Page 1: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

ITS Allied!

Construction Engineering and Inspection

I-75, from Charlotte County Line to I-275

Freeway Management System

FPID 414730-1-62-01, 414732-1-62-01, 414736-1-62-01

Construction Engineering and Inspection

I-75, from Charlotte County Line to I-275

Freeway Management System

FPID 414730-1-62-01, 414732-1-62-01, 414736-1-62-01

September 23, 2011

September 23, 2011

Page 2: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Awareness/Approach to Project

Understanding of Scope of the ProjectIdentification of Unique Project IssuesInnovative Concepts

Page 3: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Project Overview Design Build Contract

◦ $30 Million◦ 760 days◦ Three Financial Project ID’s

56 miles, from Charlotte County Line to I-275 Final Phase of the District One I-75 FMS Design, furnish, install, integrate and test ITS field devices Provide for a redundant system between SWIFT and

Satellite Traffic Management Center (STMC)

Understanding Project Scope

Page 4: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Primary Responsibility of the CEI Act as extension to FDOT staff

◦ Proactively manage the work◦ Anticipate and address project issues

Coordinate all aspects of design and construction◦ Review/ analyze CPM schedules◦ Provide interpretation of contract documents

Enforce contract requirements and implement CPPR Operate in accordance with FDOT procedures (CPAM)

Understanding Project Scope

Page 5: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Understanding Project Scope (Design)

Detailed Reviews for 60%, 90% & Final (100%)◦ Conformance with Design Build Technical Proposal - “Book of

Promises”◦ Conformance with RFP & MTRs◦ Hardware/ Software Compatibility◦ Review/ Resolution of Potential Integration Issues◦ Compatibility/Coordination with Future Projects

Confirm existing fiber (I-75/SR 70 to STMC) Provide Clarifications - RFP vs. MTRs Permit Acquisition

Page 6: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Understanding Project Scope (Design)

ERC utilization ◦ Plan submittals◦ Device Cut Sheets◦ Shop Drawings◦ Other

Field Assessments◦ ITS field device locations◦ Potential underground utility conflicts◦ Review of Right of Way limits◦ Review of existing slope conditions◦ Site survey

Page 7: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Primary Components of the Work Fiber Optic Communications

Infrastructure◦ Conduit, locate system and enclosures/

boxes◦ Two conduits (1 for FOC and 1 spare)◦ Separate conduit for electric◦ Install eight (8) feet inside northbound

right-of-way fence◦ Seven (7) bridges potentially requiring

new bridge mounted conduit

Understanding Project Scope (Construction)

BRADEN RIVER CROSSING

CHARLOTTE HARBOR CROSSING

Page 8: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Understanding Project Scope (Construction)

Fiber Optic Communications Infrastructure◦ Locate existing utilities (Sunshine One Call)◦ Bore logs to verify horizontal locations &

depths◦ Recommend field adjustments to avoid

unforeseen conflicts◦ Update plans to ensure accuracy of as-builts◦ Conduits “proofed” to ensure continuity and

absence of obstructions◦ OTDR testing

Page 9: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Understanding Project Scope (Construction)

Dynamic Message Signs (DMS)◦ 25 shown on Concept Layout◦ 24 cantilever structures, 1 half-span

truss structure◦ Ensure proper height (19.5’)◦ Allied’s structural inspector will

oversee operations of upright and sign

Page 10: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Understanding Project Scope (Construction)

Drilled Shaft Installations◦ 26 drilled shafts @ 25 DMS structures◦ DBF to perform sub-surface investigations,

analysis & design◦ DBF to develop foundation plan ◦ Drilled shaft logs to be submitted within 24

hours ◦ Cross-hole sonic logging (CSL) must be

performed on at least 30% of the shafts◦ Utilization of Allied’s Drilled Shaft QAP

Page 11: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Highway Advisory Radio System (HAR)◦ 10 transmitter stations and 20 flashing beacon

signs◦ Capable of broadcasting unique message/

synchronized global message◦ 800-foot spacing between signs◦ 1640 AM frequency/ FCC licensing process

