itp for piling
TRANSCRIPT
-
8/10/2019 ITP for Piling
1/9
-
8/10/2019 ITP for Piling
2/9
EMPLOYER ENGINEER CONTRACTOR
Ministry of Transport & CommunicationsDirectorate General of Roads & Land Transport
P.O.Box27, P.C.114Sultanate of Oman
COWI & Partners LLC
P.O.Box2115, P.C.112
Sultanate of Oman
Khalid Bin Ahmed & Sons LLC CORSAN CORVIAM JV
Al Azaiba
P.O. Box723, P.C.130
Sultanate of Oman
Contract No.: 95/2012 BS2P2 - Dualization of Bibbid-Sur Road, Section 2, Part 2DOC No: KAS-CCJV/SB2P2/ITP/QA/009 Rev.00
INSPECTION AND TEST PLAN PILING Date: 16/11/2014
(*) When the results show consistent behaviour, the tests for shear strength and pH value may be discontinued, and tests to determine density and viscosity shall be carried out as agreed with the Engineer.
INSPECTION CODE: HHold Point WWitness Point S - Surveillance NIRNo Inspection Requested
Form No.: KAS-CC/SB2P2/OP/QA/01.06 Page 2of 9
ITEM OFINSPECTION
REFERENCE DOCUMENTSFOLLOW-UPDOCUMENTS
TYPE OF INSPECTION AND FREQUENCY / INSPECTION PARTY
NOTES/ACCEPTANCE CRITERIA
SPEC. STANDARDSIndustPark
Subcont Product Survey Quality Engineer Frequency
FIRST PART _ ICL009.1
0. ITP SCOPE
SpecialSpecifications.
Section 10General
SpecificationsSection 10
This Section covers requirements for supplying andinstalling cast in-situ concrete and steel piles by boring.
1. PRELIMINARY
Special
Specifications.Sub-section10.1.3.1General
SpecificationsSub-section
10.1.3.1
KAS-CCJV/BS2P2/ICL/QA/0
09.1H H H H H 100%
Shop drawings approvedMethod Statement approvedWork program approvedITP approvedConcrete trial mixes approved
2.
SETTING OUTAND WORK
PLATFORM
SpecialSpecifications.
Section 10General
SpecificationsSection 10
2.1 Work platformavailability
SpecialSpecifications.
Section 10GeneralSpecifications
Section 10
KAS-CCJV/BS2P2/ICL/QA/0
09.1Daily report
H H W W 100% In accordance to approved drawings
2.2Temporary bench
mark location
SpecialSpecifications.
Section 10General
SpecificationsSection 10
KAS-CCJV/BS2P2/ICL/QA/0
09.1Daily report
Survey report
H H H W W 100% In accordance to approved drawings
-
8/10/2019 ITP for Piling
3/9
EMPLOYER ENGINEER CONTRACTOR
Ministry of Transport & CommunicationsDirectorate General of Roads & Land Transport
P.O.Box27, P.C.114Sultanate of Oman
COWI & Partners LLC
P.O.Box2115, P.C.112
Sultanate of Oman
Khalid Bin Ahmed & Sons LLC CORSAN CORVIAM JV
Al Azaiba
P.O. Box723, P.C.130
Sultanate of Oman
Contract No.: 95/2012 BS2P2 - Dualization of Bibbid-Sur Road, Section 2, Part 2DOC No: KAS-CCJV/SB2P2/ITP/QA/009 Rev.00
INSPECTION AND TEST PLAN PILING Date: 16/11/2014
(*) When the results show consistent behaviour, the tests for shear strength and pH value may be discontinued, and tests to determine density and viscosity shall be carried out as agreed with the Engineer.
INSPECTION CODE: HHold Point WWitness Point S - Surveillance NIRNo Inspection Requested
Form No.: KAS-CC/SB2P2/OP/QA/01.06 Page 3of 9
ITEM OFINSPECTION
REFERENCE DOCUMENTSFOLLOW-UPDOCUMENTS
TYPE OF INSPECTION AND FREQUENCY / INSPECTION PARTY
NOTES/ACCEPTANCE CRITERIA
SPEC. STANDARDSIndustPark
Subcont Product Survey Quality Engineer Frequency
2.3Pile location and
numbering
SpecialSpecifications.
Section 10General
SpecificationsSection 10
KAS-CCJV/BS2P2/ICL/QA/0
09.1Daily report
Survey reportPile Record Sheet
H H H H W 100%As per approved drawings and work program.Tolerances: Position: 75 mm in any direction at the pile head
3.FOLLOW-UP
ACTIVITIES
SpecialSpecifications.
