irec interconnection workshop oct. 1, 2003 1 interstate renewable energy council interstate...
TRANSCRIPT
IREC Interconnection WorkshopOct. 1, 2003
11
Interstate RenewableInterstate RenewableEnergy CouncilEnergy Council
Kansas Interconnection Implementation Workshop
Wichita Airport HiltonChristopher Cook, E3 Energy Svcs.
October 1, 2003
IREC Interconnection WorkshopOct. 1, 2003
22
IREC Interconnection Model
PDrawn from a variety of sources•FERC ANOPR Consensus documents•Mass. Collaborative Consensus tariff•NARUC model IA•Utility tariffs and applications•PJM Small resource interconnection
procedures
IREC Interconnection WorkshopOct. 1, 2003
33
IREC Interconnection ModelConcept
PStandardize the procedures for interconnection
PCarve out a small category of generators that should be easy to
interconnect and expedite these through the standard process
IREC Interconnection WorkshopOct. 1, 2003
44
IREC Interconnection Model - Overview
P3 procedural pathsPSimplified for 10kW and less inverter
based only (from Mass.)PExpedited for up to 2MW provided
equipment certified and meets screening criteria (from Mass. And FERC)
PStandard for up to 20MW (used FERC limit)
IREC Interconnection WorkshopOct. 1, 2003
55
Interconnection Model -Simplified
PInverter based equipment only Inverter must be certified to IEEE 929 and
listed by UL or other NRTL to UL 1741PListing by NRTL qualifies the inverter
as certified for these procedures -- no type testing
PMust pass limited number of screens
IREC Interconnection WorkshopOct. 1, 2003
66
Simplified Screens
P<10% (15% for solar) of radial ckt. peak load (at the substation)
Solar higher because of coincidence with load
P20 kVA limit on single phase connections on shared secondary
IREC Interconnection WorkshopOct. 1, 2003
77
Simplified Screens -cont.
PSingle phase on 240V center tap is no more that 20% imbalance of nameplate
rating of transformerPNo transmission level interconnections
POn spot networks, <5% of the spot network's maximum load
PNo area networks
IREC Interconnection WorkshopOct. 1, 2003
88
Simplified -- Timing and CostsSimplified -- Timing and Costs
• Recommended costs =$0
• 3 days to acknowledge receipt of application (reject if incomplete)
• 10 days to run screens
• 3 days to send IA if passes screens (where
IA not required -email notice of approval)
• 15 days default approval
IREC Interconnection WorkshopOct. 1, 2003
99
Expedited Screens (2MW)
P<10% (15% for solar) of radial circuit peak load (at the substation)
Pgenerator cannot contribute more than l0% to the distribution circuit's maximum fault current
on the high sidePgenerator cannot cause any protective
devices or customer equipment to exceed 90 percent of the short circuit interrupting capability
IREC Interconnection WorkshopOct. 1, 2003
1010
Expedited Procedure (2MW)
• Up to 2MW sized generators• (Note: some suggest this is artificial
limit -- see screen 10%)• Generator and interconnection
equipment package or interconnection equip. package must be “certified” (gen. type must be NRTL approved if equip. package only)
IREC Interconnection WorkshopOct. 1, 2003
1111
Expedited Screens (cont.)
PAggregate generation cannot exceed 10 MW in an area where there are known
or posted transient stability limitationsPgenerator is interconnected as shown:
Primary Distribution Line Configuration Interconnection to Primary Distribution Line
Three-phase, three wireIf a 3-phase or single phase generator,
interconnection must be phase-to-phase
Three-phase, four wire If a 3 phase (effectively grounded) or single- phase generator, interconnection must be
line-to-neutral
IREC Interconnection WorkshopOct. 1, 2003
1212
Expedited Screens (cont.)
P20 kVA limit on single phase connections on shared secondary
PSingle phase on 240V center tap is no more that 20% imbalance of nameplate
rating of transformerPNo transmission level interconnections
IREC Interconnection WorkshopOct. 1, 2003
1313
Networks - special screens
PSpot networks: either <5% of the spot network's maximum load, or generator must utilize a protection to ensure its
current flow will not affect the network protective devices (high speed reverse power).
PArea Networks: export allowed for inverters only and limited to 10% of the minimum annual load on the network or
500 kW. (Solar measures min. during daylight).PArea networks: For all others (and inverters above limit)
generator must utilize reverse power relays that ensure no export of power from the customer's site including inadvertent
export that could adversely affect protective devices on the network circuit.
IREC Interconnection WorkshopOct. 1, 2003
1414
TimingTiming
• 3 days to acknowledge application receipt
• 10 days to tell applicant if complete (reject
if incomplete w/ list of missing items) & to run screens under Initial Review
• 5 days to send an IA if passes screens
• 15 days total (3 weeks)
• More time for Additional Review
IREC Interconnection WorkshopOct. 1, 2003
1515
Alternative Procedural Paths
• If fails screens but utility believes it can be interconnected safely and reliably, then can go forward (includes minor system modifications)
• If fails screens, can go to Additional Review. Utility sets out what it needs to study and provides cost estimate. Gen. can decide to proceed.