Microwave Vehicle Detectors (MVDS)◦ Installed at approximate one-mile intervals

(mainline)◦ Half-mile within 2 miles of each interchange and

at each off-ramp◦ Must report for eight (8) lanes of travel for

volume, occupancy & speed

Understanding Project Scope (Construction)

Page 12: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Road Weather Information System (RWIS)◦ Two (2) to be installed along the project◦ Placed outside clear zone limits◦ Fenced enclosure for device and cabinet

Power/ Emergency Generators◦ DBF to provide all power services to

devices◦ Diesel-electric generator units required

at all power service point locations providing power; DMS locations Communications backhaul locations

Understanding Project Scope (Construction)

Page 13: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

CCTV (Closed Circuit TV)◦ Installed at approximate one-mile intervals

(70 +/-)◦ Complete coverage of both directions of I-

75 traffic, on/off-ramps, interchanges (video site survey)

◦ Shall provide for view of all DMS messages and HAR beacons

◦ Cannot be installed in the medians or top side of overpass slopes

◦ Pole height cannot exceed 65 feet◦ Locate more than 50 feet away from any

high mast light pole◦ Pre-stressed concrete pole with grounding,

lightning protection, and lowering devices

Understanding Project Scope (Construction)

Page 14: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Understanding Project Scope (Construction)

ITS Inspection◦ CEI check lists based on

Final Plans/ RFP/ MTR requirements Standards/ Specifications/ NEC FDOT 780 Supplemental Specifications Inspection Guidelists

◦ Components to be QPL/APL approved◦ Splice and pull box conformance

APL/ITS certified products Proper sizing of products

◦ Use of expanded RTVM for field inspections

Page 15: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Understanding Project Scope (Construction) MOT/ Safety

◦ MOT Certified Personnel/ Interstate (I-75) experience ◦ Minimize traffic disruptions & maximize safety◦ Ensure advance coordination for lane closures & nighttime

operations (PIO, Law Enforcement & Emergency Services) Full span truss installation – Charlotte FMS

◦ Conformance with MUTCD & FDOT standards◦ MOT & Safety as agenda item @ project meetings◦ Critical during DMS installation & bridge work (limited ROW)◦ MOT verification inspection each day prior to leaving site

Page 16: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Understanding Project Scope (Construction)

Environmental Concernso Scattered wetland presence along

northbound ROWo Potential for endangered species

Gopher tortoiseso Low-lying areas with standing water

which could impact equipment access o NPDES inspections (weekly, ½”)o Permit conformanceo Erosion Control Plano Performance Turf Specificationso Mowing requirements

Page 17: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Understanding Project Scope (Documentation)

CEI Reporting◦ Daily Reporting of Construction Activities/ Site Manager◦ Verification Testing Reports & LIMS Entry◦ MOT Reviews & Verification of Contractor’s Reports◦ CPM Reviews◦ Digital Progress Photos & Log◦ Monthly FDOT Project Status Reports (CSRS)◦ Meetings Minutes & Follow-Up Action Items

Page 18: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Understanding Project Scope (Documentation)

DBF Submittal Tracking◦ Design Submittals◦ Cut Sheets/ Shop Drawings◦ CPM Schedule/ Updates◦ Schedule of Values◦ Field Equipment Operational Manuals◦ Software Manuals/ Device Protocols◦ Test Procedures and Results◦ Training Manuals◦ 270+ Design Submittals - Charlotte FMS

We will prepare a submittal tracking log in advance of project start & track all submittals via ERC

Page 19: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Understanding Project Scope (Documentation)

Project Close Out/ Warranties◦ Timely submittal of all close out documents

As-Built plans Bore Logs/ GPS locations Spare Parts (as required)

◦ Timely/ Accurate Final Estimate Early FE submittal on Charlotte FMS and no procedural errors

◦ Warranties Pre/ post-warranty meetings Ensure warranties per contract/ technical proposal

Page 20: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Understanding Project Scope (Documentation)

