instrumentation of the maumee river crossing...instrumentation of the maumee river crossing arthur j...

150
Instrumentation of the Maumee River Crossing Arthur J. Helmicki, Victor J. Hunt University of Cincinnati Infrastructure Institute Douglas K. Nims University of Toledo for the Ohio Department of Transportation Office of Research and Development and the Federal Highway Administration State Job Number 426354 March, 2012

Upload: others

Post on 06-Jul-2020

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

Instrumentation of the Maumee River Crossing

Arthur J. Helmicki, Victor J. Hunt

University of Cincinnati Infrastructure Institute

Douglas K. Nims

University of Toledo

for the Ohio Department of Transportation

Office of Research and Development

and the

Federal Highway Administration

State Job Number 426354

March, 2012

Page 2: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

Bridge Monitoring Condition AssessmentTruckload Test Modal TestLoad Rating Nondestructive EvaluationStructural Identification

22. Price

17. Key Words

1. Report No.

FHWA/OH-2012/2

2. Government Accession No. 3. Recipient's Catalog No.

5. Report Date

March 2012

16. Abstract

This project has focused on the instrumentation, monitoring and testing of the main span unit of the VGCS, one of Ohio’s first long-span, cable-stayed

bridges and one of only a few dozen such bridges in service in the nation. This effort looked at five main areas: (1) health monitoring; assessment of

the changes in force distribution and bridge condition during erection and early service, (2) verification of design assumptions during erection, (3)

investigation of the unique design features which have been incorporated into the VGCS, (4) investigation into the unique erection features and

sequencing which will be used during its construction, and (5) investigation of stay cable vibration which is a general, unresolved issue for bridges of

this type.

The purpose of this and associated documents is to outline the completed scientific study, which happened to consist primarily of two phases. The

first phase (Nims, 2002), contracted at the District level, included the initial structural analysis, modeling, instrumentation package design for the

monitor, and casting into the segments of the embedded sensors. The goal of this first phase was to capture the critical instrumentation issues

associated with this construction project and to develop a detailed instrumentation and testing in close consultation with ODOT officials, bridge

designers, and construction contractors.

The second phase (Helmicki, 2003), contracted through Central Office, included permanent instrumentation operated through a computer controlled,

digital data acquisition system located on-site and accessible tele-remotely via direct fiber optic internet connection, field calibration of a main span

finite element model using truckload and modal field tests; verification of various design assumptions and erection load conditions; creation of a

database of measurements for use as a supplement to the designer’s maintenance manual to provide guidance for conducting future maintenance,

and determination of vibration performance of stay cable damping system under wind and rain-induced excitation.

The goal of the second phase was to finish the monitor installation begun in the first phase, establish a baseline concept of structural behavior and

performance by utilizing a combination of field tests and ambient monitoring, capturing the overall structural concept by calibration of the finite element

models, and finally benchmarking the condition of the structure by comparison of the above with its design values.

Form DOT F 1700.7 (8-72) Reproduction of completed pages authorized

12. Sponsoring Agency Name and Address

Ohio Department of Transportation

1980 West Broad Street

Columbus, Ohio 43223

9. Performing Organization Name and Address

University of CincinnatiInfrastructure InstituteML 0030Cincinnati, OH 45221-0030

4. Title and subtitle

Instrumentation of the Maumee River Crossing7. Author(s)

Arthur Helmicki, Victor Hunt, Douglas Nims

13. Type of Report and Period Covered

Final Report

15. Supplementary Notes

Prepared in cooperation with the U.S. Department of Transportation, Federal Highway Administration

14. Sponsoring Agency Code

6. Performing Organization Code

8. Performing Organization Report No.

10. Work Unit No. (TRAIS)

11. Contract or Grant No.

426354

18. Distribution Statement

No restrictions. This document is available to the

public through the National Technical Information

Service, Springfield, Virginia 2216119. Security Classif. (of this report)

Unclassified20. Security Classif. (of this page)

Unclassified21. No. of Pages

Page 3: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

Instrumentation of the Maumee River Crossing

Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School of Electronic and Computing Systems, University

of Cincinnati, Cincinnati, OH 45221-0030

Victor J Hunt, Ph.D. Research Associate Professor, University of Cincinnati Infrastructure Institute, School of Electronic and Computing

Systems, University of Cincinnati, Cincinnati, OH 45221-0030

Douglas K. Nims, Ph.D. Associate Professor, Dept. of Civil Engineering, University of Toledo, Toledo, OH 43606-3390

Report # UC-CII 12/3

University of Cincinnati Infrastructure Institute College of Engineering

Cincinnati, OH 45221-0071

March 2012

A Report to Sponsors: U.S. Department of Transportation Federal Highway Administration

and Ohio Department of Transportation

State Job No. 426354 Contract No. 20359

Prepared in cooperation with the Ohio Department of Transportation and the

U.S. Department of Transportation, Federal Highway Administration

The contents of this report reflect the views of the author(s) who is (are) responsible for the facts and the accuracy of the data presented herein. The contents do not necessarily reflect the official views or policies of the Ohio Department of Transportation or the Federal Highway Administration.

This report does not constitute a standard, specification or regulation.

Page 4: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

Acknowledgements

The authors would like to acknowledge the Ohio Department of Transportation (ODOT)

and the Federal Highway Administration (FHWA) for their cooperation and funding of this

project. Without the assistance of forward thinking agencies such as these, development of new

technologies and methods would advance at a much slower rate. Special thanks go to ODOT

personnel at the district office in Bowling Green and the main office in Columbus for help with

design plans, analysis reports, truck support, coordination, etc. The authors specifically

acknowledge the support, advice, and direction of Jeff Baker, Mike Gramza, Rich Martinko, Dan

Meyer, Hiram Crabtree, Tim Keller, Mike Loeffler, Mike Brokaw, and Chris Weiss. Throughout

the project, the management and tradespersons provided support, insight into the construction

process and patience as the instrumentation was installed and data collected. Finally, without the

support of numerous people at the district level in coordinating field support for the testing, this

project could not have been a success. Though they are too numerous to name individually, their

support is gratefully acknowledged. Matt Shamis of Ohio FHWA has also extended his

confidence and support for this project for which we are grateful. We also acknowledge the

valuable input provided by FHWA Headquarters, the Turner-Fairbank Highway Research

Center, and the Office of Research at Washington, D.C.

The work documented within this report is largely the result of a combined effort of

many people. Those include Scott Kangas, Parag Nimse, Shashank Chauhan, Kyle Bosworth,

Balram Chamariai, Robert Sexton, Robert Ward, Bryan Wright, Chong Qiao, and many others.

Page 5: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

                                                                                                                                                  

Veterans' Glass City Skyway (VGCS) Final Report

The organization of VGCS final report is presented herein as follows: Chapter 1: Introduction and Objectives

In 2002, the Ohio Department of Transportation began undertaking the construction of the Maumee River Crossing (MRC) in Toledo, OH, a monumental project by any standard. Upon its opening to traffic service in 2007, the bridge was renamed the Veteran’s Glass City Skyway (VGCS) to better represent the city in which it was built and the hard work and service of its people.

Chapter 2: Proposed and Implementation Plans

The services to be provided under this phase of the research project cover the initial activities leading up to the installation of the monitor instrumentation and the installation of the embedded sensors.

Chapter 3: Preliminary Design

A health monitoring system for the bridge was designed, planned, and implemented for the Veteran’s Glass City Skyway bridge, with data collection and archival throughout its construction and ultimately an automated, user-friendly interface on a dedicated website. The primary criteria for selecting the instrumented segments were the predicted stresses and rating factors using the analytical data provided by the designer. Bridge Plans Addendum and Construction Contract Bid Documents were developed to document the monitor design. A total of 64 vibrating wire strain gages were installed in eight segments at four cross sections to monitor the long-term behavior of this bridge.

Chapter 4: Bridge Modeling and Analysis

The chapter objective was to use the measured response of the bridge against construction live loads and programmed truck load tests to develop a field calibrated finite element model of the bridge simulating the end of construction and initial in-service behavior. This field calibrated model captures baseline information of the bridge before it was opened to traffic (Parag S Nimse, 2007).

Chapter 5: Analytical and Experimental Stress during Construction of the VGCS

This chapter compares the experimental stresses derived from the health monitoring strain gages during the life of the I-280 Veteran’s Glass City Skyway to the calculated stresses that were anticipated during design. It focuses on the comparison for construction events since the largest change in strain occurred during the main span construction, and reviewed in-depth the strain gage and analytical data (Chong Qiao, 2009; Yi, 2010; Gupta 2011).

Page 6: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

                                                                                                                                                  

Chapter 6: Monitoring of the VGCS: Vibrating Wire Strain Gage Testing.

This chapter is related to the health and monitoring of the VGCS cable stay bridge. It was to confirm that vibrating wire strain gages installed in the bridge, as well as the rest of the data collection system, worked properly during construction when data was being collected; and to perform a chain calibration on the entire data acquisition system and confirmed the validity of the field results (Kyle Bosworth, 2007).

Chapter 7: Study of Temperature Gradients

It involved studying temperature gradients within the concrete box girders to preliminarily assess the consistency of VGCS response with that of the AASHTO design code (Kyle Bosworth, 2007).

Chapter 8: A Baseline Truck Test to Calibrate a Baseline Model

This chapter covers the designing and executing a truck test, performing the initial data reduction and assessment of the bridge response. Prior construction, load tests performed on the VGCS, were studied; and output from the progressively-calibrated Larsa computer model was utilized to establish baseline data that confirms the Larsa model (Kyle Bosworth thesis, 2007). After construction, testing was performed to determine the elastic bridge response using truck load tests whereby a number of heavily loaded vehicles are driven across the structure in an attempt to determine bridge response under design loads and to accurately predict live load response for the bridge. It will include a final calibration based on end of construction; truck load tests to complete the model calibration and serve as baseline information which can be referenced in the future model (Parag S Nimse, 2007). Also a final nondestructive load testing method is preformed, in which a final Truck load test is compared to the first truck load test (Feng, X 2010).

Chapter 9: Delta Frame Monitoring and Calibration

This chapter focuses on instrumentation and monitoring system that will collect strain data for selected loading conditions in the critical regions of the delta frames in a form that can be used to validate the analyses. A study was used to confirm the analysis by determining the magnitude of the tensile strains in the critical sections in the bottom chord of delta frame and to determine its adequacy and compliance with the crack control requirements. The finite element model for the bridge was specifically calibrated for the delta frame from casting through stay stressing, simulating the end of construction baseline behavior (Parag S Nimse, 2007). This chapter deals with measuring the changes in strain in the delta frame lower chord due to two events: the tensioning of the DF-4 tendon and the stressing of the stay. The long term and short term strains caused by the stressing of the stay were examined (Bryan W. Wright, and Parag S Nimse, 2007). In addition, the hydraulic truck cranes (from Terex Demag 1998) used for segment installation were repositioned from the tip of the cantilever to the opposing side of the final gap to capture the liveload response for the instrumented delta frame (Robert J. Ward, and Parag S Nimse, 2007).

Page 7: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

                                                                                                                                                  

Chapter 10: Use Intermediate Construction Live Loads for Progressive Calibration

This chapter addresses the use the measured response of the bridge against construction live loads and programmed truck load tests to develop a field calibrated finite element model of the bridge simulating the end of construction and initial in-service behavior (Parag S Nimse, 2007).

Chapter 11: Strains in the Bottom Slab

This chapter examines two areas of tensile stress concentration in the concrete segments of a large segmental twin box girder prestressed concrete cable stayed bridge. They are the experimental studies of the tensile stresses in the bottom slab of the delta frame segments due to final post-tensioning and the stresses in the bottom chord of the delta frame due to final post-tensioning and the stressing of the stay (Bryan W. Wright, 2007). This chapter investigates the transverse bending of the bottom slab. Results of the finite element analyses generated by the construction engineer and the designer were compared with data collected at various construction stages to determine whether the predicted levels of stress occurred (Robert J. Ward, 2007). This chapter also focuses on the additional Strain Measurements that were required in the cantilever span in the bottom slab in the strain concentration regions between the bottom slab and the walls at two locations in span 28 (Robert J. Ward, and Parag S Nimse, 2007).

Chapter 12: Long Term Analytical and Experimental Stress Comparison

Data from the installed vibrating wire strain gages has been collected since the casting date of each segment. A method of assembling the time line was developed, a Matlab program was written to combine the strain time history line for the data of one strain gage, and the experimental stresses were compared to analytical stresses calculated by the contractor. This study verifies that the instrumented segments of VGCS behave as expected for the period studied.

