MINNESOTA DEPARTMENT OF TRANSPORTATION
59th Annual Asphalt Contractors’ Workshop /
MN Quality Initiative Workshop
Rebecca Embacher February 19, 2015
INTELLIGENT PAVING SPEC & PROJECTS
![Page 2: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/2.jpg)
IMPLEMENTATION TIME LINEThermal Profiling and Intelligent
Compaction
![Page 3: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/3.jpg)
Advancement of Technologies is increasing
accountability of both the Agency and
Contractor
Implementation of New Technologies
– Life of Pavements
– Annual Maintenance Costs
Enhancing Financial Effectiveness
Enhancing Financial
Effectiveness
![Page 4: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/4.jpg)
New Technologies
Technology QC QA DeploymentPiloting /
DevelopmentResearch
Intelligent compaction
Thermal Profiling
Intelligent Construction
Data Monitoring System
(Veda)
Digital Test Roller
(Ames Compaction Test
Rolling Device)
3D Production
Monitoring System (3D-
PMS) – Muck
Excavation
… …
Ground Penetrating
Radar
![Page 5: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/5.jpg)
Intelligent Compaction & Thermal Profiling Implementation Timeline for MN
2014
(10%)
2015
(10-15%)
2016
(40-50%)
2017
(50-75%)
2018
(100%)
Percent of MnDOT Projects meeting
project selection requirements.
![Page 6: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/6.jpg)
Applications
– *IC is recommended for use with 2353, only when used in conjunction with 2360
≥ 8 Lane Miles
Cellular Coverage (at least one time per day)
Project Selection Requirements
Technology Specification
Intelligent Compaction (IC) 2211, 2215, 2331, 2353*, 2360, 2365
Paver Mounted Infrared
Thermal (PMIT) System
2360, 2365
![Page 7: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/7.jpg)
Thermal Mounted Infrared Temperature System
is recommended for use in conjunction with IC
on Asphalt Pavement Applications
Project Select Decision Tree (Cont.)
![Page 8: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/8.jpg)
Project Selection Requirements (Cont.)
Geospatial Coverage
–100% Global Navigation Satellite System (GNSS)
Coverage within project limits.
• Intelligent Compaction: ± 2 inches Horizontally
• Paver Mounted Infrared Temperature System: ± 4 feet
Horizontally
![Page 9: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/9.jpg)
Veda – Summary Reports & Compiled Project
2014
(OMRR)
2015
(OMRR)
2016
(Contractor)*
2017
(Contractor)*
2018
(Contractor)*
* Department will complete QA on Summary Reports
Randomly review production days.
• 10% of total number of production days requiring
technology, or
• Minimum of 2 randomly selected days, whichever
greater.
OMRR – MnDOT Office of Materials and Road Research
![Page 10: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/10.jpg)
Veda
Intelligent Compaction – All Current VendorsPaver Mounted Infrared Temperature System – Scanning
System & Static Bar
QC / QA Spot Tests
Future Imports: GPR, Smoothness (ProVal Export), Digital Test Rolling
![Page 11: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/11.jpg)
Intelligent Compaction Data Management Workshop and
Intelligent Compaction Equipment Demonstration
April 7th – 8th, 2015
April 7th - Full day IC workshop in Shoreview, MN. (Arden Hills Training Center)
April 8th - Half-day equipment demonstration in Maplewood, MN.
(Office of Materials and Road Research)
Either one, or both days may be attended.
Registration and details:
http://www.dot.state.mn.us/materials/icdmwshop.html
Presented by the FHWA Intelligent Compaction Technical Support Service Center.
This training is intended for those who are ready to implement Intelligent
Compaction (IC). The workshop will familiarize attendees with intelligent
compaction technologies and Veda software. Hands-on software training
is provided. The second day includes IC equipment demonstration.
![Page 12: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/12.jpg)
Online Training Course for Veda
Awarded Funding
Working on Contract
Scheduled Length = 6 months
![Page 13: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/13.jpg)
WEBSITEAdvanced Materials and Technology
![Page 14: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/14.jpg)
Location of Advanced Materials and Technology Manual
http://www.dot.state.mn.us/materials/advancedmaterialsandtechnology.html
![Page 15: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/15.jpg)
Advanced Materials and Technology (AMT) Manual
Definitions
Check Lists
Best Practices
![Page 16: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/16.jpg)
PAVER MOUNTED INFRARED TEMPERATURE SYSTEM2015 Specification Changes
![Page 17: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/17.jpg)
Approval of Paver Mounted Infrared Temp. System
No longer, required, but recommended
AMT Manual Section 4.3
–Calibration of GNSS Accuracy
–Calibration of Infrared Temp. Sensor(s) Accuracy
–Calibration of DMI Accuracy
Photo Courtesy of Moba Corporation
![Page 18: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/18.jpg)
Field Review of Thermal Profiles by Department
AMT Manual Section 4.4
Recommend review of profiling data and/or
thermal summary on the system display:
–First 100 Tons of Production
–About 1,000 ton intervals, thereafter, for each day of
production
Images Courtesy of Moba Corporation
![Page 19: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/19.jpg)
No Satellite Connection
(S-xx.4.G.1) 2015 Analyses using Veda– Affects Monetary Price Adjustments
• Thermal Segregation
• Project Percent Coverage
25% of Files of one 2014 project!