DescriptionWarranty Duration Description

Warranty Duration

DMS 5 Years MFES 5 years

HAR 5 years Device server 5 years

RWIS 3 yearsVideo encoder/

decoder 2 years

CCTV 3 years* Lowering device 3 years

MVDS 2 years Surge protector 10 years

VVDS 5 years ITS field cabinets 2 years

MTDS 5 years Equipment shelter 1 year

AVDS 3 years FOC 2 years*

Pull boxes 2 years * Includes spare parts requirements

Page 21: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Satellite Traffic Management Center (STMC)◦ New Gigabit Ethernet switch◦ New SunGuide servers◦ SunGuide Software (FDOT furnished)◦ Video Wall Expansion

12 new cubes Video wall controller

◦ 5 new workstations◦ Electrical wiring

SWIFT Center◦ Video Wall upgrade to handle new CCTVs◦ Provide standby Gigabit Ethernet switch

Operations◦ STMC backup to SWIFT

Understanding Project Scope (TMCs)

Page 22: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

MTR requires:◦ Preliminary Integration Plan

30 days prior to Pre-Integration Meeting◦ Pre-Integration Meeting

Discuss Preliminary Integration Plan◦ Integration Plan

90 days prior to Integration Work◦ Testing

Factory Stand-Alone Subsystem Operational Test Burn-in

Understanding Project Scope (Testing & Integration)

Page 23: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

SW

IFT

Exis

t.

Fie

ld

Devic

es

New

Fie

ld

Devic

es

STM

C

Keys to Successful Integration:◦ Start From Day 1 (Design)◦ Good System Understanding

Main Components Software Hardware

Interfaces Software/Software Interface (SSI) Software/Hardware Interface (SHI) Hardware/Hardware Interface (HHI)

◦ Testing Right Type

Functional, Operational Right Number

When and Where Clear

Well Defined Metrics Well Defined Pass/Fail Criteria

Understanding Project Scope (Testing & Integration)

Furnished by FDOT

F&I by DBF

FieldDevices

FieldDevices

Server Software

Servers

Network

SunGuide(SWRI)

MicrosoftCluster

Servers

Work-stations

Existing

ExistingNetwork

Work-stations

SunGuide(SWRI)

SSI

SHI HHI

HHI

Page 24: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Unique Project Issues STMC / SWIFT / SunGuide

◦ First deployment of SunGuide in a back-up mode at STMC

◦ Testing of STMC back-up functionality without disrupting SWIFT operations

◦ TMC software is normally integrated at the end of the project which could impact the schedule.

◦ Two contractors (SWRI and DBF) preforming time critical interdependent work.

MOT◦ HARB at Erie Road overpass will require

MOT (lane closures) for installation as well as maintenance.

Microsoft Cluster

Oracle Data

Guard

F&I by Southwest Research Institute (SWRI)

F&I by Design Build Firm

Page 25: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Unique Project Issues

Steep Slopeso DMS

North of the Braden River North of West River Road Difficult installation Lane closures during installation and

maintenance.o No pull boxes in slopes - will make

conduit transition from underground to bridge mount difficult

Conduit 8’ from Fenceo Flooding areas could impact

maintenance / reliabilityo Numerous crossing of wet ditches

Proposed Conduit

Fence

Steep Slopes

8’ FromFence

DBF may propose

Page 26: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Innovative Concepts

Use of FDOT ERC system for all submittals Expansion of the RTVM (Traceability Matrix)o Include additional project requirements such as NECo Expand verification method (Factory, Stand-alone, Subsystem)o Develop comprehensive field check lists using the RTVM

Verification of as-built and ITSFM tool sheets with sub-foot accuracy equipment

Specialty staff only as-needed STMC agreement to provide large meeting room to reduce CEI

field office costs Project Share Site for exchange of large files

Page 27: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Proposed StaffingQuantity ProposedAvailability of StaffQualifications/ Certifications of StaffQuality/ Experience on Similar ProjectsTeam’s Past Performance on Similar Projects

The Allied TeamAllied * AIM * Genesis * Media Relations Group * Scheda * URS

Page 28: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Proposed StaffQuality Assurance

Kristina de Moya, P.E.Allied

Joe McConnell, P.E.URS Southern

Barry Wilson, P.E.Genesis

Quality AssuranceKristina de Moya, P.E.