Chapter 13: Experimental Load Rating followed by AASHTO Bridge Evaluation Manual

In another aspect of this study, the allowable stress (ASR) load rating method was used to evaluate the inventory load rating factor for analytical and experimental stresses. This work utilized results obtained from both models, long term monitoring results and truckload testing. The analytical and experimental influence lines have a good fit. Therefore, the load rating values in the analytical and experimental results are in agreement. Of the instrumented segments, the lowest inventory rating of 1.5 for an HS25 lane load was found to occur for positive moment in the southern span at the bottom of Segment 2741.   The calculated load rating from the analytical and the experimental tests should be close to what was intended in the design.

Page 8: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

                                                                                                                                                  

Chapter 14: Stay Vibration

This chapter focuses on the stay testing program that was employed on this project (Kangas, 2009). Several experiments were performed during various stages of construction to determine the capability of using traditional vibration techniques to estimate cable tensions with the non-traditional cable sheathing system of this structure. (Dr. Hemicki and Dr. Hunt, and Kangas, 2010)

Chapter 15: Modal Analysis

This chapter focuses on the operational modal analysis program that was employed on this project (Chauhan, 2008). The magnitude and direction of structural vibrations may be monitored/measured at critical locations through the use of mounted accelerometers to identify the characteristic modal shapes and frequencies of the bridge.

Chapter 16: Website Design and Documentation

This chapter focuses on the long term instrumentation package, data collection system and web site which is used to monitor and evaluate the long term environmental effects on the structure. This system provided the ability to plot strain and temperature information about the bridge in a data-form which can easily be plotted over periods of time for multiple locations. The data collection and warehousing of gage readings means not only can officials do further analysis of the bridges health but a historical archive of bridge performance is recorded. High speed connectivity allows for frequent data collection which enables close to real time monitoring of the bridge and conditions like cold weather or icing. This also allows for a close to real time model of the bridge for possible fault detection and the ability to automatically send warning notifications.

Chapter 17: Conclusions and Future Work.

A general increase in understanding of the inspection, maintenance, and bridge management issues associated with cable-stayed bridges by key personnel in the state (at universities, ODOT, and in industry) (Dr. Nims and Hamdallah, 2010).

References and Appendices

Page 9: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

1

Chapter 1 Introduction and Objectives

1.1 Significance of this Structure in Ohio

In 2002, the Ohio Department of Transportation began undertaking the construction of

the Maumee River Crossing in Toledo, OH, a monumental project by any standard. Upon its

opening to traffic service in 2007, the bridge was renamed the Veteran’s Glass City Skyway

(VGCS) to better represent the city in which it was built and the hard work and service of its

people. This structure (see Figure 1.1)consists of 56 approach spans (totaling 7,273’) and a main

span unit of 1,525’, from expansion joint to expansion joint, crossing the Maumee River for an

overall bridge length of 8,798’. The structure is of pre-cast segmental concrete design with a

deck system nearly 120’ wide carrying three lanes of traffic in each direction. The main support

tower is 379’-3” above the waterline and the main span unit sits more than 120’ above the river.

The design specifications require the structure to be able to carry Michigan Grain Train

Truck loadings in addition to the standard AASHTO HS25-44 and alternate military live

loadings. The construction plans called for a portion of the erection to occur directly over the

existing I-280 interstate in a staged fashion making use of temporary pier columns so as allow

continued use of the interstate during erection.

Now completed, this structure is a key transportation link along the I-280/75/90/80 (see

Figure 1.2) corridor in the northwestern part of the state, a highly visible monument for the City

of Toledo (see Figure 1.3), the surrounding communities and the state, and represents a

significant investment of state resources.

The main span unit of the VGCS is one of Ohio’s first long-span, cable-stayed bridges

and one of only a few dozen such bridges in service in the nation at this writing. As such, this

structure is vastly different from the types of structures that are currently in the Ohio bridge

inventory. In fact, bridges of this design type, together with the set of associated construction

technologies necessary to build them, have been used extensively around the world only for the

past 2 decades.

1.2 Significance of Monitoring and Testing this Structure in Ohio

Because of the relative novelty of the cable stayed bridge design, it is important that

issues related to maintenance and bridge management be addressed early on with an effective

Page 10: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

2

bridge monitoring system so that long-term bridge behavior, as well as any changes in bridge

condition, can be tracked through the use of a longitudinal study beginning during bridge

construction. Such an approach will capture certain critical design, construction, maintenance,

and performance parameters that cannot be captured or quantified visually.

Figure 1.1 Plan and Elevation Views of MRC/VGCS (Nims, 2002)

Figure 1.2 Artistic Rendering of VGCS (Nims, 2002)

Page 11: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

3

Figure 1.3 Location of VGCS (Nims, 2002)

Page 12: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

4

Over the past decade, ODOT has supported numerous projects aimed at investigating

bridge behavior through instrumentation, nondestructive field testing, and structural

modeling/identification. These projects have revealed the advantages of incorporating

monitoring and testing in dealing with a wide variety of maintenance and management issues

covering dozens of bridges of various types (e.g., steel girder, truss, concrete, etc.) throughout

the state. The key feature of this approach is that it provides a solid, objective database of

information that can be put to a variety of uses including: verification of design assumptions and

analyses, monitoring of construction processes and methods, tracking of bridge responses at key

locations for rating, support of inspection and maintenance practices, long term monitoring of

structural behavior, etc.

1.3 Objectives for this Project and its Phases

The size, complexity, and relative novelty of the VGCS make it an ideal candidate for

the application of instrumented monitoring techniques. The instrumentation suites, sampling

rates, data acquisition hardware, communications network/bandwidth requirements, etc. utilized

for such a monitor are a direct function of the objectives for the monitor. A comprehensive

instrumentation system that addresses all the wishes for data may be prohibitively expensive.

Therefore, tradeoffs must be made in order to optimize the cost-benefit ratio.

In the case of the VGCS, the design of an instrumentation package focused on five main

areas: (1) health monitoring; assessment of the changes in force distribution and bridge condition

during erection and early service, (2) verification of design assumptions during erection, (3)

investigation of the unique design features which have been incorporated into the VGCS, (4)

investigation into the unique erection features and sequencing which will be used during its

construction, and (5) investigation of stay cable vibration which is a general, unresolved issue for

bridges of this type. Correspondingly, a scientific study focusing on these aspects of performance

of the VGCS will add great value to the understanding of this specific structure as well as the

general characteristics of the cable-stayed bridge type.

The purpose of this and associated documents is to outline the completed scientific

study, which happened to consist primarily of two phases. The first phase (Nims, 2002),

contracted at the District level, included the initial structural analysis, modeling, instrumentation

package design for the monitor, and casting into the segments of the embedded sensors. The goal

Page 13: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

5

of this first phase was to capture the critical instrumentation issues associated with this

construction project and to develop a detailed instrumentation and testing in close consultation

with ODOT officials, bridge designers, and construction contractors.

The second phase (Helmicki, 2003), contracted through Central Office, included

permanent instrumentation operated through a computer controlled, digital data acquisition

system located on-site and accessible tele-remotely via direct fiber optic internet connection,

field calibration of a main span finite element model using truckload and modal field tests;

verification of various design assumptions and erection load conditions; creation of a database of

measurements for use as a supplement to the designer’s maintenance manual to provide guidance

for conducting future maintenance, and determination of vibration performance of stay cable

damping system under wind and rain-induced excitation. The goal of the second phase was to

finish the monitor installation begun in the first phase, establish a baseline concept of structural

behavior and performance by utilizing a combination of field tests and ambient monitoring,

capturing the overall structural concept by calibration of the finite element models, and finally

benchmarking the condition of the structure by comparison of the above with its design values.

1.4 Expected Benefits and Deliverables of this Project

The primary benefit of the overall project has been a bridge management process for the

VGCS bridge in particular and cable-stayed bridges in Ohio in general. This process will help

these bridges reach their 100-year lives economically. Specific benefits include:

Health monitoring of the bridge during construction, as changes primarily due to

creep shrinkage and relaxation occur, and early service as the bridge responds to live load.

Verification of the performance of the bridge during construction.

Formation of a team with the knowledge and personnel to support ODOT’s efforts

to effectively manage cable-stayed bridges.

A general increase in understanding of the inspection, maintenance, and bridge

management issues associated with cable-stayed bridges by key personnel in the state (at

universities, ODOT, and in industry).

Calibrated analytical FE models of the VGCS main span system complete with

analysis/simulation results indicating all critical load carrying members and load paths. These

Page 14: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

6

models will be used by university researchers and ODOT officials for a variety of purposes:

Modeling results will be used as a theoretical gauge against which field measurements will be

compared in order to determine if the structure is behaving as predicted. These, in turn, can be

used for verification of design assumptions, monitoring of construction processes, augmentation

of routine inspection and maintenance activities, information to support management and

decision making, etc. In addition, modeling results can be used by ODOT to simulate and rate

the structure under special loading conditions such as in the case when overload permits are

requested.

The development of field ready monitoring strategies, together with an

instrumentation plan, aimed at supporting inspection, maintenance and management activities

and reducing life-cycle costs associated with the VGCS. The first step in supporting these long-

term objectives was the training session in December 2011. Further, activities to continue this

training are recommend.

Examination of the stay cable vibration and damping.

A detailed instrumentation of the VGCS’s critical locations with instrumentation

protection suitable for long-term, reliable operation over the next 3-5 years. This instrumentation

plan will be configured so that future truck-loading tests can be run intermittently at ODOT’s

discretion and so that long-term environmental monitoring can be run continuously in an

automated mode.

Provision of a solid, objective database of information that can be put to a variety

of uses such as: verification of design assumptions and analyses, monitoring of construction

processes and methods, a baseline truck-load test, ambient vibration tests, and long-term

environmental monitoring. These will form a baseline for continued health monitoring of the

main span on into its service life. This information is presented on the VGCS website.

A detailed analysis of all data obtained from field testing operations to reveal

member/connection load carrying capacities at all instrumented locations, structural performance

at all instrumented locations during erection, characteristics of stay cable vibration

characteristics, etc.

Page 15: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

7

Development and presentation of a training component for ODOT personnel

(Central Office and District) to read and analyze data. Program shall also be designed to train

ODOT personnel to carry on data collection for the design life of the structure.

Recommendations for a health monitoring program coordinated with any

maintenance manual prepared for the bridge.

A detailed, written reporting of all activities and findings obtained by researchers

in the course of conducting this project, including a detailed explanation of how “lessons

learned” from this structure can be applied to other cable stay bridges.

1.5 Research Results and Conclusions

Based on the discussion above, this project sought to implement and operate an

appropriate instrumentation and field testing program to support management of the VGCS

through construction and on into its service life. This program augments the traditional visual

inspection program to provide objective, quantitative data for use by ODOT in assessing the

status of the structure.

References

1. D. Nims, A. Helmicki, V. Hunt, “Instrumentation of the Maumee River Crossing, Phase I:

Modeling, Design of Instrumentation Suite and Installation of Embedded Sensors,” Proposal

to ODOT, District 2, by University of Toledo and University of Cincinnati, 2002.

2. A. Helmicki, V. Hunt, D. Nims, “Instrumentation of the Maumee River Crossing,” RFP: #

PS-04-14,” Proposal to ODOT and FHWA, by University of Cincinnati and University of

Toledo, 2003.

Page 16: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

1

Chapter 2 Proposed and Implementation Plans

2.1 Proposed Design of the Monitor and Test Program

As you may recall, this research project was conducted in two phases. The first phase,

regarding the design of the monitor and test program, was contracted through the District. The

services to be provided under this phase of the research project cover the initial activities leading

up to the installation of the monitor instrumentation and the installation of the embedded sensors.

They can logically be broken down into the following tasks:

Task 0: Bridge Plans Addendum and Construction Contract Bid Documents

This task encompasses all pre-planning activities necessary to develop Addenda for the

bridge plans and documentation to be inserted into the construction bid package so that all

contractors are aware of the research and instrumentation aspects at the MRC and so that all

necessary equipment and access requirements are met in order for the research to proceed in

conjunction with construction. The researchers are and will continue to work closely with ODOT

and the bridge designers to provide the necessary language for bid documents and engineering

change orders so that all preparatory work for instrumentation and testing are properly addressed

with the construction contractor. In addition, these documents will outline the equipment

necessary for instrumentation and the requirements for access during construction and testing. In

this way, the contractor, as part of the construction contract, will absorb all the costs for the

equipment and access.

