introduction to the new guilford high school
DESCRIPTION
Introduction to the New Guilford High School. State of the Schools May 15, 2013. Current Site & Existing School Structure. Tai Soo Kim Partners Architects. Illustration of Construction on Site. Tai Soo Kim Partners Architects. New Site Plan. New School. - PowerPoint PPT PresentationTRANSCRIPT
Introduction to the New Guilford High School
State of the SchoolsMay 15, 2013
Current Site & Existing School Structure
Tai Soo Kim Partners Architects
Illustration of Construction on Site
Tai Soo Kim Partners Architects
New School
New Site Plan
Tai Soo Kim Partners Architects
West Entry – Parents & Visitors
Tai Soo Kim Partners Architects
Cafeteria/Commons - West Lobby
Tai Soo Kim Partners Architects
South Gallery
Tai Soo Kim Partners Architects
Dining Terrace / Outdoor Classroom
Tai Soo Kim Partners Architects
North Entry – Bus Loop
Tai Soo Kim Partners Architects
Bid Period: June – August 2013
Start Site Work : July & August
2013
Start New Building Construction: September
2013
Move into New Building: 2015
Remove Old Building: August – October
2015
Finish Site Work: April 2016
Construction Phase Schedule
Tai Soo Kim Partners Architects
Board of Education: Bill Bloss, ChairDr. Paul Freeman, Superintendent of Schools
Guilford HS Committee: Scott Pinckney, Chair
Architect: Tai Soo Kim Partners www.tskp.com
MEP Engineer: Kohler Ronan www.kohlerronan.com
Structural Engineer: Michael Horton & Assocs. www.mha-eng.com
Site / Civil Engineer: Milone & MacBroom www.miloneandmacbroom.com
Landscape Architect: Milone & MacBroom
www.miloneandmacbroom.comMikyoung Kim Design www.mikyoungkim.com
Construction Manager: Fusco Corporation www.fusco.comO&G Industries www.ogind.com
Design & Engineering Team