AlliedJoe McConnell, P.E.

URS SouthernBarry Wilson, P.E.

GenesisSenior Project Engineer

Vay Scott, P.E.Allied

Senior Project EngineerVay Scott, P.E.

Allied

Sr. ITS EngineerAlex Mousadi, P.E.

URS Southern

Sr. ITS EngineerAlex Mousadi, P.E.

URS Southern

FDOT District OneJim Nichols

Construction Project ManagerKatherine Duvall/ Mark Roberts

Traffic Operations

FDOT District OneJim Nichols

Construction Project ManagerKatherine Duvall/ Mark Roberts

Traffic Operations

Project AdministratorLisa Propps

Allied

Project AdministratorLisa Propps

Allied

Principal-In-Charge/ Project Manager

Paula McQueen, CPAAllied

Principal-In-Charge/ Project Manager

Paula McQueen, CPAAllied

Contract Support SpecialistChris Morris

Allied

Contract Support SpecialistChris Morris

Allied

ITS Engineer (Field)Matt CousinsURS Southern

ITS Engineer (Field)Matt CousinsURS Southern

Sr. ITS InspectorCarmon Thompson

AIMJames Randy Cosby

URS Construction Services

Sr. ITS InspectorCarmon Thompson

AIMJames Randy Cosby

URS Construction Services

CEI Sr. InspectorTed Garcia

AlliedRobert Walker

Genesis

CEI Sr. InspectorTed Garcia

AlliedRobert Walker

Genesis

ITS InspectorRon Horn

URS Construction Services

ITS InspectorRon Horn

URS Construction Services

CEI InspectorKenneth Hilton

Genesis

CEI InspectorKenneth Hilton

Genesis

Secretary/ RCSKim Grebe

Allied

Secretary/ RCSKim Grebe

Allied

Additional InspectionMatt Hicks, Densel Landrum

Dean Greathouse, Mark WaltersAllied

Tony Cognina Genesis

Additional InspectionMatt Hicks, Densel Landrum

Dean Greathouse, Mark WaltersAllied

Tony Cognina Genesis

Specialty StaffPublic Information Officer

Alicia Gonzalez (MRG)Ken Nelson (AIM)

CEI EnvironmentalistSarah Johnson, MS

(Scheda)Professional SurveyorBob Potter, PSM (AIM)

Building InspectorMark Smalley (Allied)

Specialty StaffPublic Information Officer

Alicia Gonzalez (MRG)Ken Nelson (AIM)

CEI EnvironmentalistSarah Johnson, MS

(Scheda)Professional SurveyorBob Potter, PSM (AIM)

Building InspectorMark Smalley (Allied)

Page 29: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Quantity/ Availability Proposed

34,875 Man-hours

Key staff full-time through design Core inspection/field staff during construction/testing Specialty staff as-needed Reduced staff during Operational Period/ Burn-in All team members 100% available (February, 2012)

Page 30: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Qualifications/ Certifications of Staff

Vay Scott, P.E. - Sr. Project Engineer◦ 28 years experience on FDOT projects◦ Florida Licensed Professional Engineer◦ Significant CEI management experience

Lakeland CCTV Installation Project QA Manager for Charlotte FMS and Charlotte ATMS Projects

◦ Proactive approach to issue identification and resolution

Early completion of complex US 92 project in D7!