Task 1: Bridge Modeling and Analysis

This task encompasses FE modeling and structural analysis (static and dynamic) of the

bridge both during construction phases and in its final, in-service state. An FE model of the

superstructure system will be developed using the information provided in the drawings. The

model will reflect the characteristics of the sectional properties and will be adjusted to reflect any

reported changes to the plans during construction. This model will be used to simulate the

structural response of the bridge due to dead load, the expected forces in the stay cables,

unexpected cable loss, the intended scenario for cable replacement, wind loads, thermal loads,

time dependent effects, construction sequence, and the specified vehicle and lane loadings for

both capacity and fatigue as per the construction drawings and AASHTO Specifications. The

Page 17: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

2

results will be analyzed to determine critical load carrying paths and to bound expected response

levels and characteristics. These findings will, in turn, be used as one of the inputs to the sensor

suite design and controlled test design described below.

In addition, the model will be adjusted to compensate for possibly undetected anomalies

or for previously unexplored conditions at cable stay locations and supports (e.g., varying

degrees of fixity, axial forces upon the exterior girders, etc.). Again, the above loading

simulations will be run to consider the effects of these hypothetical or worst-case scenarios.

These modified simulations will be used to maximize the effectiveness of the instrumentation.

Model validation will occur in two phases: (1) initially, the model will be validated

against the independent design calculations provided by the designer to ODOT, and (2) once

sensors are in place and data is obtained from actual field measurements, these measurements

will be compared against theoretically expected model output and used to tune the model.

Task 2: Instrumentation Suite Design and Installation

This task encompasses the use of modeling results from Task 1 as a basis to select exact

types, numbers, and locations for all sensor and data acquisition placements. In addition,

ordering of all components and communications with component vendors will be initiated.

In this task, researchers will make an initial indication as to which locations and cables

are to be instrumented as well as what the particular instrument configurations (e.g., numbers

and types of sensors) are likely to be. The inputs that will drive this selection process include the

following:

Modeling analysis results from Task 1,

Critical members, connections, cable details specified within the design plans and

construction manuals

Members, connections, details indicated by consultation with the design engineers, the

contractor, other noted designers, specialists in the field of cable stay assessment, and

Members, connections, details indicated by ODOT as regions of concern.

Based on our past field testing experiences, the sensor suite is likely to consist of vibrating wire

strain/temperature gages (used to obtain reliable long-term environmental response

Page 18: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

3

characteristics) and resistive-based, high speed strain gages (used to obtain low noise, dynamic

load response characteristics). Additional gaging (i.e., accelerometers) will be used for ambient

vibration studies. A weather station will be erected to monitor wind speeds in three dimensions,

rainfall, temperature, and humidity.

It is assumed that all instrumentation will be operated by an automated, computer

controlled, digital data acquisition system located on-site and accessible either manually or tele-

remotely (e.g., via either direct modem/telephone connection). Where possible, the researchers

will employ proven, off-the-shelf, turn-key components to assemble the pieces of the proposed

monitor. This will serve to minimize monitor development time and maximize reliability.

Also, where possible, all gaging will be placed embedded in (i.e., attached to rebar, etc.)

or affixed on (i.e. tack-welded or epoxied to steel surfaces, etc.) the structure during fabrication.

When precast elements are employed, researchers will travel to the precasting site to embed

gages during fabrication. During this phase of the project, sensors, typically vibrating wire and

electrical resistance strain gages, will be cast into the mainspan segments as segment production

permits. As part of this task, the operation of the cast-in-place instruments will be verified for

proper functioning.

Task 3: Data Collection, Archival, and Interpretation

Based on the construction schedule, erection of the main span was nearly half complete

by the end of Phase I of the research project, i.e., October 2003. Therefore, collection of the

initial construction data necessarily began.

Task 4: Preparation of a Research Proposal for Phase 2

A research proposal for Phase II of this research, including monitoring of the balance of

construction and initial service, will be prepared and submitted to the Ohio Department of

Transportation. Phase II includes gathering, storing and interpreting all remaining data from

construction, traveling to site to periodically collect in-service monitoring data during the first

year of service, and subsequent interpretation of construction and in-service data.

Page 19: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

4

2.2 Proposed Execution of the Monitor and Test Program

The second phase, regarding the execution of the monitor and test program, was

contracted through Central Office. This phase of the research will follow on the heels of the

Phase I activity wherein structural analysis, preliminary modeling, and instrumentation suite

design have been completed. In addition to continuing effort on the above Phase 1 tasks, the

work of Phase 2 can logically be broken down into the following tasks:

Task 5: Establish test schedule

Design activities will be conducted to develop a regimen of bridge tests and strategies:

§ Construction event monitoring: The research team will work with the designer and

contractor to identify key/critical construction events such as movement of construction

equipment on the structure, installation of specific segments, tensioning of tendons and stays,

etc. Researchers will use these as opportunities to collect data for use in subsequent analysis,

verification, and calibration studies.

§ Truck-load testing: Both static and crawl speed tests will be considered. Truck-load

configurations and transit paths will be developed. Several loaded and weighed tandem or larger

trucks will be required to force a measurable response from the structure and the installed

sensors.

§ Ambient vibration monitoring: An ambient modal test will be designed to evaluate

vibrational characteristics in the selected locations. The results of this testing will serve to further

clarify the loading environment by wind, traffic, and other forces, vibrational patterns of the

cable response, member and connection responses, and possible fatigue-prone regions within the

system.

§ Long-term environmental monitoring: An automated data acquisition system will be

designed to interface with that portion of the sensor suite developed to track the long-term

environmental response of the bridge. This system will be configured to run continuously in the

standalone mode to sample and record measurements at fixed intervals (e.g., every 15-30

minutes) without human intervention. Periodically, the data will be downloaded for analysis and

to clear the data acquisition system memory for more measurements. The download operation

will be handled initially by manually plugging a laptop into the data acquisition system at the

Page 20: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

5

site. Upon completion of construction, the system will be upgraded so that data can be obtained

remotely through the use of a fiber optic internet connection.

Task 6: Conduct construction event and ambient monitoring

In order to validate the design steps for both the structure and its monitoring system

above, the researchers will immediately begin the regular and automated data acquisition with a

permanent data system for the first and successively installed sensors in each of the instrumented

segments. In addition, a high-speed data system would be used temporarily to collect dynamic

ambient (e.g., wind, construction) measurements from the appropriate sensors by the research

team on day trips to the construction site once segments are installed on the main span. The data

obtained from this monitoring would be used for several purposes:

§ validate (by comparison of theoretical estimates from modeling and actual field measurements)

the results obtained from the analytical modeling studies upon which the sensor suite and testing

plan designs were based,

§ obtain preliminary data on some of the critical locations to initiate the procedures for data post-

processing and analysis for member capacity, etc., and

§ debug field operations specific to the site, installation methods, access issues, provide

information for data system calibration, etc.

Task 7: Field testing for baseline and service condition assessment

Truck-load testing will consist of an initial baseline test to track any changes in bridge

state in response to live loadings. The truck-load test will take several days to complete and

require several loaded, pre-weighed tandem or larger trucks of a known axle configuration.

When appropriate, lane or bridge closure, traffic control, and the loaded trucks will be provided

by ODOT. Full bridge closure will be necessary during portions of the test. Ambient vibration

monitoring will also take several days to establish the vibrational levels and characteristics of the

structure, including cable stays. Accelerometers would be temporarily bonded to a select subset

of stay cable conduits at certain intervals along their length in order to record their response

profiles to ambient loading. Bridge traffic will provide input excitation for the structure and so

the bridge will remain open to traffic for most of the test. However, identification of the bridge

response to wind loading will require full closure of the bridge and should be conducted just

Page 21: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

6

before the bridge goes into service. Scaffolding, rigging, snooper or bucket truck, or other means

of access may be required to install and remove the accelerometers from the stay cables.

Task 8: Data analysis/reporting phase

All test data would be post-processed and findings delivered to ODOT. Intermediate

results and findings will be reviewed with ODOT on a continuing basis as they become

available. Findings would include: breakdown of construction, truckload and ambient bridge

member responses, comparative analysis of bridge member response both temporally and

spatially, verification of design calculations, and capacity rating of instrumented members. In

order to reduce life-cycle costs, recommendations will be made for actions to take during the

service inspection, maintenance and management activities for the MRC in particular and for

cable stay bridges in general. A detailed description of the analysis to be performed includes:

§ Evaluate segment/cable/connection performances using long-term environmental monitoring to

determine: dead load stress at the instrumented locations, peak and cumulative stress from all

construction at instrumented locations, thermal induced stress/cycles, and thermal effects on

instrumented locations

§ Evaluate member/cable/connection performances using baseline and service field tests to

determine: load-carrying/transfer capability for controlled loading, maximum measured stresses

within members/connections and where such measured stresses occur, maximum vibration

amplitude (g’s) at instrumented locations, natural frequencies, and vibration (mode) shapes, and

HS25-44 load, Michigan grain train, and fatigue rating of instrumented members

Task 9: Reporting Activities

In addition to the normal communication of findings as described above, the research

team shall formally submit quarterly progress reports to ODOT in the required format. Six

months prior to the completion of the contract, the research team shall submit a draft of the

project final report complete with executive summary for ODOT’s review. This report will fully

describe the activities undertaken on the project, incorporate all results and findings obtained, as

well as any recommendations for actions to take during the service inspection, maintenance and

management activities for the MRC in particular and for cable stay bridges in general. After

Page 22: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

7

review of the report, ODOT comments and suggestions will be incorporated in a final version of

the project report and be officially submitted to ODOT.

Task 10: Training Activities

A primary goal of this research is the formation of a team (including government, industry, and

university personnel) with the knowledge to support ODOT’s efforts to effectively manage the

MRC and other cable-stayed bridges in the state. An important component of this goal will be to

provide training to ODOT employees to allow for future periodic data acquisition for the purpose

of MRC health monitoring.

2.3 Proposed Implementation Plan for ODOT

Any proposal submitted to the ODOT Research Office has a requirement for a proposed

plan on the implementation of the research by the department. We recommended that a number

of deliverables as discussed above could form the basis of items which could be immediately

implemented to enhance and improve ODOT’s understanding of this unique structure and its

operations, maintenance, etc. Others form the basis for more long term strategies which involve

either this particular structure or the class of cable stayed bridges in general. In the section, the

researchers try to present a breakdown of some of these issues. The goal will be to identify

specific ODOT design, construction, operation, and maintenance codes/practices/activities which

could and should be modified for structures of this type in order to maximize performance and

reduce total life cycle costs. Thus, in this sense, the implementation plan for this research is a

work-in-progress.

Short Term Implementation Issues: The main goal of this research is the development of a

database of objective information on the structural behavior of the MRC obtained through the

analysis of measurements taken by an instrumented monitoring system designed and installed

concurrently with the bridge’s fabrication and erection. The process of designing this monitor

and its sensor suite as well as the process of collecting and analyzing the preliminary data present

several natural and immediate opportunities for implementing the research.

The design and construction of a bridge such as the MRC is a highly complex and

iterative process. Not all the details are worked out ahead of time. Many are finalized as the

process proceeds. Moreover, many of the structural characteristics of the final bridge depend as

Page 23: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

8

much on how the erection is sequenced as on the design details found on the plan sheets. At each

step as the fabrication of bridge components proceeds, designers and ODOT engineers are

working through a myriad of finalizing, low-level decisions. At certain points in this process,

problems arise, new ideas come to mind, etc. At a number of these points, instrumented

monitoring and the associated scientific, quantitative data obtained provide a useful tool in the

decision making process.

Where the data is already in hand as part of the ongoing research operations, it will be

freely shared to aid in decision making. One such instance that has recently occurred might serve

as an example of this type of implementation: The instrumentation design process ongoing under

Phase I has identified certain critical bridge main span segments for instrumentation. In order to

maximize reliability and life expectancy of the instrumentation package, sensors are being

embedded as these segments are formed and poured. A natural by product of this sequence of

events is that for selected segments data (temperature, strain, etc.) can be obtained during

casting, curing, post-tensioning, and storage. This data will be reported to ODOT. It can be used

by ODOT and the fabricators for comparison against expected profiles and may shed light on

how the fabrication process is proceeding. In fact, recent temperature measurements taken from

the practice instrumentation of a segment have revealed rather large internal thermal gradients

which may contribute to segment micro-cracking during fabrication. While this micro-craking is

in a compression region, it may provide a pathway for moisture to penetrate the segment and

initiate subsequent deterioration mechanisms. The measurements have identified specific regions

where localized heating of the casting form could be implemented in order to equilibriate these

gradients during curing operations immediately after a pour.

Similarly, readings taken during segment transport and storage at the casting yard may

prove insightful and useful. This is especially true as winter approaches and the environment in

the casting yard is likely to see significant fluctuations.