Section 10
GeneralSpecifications
Section 10
3.1 Piling rig setting up
SpecialSpecifications.
Subsection10.1.3.2General
SpecificationsSub-section
10.1.3.2
KAS-CCJV/BS2P2/ICL/QA/0
09.1Daily report
Pile record Sheet
S S W W 100%In accordance to approced shop drawing.
Approved equipment is used
3.2Casing verticalityand position for
Bucket & Auger pile
SpecialSpecifications.Sub-section
5.3.3.9. Item
16a
KAS-CCJV/BS2P2/ICL/QA/0
09.1Daily report
Pile record Sheet
S S W W 100% Verticali ty: 1 in 75 deviation
-
8/10/2019 ITP for Piling
4/9
EMPLOYER ENGINEER CONTRACTOR
Ministry of Transport & CommunicationsDirectorate General of Roads & Land Transport
P.O.Box27, P.C.114Sultanate of Oman
COWI & Partners LLC
P.O.Box2115, P.C.112
Sultanate of Oman
Khalid Bin Ahmed & Sons LLC CORSAN CORVIAM JV
Al Azaiba
P.O. Box723, P.C.130
Sultanate of Oman
Contract No.: 95/2012 BS2P2 - Dualization of Bibbid-Sur Road, Section 2, Part 2DOC No: KAS-CCJV/SB2P2/ITP/QA/009 Rev.00
INSPECTION AND TEST PLAN PILING Date: 16/11/2014
(*) When the results show consistent behaviour, the tests for shear strength and pH value may be discontinued, and tests to determine density and viscosity shall be carried out as agreed with the Engineer.
INSPECTION CODE: HHold Point WWitness Point S - Surveillance NIRNo Inspection Requested
Form No.: KAS-CC/SB2P2/OP/QA/01.06 Page 4of 9
ITEM OFINSPECTION
REFERENCE DOCUMENTSFOLLOW-UPDOCUMENTS
TYPE OF INSPECTION AND FREQUENCY / INSPECTION PARTY
NOTES/ACCEPTANCE CRITERIA
SPEC. STANDARDSIndustPark
Subcont Product Survey Quality Engineer Frequency
3.3
Pile diameter,length, bottomcleaning and
concreterequirement
checking
SpecialSpecifications.Sub-section
10.1.3.2General
SpecificationsSub-section
10.1.3.3
KAS-CCJV/BS2P2/ICL/QA/0
09.1Daily report
Pile record Sheet
H H S W 100%
Pile diameter an length per drawings.On completion of boring, the base of the pile shall becleaned thoroughly with a cleaning bucket to ensure thatthere is no loose material in the baseDrilling fluid shall be tested and results in accordance tomanufacturer recommendations. If bentonite is isuedproperties will be: Density less 1.20 g/cm3 Fluid loss less than 40 mils (1.016 mm)
Marsh viscosity less than 60 s Plastic viscosity less than20 cP Sand content less tha 3% Shear Strength 4 to 25 N/m2 pH: 9.5 to 11.7
Approved class 40 concrete mix design
3.4 Reinforcement cage
SpecialSpecifications.Sub-section 5.2
GeneralSpecifications
Sub-section 5.2
KAS-CCJV/BS2P2/ICL/QA/0
07.1Daily report
Pile record Sheet
H H H H 100%In accordance to drawings and ITP No. KAS-CCJV/BS2P2/ITP/QA/007
3.5 Concrete placement
SpecialSpecifications.Sub-section 5.2
GeneralSpecifications
Sub-section 5.2
KAS-CCJV/BS2P2/ICL/QA/0
07.1
Daily reportPile record SheetConcrete
Placement Record
S S W W 100% In accordance to ITP No. KAS-CC JV/BS2P2/ITP/QA/007
3.6 Concrete level
SpecialSpecifications.