Page 31: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Qualifications/ Certifications of Staff

Lisa Propps, E.I. - Project Administrator◦ Degreed Civil Engineer◦ Over 14 years of CEI experience◦ PA on $230 Million Tampa Airport Interchange

Oversight of project staff of 18 Included ITS device (40+) and fiber installations

◦ PA on District 7 Push Button Traffic Operations Project $25 Million contract/ 33 Task Work Orders assigned to date Design Build contracting method

Responsible for Final Plan reviews of 33 District Wide TWO’s

Page 32: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Qualifications/ Certifications of Staff

Alex Mousadi, P.E., Sr. ITS Engineer◦ Electrical Engineer◦ Over 21 years experience in the ITS industry◦ Experience encompasses design, construction, testing & integration◦ Key projects include;

23 miles of I-75 for the Charlotte FMS for FDOT District 1 Roadside Animal Detection System (RADS) for FDOT District 1 250+ interstate ITS work in Florida (I-4, I-75, I-275, I-595, I-95) I-595 PPP in District 4 Participated in development/integration of eight (8) TMC’s nationally Lead system designer & integrator for Tampa Bay SunGuide Ph 3

Diverse background allowing for prompt and efficient issue resolutions!

Page 33: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Qualifications/ Certifications of Staff Matt Cousins, ITS Engineer (Field)

◦ BS in Electrical Engineering, MS in Civil Engineering

◦ Six years experience in electrical & traffic engineering

◦ Three years experience dedicated to ITS planning & design

◦ Design background includes fiber optics, CCTV, DMS radar detection sub-systems, and power distribution

◦ Recent SunGuide experience includes; 23 miles of I-75 for Charlotte FMS, District 1 Tampa Bay FMS Phase 3 (50 miles of I-4, I-275 and

Skyway Bridge) FTE SunNav West (80 miles of Florida Turnpike)

Responsible for resolution of integration issues @ SWIFT- Charlotte FMS

Page 34: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Qualifications/ Certifications of Staff

Chris Morris – Contract Support Specialist◦ Over 13 years of construction inspection experience for FDOT◦ Qualified CSS, Assistant PA, Sr. Inspector◦ CSS/ Assistant PA on Charlotte FMS◦ IMSA level I & II, drilled shaft certified◦ Available to assist in the field as needed◦ Inspected 450 miles of fiber optic interstate installation nation-wide

Allied’s

Secret Weapo

n

Page 35: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Qualifications/ Certifications of Staff

Carmon Thompson – CEI ITS Senior Inspector

◦ Extensive experience in traffic signal & intersection design/inspection

◦ Sr. ITS Inspector for: City of Naples ATMS Collier/ Lee FMS (98 miles along I-75) Charlotte County FMS (23 miles along I-75) Roadside Animal Detection System (RADS)

◦ Drilled shaft, fiber and ITS device installation experience◦ Certifications include;

IMSA Level I and II, Traffic Signal Inspector FDOT Advanced MOT

34 years in working with FDOT District 1 (direct employee and

CCEI)

Page 36: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Qualifications/ Certifications of Staff

Teddy Garcia – CEI Senior Inspector◦ 17 years construction inspection

experience◦ Charlotte County ATMS◦ Charlotte County FMS

23 miles along I-75◦ IMSA Level I & II◦ Drilled shaft, fiber and ITS device

installation experience

Successful track record in working with Sarasota Operations

Page 37: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Qualifications/ Certifications of Staff Specialty Inspectors

◦ Matt Hicks / Dean Greathouse (Drilled Shaft QA)

◦ Mark Smalley (Building/ Structural Inspector)

Additional Resources◦ Scheda Ecological Associates (Sarah

Johnson, MS)◦ AIM Engineering and Survey (Bob

Potter, PSM)◦ Media Relations Group (Alicia

Gonzalez, Primary PIO)◦ Ken Nelson (AIM, Back-up PIO)

Page 38: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Quality/ Experience on Similar Projects

Recent Relevant Project Experience

Project/ Client Construction Amount ($M) Start End Scope of Work

I-75 Charlotte County FMS/ FDOT District One $10 M Apr-09 Mar-11 23 miles

Charlotte County ATMS/ FDOT District One $6 M Jan-06 May-08 28 miles (84 int.)

