itp for insulation of hvac system(asab)

3
Energy Management Transmission Solutions Format No-4G79371-Q0010-Y005A 1 of 3 08/23/2022 Inspection & Test Plan for Insulation of HVAC Ducts for ASAB Main Contractor: SIEMENS Consultant: Customer:ADCO Description of Activity Responsibility Type of check Ref. Documents Acceptance Norms Format of record Inspection Authority Contractor Consultant Customer 1 QA/QC H W W /S Manufacturer test report Contractor (Sub for Siemens): EMCC Co.LLC Project Title: New Power Upgrade Project Power System Study & FEED at All ADCO Fields ADCO Doc. No.: 14-40-31-4814 SLLC Doc. No.: (4)G37971-H0303-P4814-1 ITP No.: ASAB-ITP-INSU-001 Rev. No.:A Rev. Date: 05 July 2015 Prepared By: Naveen Checked By: Nicholas Approved By: Siva Kumar Sl. No. Main Contractor Material Receiving inspection Visual verification& Review documents Approved Material Submittal (MAR), Delivery Notes Item delivered conforms to the Drawings. RFI , Test Certificates, Country of Origin Certificate etc. Quantity delivered as per requested. Material delivered in original container / package as applicable. No physical damage to the delivered item / material. Material expiry date / shelf life known as applicable. (if required)

Upload: naveenkrishnas

Post on 03-Sep-2015

232 views

Category:

Documents


5 download

DESCRIPTION

ITP for Insulation of HVAC System(ASAB)

TRANSCRIPT

ITP Formats

Sheet1Inspection & Test Plan for Insulation of HVAC Ducts for ASABMain Contractor: SIEMENSConsultant:Customer:ADCOContractor (Sub for Siemens): EMCC Co.LLCProject Title: New Power Upgrade Project Power System Study & FEED at All ADCO FieldsADCO Doc. No.: 14-40-31-4814SLLC Doc. No.: (4)G37971-H0303-P4814-1ITP No.: ASAB-ITP-INSU-001Rev. No.:ARev. Date: 05 July 2015Prepared By: NaveenChecked By: NicholasApproved By: Siva KumarSl. No.Description of ActivityResponsibilityType of checkRef. DocumentsAcceptance NormsFormat of recordInspection AuthorityContractorMain ContractorConsultantCustomer1Material Receiving inspectionQA/QCVisual verification& Review documentsApproved Material Submittal (MAR), Delivery NotesItem delivered conforms to the Drawings.RFI , Test Certificates, Country of Origin Certificate etc.HWW /SQuantity delivered as per requested.Material delivered in original container / package as applicable.No physical damage to the delivered item / material.Manufacturer test reportMaterial expiry date / shelf life known as applicable. (if required)2Storage,Handling & Preservation.PE/QA/QCVisual verificationApproved Specifications & Approved Method Statement-Check and verify the Storage Procedure and make sure the proper Storage,Handling & Preservation is done as per procedure.RFIHWW/S3Condition of duct Surface prior to Insulations.PE/QA/QCVisual verificationApproved IFC Drawing , Specifications & Approved Method Statement-Check duct surface prior to insulation as per approved specification & Method statement and make sure that there is no dust & debris.RFIHWW /S4Tightening of JointsPE/QA/QCVisual verificationApproved IFC Drawing , Specifications & Approved Method Statement- Check & Verify the Tightening of joints as per approved specification & Method statement.RFIHWW /S5workmanshipPE/QA/QCVisual verificationApproved IFC Drawing , Specifications & Approved Method Statement- Check & Verify the workmanship as per approved specification & Method statement.RFIHWW /S6Application of SealantPE/QA/QCVisual verificationApproved IFC Drawing , Specifications & Approved Method Statement-Check & Verify the application of sealant as per approved specification & Method statement.RFIHWW /S7Sealing of JointsPE/QA/QCVisual verificationApproved IFC Drawing , Specifications & Approved Method Statement-Check & Verify the Joints sealing as per approved specification & Method statement & make sute that there is no leakage.RFIHWW/SInspection Authority LegendsFormat of recordResponsibility LegendsHHoldRFIRequest for InspectionPMProject ManagerIInspectionMTSMaterial Transmittal ApprovalPEProject EngineerWWitnessNOCNo Objection CertificateQA/QCQA/QC EngineerSSurveillanceDTSData Transmittal SheetsCECommissioning EngineerAApprovedIFCIssued for ConstructionHSESafety EngineerRReview Documents

&L&"Siemens Sans,Bold"&16&G&R&"Arial,Bold"&11Energy ManagementTransmission Solutions&L&8Format No-4G79371-Q0010-Y005A&R&8&P of &N&D

Sheet2

Sheet3