Integrating Technology with Lean ConstructionNWCCC
November 17, 2010
![Page 2: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/2.jpg)
Agenda
Lewis Lean Case Study: Modeled Work Packages Case Study: Bluebeam Case Study: SharePoint Q & A
![Page 3: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/3.jpg)
Minimize Waste
Optimize Delivery
![Page 4: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/4.jpg)
Minimize Waste
1. Reduce worker idle time2. Prevent accidents3. Avoid over/under design4. Optimize just in time delivery5. Eliminate unnecessary steps6. Prevent defects7. Shorten learning curve
Minimize Waste
![Page 5: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/5.jpg)
Optimize Delivery
1. Align goals2. Foster trust3. Establish accountability4. Ensure peak performance
Optimize Delivery
![Page 6: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/6.jpg)
Checklist
![Page 7: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/7.jpg)
Modeled Work Packages
Case Study
![Page 8: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/8.jpg)
Modeled Work Packages
![Page 9: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/9.jpg)
The Project: UW Housing Concrete Self-performed concrete work Design-bid-build delivery Lump sum, down-market bid
The Challenge: Accomplish tight schedule Prevent injuries and accidents Eliminate impacts and rework Beat aggressive labor budget
![Page 10: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/10.jpg)
The Approach: Put the Model in Our Crews’ Hands
Approach Technology Lean Objectives Fulfilled
1. Identify conflicts Revit Prevent defects
2. Visualize the work Revit Eliminate unnecessary steps
3. Segment the work Revit Ensure peak performance
4. Remove obstacles Last PlannerTM
Prevent defects
Prevent accidents
Foster trust
5. Set goals Lewis TC/WP Program Reduce worker idle time
Establish accountability
6. Provide feedback Lewis TC/WP Program Shorten learning curve
![Page 11: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/11.jpg)
The Approach: Combine the Model with Work Packages
![Page 12: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/12.jpg)
Identifying Document Conflicts Virtually, Not in the Field
![Page 13: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/13.jpg)
Using the Model’s Visualization to Plan the Work
![Page 14: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/14.jpg)
Plan Forming and Pours
![Page 15: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/15.jpg)
Identify Repetition for Prefab
![Page 16: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/16.jpg)
4D to Fine-Tune Schedule
![Page 17: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/17.jpg)
G2 – East: Conc: 52 CY Form: 3,062 SF
G2 – West: Conc: 55 CY Form: 3,122 SF
G1 – East: Conc: 75 CY Form: 4,356 SF
G1 – West: Conc: 72 CY Form: 4,076 SF
Quantities to Prorate Budgets
![Page 18: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/18.jpg)
Breaking Down the Model into the Work Segments
![Page 19: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/19.jpg)
Using Modeled Assembly Drawings to Execute the Work
![Page 20: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/20.jpg)
Many Types of Activities to Build
![Page 21: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/21.jpg)
Shear Walls: One Type of Activity
![Page 22: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/22.jpg)
G1 - West
Shear Walls: Broken into Segments
![Page 23: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/23.jpg)
G1 - East
Shear Walls: Broken into Segments
![Page 24: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/24.jpg)
G2 - West
Shear Walls: Broken into Segments
![Page 25: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/25.jpg)
G2 - East
Shear Walls: Broken into Segments
![Page 26: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/26.jpg)
G1 - West G1 - East
G2 - West G2 - East
Shear Walls: Broken into Segments
![Page 27: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/27.jpg)
Assembly Drawing for Each Segment
![Page 28: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/28.jpg)
Planning Work Packages to Remove Obstacles
![Page 29: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/29.jpg)
Coupling Modeled Assembly Dwgs with Work Packages
![Page 30: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/30.jpg)
Sharing the Budget with Our Crews for Goal Setting
![Page 31: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/31.jpg)
Shear walls total: Conc: 255 CY = 89 Hrs Form: 14,616 SF = 1,169 Hrs
Breaking the Budget into Segments
![Page 32: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/32.jpg)
Shearwalls
G2 – East G2 – West
G1 – East G1 – West
![Page 33: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/33.jpg)
Shearwalls
G2 – East: Conc: 52 CY Form: 3,062 SF
G2 – West: Conc: 55 CY Form: 3,122 SF
G1 – East: Conc: 75 CY Form: 4,356 SF
G1 – West: Conc: 72 CY Form: 4,076 SF
![Page 34: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/34.jpg)
Shearwalls
Conc. Placing = 0.35 MH/CY Wall Forming = 0.08 MH/SF
G2 – East: Conc: 52 CY Form: 3,062 SF
G2 – West: Conc: 55 CY Form: 3,122 SF
G1 – East: Conc: 75 CY Form: 4,356 SF
G1 – West: Conc: 72 CY Form: 4,076 SF
![Page 35: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/35.jpg)
Shearwalls
Conc. Placing = 0.35 MH/CY Wall Forming = 0.08 MH/SF
G2 – East: Conc: 52 CY = 18 Hrs Form: 3,062 SF = 245 Hrs