IREC Interconnection WorkshopOct. 1, 2003
1616
Before Operation
• Local Code official sign off (not necessarily part of the IP)
• Utility can witness IEEE 1547 commissioning test
IREC Interconnection WorkshopOct. 1, 2003
1717
Expedited IP --FeesExpedited IP --Fees
• Total cost = $50 plus $1 per kW
• Example: 500kW unit pays $550 to complete interconnection
• Minor system modifications and Additional review at cost -- paid by the generator
IREC Interconnection WorkshopOct. 1, 2003
1818
Expedited Procedures -notesExpedited Procedures -notes
• No external disconnect required (unless one of the NEC required disconnects is located outside)
• Reason: not a critical safety component;> seldom if ever used;> cost can be high.
IREC Interconnection WorkshopOct. 1, 2003
1919
Standard ReviewStandard Review
• For all generators not qualifying for expedited treatment
• Limited to 20MW (5MW KS)
• Idea is to set out procedural guidelines so that state/national standards can be developed
IREC Interconnection WorkshopOct. 1, 2003
2020
Standard Review - procedureStandard Review - procedure
• Scoping meeting/feasibility study
• Gives generator a quick overview of what can be expected based on the proposed point of interconnection
• Utility offers to conduct Impact Study and provides a good faith estimate of anticipated cost
IREC Interconnection WorkshopOct. 1, 2003
2121
Standard Review - IP (cont.)Standard Review - IP (cont.)
• If gen agrees, undertakes impact study including coordination with affected systems
• If scoping meeting/impact study identifies power flows onto transmission, additional transmission feasibility/impact studies may be required (>2MW)
IREC Interconnection WorkshopOct. 1, 2003
2222
Impact Study elements -dist.Impact Study elements -dist.
• Load Flow Study
• Short-Circuit Study
• Circuit Protection and Coordination Study• Stability Study (and the conditions that would justify
including this element in the Impact Study)
• Voltage Collapse Study (and the conditions that would justify including this element in the Impact Study).
IREC Interconnection WorkshopOct. 1, 2003
2323
Transmission Study digression
• Can usually skip for < 2MW
• Like distribution standard review includes:
• Feasibility
• Impact
• Facilities Study (both trans. and dist.)
IREC Interconnection WorkshopOct. 1, 2003
2424
Feasibility Study - transmission
• High level look for any criteria violations that would suggest Transmission Impact Study is required
• Expedited version of LGIP• examine a limited contingency set• Linear analysis tools used to evaluate
compliance contingency criteria (SPP).• Short circuit calculations
IREC Interconnection WorkshopOct. 1, 2003
2525
Impact Study - trans.
• Often waived for generators <5MW
• If required, expedited version of LGIP• Load deliverability only for areas where margins are
known to be limited.
• Stability analysis is generally not performed
• Short circuit calculations
• Grounding review
IREC Interconnection WorkshopOct. 1, 2003
2626
Facilities StudyFacilities Study
• If (either) Impact Study shows facilities needed to address identified impacts, utility provides a Facilities Study agreement (and good faith estimate of cost ±25%)
• Facilities study identifies in detail the utility equipment needed to interconnect the generator (breakers, conductors, poles, xformers, etc.)
IREC Interconnection WorkshopOct. 1, 2003
2727
Final steps - Standard IPFinal steps - Standard IP
• Costs for facilities and time to construct incorporated into an interconnection agreement.
• Commissioning test required (IEEE 1547 governs test)
• Provided commissioning tests satisfactory, interconnected operation approved.
IREC Interconnection WorkshopOct. 1, 2003
2828
Standard -feesStandard -fees
• Application fee of $100 plus $2 per kWExample: 2 MW generator
pays application fee of $4100
• Gen. also pays for costs of studies and facilities (study costs limited to $100/hr)
IREC Interconnection WorkshopOct. 1, 2003
2929
Misc. Provisions -All IPsMisc. Provisions -All IPs
• Generator must conduct an annual disconnect test where is verifies that it will not island.
• Manufacturer recommended testing must be followed
• Utility can inspect at reasonable hours and disconnect if not in compliance
IREC Interconnection WorkshopOct. 1, 2003
3030
Dispute ResolutionDispute Resolution
• PUC may designate a technical master w/ binding arbitration powers
• Master may be a university, DOE laboratory or RTO
IREC Interconnection WorkshopOct. 1, 2003
3131
Standard Form IAsStandard Form IAs
• Simplified - one page (application and IA on one form)
• Expedited and Standard -- Interconnection Agreement based on NARUC model with operating rules from Mass. Included
IREC Interconnection WorkshopOct. 1, 2003
3232
IA detailsIA details
• Mutual non-interference: Generator operations will not interfere with utility and utility will not hinder generator operations (voltage, harmonics, etc.)
Gen. May disconnected if it is causing problems. Utility agrees to modify itssystem if its operations adversely
affect generator operations.
IREC Interconnection WorkshopOct. 1, 2003
3333
IA details (cont.)IA details (cont.)
• Right to access
• Right to review maintenance and testing logs (except simplified) Mutual liability and indemnification
• Insurance: no specific utility requirement
IREC Interconnection WorkshopOct. 1, 2003
3434
IA details (cont.)IA details (cont.)
• Disconnection: Utility may disconnect for maintenance after 7 days notice.
• Customer may disconnect temporarily w/o notice or permanently after 60 days notice.
IREC Interconnection WorkshopOct. 1, 2003
3535
Standard Form ApplicationStandard Form Application
• Based on SGC version of FERC Application
• Limited details required. For Standard review many of the details provided during the process. Specific gen. May not be known at time of interconnection request.
IREC Interconnection WorkshopOct. 1, 2003
The EndStay Up-To-Datewww.irecusa.org