On occasion, questions about various bridge components have and will arise that are

outside the main scope of the research described herein, but for which quantitative measurements

would prove valuable. At these points, researchers will augment their instrumentation efforts to

obtain the needed measurements at minimum additional cost for ODOT. One such example is the

recent instrumentation of a main span delta frame to measure stresses induced during fabrication.

Page 24: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

9

As the fabrication of delta frames drew near, final design calculations revealed possible

overstressing at certain locations as the delta frames were lifted out of the form and placed into

storage and again when the delta frame is erected. Certain changes in the re-steel and member

dimensions were implemented to address these issues. However, in addition, the research team

was asked to place strain gages in one delta frame during fabrication in order to obtain

measurements for verification of the predicted fabrication/erection-induced stresses. This

additional monitoring effort has been implemented, monitoring efforts are currently under way,

and the data is being delivered to ODOT, Figg, and Fru-Con.

Once erection of the main span begins, the monitoring system architecture has been

configured so that data can be continuously obtained from the segments instrumented during

fabrication. This data will be used for comparison against the erection and construction loads

predicted by the design and erection analyses, particularly during construction events deemed

“critical” by the designer and contractor. On one hand this data will provide validation of sensor

installation and operation. On the other hand, this data will be available to document the erection

state of stress and dead loads. The capacity ratings of a structure as massive as the MRC are

mainly a function of the dead load distribution, which, for the class of cable-stay bridges, is

heavily dependent on the erection sequencing. For this particular design, this is even more

critical due to the unique features of the continuous cable stays and cradle arrangement at the

plyon. In addition, the designers will be trying to conduct the erection using a one-time only stay

tensioning operation. The data obtained during erection will therefore serve implement the

feedback of very important information on the erection behavior of certain unique features of this

structure.

Near the end of erection, but before the bridge is opened to service, a series of baseline

tests will be conducted as part of the research project. These will include truck-load tests and

ambient vibration monitoring studies. The results of this testing will serve to further clarify: the

live loading environment due to wind, traffic, and other forces; vibrational patterns of the cable

and superstructure response; and possible fatigue-prone regions within the system. These

baselines, together with the archive of dead loads from above will serve to completely

characterize the bridge performance at the instrumented locations. This database will have a

number of ready implementations: The data will provide a check of the loading behavior

predicted by design and erection engineers. A regular regime of readings taken during the

Page 25: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

10

bridge’s service life can be incorporated into the bridge’s maintenance and inspection process

(particularly in regions where high stress amplitude and/or stress cycles are observed). These can

be compared against the baseline readings in order to track and/or trend changes on structural

performance. Once the bridge is opened to service, the embedded sensors will serve to monitor

both the structure’s responses to environmental events (wind, temperature. etc.) as well as its

responses to traffic. Data will be collected and archived in an automated fashion. This database

of ongoing, long term measurements will serve to augment visual inspections and track structural

performance. Identifying exactly which sensor readings will provide the most useful information

and what post-processing of the readings is needed for interpretation is a major part of the

proposed research project.

At the end of the research project, a calibrated analytical FE model of the MRC main

span system will be available. This model can be used as a tool of ODOT structural engineers to

perform simulation studies for various purposes. In the near term, such a model could be used

much like BARS to provide information necessary for overload permit issuance and load rating.

In the long term, the model will be available for simulation-based studies in case of damage

occurs or repairs or retrofits are needed. Also, the model will be available in the unlikely event

that one or more aspects of the performance of the bridge does not turn out as anticipated by the

designers (e.g., vibration levels, etc.).

The examples above give the flavor of some of the short term implementations that are

likely to accrue from the proposed research on and installation of an instrumented monitor

system on the MRC. As with many of UCII’s previous projects, still other implementations, as

yet un-thought-of, will reveal themselves as the research proceeds and information on structural

behavior is collected and analyzed. The researchers intend that such circumstances will be

reviewed with ODOT personnel and further investigated on a case-by-case basis as a byproduct

of the proposed research project.

At the end of the project, all such findings, together with a full set of recommendations

for a routine MRC health monitoring program will be developed and coordinated into any

maintenance manual prepared for the bridge. This activity will be perhaps the most direct

implementation of the research and will be conducted jointly with the researchers and ODOT

personnel. This will include full documentation of the monitor system hardware and software

Page 26: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

11

together with a comprehensive listing of the data to be collected, the frequency of collection, any

data post-processing steps necessary, and a standardized set algorithms/methods/strategies for

data interpretation.

Medium-to-Long Term Implementation Issues: The discussion above focuses on several

potential implementations relating directly to the research project objectives and the immediate

findings of the monitoring conducted during the research project. Follow-on developments

and/or enhancements to this research could include a number of items such as the following:

The detailed, final written report of all activities and findings obtained by researchers in

the course of conducting this project will be delivered to ODOT. It will include an explanation of

how “lessons learned” from this structure can be applied to other cable stay bridges.

The members of the research team will be available to ODOT throughout the period of

the contract to discuss findings of the project and their interpretation for cable stay bridges. After

the contract has expired, the members of the research team will be available to serve ODOT as

part of a pool of expertise.

After the period of this contract, continued operation of the monitor could either be

handled by ODOT personnel or contracted back to the researchers. Along similar lines, it would

be ideal to revisit the full diagnostic schedule of tests after one year of service life for the bridge

and then again at regular intervals. A series of truckload, modal/vibration, and ambient

monitoring tests would be conducted for comparison against baseline tests run prior to placing

the bridge in service. These would serve to track changes in bridge behavior. In order to

minimize the effect upon bridge traffic, the test configuration could be designed for either

intermittent bridge closure, intermittent lane closure, or “rolling” lane closure. Otherwise the

bridge would be fully open to traffic during testing.

Based upon and incorporating the above physical and learned results for this specific

bridge, a full scale and dynamic bridge health monitor could be designed in the future by the

research team. This monitor would incorporate the hardware and software on the bridge at the

completion of this project. In addition, the monitor would incorporate additional cutting-edge

infrastructure technologies such as, but not limited to:

Page 27: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

12

a) weigh-in-motion scales or pavement loops for real-time monitoring and statistical

documentation of every vehicle/axle weights, speeds, and classification;

b) real-time, on-line capacity assessment of the instrumented members/locations;

c) real-time, instantaneous control actions including electronic paging/email, variable

message signs (VMS), video camera surveillance, etc.;

d) Internet connectivity for a user-friendly and graphical presentation of the collected

database and current bridge condition to any ODOT engineer’s desktop; and

e) a dedicated website for community access to the bridge history, general description,

selected bridge and traffic conditions, future plans, email feedback, etc.

Here, the authors would like to note that we actually did implement the latter two bullets

in the list above as part of our deliverable to provide documentation and training to ODOT for

continued use of the bridge monitoring system.

The intended audience or market for these research products would be any current or

prospective owner of a cable stay bridge, in general. However, the Ohio Department of

Transportation is the specific client that is expected to benefit primarily from this research. The

team, which includes key personnel in the Structures Office, will be immediately available to

implement these proven strategies on other cable stay bridges in Ohio. Inspection and

maintenance concerns will be addressed directly within the plans for future bridges as either new

standards or comments on the General Notes pages, key events or action items during

construction on the Bridge Staging pages, or additional comments or specifications on the

individual pages of each section and/or member of the bridge. There are few impediments to this

implementation and the additional costs to ODOT would be quite minimal.

At the discretion of each bridge owner, additional research studies may be implemented

on other existing or future bridges of this type. Although it is hard to estimate here the costs for

such efforts, it is clear that such research could build on the knowledge obtained from this

project or could simply apply a subset of the proven field methods to check the critical results

discovered in this undertaking.

Page 28: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

13

2.4 Research Results and Conclusions

Based on the discussion above, this project sought to implement and operate an

appropriate instrumentation and field testing program to support management of the MRC

through construction and on into its service life. This program augments the traditional visual

inspection program to provide objective, quantitative data for use by ODOT in assessing the

status of the structure.

References

1. D. Nims, A. Helmicki, V. Hunt, “Instrumentation of the Maumee River Crossing, Phase I:

Modeling, Design of Instrumentation Suite and Installation of Embedded Sensors,” Proposal

to ODOT, District 2, by University of Toledo and University of Cincinnati, 2002.

2. A. Helmicki, V. Hunt, D. Nims, “Instrumentation of the Maumee River Crossing,” RFP: #

PS-04-14,” Proposal to ODOT and FHWA, by University of Cincinnati and University of

Toledo, 2003.

Page 29: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

1

Chapter 3 Preliminary Design

3.1 Design of Instrumentation Plan

The selection of segments to be instrumented was done in phase I of the research project.

The primary criteria for selecting the segments to be instrumented was predicted stresses and

rating factors using the analytical data provided by the designer (Figure 3.1). Four segments

were selected (Figure 3.2), two controlled by positive moment and two by negative moment. A

practice segment was located in Span 26. Within each segment, the gage locations were selected

to capture the desired response and permit ease in installation. Special care was taken to make

sure that the gages in the segments were placed away from areas of high strain concentration.

These typically occur in delta frame segments associated with stay anchorages and deviator

segments with arrangements for longitudinal (along the length of the bridge) tendon deviators.

Approximate gage locations for a typical NB and SB segments are shown in Figure 3.3.

The gage locations for SB segments are symmetric to NB segment locations. There are sixteen

gages in each instrumented segment, eight vibrating wire gages and eight embedment foil gages,

for a total of 128 strain gages. It should also be noted that each vibrating wire gage includes a

thermistor to account for thermal affects. Hence, the total number of sensors would be 192.

Sampling rate for vibrating wire gages has a lower bound of 1 per second, whereas for foil gages

the sampling rate can be set much faster in order to measure events in near real time (e.g. 200 per

second). The more stable vibrating wire gages are used for long-term measurements and, in the

case of truck load tests, for static load positions. The embedment foil gages are used for dynamic

load cases like the pseudo static load case, as in low speed moving truck load tests or for

construction live loads. Construction live loads considered included response to loads such as

continuous segment hauler movement and the crane roll-off loading.

At each of the sensor locations shown in Figure 3.3, there are two gages, vibrating wire

gage and an embedment foil gage. The first character in the nomenclature is “V” or “F” for

vibrating wire gages and foil embedment gages, respectively. The second character can be “T”,

“W” or “B” representing the top flange, the web or the bottom flange of the segment. The third

character indicates transverse location starting from the outside end (outside parapet of the

bridge) going towards the median end (inside parapet close to center line of the bridge) and is

Page 30: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

2

represented by characters from “A” to “K”. And the last character in the nomenclature designates

the orientation of the gages where, “L” stands for longitudinal direction of the bridge and “T”

stands for transverse. At all the locations, the embedment foil gage and the vibrating wire gages

were placed close to each other and their locations were recorded when the gages were installed.

IBT STRESSES RATING FACTORS

RF = (ALLOWABLE STRESS - SDL)/LIVE LOAD

1.0

10.0

100.0

1000.0

10000.0

0

50

10

0

15

0

20

0

25

0

30

0

35

0

40

0

45

0

50

0

55

0

60

0

65

0

70

0

75

0

80

0

85

0

90

0

95

0

10

00

10

50

11

00

11

50

12

00

12

50

13

00

13

50

14

00

14

50

15

00

15

50

16

00

ABSCISSA (ft)

RA

TIN

G F

AC

TO

RS

EOC BOT EOC TOP DAY4000 BOT DAY4000 TOP

Figure 3.1 Inventory Allowable Stress Ratings of Superstructure (Figg, 2001 and IBT, 2003)

Figure 3.2 Instrumented Segments of MRC/VGCS (darkened segments are the instrumented

segments. E.G. 27 NB & SB 04) (Nimse, 2007)

Page 31: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

3

Figure 3.3 Section Diagram of Segment Instrumentation (Nimse, 2007)

3.2 Incorporation within the Bridge Construction Plans

An addendum to the plans was prepared in order to facilitate the research project

(University Research Team, 2001). This documented the items to be installed by the contractor

(e.g., conduit, junction boxes, main data cabinet, phone service, power outlets, etc.), the general

plan for instrumentation and testing (see also Chapter 2), the required access to the site and

casting yard by the university research team (URT), the requirements for notification during

construction, and the protection of instrumentation, wiring, and data acquisition equipment. The

Contractor was to coordinate the construction of the permanent conduit runs to along the parapet

and through the pylon as shown on the Preliminary Schematic Instrumentation Permanent

Wiring Plan (Figure 3.4). This plan sheet was later revised to include more details (Figure 3.5).

