpose

Page 22: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

22

• R1 is intended to ensure that the TP provides information to the GO(s) necessary to ensure that they provide a useable model in an acceptable format (from an approved model list). This ensures that GOs can comply with Requirement R2.

MOD-027 R1 (TP)

Page 23: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

23

Within 90 days of a request from the GO the TP shall:• Provide a approved model list.• Provide data (model) being used historically

for the GO.

MOD-027 R1 - Audit approach

Page 24: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

24

• R2 requires GOs to provide TP with a verified turbine/governor and load control or active power/frequency control model for each applicable unit, including documentation and data in accordance with the periodicity specified in Attachment 1.

MOD-027 R2 (GO)

Page 25: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

25

Not auditable until July 1, 2018• July 1, 2018 - 30%• July 1, 2020 - 50%• July 1, 2024 - 100%

MOD-027 R2 - Audit approach

Page 26: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

26

• R3 provides response requirements for a GO when it receives certain requests from the TP. This communication ensures that GOs have an obligation to respond in a timely fashion when there are demonstrated problems with a model that was provided by the GO.

MOD-027 R3 (GO)

Page 27: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

27

GO response to TP in 90 days when:• Model is unusable• Model has technical concerns• Model response concerns

• R3 details what should be in the GO response

MOD-027 R3 - Audit approach

Page 28: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

28

• R4 ensures that when a GO makes a change to an applicable unit that would affect the model provided in accordance with Requirement R2, the GO then has an obligation to determine whether there is an impact on the model and to provide the TP with revised model data or plans to perform model verification.

MOD-027 R4 (GO)

Page 29: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

29

• Were changes made to the units?• Were models updated?• Were timelines met?

MOD-027 R4 - Audit approach

Page 30: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

30

• R5 requires the TP to inform the GO within 90 calendar days whether a model is useable or not. The response from the TP verifies that the TP has sufficient information and ensures that the verification process is complete.

MOD-027 R5 (TP)

Page 31: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

31

• TP communicated to the GO(s) that the model is or is not useable.

• TP shall provide a technical description why the model is not usable.

MOD-027 R5 - Audit approach

Page 32: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

32

• Satisfies these two standards

WECC Certification is the gold standard.

WECC Generator Testing Program

Page 33: Jay Loock SR Compliance Auditor Operations & Planning Audit Approach MOD-026 & MOD-027 CUG Meeting June 3 – 5 Salt Lake City, UT

Jay Loock

801-883-6864

[email protected]

Questions?