G2 – West: Conc: 55 CY = 19 Hrs Form: 3,122 SF = 250 Hrs
G1 – East: Conc: 75 CY = 26 Hrs Form: 4,356 SF = 349 Hrs
G1 – West: Conc: 72 CY = 25 Hrs Form: 4,076 SF = 326 Hrs
![Page 36: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/36.jpg)
G2 – West: Conc: 55 CY Form: 3,122 SF
![Page 37: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/37.jpg)
G2 – West: Conc: 55 CY Form: 3,122 SF
![Page 38: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/38.jpg)
G2 – West: Conc: 55 CY Form: 3,122 SF
![Page 39: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/39.jpg)
G2 – West: Conc: 55 CY Form: 3,122 SF
![Page 40: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/40.jpg)
Providing Feedback to Optimize Performance
![Page 41: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/41.jpg)
G2 – West: Conc: 55 CY Form: 3,122 SF
![Page 42: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/42.jpg)
G2 – West: Conc: 55 CY Form: 3,122 SF
![Page 43: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/43.jpg)
G2 – West: Conc: 55 CY Form: 3,122 SF
![Page 44: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/44.jpg)
![Page 45: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/45.jpg)
Tracking the Work Segments to Optimize Productivity
![Page 46: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/46.jpg)
The Results: Exceeded budget goals Empowered crews Promoted safety Eliminated waste Promoted learning culture Ensured peak performance
![Page 47: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/47.jpg)
Bluebeam
Case Study
![Page 48: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/48.jpg)
Bluebeam
![Page 49: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/49.jpg)
The Projects: 362,000 Amazon Headquarters TI 5,000 SAM TI 250,000+ First & Main GSA
The Challenge: Efficient and timely drawing updates Multitude of Subcontractors
including owner subs Large open floor plans
![Page 50: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/50.jpg)
The Approach: Hyperlinked as-builts Electronic overlays Electronic punch list
The Technology: Bluebeam .pdf software
![Page 51: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/51.jpg)
SharePoint
Case Study
![Page 52: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/52.jpg)
SharePoint
![Page 53: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/53.jpg)
The Project: Shorenstein property 250,000+ First & Main GSA LEED gold TI 5 month duration 6 agencies over 12 floors
The Challenge: 6 contracts with 6 separate
document streams 5 architects, 4 engineers 24hr turn on submittals and RFIs
![Page 54: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/54.jpg)
GSA
Bldg Owner
Lewis
Subcontractors
A/E
VBACorporate
VBALocal
DEA Corporate
DEALocal
OIG Corporate
OIGLocal
AFRCorporate
AFRLocal
IRS-P Corporate
IRS-PLocal
IRS-TCorporate
IRS-TLocal
Project Tenants
![Page 55: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/55.jpg)
Traditional Approach: 6 couriered hardcopies Email / FTP sites Separate tracking/Log comparison
Waste: Delivery time Lost or inadvertent deletion of
Email Time spent tracking documents Working with the wrong file Confusing FTP sites
![Page 56: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/56.jpg)
The Approach: Go digital
The Technology: Utilize SharePoint to organize,
distribute and track project documentation
Sub
•Submit to Lewis
Lewis
•Review
•Submit to Architect
Arch
•Review
•Return to Lewis
Lewis
•Return to Subcontractor
Team
•Review
•Respond
![Page 57: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/57.jpg)
SharePoint
![Page 58: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/58.jpg)
Project Main Page
![Page 59: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/59.jpg)
User Specific Views
![Page 60: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/60.jpg)
Owner View
![Page 61: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/61.jpg)
Owner View
![Page 62: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/62.jpg)
Architect View
![Page 63: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/63.jpg)
Email Notifications
![Page 64: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/64.jpg)
Architect View
![Page 65: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/65.jpg)
Subcontractor View
![Page 66: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/66.jpg)
Subcontractor View
![Page 67: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/67.jpg)
Subcontractor View
![Page 68: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/68.jpg)
Subcontractor View
![Page 69: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/69.jpg)
Subcontractor View
![Page 70: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/70.jpg)
Live Shared As-builts
![Page 71: Integrating Technology with Lean Construction NWCCC November 17, 2010](https://reader038.vdocuments.mx/reader038/viewer/2022103015/5516afa3550346a25b8b59f2/html5/thumbnails/71.jpg)
The Result: Faster document review Reduction in Cost Report turnaround time Effective Meetings Less paper use
“Using Lewis’ SharePoint as a portal between the design team and contractor really helped to streamline the document exchange process. Given the compressed timeline of the GSA projects, I don't think we could have been able to meet the schedule without SharePoint. I would gladly use it again and would look for ways to implement a similar technology in my own organization.”
Whit Middlecoff, AIAGBD ARCHITECTS Incorporated
“