Page 32: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

4

Figure 3.4 Preliminary Schematic Instrumentation Permanent Wiring Plan (URT, 2001)

Page 33: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

5

Figure 3.5 Final Schematic Instrumentation Permanent Wiring Plan, Revised (Final VGCS Plans, Drawing 1501A)

Page 34: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

6

3.3 Initial Data Collection during Construction

Once these gages were installed on the rebar cage of the segment before it was cast, the

lead wires were routed to the inside parapet end. The wires and electronics were protected from

the elements by using trash bags and a white NEMA 4 box (Figure 3.6) in order to limit the

humidity and potential for damage prior to and during shipment. Each box was tied to the

segments through scupper holes on the wings using steel tie cables to ensure it would not fall

during shipment and installation. The vibrating wire gage wires were passed through a

multiplexer (MUX) to allow the inputs from all gages to be switched through a single output to a

vibrating wire interface and recorded by a Campbell Scientific CR10X datalogger. Initially,

each segment was handled independently (e.g., in the casting yard), but ultimately both

northbound and southbound segments were combined at one MUX after their installation on the

bridge. The CR10X used calibration factors provided by Geokon Inc. to translate voltage

measurements into strain and temperature values which were stored onboard until a site visit was

made to download the data and change batteries. Data collection began before the segment was

cast and in many cases has been continuous throughout storage and construction. The

embedment foil gage lead wires were left in a protected environment until needed, when they

were attached to a portable Optim Megadac data acquisition system (DAS) for truckload tests.

Page 35: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

7

Figure 3.6 Data Collection during Construction (Wright, 2007)

3.4 Final Data Collection and Archival System

As per the plans, the contractor installed conduit along the length of the parapet,

mounted the white boxes to the side of the parapet, installed the main data cabinet near the

pylon, and connected all these together to enable one common architecture for the health

monitoring system. In addition, specified cable was pulled through the conduit such that all the

electronics could be interconnected and controlled from the loggers, now relocated to the main

cabinet. The main cabinet was provided with 120VAC power, air conditioning, shelving, and a

high speed internet connection from the local fiber optic network for the roadway weather

information system (RWIS) installed by ODOT. With an IP address as specified by ODOT, the

loggers may be polled remotely by the computers at the university labs, archived in various

database formats, and provided in a user-friendly manner by a dedicated website service.

Page 36: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

8

Figure 3.7 Data Collection after Construction (Helmicki, 2010)

As part of the VGCS Ice Prevention and Removal Project, information from the RWIS

and strain are posted on the VGCS website. This compactly presents icing conditions and strain

information on one website. Thus, the website is a “one-stop-shop” for all archived and ongoing

VGCS information. The diagram in Figure 3.8 shows the relationship of the two instrumentation

backbones and how the data would be collected, archived, processed and made available for

analysis. This would involve making the RWIS sensor and video camera data available for on-

demand retrieval, as we have done already with the bridge sensors.

Page 37: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

9

Figure 3.8 Dual Purpose Website Implementation (Nims, 2010)

The coordination of this with any additional data available already on the Internet (e.g.

national weather service, conditions at the local airport, etc.) can be collected and used for local

weather condition analysis in order to address the icing issue for the bridge stays. Available

information to monitor icing is on the VGCS website. As additional metrological instruments

are added or other aspects of VGCS are addressed, the information will be posted on the website.

When the system begins operation it will be necessary to review the data closely and ascertain

the system is functioning properly. This will be facilitated by the web application which will

provide the ability to check the status of, plot and access all sensor data and archived video from

both the RWIS and the research instrumentation backbones. This will also provide the research

group the information needed to assess the equipment and system performance and validate any

research findings or conclusions.

Page 38: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

10

3.5 Research Results and Conclusions

A health monitoring system for the bridge was designed, planned, and implemented for

the Veteran’s Glass City Skyway bridge, with data collection and archival throughout its

construction and ultimately an automated, user-friendly interface on a dedicated website. The

primary criteria for selecting the segments to be instrumented was predicted stresses and rating

factors using the analytical data provided by the designer. An addendum to the plans was

prepared to document the items to be installed by the contractor (e.g., conduit, junction boxes,

main data cabinet, phone service, power outlets, etc.), the general plan for instrumentation and

testing, the required access to the site and casting yard by the university research team (URT),

the requirements for notification during construction, and the protection of instrumentation,

wiring, and data acquisition equipment. Once gages were installed on the rebar cage of the

segments, the lead wires were routed to the inside parapet and protected from the elements by

using trash bags and a white NEMA 4 box. Initially, each segment was handled independently

(e.g., in the casting yard), but ultimately both northbound and southbound segments were

combined at one multiplexer after their installation on the bridge. As per the plans, the

contractor installed conduit along the length of the parapet, mounted the white boxes to the side

of the parapet, installed the main data cabinet near the pylon, and connected all these together to

enable one common architecture for the health monitoring system. This will be facilitated by the

web application which will provide the ability to check the status, plot and access all sensor data

from the instrumentation backbones. This will also provide the research group the information

needed to assess the equipment and system performance and validate any research findings or

conclusions.

Page 39: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

11

References

1. A. Helmicki, V. Hunt, D. Nims, “Instrumentation of the Maumee River Crossing/Veterans’

City Glass Skyway Phase II ,” Annual Project Review Meeting, University Research Team,

University of Cincinnati, University of Toledo, Columbus, OH, 2010.

2. Nims, D., Helmicki, A., Hunt, V., “Ice Prevention or Removal on the Veteran's Glass City

Skyway Cables ,” Annual Project Review Meeting, University Research Team, University of

Cincinnati, University of Toledo, Columbus, OH, 2010.

3. C. Qiao, “Analytical and Experimental Stress During Construction of the Veteran’s Glass

City Skyway,” Thesis, University of Toledo, 2009.

4. P. Nimse, “Calibrated Baseline Model of a Large Cable Stay Bridge,” Dissertation,

University of Toledo, 2007.

5. R. Ward, “Short-term Construction Load Monitoring & Transverse Bending of the Bottom

Slab on the I-280 Veteran’s Glass City Skyway,” Thesis, University of Toledo, 2007.

6. K. Bosworth, “Health Monitoring of the Veterans’ Glass City Skyway: Vibrating Wire Strain

Gage Testing, Study of Temperature Gradients and a Baseline Truck Test,” Thesis,

University of Toledo, 2007.

7. B. Wright, “Experimental and Analytical Analysis of Concrete Strain Concentrations on the

I-280 Veterans Glass City Skyway Cable Stayed Bridge,” Thesis, University of Toledo,

2007.

8. International Bridge Technologies (IBT), Bridge Designer II-D (BD2) Model of Maumee

River Mainspan, Ohio Department of Transportation, Columbus, OH, 2003.

9. University Research Team (URT), Addendum 10, Support of Instrumentation and Testing of

Superstructure, Maumee River Crossing Plans (LUC-280-2.96), PID 20208, Project No.

010493, Ohio Department of Transportation, Columbus, OH, 2001.

10. Figg Engineering, Maumee River Crossing Plans (LUC-280-2.96), PID 20208, Project No.

010493, Ohio Department of Transportation, Columbus, OH, 2001.

Page 40: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

1

Chapter 4 Bridge Modeling and Analysis

4.1 Introduction

With the recent increase in the cable stayed bridge inventory in the US, a better

understanding of cable stayed bridge characteristics and the development of accurate 2D and 3D

models of these structures have been realized. Collecting strain data through monitoring of

bridges is a useful tool for obtaining baseline structural behavior and maintenance planning.

Moreover, development of an as-built calibrated finite element model is another efficient tool

that may serve as a baseline for future reference.

Development of a finite element model and its subsequent calibration is the ultimate goal

of this work. For calibration in general, the steps are 1) Selection of model type, two dimensional

or three dimensional and preliminary development of the model, 2) conduct load tests and

monitor the response, 3) simulate the load test on the model and compare the model output

against the measured response, and 4) make changes in the model so that the model output

correlates with the measured response. This chapter is focused on the preliminary development

of the model and the rest of the steps are included in the following chapters.

Cable-Stayed Bridges in general are highly nonlinear and undergo large deformations

under loading. For such structures, it is essential to account for the deformed configuration in

analysis. But the VGCS is a short span bridge and for its span the arrangement of box girders and

delta frames make it very stiff. It is therefore expected to undergo small deformations only.

Considering this, the design [IBT, 2005] models had assumed linear behavior. The linearity

assumption allows superposition of responses to all the loads. This assumption of linearity can be

verified by doing visual inspection of data. Apart from this, the assumption of linearity can be

verified by performing linear analysis and comparing it with the measured response. The only

nonlinearity considered in the design models was that of material nonlinearity. The other

important assumption, as far as model development is concerned, is that the arrangement of delta

frames and segments means there is no contribution to longitudinal stiffness from the delta

frame. The available design models are two

dimensional and were used for self weight and construction dead load analysis as well as live

load analysis. Separate models were also available for critical load combination analysis.

Page 41: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

2

It would have not been possible to simulate the test load configurations with a two

dimensional model and get an output that correlates well with the measured response. Thus, a

three dimensional model was necessary to represent truck load in 3D. Also, since the design

models are not necessarily required to be very accurate, and as long as they satisfy the code

requirements, the level of detail is not sufficient for maintenance. Whereas, a baseline calibrated

model essentially is a very important maintenance tool. Therefore, a three dimensional model

able to represent the real three dimensional bridge geometry accurately, as well as having the

ability to simulate symmetrical and unsymmetrical loading, was needed.

4.2 Model Description

The delta frame model, described in chapter four of Nimse (2007) dissertation, was used

to simulate the component stiffness of the delta frames in the full bridge model. This was done

with confidence since the delta frame model correlation which showed a close match with the

measured data and verified that the elements used to represent the delta frames accurately

simulated the stiffness under varying loading and boundary conditions. The delta frame does not

provide longitudinal stiffness.

Larsa 4D [Larsa 4D, 2007] was used to develop a three dimensional finite element model

of the bridge simulating as-built geometry, stiffness and boundary conditions. A few assumptions

were made for developing the model and are based on the design assumptions [IBT, 2005]

1) Bridge response is linear (small deformation theory). Small deformations can be expected

and the progressive calibration and final calibration support this assumption, as were

discussed in chapters 6 and 7 of Nimse (2007) dissertation.

2) The elastomeric bearings at the permanent piers offer minimal stiffness in longitudinal,

transverse and all the rotational directions and so their stiffness contribution in those

directions was neglected. The assumption of neglecting bearings stiffness was validated

by calibrating the model to field results. The combination of bearing stiffness and

permanent concrete pier stiffness is simulated by providing a vertical spring with

compressive stiffness of 87,971 kips/ft. The

3) The stays for the VGCS are continuous through the cradle, but in the model they are

represented by two separate stays stressed at the same time. Instead of strand by strand

Page 42: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

3

stressing the sum of the forces in all the strands of a particular stay are applied as a single

pretension force.

The values for spring stiffness are physically reasonable and provide reasonable results,

which were shown in chapters 6 and 7 of Nimse (2007) dissertation. The breaking down of

single stays into two separate stays and stressing them simultaneously is supported by the results

of the tests done on the cradle [Public Roads, 2002]

The bridge will experience maximum deformation during construction of the cantilever

span under self weight and during stay stressing. This work calibrated the model for two stages.

The first one is very close to end of construction except for the boundary conditions and two

stays unstressed (chapter six of Nimse 2007 dissertation). The second corresponds to end of

construction before the bridge is opened to traffic (chapter seven of Nimse 2007 dissertation).

For both the stages it is expected that the deformations under self weight are higher than due to

live loads. For developing the model, one of the elements used is the cable element which is a

nonlinear element with stress stiffening properties and requires nonlinear analysis. However,

since the self weight is so high it is expected that the cables will always be in tension and none of

the expected live loads would reverse the cable stresses. Therefore, the stress stiffening

properties were not utilized. These arguments were verified since the linear and nonlinear

analysis responses were found to be similar, and were explained in chapter six and seven of

Nimse 2007 dissertation.

4.3 Elements

Three types of elements are used, the Larsa 3D beam element, the Larsa cable element

and the Larsa grounded spring element.

The beam element [Larsa 4D, 2007] has six degrees of freedom at each end joint:

translational displacements in X, Y and Z directions and rotational displacements about X, Y and

Z directions. This element includes axial and shear deformations, twisting about its x-axis,

bending in two perpendicular planes, and associated shears. The beam element is capable of

exactly representing constant axial deformation along the beam with constant torsional shear

deformation and linear bending deformations within the element. This is accurate for analyzing

structures with loads applied at joint points. However, modeling these deformations requires a

Page 43: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

4

higher order representation due to axial loads, torsional loads, lateral loads, and moments along

the elements.