Section 10General
SpecificationsSection 10
KAS-CCJV/BS2P2/ICL/QA/0
09.1Daily report
Pile record Sheet
S S W W 100% As per drawings
-
8/10/2019 ITP for Piling
5/9
EMPLOYER ENGINEER CONTRACTOR
Ministry of Transport & CommunicationsDirectorate General of Roads & Land Transport
P.O.Box27, P.C.114Sultanate of Oman
COWI & Partners LLC
P.O.Box2115, P.C.112
Sultanate of Oman
Khalid Bin Ahmed & Sons LLC CORSAN CORVIAM JV
Al Azaiba
P.O. Box723, P.C.130
Sultanate of Oman
Contract No.: 95/2012 BS2P2 - Dualization of Bibbid-Sur Road, Section 2, Part 2DOC No: KAS-CCJV/SB2P2/ITP/QA/009 Rev.00
INSPECTION AND TEST PLAN PILING Date: 16/11/2014
(*) When the results show consistent behaviour, the tests for shear strength and pH value may be discontinued, and tests to determine density and viscosity shall be carried out as agreed with the Engineer.
INSPECTION CODE: HHold Point WWitness Point S - Surveillance NIRNo Inspection Requested
Form No.: KAS-CC/SB2P2/OP/QA/01.06 Page 5of 9
ITEM OFINSPECTION
REFERENCE DOCUMENTSFOLLOW-UPDOCUMENTS
TYPE OF INSPECTION AND FREQUENCY / INSPECTION PARTY
NOTES/ACCEPTANCE CRITERIA
SPEC. STANDARDSIndustPark
Subcont Product Survey Quality Engineer Frequency
3.7 Pile as built position
SpecialSpecifications.
Section 10General
SpecificationsSection 10
KAS-CCJV/BS2P2/ICL/QA/0
09.1Daily report
Pile record SheetSurvey report
H H H W W 100%As per drawings.Tolerances 75 mm in any direction at the pile head.
FIRST PART _ ICL009.2
4. TESTING
Special
Specifications.Section 10General
SpecificationsSection 10
4.1
Drilling fluid testing.
Density
(To be made onpolymer if
recommended bymanufacturer) (*)
SpecialSpecifications.Sub-section
10.1.2General
SpecificationsSub-section
10.1.3.2
API RP 138 B-1ASTM D 4380
KAS-CCJV/BS2P2/ICL/QA/0
09.2Daily report
Pile Record SheetTest report
H H W W
Once aday as
suppliedto drillingprocess
Each pilefrom top
andbottom ofthe pileprior
concreting
If polymer: as per technical data sheet of themanufacturerIf bentonite: During drilling, 1.10 g/cm3; fromexcavation prior concreting, 1.20 g/cm3
-
8/10/2019 ITP for Piling
6/9
EMPLOYER ENGINEER CONTRACTOR
Ministry of Transport & CommunicationsDirectorate General of Roads & Land Transport
P.O.Box27, P.C.114Sultanate of Oman
COWI & Partners LLC
P.O.Box2115, P.C.112
Sultanate of Oman
Khalid Bin Ahmed & Sons LLC CORSAN CORVIAM JV
Al Azaiba
P.O. Box723, P.C.130
Sultanate of Oman
Contract No.: 95/2012 BS2P2 - Dualization of Bibbid-Sur Road, Section 2, Part 2DOC No: KAS-CCJV/SB2P2/ITP/QA/009 Rev.00
INSPECTION AND TEST PLAN PILING Date: 16/11/2014
(*) When the results show consistent behaviour, the tests for shear strength and pH value may be discontinued, and tests to determine density and viscosity shall be carried out as agreed with the Engineer.
INSPECTION CODE: HHold Point WWitness Point S - Surveillance NIRNo Inspection Requested
Form No.: KAS-CC/SB2P2/OP/QA/01.06 Page 6of 9
ITEM OFINSPECTION
REFERENCE DOCUMENTSFOLLOW-UPDOCUMENTS
TYPE OF INSPECTION AND FREQUENCY / INSPECTION PARTY
NOTES/ACCEPTANCE CRITERIA
SPEC. STANDARDSIndustPark
Subcont Product Survey Quality Engineer Frequency
4.2
Drilling fluid testing.
Viscosity(To be made on
polymer ifrecommended bymanufacturer) (*)
SpecialSpecifications.Sub-section
10.1.2General
SpecificationsSub-section
10.1.3.2
API RP 138 B-1ASTM D 6910
KAS-CCJV/BS2P2/ICL/QA/0
09.2Daily report
Pile Record SheetTest report
H H W W
Once aday as
suppliedto drillingprocess
Each pilefrom top
andbottom of
the pileprior
concreting
If polymer: as per technical data sheet of themanufacturerIf bentonite: During drilling, 30 to 40 s; from excavationprior concreting, 60 s
4.3
Drilling fluid testing.
