CONSTRUCTION UPDATE – January 2015Dr. Prem Reddy Health & Science
Metal decking installed at digital
nurses lab
Metal Decking being set
Metal roof deck installed
At science labs
Perimeter walls being framed in medical supplies & equipment
Boring for columns
for shade structure
Metal deck installed at restrooms.
Perimeter wall framing and structural steel set in faculty office area.
Perimeter wall framing in nursing fundamentals lab.
Also overhead piping installed.
Metal decking, perimeter wall framing in nursing
fundamentals and corridor 127
Plywood covers holes bored for shade
structure posts in new courtyard area
Steel set in admin & workroom areas.
Metal Decking installed at faculty offices
Metal Decking at nursing fundamentals lab.
Overhead piping installed.
Rear view of rotunda.
Looking towards faculty offices from corridor 127
Overhead piping, perimeter framing, and metal decking installed at beds &
equipment
Interior view of main entrance
Perimeter framing at workroom and admin areas
More perimeter framing at anatomy labs.
Preparation for footings at new trash enclosure
New doorway cut into existing science bldg.
(Temporary Door)
Metal decking installed at anatomy labs
SIM Lab area perimeter wall framing installed. Decking in process of
install.
Perimeter wall framing and metal decking installed at
deans office / meeting rooms
Holes bored for covered walkway
pilasters.
Framing for walls along corridor 127
Progress on metal decking at nursing fundamentals
Top view of metal decking installation
Another top view of metal decking. Looking towards the second floor
mezzanine and rotunda
Stored duct waiting for install is covered to
prevent dirt and debris from accumulating inside.
Stored duct waiting for install is covered to
prevent dirt and debris from accumulating inside.
Duct being installed in chemistry lab
Decking installed over corridor 127
Installing in wall conduits for power and piping for
roof drains.
Electrical room 132
Rebar laid out on metal decking in mezzanine for
concrete topping and equipment pad.
Looking down into courtyard area
Opening for duct from HVAC unit in mezzanine.
Signed steel beam set into place
Temporary jacks set in place in preparation of
concrete being poured on deck above
Concrete being poured on mezzanine deck
Footing poured for trash enclosure
Interior walls being framed for faculty offices
Framing of interior walls in the admin, workroom,
deans office areas
Concrete poured out for revolving door at main
entry
Mezzanine concrete and equipment pad- North
side
Mezzanine concrete and equipment pad- South
side