The cable element is identical to the truss element except a cable element cannot resist

compressive force. The cable element can only be used in a nonlinear analysis. If the axial force

in a cable element becomes compressive during the analysis, then the cable element is assumed

to have no axial stiffness and cannot carry any load. It is kept in the model as an inactive element

with no contributing stiffness. During the loading process of a nonlinear analysis, if the element

can become tensile again, it is included in the model with contributing stiffness to the system.

This element has geometric nonlinearity and stress-stiffening in all nonlinear analysis types. But,

for VGCS the basic assumption of linear behavior was made. Therefore, linear analysis was run

and Larsa converted the nonlinear cable element into linear truss elements for linear analysis.

The truss element has only translational displacements in X, Y and Z directions at each end and

it has no rotational stiffness. These elements can carry axial force only. The cross-sectional area

determines the axial stiffness of the element, and it is the only stiffness required to be entered for

sections assigned to truss element members. The values for Ix, Iy, Iz and shear areas are ignored

for truss and cable elements.

The grounded spring element is defined using a single joint and there is no length

associated with the element. The element represents a spring connecting a joint in the structure to

the ground. The nonlinear grounded spring element is a general foundation element. Since the

pier segments for VGCS are placed on elastomeric bearings attached to the top of the concrete

piers and there is no structural element connecting the pier segment to the bearing, the

compression stiffness provided by the bearings is very high compared to the tension stiffness

provided by the bearing. However, completely neglecting the tension stiffness will lead to use of

a nonlinear spring requiring nonlinear analysis. Because no gaps due to uplift were observed

during construction between the pier segment and the elastomeric bearing, a tension stiffness

equal in magnitude to the compression stiffness was assigned for the bearing spring.

4.4 Arrangement of beam elements

The delta frame model is shown in Fig. 4.10 and Fig. 4.11 of Nimse 2007 dissertation.

Page 44: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

5

Fig. 4.1 shows the use of the delta frame model in the arrangement of beam elements at

the cross-sections of VGCS where stays are anchored. The delta frames are connected to the

nodes of the main span beam elements (representing the box girders) using rigid members.

Figure 4.1 Arrangement of beam elements at stay anchor cross-section (Nimse 2007, Fig. 5.1)

A partly isotropic elevation of the bridge, which shows the point where the stays are

connected to the delta frame can be seen in Fig. 5.2 and Fig. 5.3 of Nimse 2007 dissertation.

They also show the details of the stay and pylon connection. It can be seen that the stay is

connected to rigid members, which are connected to the pylon. The node where the stay connects

to the pylon corresponds to the point in the physical structure where the cradle begins for that

individual stay. Fig. 4.2 shows the full isotropic elevation with pylon support and span 26 and

span 29 with their spring supports.

Figure 4.2 Full elevation (Nimse 2007, Fig. 5.5)

4.5 Conclusion

Since a cable stayed bridge may exhibit a complex nonlinear behavior, it necessitates that

all the assumptions made during the design stage be verified. Above all, if the cable stayed

bridge is made of concrete segments whose behavior is inherently time dependent, it adds to the

Page 45: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

6

problem of predicting a response. It was concluded from the literature references that

assumptions and choices affect the analytical precision required are: 1) the 2D or 3D analysis, 2)

the use of particular type of finite element for elements like segments and cables, 3) the material

property representation in the model, and 4) the assumption regarding the way the bridge is

going to behave at the connections. These all help in determining the validity of the model.

These assumptions might speed up the analysis and may be acceptable at the design stage but

they need to be verified before they could be used to generate quantitative data to be used for

maintenance. For the proposed study, reviewing previous literature research efforts have yielded

significant information that will used to develop initial models in such a way that they will

require minimum changes afterwards to calibrate them. Also keeping in mind that the

instrumentation suite employed for VGCS is a sparse one, it was decided to progressively

calibrate the model, that is, make changes to the model parameters such as stiffness and support

conditions so that the model output correlates well with the measured data even for intermediate

stages of construction. This was done to instill confidence in the use of the model that give a

baseline dead and live loads for the bridge. Future changes in stress indicate a change in bridge

condition. Therefore, a calibrated model is an essential maintenance tool.

References

1. Nimse, P.S., 2007, “Calibrated Baseline Model of a Large Cable-Stayed Bridge.” Ph. D.

Dissertation, The University of Toledo.

Page 46: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

1

Chapter 5 Analytical and Experimental Stress during Construction of the

Veteran’s Glass City Skyway (VGCS)

5.1 Introduction

Previous short-term studies on the VGCS have been performed by Dr. Parag Nimse

(2008) and Mr. Robert Ward (2008). This study was the first review of the long-term

performance of the bridge. The bridge segments were instrumented when they were cast and data

has been collected from the casting through the present in order to compare experimental and

actual stresses, and verify the long-term performance of the health monitoring system (Chong

Qiao, 2009; Yi, 2010; Gupta 2011).

The fundamental problem is to compare the experimental stresses derived from the health

monitoring strain gages during the life of the I-280 Veteran’s Glass City Skyway to the

calculated stresses that were anticipated during design. The work performed herein focuses on

stress comparison for construction events since the largest change in strain occurred during the

main span construction, which represents the initial in-depth review of the strain gage and

analytical data. Therefore, the focus is on reasonableness and behavior rather than an exact

procedure. This comprehensive overview will be used to define the future data reduction tasks

that will be completed.

The measured strain time histories at selected locations were converted to stress time

histories and compared to the construction stress time histories calculated by International Bridge

Technologies for the contractor, Fru-Con. Data without corrections for time and temperature

effects were reviewed to get a basic understanding of the data and the necessary resources to

perform the required comparison. The strains at all gage locations were reviewed to establish the

validity of the approach and identify areas for refinement. Based on this initial review, data

reduction were recommended.

Previous works done by Nimse (2008) and Ward (2008) present the strain gage installment

method. 128 health monitoring strain gages were installed at four sections (32 gages for each

section) to measure the actual effects of construction or load effects. Selected segments and gage

locations are shown as figure 3.2 and figure 3.3. Each location has 2 gages. One strain gage is a

vibrating wire. The vibrating wire gage has a built in thermister to measure temperature. The

other strain gage is a foil resistive gage. This present study addresses long term effects, so only

the vibrating wire gages are considered.

Page 47: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

2

For each gage, the strain and temperature are reported. The strain data are recorded in micro

strain ( ) , while the temperature data are recorded in degree Celsius. For each section, the files

of collected data were formed and transferred to a simple matrix for each gage’s information

utilizing Matlab software. Of the eight segments which have strain gages installed, northbound

and southbound span 28 segment 28 (28BB28) would be significantly influenced by construction

procedures since it is located at middle span of span 28 which was a cantilever in construction.

Data from 28BB28 was recorded in main span construction procedure which made 28BB28 a

good trial section to see if the data set holds up. A command program was written (Chong 2009,

Appendix) to combine data and to illustrate the strain time line history for a certain gage.

By comparing the entire strain time history line of northbound and southbound spans, a

difference was found for span 27 directions due to a difference in construction methods.

Southbound spans were constructed using an under-slung truss that carried the segments at the

lower surface, while the northbound side of the backspan was constructed using the AG-1 gantry

that supported the segments from the upper flange. At the end of the construction, the temporary

supports were released and then these north and south bounds performed identically thereafter.

From the same trend during construction, the assumption of identical performance in both spans

has been confirmed.

Fru-Con’s model is a 2 dimensional model. Therefore, the stresses reported by the model

depend only on the longitudinal position and gage elevation. The calculated stresses are

independent of transverse position. Strain from gages at the same elevation within one segment

and on the northbound and southbound have been compared and found similar. In general, this

means only one gage or an average at each elevation needs to be examined at each section. For

each cross section’s load condition, one top longitudinal gage and one bottom longitudinal gage

were studied.

5.2 Obtaining Stress from the Analytical Model

The construction company Fru-con developed a construction simulation finite element

model by using BRIDGE DESIGNER II (BD2) to simulate construction events in different

phases. It uses basic matrix structural analysis formulation combined with time-dependent

material properties, to carry out a time simulation of the bridge design during construction.

During this process, all stress conditions are checked at every construction step as well as in

Page 48: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

3

service. Every construction stage was simulated in the model. Additionally, stresses and

deformations are calculated at specific times. Fru-Con adopted the FIP-CEB model to estimate

the time dependent behavior of modulus of elasticity of concrete. However, for data reduction,

an approximate equivalent constant E was used.

5.3 Comparing the Stress Time History Data from Measurement and Analysis

Experimental strain data was extracted from the collected strain data file, and plotted as a

strain time history line for checking with construction events. The initial strain was obtained

from the time history information at the casting date. Then the strain time history line was

normalized by subtracting the initial strain. The experimental stress can be obtained by

multiplying the strain by an estimated modulus of elasticity E. The stress information for each

cross section was picked from the stress output file. The stresses for representative events were

picked out and arranged in the stress time history line to check the consistency between the

analytical and experimental result.

Experimental data from span 28 strain gages matched analytical data during construction.

For gages at bottom of segment such as 28NB28BFL and 28NB06BFL, the analytical stresses

and the experimental stresses have almost perfect fit in both trend and value. For gages at top of

segment such as 28NB28TFL and 28NB06TIL, since they are located near the neutral axis which

is about one third of the segment’s height from the upper surface, the stresses amplitudes are not

as large as bottom gages, but they also show good matches between analytical stresses and

experimental stresses.

The stay cable stressing processes generated the most obvious signatures of strain, and it

was the most convenient set of events for checking because the change in strain amplitude was

big and the exact time information was available in the cable stressing log. Figure 5.1 shows the

28NB28BFL comparison between analytical and experimental stresses in stay cable stressing

construction events. The analytical stresses are from segment #330 in Fru-Con’s model.

Data from span 27 strain gages did not fit as well as span 28 during construction. Because

span 27 was erected span-by-span and supported by temporary piers there are not the large

changes in stress as seen in span 28. The reasons for these differences may come from the

complex load conditions in span 27. The analytical stresses and the experimental stresses in span

27 have a basic match.

Page 49: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

4

Fig. 5.1 Events comparison between experimental and analytical stresses in 28NB28BFL

(Chong 2007, figure 4.4 and 5.5)

The day 2000 match for each gage is not a good fit. This discrepancy reflects the assumption of

the constant modulus of elasticity. A time varying modulus is necessary to simulate long term

behavior.

5.4 Conclusions and Future Studies

A total of 128 vibrating wire strain gages were installed in eight segments at four cross

sections to monitor the long-term behavior of this bridge. Data from these gages has been

collected since the casting date of each segment. During Chong (2009) work, a method of

assembling the time line was developed, a Matlab program was written to combine the strain

time history line for the data of one strain gage, and the experimental stresses were compared to

analytical stresses calculated by the contractor.

From the sample study of the time history line from 28NB28BFL, a good match between

construction events from the construction log and health monitoring strain gage data was

observed. Other gages’ data also showed a good fit to construction events. These good matches

Page 50: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

5

indicated that the gages worked properly during construction, and the data from these gages is an

accurate reflection of the actual strains in the bridge.

By checking the gages at the same elevation located in the same longitudinal position, the

assumption of a two dimensional model, where there is little bending about the vertical axis was

verified. Based on this verification, information from one top and bottom gage in each cross

section is concluded to be representative for the local load condition.

The next step was using the strain gage data to derive experimental stress time histories to

compare them to the construction finite element analyses. To calculate converted stress time

histories, the initial strain and modulus of elasticity are required. The initial strain for each gage

can be obtained from the strain time history on the casting date. It is a reasonable first

approximation to consider the modulus of elasticity to be a constant because the construction

procedure took a few months and the segments were typically several hundred days old. Thus,

looking at Fig 12.2 the modulus was nearly constant.

By following this research procedure, the comparisons between analytical stress and

experimental stress for selected gages were done.

Above all, this work supplied a convincing confirmation of both the accuracy of the gage

monitoring process and the finite element analysis used in the design and construction of the

VGCS.

The following actions are recommended for further data review:

The modulus of elasticity as a time dependent coefficient should be used in the future to

generate a more accurate experimental stress time history line for a long time comparison

and prediction.

The continuous database of collected strain should be updated in the future. Based on this

database, the long-term monitoring, the future load condition prediction, and load rating

can be correlated with the contractor’s or another model.

The zero strain estimate for each strain gage is inherently uncertain. The method of

determining the zero strain should be more fully developed to minimize the uncertainty

Other factors, such as temperature and geometry, which could influence the reduction of

the strain gage data needs to be studied in the future to get a more accurate result.

