1.)Planning for the project is done in order to:

A. Decide the work that needs to be done

B. Plan the scope of the project

C. Plan the time, scope of the project

D. Understand what we need to do and plan how to do the work

Page 3: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

2.)A plan is necessary to:

A. Organize the work

B. Define the scope of work

C. Mobilize resources.

D. All of the above

Page 4: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

3.)Projects are undertaken to create:

A. Products and servicesB. Employment and job satisfactionC. High performing teams D. Continuity of operations and

services

Page 5: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

4.)How much clarity should the description of the product or service being created by the project?

A. High level

B. Low level

C. Medium level

D. Reasonable

Page 6: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

5.)Project financing is one of the step of project management

A. TrueB. False

Page 7: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

6.)Performance is done after implementation

A. TrueB. False

Page 8: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

7.) Project is a planned activity:

A. True

B. False

Page 9: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

8.)Which of the following type of project interfaces with the organization

A. Information system

B. Embedded system

C. Process control system

D. Objective driven system

Page 10: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

9.) The products handed over to the clients at the end of projects are called as:

A. Software

B. Application program

C. Deliverables

D. Intermediate products

Page 11: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

10.)The relationship between program design and program specification can be portrayed in

A. Data flow diagram

B. Product fow diagram

C. Network diagram

D. Data flow diagram

Page 12: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

11.)The time between start and end of a task are

A. Turnarround

B. Elapsed

C. Throughput

D. Pessimistic time

Page 13: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

12.)The process of project planning is called:

A. Continuous

B. Iterative

C. Time consuming

D. Conventional

Page 14: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

13.)A collection of projects that all contribute to the same overall organizational goals are called:

A. Software

B. Task

C. Programme

D. Activity

Page 15: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

14.)The standard way of evaluating the economic benefits of any projects is to carry out a:

A. Price benefit analysis

B. Cost benefit analysis

C. Cashflowanalysis

D. Fund flow analysis

Page 16: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

15.)The costs that include the salaries and other employment costs of the staff involved in the project development and all associated costs are called

A. Operational cost

B. Development cost

C. Setup cost

D. Direct cost

Page 17: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

16.)The longer term benefits that are considered very difficult to quantify are called:

A. Direct benefits

B. Assessable benefits

C. Indirect benefits

D. Intangible benefits

Page 18: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

17.)The time taken to break even or pay back the initial investment is called:

A. Back period

B. Payback period

C. Cash back period

D. Rate of return

Page 19: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

18.)The first phase of waterfall model is

A. Analysis

B. Feasibility Study

C. Coding

D. User requirements

Page 20: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

19.)The working model of one or more aspects of the projected system is

A. Evolutionary model

B. V-process model

C. Spiral model

D. Software prototyping

Page 21: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

20.)Risk management consists of

A. Risk analysis and risk estimationB. Risk control and risk planningC. Risk identification and

monitoringD.Riskcontrol,planning,identificatio

nand monitoring

Page 22: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

21.)Comparing of existing project comes under:

A. Risk analysis

B. Risk control

C. Risk identification

D. Risk evaluation

Page 23: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

23.)RRL is:

A. Risk reduction leverage

B. Risk relax leverage

C. Risk reading letter

D. Risk resource letter

Page 24: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

23.)Analyzing the functionality of hardware and software is called:

A. Project evaluation

B. Strategic assessment

C. Economic criteria

D. Technical assessment

Page 25: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

24.)Recruitment and training cost falls under:

A. Development cost

B. Data cost

C. Profit cost

D. Setup cost

Page 26: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

25.)The commonly published lists and charts are called

A. Resources

B. Work plan

C. Study plan

D. Budgets

Page 27: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

26.)Risk reporting is essential in

A. Risk evaluationB. Risk monitoringC. Risk managementD. Risk authorities

Page 28: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

27.)Product quality is defined as:

A.Delivering a product with correct requirement

B.Delivering a product using correct development procedures

C.Delivering a product which is developed iteratively

D.Delivering a product using high quality procedures

Page 29: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

28.)The main goal of quality assurance is to

A. Set coding standards

B. Improve software project management

C. Reduce the technical and programmatic risks in developing the software

D. Specify corrective actions

Page 30: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

29.)Which relates to the effort needed to make changes to the software

A. Functionality

B. Maintainablity

C. Reliability

D. Efficiency

Page 31: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

30.)Which of the following statements is NOT true?

A.Requirement must be testable

B.Requirement must be concerned with system functionality only

C.Requirement must be complete

D.Requirement must be unambiguously stated

Page 32: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

31.)LOC means

A. Lines of code

B. List of code

C. Length of code

D. Legend of code

Page 33: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

32.)Production of software is characterized by

A. Planning

B. Determination and review of customer requirements

C. Requirement measurement

D. Planning, determination, review of customer requirement and measurement

Page 34: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

33.)Software requirement analysis will identify:

A. Product

B. Job

C. Process

D. User

Page 35: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

34.)Cost benefit analysis is done for

A. Social feasibility

B. Technical Feasibilty

C. Process feasibility

D. Economical feasibility

Page 36: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

35.)The functional and Non-functional comes under

A. Project

B. Requirement

C. Start date

D. Risk

Page 37: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

36.)Time behavior is the sub-characteristics of

A. Maintainability

B. Efficiency

C. Usability

D. Reliabilty

Page 38: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

37.)The diagrammatic form for flow oriented modeling is called

A. Functional diagrams

B. ER diagrams

C. Data flow diagrams

D. System flow diagrams

Page 39: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

38.)The capability of the software to maintain its level of performance comes under

A. Functionality

B. Maintainability

C. Reliability

D. Usability

Page 40: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

39.)The ability of the software to interact with other systems refers to

A. Interoperability

B. Reliability

C. Functionality

D. Efficiency

Page 41: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

40.)The part of design modeling is called

A. User interface design

B. Testing

C. Behaviour model

D. Analysis

Page 42: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

41.)Which forms the basis for management control of software project?

A. Methods

B. Tools

C. Process

D. Quality focus

Page 43: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

42.)Requirement engineering provides the mechanism for

A. Understanding custom needs

B. Assessing facility

C. Analyzing need

D. All of the above

Page 44: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

43.)The key of software prototyping is to serve as a mechanism for defining

A. Data

B. Fact

C. Requirements

D. Plan

Page 45: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

44.)Requirement analysis results in the specification of software’s :

A. Operational characteristics

B. Basic characteristics

C. Essential characteristics

D. Useful characteristics

Page 46: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

45.)The user requirements are clarified by

A. RAD model

B. Spiral model

C. Incremental model

D. Prototyping model

Page 47: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

46.)Selecting and training people for positions in the organization is called

A. Directing

B. Planning

C. Controlling

D. Staffing

Page 48: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

47.)Establishing, measuring and evaluating performance of project activities comes under

A. Oraganizing

B. Directing

C. Controlling

D. Staffing

Page 49: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

48.)Predetermining a course of action for accomplishing oraganizational objectives are called

A. Controlling

B. Directing

C. Staffing

D. Planning

Page 50: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

49.)The process of identifying an organization’s long term goals are called

A. Economic criteria

B. Project execution

C. Strategic planning

D. Technical assessment

Page 51: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I

50.)The heart of the software development stage is called

A. Coding

B. Testing

C. Implementation

D. Design

Page 52: IT2403 - SOFTWARE PROJECT MANAGEMENT TECHNICAL QUIZ - I