Plastic Viscosity
(To be made onpolymer if
recommended bymanufacturer) (*)
SpecialSpecifications.Sub-section
10.1.2General
SpecificationsSub-section
10.1.3.2
API RP 138 B-1
KAS-CCJV/BS2P2/ICL/QA/0
09.2Daily report
Pile Record SheetTest report
H H W W
Once aday as
suppliedto drillingprocess
Each pilefrom top
andbottom ofthe pileprior
concreting
If polymer: as per technical data sheet of themanufacturerIf bentonite: During drilling, 10 cP; from excavationprior concreting, 20 cP
-
8/10/2019 ITP for Piling
7/9
EMPLOYER ENGINEER CONTRACTOR
Ministry of Transport & CommunicationsDirectorate General of Roads & Land Transport
P.O.Box27, P.C.114Sultanate of Oman
COWI & Partners LLC
P.O.Box2115, P.C.112
Sultanate of Oman
Khalid Bin Ahmed & Sons LLC CORSAN CORVIAM JV
Al Azaiba
P.O. Box723, P.C.130
Sultanate of Oman
Contract No.: 95/2012 BS2P2 - Dualization of Bibbid-Sur Road, Section 2, Part 2DOC No: KAS-CCJV/SB2P2/ITP/QA/009 Rev.00
INSPECTION AND TEST PLAN PILING Date: 16/11/2014
(*) When the results show consistent behaviour, the tests for shear strength and pH value may be discontinued, and tests to determine density and viscosity shall be carried out as agreed with the Engineer.
INSPECTION CODE: HHold Point WWitness Point S - Surveillance NIRNo Inspection Requested
Form No.: KAS-CC/SB2P2/OP/QA/01.06 Page 7of 9
ITEM OFINSPECTION
REFERENCE DOCUMENTSFOLLOW-UPDOCUMENTS
TYPE OF INSPECTION AND FREQUENCY / INSPECTION PARTY
NOTES/ACCEPTANCE CRITERIA
SPEC. STANDARDSIndustPark
Subcont Product Survey Quality Engineer Frequency
4.4
Drilling fluid testing.Shear Strength
(To be made onpolymer if
recommended bymanufacturer) (*)
SpecialSpecifications.Sub-section
10.1.2General
SpecificationsSub-section
10.1.3.2
API RP 138 B-1
KAS-CCJV/BS2P2/ICL/QA/0
09.2Daily report
Pile Record SheetTest report
H H W W
Once aday as
suppliedto drillingprocess
Each pilefrom top
andbottom of
the pilepriorconcreting
If polymer: as per technical data sheet of themanufacturerIf bentonite: During drilling, 4 to 25 N/m2; fromexcavation prior concreting, 4 to 25 N/m2
4.5
Drilling fluid testing.
Sand Content
(To be made onpolymer if
recommended bymanufacturer) (*)
SpecialSpecifications.Sub-section
10.1.2General
SpecificationsSub-section
10.1.3.2
API RP 138 B-1ASTM D 4381
KAS-CCJV/BS2P2/ICL/QA/0
09.2Daily report
Pile Record SheetTest report
H H W W
Once aday as
suppliedto drillingprocess
Each pilefrom top
andbottom ofthe pileprior
concreting
If polymer: as per technical data sheet of themanufacturerIf bentonite: During drilling, 1%; from excavation priorconcreting, 3%
-
8/10/2019 ITP for Piling
8/9
EMPLOYER ENGINEER CONTRACTOR
Ministry of Transport & CommunicationsDirectorate General of Roads & Land Transport
P.O.Box27, P.C.114Sultanate of Oman
COWI & Partners LLC
P.O.Box2115, P.C.112
Sultanate of Oman
Khalid Bin Ahmed & Sons LLC CORSAN CORVIAM JV
Al Azaiba
P.O. Box723, P.C.130
Sultanate of Oman
Contract No.: 95/2012 BS2P2 - Dualization of Bibbid-Sur Road, Section 2, Part 2DOC No: KAS-CCJV/SB2P2/ITP/QA/009 Rev.00
INSPECTION AND TEST PLAN PILING Date: 16/11/2014
(*) When the results show consistent behaviour, the tests for shear strength and pH value may be discontinued, and tests to determine density and viscosity shall be carried out as agreed with the Engineer.