Page 51: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

6

Based on future truck testing and improving the accuracy of the long term strain data

reduction, improved estimates of the short term and long term stresses can be made. These

estimates of live load and dead load stresses can be used to establish an experimental load rating.

References

1. Nimse, P.S., 2007, “Calibrated Baseline Model of a Large Cable-Stayed Bridge.” Ph. D.

Dissertation, The University of Toledo.

2. Qiao C., 2009, “Analytical and Experimental Stress During Construction of the Veteran’s

Glass City Skyway” Master Thesis, The University of Toledo.

Page 52: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

1

Chapter 6 Monitoring of the Veterans’ Glass City Skyway Vibrating Wire

Strain Gage Testing

6.1 Introduction

Vibrating wire strain gage technology has been around for quite some time and has

become a well-established and trustworthy system of instrumentation. Vibrating wire strain

gages have been used on a variety of infrastructure projects including dams, tunnels, foundations,

bridges and buildings (Coutts, 2001). The ability of these gages to accurately track long-term

stresses can lead to a better understanding of the behavior of construction materials which can

lead to less over-designing and a higher quality product.

These gages have shown throughout the years that they are robust, easy to install, and

accurate. In comparison to other gages, vibrating wire strain gages are more rugged, and can be

used for long term monitoring for 20 to 30 years without worry of glue debonding from the

specimen, or drift, which plagues bonded electrical resistance strain gages. For example, many

vibrating wire gages can be attached externally by welding or epoxy, and can even be embedded

into the specimen, (Bosworth 2007, figures 2.1, 2.2, and 2.3 respectively).

Vibrating wire strain gages measure strain by use of a frequency-sensitive sensor, which

determines the frequency of the wire contained within the metal sheath. The gage is capable of

determining the strain in a specimen by determining the fundamental frequency of the wire,

which depends on the length and tension of the wire, which in turn depends on the strain in the

specimen.

While vibrating wire strain gages are resilient and accurate, they have their drawbacks.

One drawback is the small number of readings they are capable of in a period of time. The

process of determining the fundamental frequency of the wire is accurate yet slow, as typically

vibrating wire strain gages can at most take one reading per minute. This speed means that it is

not capable of measuring rapidly changing conditions, The second drawback is the effect of

temperature on the gage. The second drawback stems from the difference between the

coefficients of thermal expansion of the gage and the specimen, which causes the gage and

specimen to expand or contract at different rates. However, since the gage is permanently

affixed to the specimen, the gage is forced to expand or contract with the specimen; thus

introducing thermal strains and/or stresses into the gage readings which was accounted for by

installing a thermistor within the vibrating wire strain gage housing, which records the

Page 53: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

2

temperature along with the strain. With the temperature of the gage and specimen known

(assuming the gage and specimen are at the same temperature), it is theoretically possible to

determine the strain associated with the loading separately from the strain due to temperature by

adding the change in temperature multiplied by the difference in thermal coefficients for the gage

and the material which is being monitored.

6.2 VIBRATING WIRE STRAIN GAGE LAB TESTING

During construction there was concern about stress concentrations in the bridge. The

stresses predicted by the model were high enough to warrant an elaborate finite element analysis

and a field study. Therefore, external vibrating wire strain gages were installed in segments

28SB25 and 28SB15 where the high strains were expected. These gages were mounted on the

bottom slab of the concrete box segments to measure the strains due to self-weight as shown in

(Bosworth 2007, Figures 1.1 and 1.2). Initial data retrieved from the gages showed very small

strains in comparison to what the model predicted, on the order of 25 times smaller. Due to this

discrepancy, the URT is investigating the gages and the whole chain of data collection

equipment, including the CR-10X system, ribbon cables and the laptops used to download the

data from the CR-10X. This investigation confirmed the data obtained was accurate that no

problem existed in any piece of the data collection equipment.

6.3 Lab Testing Setup

In order to check the proper functioning of the installed strain gages and data collection

equipment, a test setup was designed and manufactured, as seen in Figure 6.1. This setup will be

similar in design to the setup that Geokon uses to calibrate their strain gages, seen in Figure 6.2.

The gages tested were Geokon Model 4000 Vibrating Wire Strain Gages. The main components

of the test setup as described in section 2.2.2 and Figure 2.6 of Bosworth 2007 thesis.

Page 54: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

3

Figure 6.1. URT’s Vibrating Wire Strain Gage Test Setup (Bosworth 2007, Fig. 2.4)

Figure 6.2. Geokon’s Vibrating Wire Strain Gage Test Setup (Bosworth 2007, Fig. 2.5)

6.4 Data Collection and Processing

Page 55: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

4

In order to confirm the proper functioning of the gages installed in 28SB15 and then

28SB25 as well as the whole chain of data collection equipment, several tasks were

accomplished. See Appendix “A” of Bosworth (2007) thesis for a complete step-by-step

description of how to perform the calibration. First, the gages were removed as carefully as

possible from the segment and brought back to the lab, identifying which gage was in which

location in case anomalies required further investigation. Figure 6.3 shows the gages as they

were installed in the bottom slab. It should be noted that several of the gages had become

partially embedded in grout during the construction process, as seen circled in Figure 6.3, and as

such, removal of the gages involved hammers, screw drivers, fine chisels and a powered rotary

tool. The removal methods used by the URT team members were crude with respect to the level

of sophistication and accuracy of the vibrating wire strain gages; however, it certainly confirmed

the robustness of the gages after all the gages were tested and found to work properly. Back

inside the lab, testing was performed in a room with a fairly constant temperature, as this avoids

the use of temperature correction equations and the use of a reference gage. Next, the LVDT

was calibrated (Bosworth 2007, section 2.2.3). Then, each gage was tested in the test setup using

the GK-403 Readout Box. Finally, each gage was tested using the CR-10X system, which

allowed the URT to check the performance of the CR-10X system and the laptop used to

download the data from the CR-10X.

After the data was collected, the data was processed and analyzed to extract the information

required to check the proper functioning of the URT data collection equipment. One goal of

using the test setup was to compare the strain readings of vibrating wire strain gages to the

known displacements of the LVDT, which was used to calculate the strain in the gage based on

the LVDT.

The strain readings from the vibrating wire strain gages were manipulated into an easy to use

format: the strain readings were zeroed based on the average strain readings at zero

displacements of the LVDT and then multiplied by the batch factor, a calibration factor used to

correct the readings obtained from the vibrating wire strain gages.

Page 56: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

5

Figure 6.3. Vibrating Wire Strain Gages in Segment 28SB25, Partially Embedded (Bosworth

2007, Fig. 2.8)

In order to obtain the strain reading based on the displacements of the LVDT, several

steps were taken. First, the final output of the LVDT and Oscillator/Demodulator was DC

voltage, which was converted into distances based on the calibration done with a micrometer.

Once the strain based on the LVDT was determined, it was directly compared to the

experimental strain as output by the strain gage and plotted on graph of Strain vs. Displacement

so as to determine if the gages installed in the concrete box segments were functioning properly.

Lastly, an experimentally determined batch factor was calculated by minimizing the percent

error when comparing the strain readings from the GK-403 Readout Box to the strains based on

the LVDT displacements.

6.5 Results and Conclusions

The main task concerning the topic of vibrating wire strain gages was to perform a chain

calibration on the data collection equipment used by the URT when data was being collected and

monitored in a segment.

Results for the seven Model 4000 Vibrating Wire Strain Gages that were installed in

28SB25 were plotted and analyzed, and can be seen in Appendix B of Bosworth 2007. Based on

these results it can be said with certainty that there was nothing inherently wrong with these

Page 57: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

6

gages, except Gage 6, which may have been damaged during removal, as they were tested in the

same test fixture with two different methods of data collection. It is also highly unlikely that all

seven gages were somehow installed improperly and yet yielded readings that seemed

reasonable, both during construction and in the lab. When a basic installation procedure was

violated, such as placing a wire in the wrong connector, crossing wires or improperly tightening

set screws, it was obvious in the results, as the data for a gage might read -55°C or +or-9999με.

After checking the data from the CR-10X and laptop used to download the data with the data

obtained from the GK-403 Readout Box, the URT is confident that the CR-10X and laptop

worked properly when data was being collected. Not only did this test fixture confirm the

functioning of the whole string of data collection equipment, it can be used in the future to

calibrate Geokon gage Models 4000 (End Block Gage), 4200 (Embedment Gage) and 4220

(Crackmeter), all of which are in use or have been used on the VGCS to monitor its health.

References

1. Coutts, D.R., Wang, J., and J.G.Cai. “Monitoring and Analysis of Results for Two Strutted

Deep Excavations Using Vibrating Wire Strain Gauges.” Tunneling and Underground Space

Technology, V. 16, 2001.

2. Bosworth, K. J. 2007. “Health monitoring of the veterans' glass city skyway: vibrating wire

strain gage testing, study of temperature gradients and a baseline truck test.” Master’s thesis,

The University of Toledo.

3. Nimse, P.S., 2007, “Calibrated Baseline Model of a Large Cable-Stayed Bridge.” Ph. D.

Dissertation, The University of Toledo.

Page 58: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

1

Chapter 7 Study of Temperature Gradients

7.1 Introduction

The effects of temperature on concrete bridges must be accounted for in design, as

changes in temperature can lead to expansion, shrinkage and thermal-induced stresses and/or

strains. There are two main types of temperature effects to be considered for bridges: effective

bridge temperature and temperature gradients. Designing for effective bridge temperature

assumes the whole cross section of the bridge changes temperature uniformly and the bridge

attempts to expand or contract. Depending on the fixity of supports, this temperature change

could cause an expansion or contraction if the bridge is permitted to do so; or if the bridge has

fixed supports, the temperature change may cause thermal stresses since the bridge tends to

expand but cannot. Another temperature effect is a differential temperature effect, also known as

a temperature gradient, where the temperature varies across the depth of the cross section. There

are two types of gradients observed and defined: positive and negative. The positive temperature

gradient is defined as occurring when the top of the cross section is warmer than the middle and

bottom. Conversely, the negative temperature is defined as occurring when the top of the cross

section is colder than the middle. The temperature gradient effect in bridges is typically of more

concern than the effective bridge temperature. Negative temperature gradients in particular can

cause unacceptable levels of tension in the top slab, which can cause the concrete to crack unless

sufficient reinforcing or pre/post tensioning is provided. These small cracks pose a large

potential problem for prestressed concrete bridges, as cracking can allow water to seep into the

cross section and corrode the prestressing strands, which is typically undetectable.

The research work in this chapter involves studying temperature gradients within the

concrete box girders. The purpose of studying the temperature gradient, with special attention

given to the negative temperature gradient, was to preliminarily assess if the VGCS response is

consistent with the AASHTO design code; and to lay the foundation for future temperature

gradient studies.

To accomplish this task, a large amount of data must be collected over several years

spanning several seasonal temperature cycles in order to draw firm conclusions about how a

bridge behaves in response to temperature. At the time of this study, a relatively small data set

had been collected from the bridge segment studied, only 8 full months of data. Therefore, the

Page 59: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

2

results from this study were only used as a preliminary assessment and to set a basis for future

work.

Data was collected from the bridge by use of a temperature gun for surface temperatures,

which was used to confirm the reliability of the thermistors embedded in the segments with the

vibrating wire strain gages. Once confirmed, the temperature readings from the thermistors were

used for the remainder of the study. This collected data was compared to the temperature

gradients as specified by codes, as shown in Figure 7.1 for both positive and negative

temperature gradients. From such figures it can easily be seen whenever the temperature gradient

exceeds the AASHTO Code. Lastly, a conclusion was made based on the results.

Figure 7.1 AASHTO Design Gradients (Bosworth, 2007)

To ensure that the thermistors function properly, a comparison of the measured temperature

difference to the maximum based on AASHTO was performed to determine if the thermistors

produce reliable data. All thermistors were found to have reasonable agreement with the nearest

surface temperature data when compared to the Code, therefore, the thermistors were further

confirmed by use of Priestly curve, that is, a temperature gradient that varied as a fifth-order

Page 60: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

3

curve across the height of the section according to New Zealand specification. Priestly curve was

used to predict surface temperatures based on the temperature readings of the thermistors at the

depth of the gage. Only the gages in the top slabs of segments 28BB28 were used for predicting

the surface temperature, since the Priestly curve does not always accurately predict temperature

below the top-most foot or two of the section.