![Page 20: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/20.jpg)
S-xx.4.G.2 Data Evaluation
Evaluate thermal segregation using 100% of data.– Lower GNSS accuracy – prevent mass filtering/cleaning of
data
– Ensure measurements are not capturing shoulders, turn lanes, adjacent pavement.
Turn Lane
![Page 21: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/21.jpg)
Effects of Brackets on Thermal Profile
(S-xx.3.B) Ensure that no brackets, or other obstructions are
located in the measurement area.
![Page 22: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/22.jpg)
More Detailed Clarification of Thermal Segregation Calculations
S-xx.3.G.2.a 150-ft sublots
S-xx.3.G.2.b Excludes temperatures < 180F
S-xx.3.G.2.c Exclude thermal profile data with 2 ft
prior to and 8 ft after paver stops
greater than 1 min. in lengthPaver Stop
2 ft
(0.5 m)8 ft
(2.5 m)
Paving Direction
![Page 23: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/23.jpg)
More Detailed Clarification of Thermal Segregation Calculations
S-xx.3.G.2.d-e Exclusion of data less than 1
percentile and greater than the 98.5 percentile
![Page 24: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/24.jpg)
S-xx.3.H.1 Monetary Price Adjustment – Thermal Coverage
Table S-xx.5
Monetary Price Adjustment for
Thermal Coverage (TC)
Thermal
Coverage (%)Total Price Adjustment Per Lift
≥ 70 No Price Adjustment
< 70
Total Price Adjustment (Deduct) =
(20 × TC $1500) × (LM)
where:
TC = Thermal Coverage for given lift, %
LM = Total Number of Lane Miles for the given
lift, miles
(this value includes the driving lanes of the paving
operation where use of the PMIT system is
required)
No longer connected to lump sum payment (2016.601 Quality Management – Lump Sum).
![Page 25: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/25.jpg)
INTELLIGENT COMPACTION2015 Specification Changes
![Page 26: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/26.jpg)
2015 Construction Season
Use of County Coordinate System File and Geoid
Model for Site Calibration
Alternating Control Points placed for one more
season.
Geoid Model – Site Calibration
1.5 miles
(maximum)
within 150 ft of centerline
![Page 27: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/27.jpg)
Reminder: Layer & Lane Identification (ID)
Asphalt Pavement Surface/Wear Course (Layer ID = HMA L2SB)
Asphalt Pavement Base Course (Layer ID = HMA L1SB)
Base (Layer ID = Pre-grind NB, SFDR-NB, CL5NB, CL5SB)
Subbase (Layer ID = Select Granular)
Reference name of the Material, Lift, and Lanecurrently being compacted.
Example: Trimble’s System
HMA L1NB
![Page 28: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/28.jpg)
Effects of Incorrect Layer IDs on Roller Coverage
![Page 29: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/29.jpg)
S-x.2.E.2 Number of Rollers
All rollers are required to be instrumented.
Instrumented rollers are required for all
compaction efforts.
Entire Paving Train
100% of Mainline (driving and auxiliary lanes)
![Page 30: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/30.jpg)
S-x.3.C.2 Measurement Passes
Table S-xx.5
Required Measurement Pass Locations
Specification Measurement Pass Location
Subbase
2105 / 2106
All roller passes on the Top of Subgrade.
(When the depth is within 6 ft (2 m) of Grading Grade.)
All roller passes on final Grading Grade Lift.
Bases, CIR
2211, 2215, 2331All roller passes on each Lift.
Asphalt Pavement
2353, 2360, 2365
100% Mainline including Control Strips
![Page 31: INTELLIGENT PAVING SPEC & PROJECTS · Technology QC QA Deployment ... The workshop will familiarize attendees with intelligent ... –About 1,000 ton intervals,](https://reader031.vdocuments.mx/reader031/viewer/2022022518/5b1478107f8b9a437c8d3077/html5/thumbnails/31.jpg)
S-x.3.G Monetary Price Adjustment – Roller Coverage
Table S-xx.6
Monetary Price Adjustment for
Roller Coverage (RC)
Roller Coverage
(RC) (%)Total Price Adjustment Per Lift
≥ 70 No Price Adjustment
< 70
= (20 × RC $1400) × (LM)
where:
PPC = Project Percent Coverage, %
LM = Total Number of Lane Miles for the
given lift, miles
(this value includes the driving and auxiliary
lanes of the paving/grading operation where use
of the IC system is required)
No longer connected to lump sum payment (2016.601 Quality Management Special – Lump Sum).