INSPECTION CODE: HHold Point WWitness Point S - Surveillance NIRNo Inspection Requested
Form No.: KAS-CC/SB2P2/OP/QA/01.06 Page 8of 9
ITEM OFINSPECTION
REFERENCE DOCUMENTSFOLLOW-UPDOCUMENTS
TYPE OF INSPECTION AND FREQUENCY / INSPECTION PARTY
NOTES/ACCEPTANCE CRITERIA
SPEC. STANDARDSIndustPark
Subcont Product Survey Quality Engineer Frequency
4.6
Drilling fluid testing.pH
(To be made onpolymer if
recommended bymanufacturer) (*)
SpecialSpecifications.Sub-section
10.1.2General
SpecificationsSub-section
10.1.3.2
API RP 138 B-1ASTM D 4381
KAS-CCJV/BS2P2/ICL/QA/0
09.2Daily report
Pile Record SheetTest report
H H W W
Once aday as
suppliedto drillingprocess
Each pilefrom top
andbottom of
the pilepriorconcreting
If polymer: as per technical data sheet of themanufacturerIf bentonite: During drilling, 1%; from excavation priorconcreting, 3%
4.7
Caliper logging teston the entire lengthof bored hole prior
to concreting
SpecialSpecifications.Sub-section
10.1.3.2ASTM D 6167
KAS-CCJV/BS2P2/ICL/QA/0
09.2Daily report
Pile Record SheetTest report
H H W W
5 No inthe firstweek
Provisionally 10 Nothereafter, equallyspacedthrough
theworks.
Acceptance in accordance to test result interpretarion
4.8
Low strain dynamic
test, sonic eco testor
High straindynamic testing
or
Cross-hole soniclogging
Special
Specifications.Sub-section
10.2General
SpecificationsSub-section
10.2
ASTM D 5882
ASTM D 4945
ICE-Section 9
KAS-CCJV/BS2P2/ICL/QA/0
09.2Daily report
Pile Record SheetTest report
H H H H 1% Acceptance in accordance to test result interpretarion
-
8/10/2019 ITP for Piling
9/9
EMPLOYER ENGINEER CONTRACTOR
Ministry of Transport & CommunicationsDirectorate General of Roads & Land Transport
P.O.Box27, P.C.114Sultanate of Oman
COWI & Partners LLC
P.O.Box2115, P.C.112
Sultanate of Oman
Khalid Bin Ahmed & Sons LLC CORSAN CORVIAM JV
Al Azaiba
P.O. Box723, P.C.130
Sultanate of Oman
Contract No.: 95/2012 BS2P2 - Dualization of Bibbid-Sur Road, Section 2, Part 2DOC No: KAS-CCJV/SB2P2/ITP/QA/009 Rev.00
INSPECTION AND TEST PLAN PILING Date: 16/11/2014
(*) When the results show consistent behaviour, the tests for shear strength and pH value may be discontinued, and tests to determine density and viscosity shall be carried out as agreed with the Engineer.
INSPECTION CODE: HHold Point WWitness Point S - Surveillance NIRNo Inspection Requested
Form No.: KAS-CC/SB2P2/OP/QA/01.06 Page 9of 9
ITEM OFINSPECTION
REFERENCE DOCUMENTSFOLLOW-UPDOCUMENTS
TYPE OF INSPECTION AND FREQUENCY / INSPECTION PARTY
NOTES/ACCEPTANCE CRITERIA
SPEC. STANDARDSIndustPark
Subcont Product Survey Quality Engineer Frequency
4.9 Static Load Test
SpecialSpecifications.
Sub-section10.2General
SpecificationsSub-section
10.2
In accordance toSpecial
Specification,
Tables 10.2.3.1and 10.2.3.2ASTM D 1143
orASTM D 5882
Approved MethodStatement
KAS-CC
JV/BS2P2/ICL/QA/009.2Daily report
Pile Record SheetTest report
H H H H
2preliminarypile testsshall be
undertakenat eachbridge
location oragreed with
theEngineer
At least onepercent ofworkingpile testsshall be
undertakenon piles
agreed withthe
Engineer,or as
shown onthe
Drawings
A preliminary test pile shall be considered to have failedwhen any of the following conditions apply: Any of the above criteria apply at working loads The maximum load specified has not been achieved
A working pile shall be considered to have failed when
any of the following conditions apply: On completion of a load test, the residual settlement
after rebound exceeds 6 mm. The test load as specified in the contract shall not
have been achieved. The maximum settlement under 1.5 working load
specified on the drawings exceeds 10mm or 1% ofthe least lateral dimension of the pile, whichever isthe greater.