Collier Co. & City of Naples ATMS/ FDOT JPA (Ph 1 & 2) $5 M Jun-02 May-06 20 miles

City of Lakeland ATMS $15 M Jul-07 Jan-08 5 miles

Lee/Collier ITS FMS/ FDOT District One $35 M Oct-05 Dec-09 98 miles

Tampa SunGuide Phase 3 $28 M Feb-07 On-going 50 miles

Over 175 Miles of ITS/ATMS Installations in FDOT District One

Page 39: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Quality/ Experience on Similar Projects

Device Description Charlotte Co. ATMS

I-75 Charlotte Co. FMS

I-75 Sarasota-Manatee FMS

CCTV Cameras 84 30 75 +/-

DMS Signs N/A 10 25

Vehicle Detectors N/A 44 18

HART/ HARB N/A 5/1 10/20

RWIS N/A 1 2

Fiber Optic/Conduit 28 miles+/- 23 miles+/- 56 miles+/-

Wireless Devices 2 5 N/A

Page 40: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Team’s Past Performance on Similar Projects

Charlotte County ATMS ◦ Returned $80,000 in CEI Fees◦ Final Grade of 4.2◦ Set the standard in communication, coordination & proactive

issue resolution Charlotte County FMS

◦ Returned $50,000 in CEI Fees◦ Final Grade of 3.9◦ Continued to establish new standards in communication,

coordination & proactive issue resolution

Page 41: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Team’s Past Performance on Similar Projects

Strong QA Program = Quality services QA Team:

◦ Kristina de Moya, P.E. (Allied)◦ Joe McConnell, P.E. (URS)◦ Barry Wilson, P.E. (Genesis)

50 years CEI experience with significant ITS installations

Reviews per the Scope of Services to include; ◦ Quality & quantity of personnel assigned◦ Quality of project records◦ Communication & feedback with FDOT

Page 42: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Other ConsiderationsCommunication AbilitiesCommitment to Satisfy Department’s Needs

Page 43: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Communications Abilities

Coordination with Cindy Clemmons from day one for all PI activities

Two prong approach: day to day PI issues/overall communication of benefits (awareness and education)

Coordination with all local PIOs in order to have consistent and strong project message

Maximize existing communication resources available

Message the project benefits in real-time

Public Information

Page 44: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Communications Abilities

MPO presentations Sarasota-Manatee Transportation

Incident Management Team presentation and engagement

Work with 511 Newsletter for local and state

publications on progress Opportunity to showcase District

One at ITS Florida Bring in media early

PIO - Proven Effective on Charlotte FMS

Media coverage helps raise public awareness for ITS program in the community.

Page 45: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Communications Abilities

Effective Communications with Stakeholders Began in advance of CEI advertisement

◦ FDOT - Traffic Operations, Sarasota Operations, District Construction, District PIO, SWIFT Center

◦ Manatee County and Sarasota County◦ Attended DB Pre-Proposal Meeting

Stay involved in DBF Selection Process Facilitate Project Meetings

◦ Action Item Log◦ Thorough Documentations

CEI Performance Evaluation:

Provided necessary project information to

all project stakeholders – 5!

“Excellent communication between CCEI staff, contractor,

Department & local municipalities”

Page 46: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Commitment to Satisfy Department Needs DRB letter recognizing the

Allied team for their outstanding performance on Charlotte FMS

Nominated for FTBA Excellence in Construction Award

Nominated for ITS Florida Outstanding Achievement Award

Page 47: ITS Allied!. C E I S E R V I C E S F O R I – 7 5 F M S | 0 9.2 3. 2 0 1 1 ITS Allied! Understanding of Scope of the Project Identification of Unique Project

C E I S E R V I C E S F O R I – 7 5 F M S | 0 9 .2 3. 2 0 1 1ITS Allied!

Commitment to Satisfy Department Needs5 Proven abilities to interpret the contract and resolve issues

at project level5 Proven knowledge of technical issues5 Proven abilities to properly document and inspect the work5 Proven communication abilities5 Proven ability to manage CEI and construction dollars5 Proven Commitment to FDOT

EXPERIENCED TEAM!

ITS Allied!