Page 1: ISS Commercial Resupply Services

ISS Commercial Resupply Services

Kathryn Lueders

NASA ISS Program Office

FAA\AST Conference

February 16, 2012

Page 2: ISS Commercial Resupply Services

Current Status

2

● Assembly of the ISS vehicle is now complete. The priority is now on fully utilizing this science asset. That requires safe and reliable transportation.

● Post Shuttle retirement, commercial cargo services becomes a key aspect of ISS upmass/return capability. Current ISS transportation strategy through 2015.

• ISS has procured crew rotation services from Roscosmos.

• ESA is providing Automated Transfer Vehicles (ATVs).

• JAXA is providing H-II Transfer Vehicles (HTVs).

• NASA provides the ISS Commercial Resupply Services (CRS) - SpaceX and Orbital.

● Two ISS CRS contracts in work:

● SpaceX - Twelve pressurized and unpressurized upmass and return missions.

● KSC Launch Site

● Orbital – Eight pressurized and disposal missions.

● Wallops/MARs Launch Site

● Reliable commercial cargo transportation will be critical for the continued support of the ISS through 2020.

● Scheduling and planning for these multiple vehicles is an additional challenge for the program.

Page 3: ISS Commercial Resupply Services

Q3Q2Q1Q4Q3Q2Q1Q4Q3Q2Q1Q4Q3Q2Q1

CY2014CY2013CY2012CY2011

01/31/12 SpaceX IMS

SpX-1 Launch (8/9/12)

PSR - Dragon

FRR SORRCIR PFR

Engine Prod./Test

Engines installed

1st Stage

@ Cape

2nd Stage

@ Cape Mate

Dragon

Dragon

Ship

SORR

SpX-2 Launch (12/8/12)

EIR CIR

PSR - Dragon

PFR

Engine

Prod./Test

Engines

installed

1st Stage

@ Cape2nd Stage

@ Cape

Mate

Dragon

Dragon

Ship

SpX-3 Launch (7/18/13)

SORRMIR EIR CIR

PSR - Dragon

PFR

SpX-4 Launch (11/3/13)

SORR

VBR MIR CIR

PSR - Dragon

PFR

SpX-5 Launch (4/1/14)

SORRATP VBR MIR CIR

PSR - Dragon

PFR

Vehicle Milestones

Milestones

Launch Date

Hardware schedule in work

for Falcon 9 version 1.1

Hardware schedule in work

for Falcon 9 version 1.1

Hardware schedule in work

for Falcon 9 version 1.1

SpaceX CRS Mission Schedule Overview

Page 4: ISS Commercial Resupply Services

4

Q4Q3Q2Q1Q4Q3Q2Q1Q4Q3Q2Q1Q4Q3

CY2014CY2013CY2012CY2011

01/10/12 Orbital L1 Board

Orb-1 Launch (10/2/12)

SORR

FRR PFRCIRPQR

1st

Stg

Core2nd

Stg

FairingPCM SM Cygnus

Mate

Orb-2 Launch (4/8/13)

SORR PFR

MIR CIRPQR

Core1st

Stg

2nd

Stg

Fairing PCM SM Cygnus

Mate

Orb-3 Launch (10/1/13)

SORR PFRMIR CIRPQR

VBR

1st

Stg

Core 2nd

Stg

Fairing PCM SM Cygnus

Mate

Orb-4 Launch (6/1/14)

SORR PFRMIR CIRPQRVBR

Core1st

Stg 2nd

Stg

Fairing PCMSM Cygnus

MateVehicle Milestones

Milestones

Launch Date

Orbital CRS Mission Schedule Overview

Page 5: ISS Commercial Resupply Services

5

Multiple support vehicles require complex manifest planning.

Reliable performance will be key to making this work.

Page 6: ISS Commercial Resupply Services

6

Conclusion

● We are continuing to make progress towards operational missions. but still

have considerable work ahead.

● Finalizing integrated products and activities with NASA and International

Partners

● Successful demonstration is critical for CRS missions.

● Stability of launch windows is key.

● Important to begin flying in CY 2012.

● This cargo capability is important to the ongoing sustainment of the ISS

vehicle.