7.2 Comparison of Code To Collected Data

With the confidence that the thermistors were reliable, the temperature data for each gage

was plotted against time and the calculated maximum positive or negative temperature gradient

from October 2005 to September 2006 for Segment 26NB14 (Bosworth, 2007). In order to

compare each gage with the positive or negative temperature gradients, the location of each gage

was used so that the design temperature gradient at the height of each gage could be determined

(see Figure 7.2).

Figure 7.2. Height of Section and Temperature Gradient (Bosworth, 2007)

Another important assumption that was used for processing the data was that the bottom

slab gage, VBEL, was the coldest temperature in the segment for the positive temperature

gradients, and the warmest temperature in the segment for the negative temperature gradients.

This assumption was based on the design temperature gradients, where there is a zero

temperature gradient throughout the mid height to the bottom of the cross section.

A Matlab program was written to determine the highest positive and negative temperature

gradient in each month and plotted out the two temperature profiles for further analysis (Nimse,

2007). For the positive temperature gradient, the Matlab program took the maximum

Page 61: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

4

temperature from the five top slab gages and compared that to the temperature of the bottom slab

gage VBEL for all points in time for each month. Then, for each month the time at which the

maximum difference between the top gage and gage VBEL occurred was used to plot the

temperatures in all the gages over the height of the section, or temperature profile, as this was

considered to be the maximum positive temperature gradient for that month. Similarly, the

negative temperature profile for each month was plotted, except the minimum temperature from

the top gages was subtracted from VBEL, and the maximum difference was used to then find the

time that it occurred, and then the temperature profile was plotted. These plots were then

overlaid with the design temperature gradients, placing the zero portion of the gradient in line

with gage VBEL, similar to what is shown in Figure 7.3. As mentioned earlier, it should be

noted that the VGCS was not outfitted with gages to specifically track the temperature gradient

across the height of the section. Consequently, these plots may not allow as much information to

be gathered and inferred as a cross section that was specifically instrumented to monitor the

temperature gradient. However, these plots will still be helpful in determining how the bridge

responds to temperature changes and if the bridge performed within AASHTO guidelines.

Figure 7.3 Temperature Gradient Over the Height of the Section (Bosworth, 2007)

7.3 Results and Conclusion

Temperature gradients in the VGCS were studied with two main goals: to preliminarily

assess if the bridge behaves as the AASHTO Code predicts, and to lay the foundation for future

studies of temperature gradients.

Results of the maximum and minimum temperature gradients in Segment 26NB14 were

plotted for October, November, December of 2005 and January, February, March, April and

Page 62: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

5

September of 2006. It should be noted that the accuracy of the thermistors is +/- 0.5ºC, or +/-

0.9ºF. This amount of error could have a significant effect on the shape of the temperature

gradients, as will be seen in the following figures, as often the range of temperatures for a

temperature gradient was at most 8ºF. Depending on which way the individual thermistors err,

the range of 8ºF could easily decrease to almost 6ºF or increase to nearly 10ºF.

Plots of the Positive Temperature Gradients were fairly consistent for most of the eight

months of collected data. This consistency was in the shape of the gradient, while the actual

temperatures varied.

Consistency, however, was not the only attribute to observe from the temperature

gradients; comparison of the actual gradients to the design gradient was done as well. It was

found by inspecting the plots that the actual gradients follow and typically fall within the design

gradient. One interesting similarity in the positive temperature gradient plots is that one or two

of the upper gages, Gage VTHL and VTHT, was consistently colder than the bottom slab gage

VBEL. This anomaly could be explained by the gage being located in a spot where it is

surrounded by more concrete than other gages and that at the time of the maximum positive

temperature gradient occurring the concrete immediately surrounding the gage did not have

sufficient time to warm up as did gage VBEL. Lastly, the upper-most gages all fell within the

design code, reaching upwards of 8ºF warmer than gage VBEL, while the design code

temperature difference is 11ºF for the cross section at the height of those gages.

Plots of the negative temperature gradients were not as consistent as the positive

temperature gradients, however, they were still insightful. Plots for two of the eight months of

negative temperature gradients followed the general idea of the top slab being colder than the

bottom slab, while the other six months actually were positive temperature gradients, indicating

that negative temperature gradients never occurred during those months. Looking at the

temperature difference in December between the coldest top slab gage and gage VBEL, it was

found that this value was within the specified code value of 3.3ºF. However, in November, the

gradient was not a maximum between the top-most gage and gage VBEL, it was between the one

upper gage and the top-most gage. This could be explained in a similar way as in the positive

temperature gradients when the gage takes longer to be affected by temperature changes since it

is embedded deeper in concrete than other gages.

Page 63: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

6

Based on the results from the small set of data used, it can be said that the VGCS behaves

within reason to the AASHTO Design Code. Sometimes the gradient didn’t follow the code

well, as seen with the variability in even the well-behaved positive temperature gradients, or the

two negative temperature gradients that occurred. However, taking into consideration the error

of the thermistors, the variability of temperature cycles, the fast-changing weather patterns of

northwest Ohio and the small data set available, the results were reasonable enough to indicate

that the bridge performed within the code. Based on the confirmation of the thermistors and the

preliminary results from eight months of temperature data, it is recommended that temperature

gradients in the instrumented bridge segments are studied for long periods of time, on the order

of years, using the framework from this thesis and the Ph.D dissertation by Nimse (Nimse, 2007)

as a basis.

The fact that only two of the eight months produced negative temperature gradients

demonstrates that negative temperature gradients do not occur very often, and underlines the

importance of studying temperature gradients and analyzing several years’ worth of data versus

several months.

References

1. Bosworth, K. J. 2007. “Health monitoring of the veterans' glass city skyway: vibrating wire

strain gage testing, study of temperature gradients and a baseline truck test.” Master’s thesis,

The University of Toledo.

2. Nimse, P.S., 2007, “Calibrated Baseline Model of a Large Cable-Stayed Bridge.” Ph. D.

Dissertation, The University of Toledo.

Page 64: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

1

Chapter 8 A Baseline Truck Test to Calibrate a Baseline Model

8.1 Introduction

There are several purposes for carrying out the truck test on the VGCS that occurred on

June 17th, 2007. The main purpose of the truck test, which employed both static and dynamic

loading, is to gather strain information that will be the baseline for the long-term monitoring of

the bridge. This baseline has set the stage for future truck tests to be run, and by integrating the

baseline with other information, researchers will be able to monitor the health of the bridge.

A second purpose of the truck test is to further confirm the Larsa model, a finite element

model created by Nimse (Nimse, 2007), by checking if the strains predicted by the model match

with the strain data collected during the truck test.

Two types of strain gages are installed on the VGCS, Geokon vibrating wire strain gages

and bonded electrical-resistance (foil) strain gages. In the main span segments of the bridge,

vibrating wire and foil gages are paired together embedded in the concrete (see fig. 8.1 for

instrumented segments). While the electrical-resistance strain gages are well-suited for rapidly

changing loading conditions, the vibrating wire strain gages excel in long-term monitoring. For

the dynamic truck tests, in which the trucks traveled at speeds of about 10mph, only data from

the electrical-resistance strain gages will be used. However, for the static truck tests, readings

from both vibrating wire gages and electrical resistance strain gages will be reviewed. Due to the

limitation of vibrating wire strain gages only taking readings at most once per minute, the trucks

will be required to remain in the appropriate loading location for a minimum of 5 minutes to

obtain several readings.

Fig. 8.1 Instrumented Sections

Page 65: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

2

8.2 Truck Test

In order to obtain the best results and an acceptable response of the bridge, from the truck test,

previous tests, such as Crane Withdrawal and Mini Truck tests (Bosworth, 2007) performed

during construction and subsequent analyses have been investigated, along with model output.

Influence lines for each instrumented segment were analyzed to find the locations of the

maximum and minimum strains outputted by the Larsa model, which clearly shows the locations

of maximum positive and negative moments. These locations were then used to place the trucks

in the static load cases in order to obtain the maximum response of the gages.

A total of 25 configurations were planned and carried out for the Truck Test. These

configurations fell into two main categories: static and dynamic. The static tests focused on

maximizing the response from the gages, with typical loadings as well as worst-case scenario

loadings. Dynamic tests focused on obtaining influence lines for the main span, which tracks the

gage response as the loads moved across the bridge. Both static and dynamic tests were further

categorized depending on the positions of the trucks, including symmetrical and asymmetrical

cases about the longitudinal axis of the bridge. Some of the asymmetrical cases were aimed

specifically at tracking the effect of placing loads at differing lateral positions. Figure 8.2 shows

the main span of the bridge labeling specific piers, spans between piers and instrumented

segments.

Fig. 8.2 Mainspan of Bridge, Plus Span 25 and Span 30

The goal of performing static load tests was to maximize the strain response from the

gages by placing trucks in varying configurations. For most static cases, the trucks started at a

location that was off the main-span of the bridge, south of Pier 26 in order to provide zero

readings in the vibrating wire and foil strain gages. Then, the trucks moved into their appropriate

positions according to previously planned configuration, recording the time that the trucks

reached the position. Once in position, the lateral position of the trucks was determined by

Page 66: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

3

measurements from the interior barrier or exterior parapet. The lateral positions were very

important to obtain so that the trucks could be placed in the computer model at the correct

position and then the results from the computer model could be compared to the field results with

confidence. After recording the lateral positions of the trucks, the trucks remained in position

until they had been there for a minimum of 5 minutes so that the vibrating wire strain gages,

which collect strain data at a rate of one data point per minute, could record a sufficient amount

of data.

The main goal of the dynamic load tests was to obtain influence lines for various

configurations of trucks. Similar to the static load test, dynamic tests simulated typical loadings

such as two trucks driving side by side on the bridge, as well as heavier loadings where three

trucks drove side by side down one side of the bridge, maintaining in line positions with each

other while driving side by side, and a relatively slow speed of 10mph was used to keep the

trucks moving together. For all dynamic tests, the trucks started from rest at the center of Span

25, the span just south of the mainspan of the bridge. Trucks in this test moved across the bridge

and as soon as they crossed the expansion joint, time was recorded and two data acquisition

systems recorded data. When possible, the team data recorder noted the times when the trucks

passed landmarks on the bridge, such as the center of the pylon, or a particular stay anchor,

which was useful in determining the speed of the trucks as well as being able to match strain data

with locations of the trucks at particular times.

8.3 Load Cases

Symmetrical load cases were used to check symmetry on the bridge. Checking the

symmetry of the bridge is a valuable use of time since the bridge was designed and was

anticipated to act symmetrically. In order to check symmetry, load cases were run in pairs; for

example, one test would entail two trucks driving down the Northbound side of the bridge,

followed by a test with two trucks driven down the Southbound side of the bridge. Then,

according to symmetry, the results of the trucks driving down the Northbound lanes should be

theoretically equal to the results from the test where trucks drove down the Southbound lanes.

Another type of load case used for the Truck Test was created to be able to check the

superposition of loads on the bridge. Using the principle of superposition is a fairly common

task in structural engineering, as most loadings are not high enough to cause non-linear effects.

Page 67: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

4

While common, it is still highly valuable to confirm that the principle of superposition can be

used for the Truck Test since it is a basic assumption in the model.

8.4 Results

While 25 load cases were run on the day of the Truck Test, Bosworth work (Bosworth,

2007) discussed a small subset of load cases, covering the ideas of influence lines, symmetry and

superposition of loads.

One important step in analyzing the results of the Truck Test was to filter the noise from

the foil gage data. In order to do so, an ideal fft-ifft (Fast Fourier Transform-Inverse Fast Fourier

Transform) filter was created in Matlab. By removing the high frequency portion of the signal

considered to be noise, the remaining data was the desired strain signal. It was important to filter

the data to clearly obtain the values of the maximum and minimum strains and where they

occurred.

After processing and reviewing the data from the truck test it was found that good data

was collected from about 95% of the gages installed on the VGCS. Fortunately, all gages that

had no valuable data are located in the top slab of the segments, where there are five other gage

pairs. This is a much better situation than losing the one gage pair in the web, WDL, or the one

bottom slab gage, BFL, as these gages are the only ones in their respective height of section.

For analyzing the results of the Truck Test, influence lines from the model were

compared to the influence lines obtained from the dynamic truck load cases. In order to compare

the Larsa influence line to the influence line obtained from the foil gages, bottom slab gage BFL

was selected since positive moment in the segment leads to tension in the bottom, or positive

strain . When analyzing the two figures, two ideas were kept in mind to account for dimensional

irregularities, even though the general shape of both figures was the same. The model output

plotted the influence line as Moment vs. Load Position; however, data from the foil gages was

outputted initially as Strain vs. Time. These irregularities were overcome by understanding that

on the y-axis, moment is a function of strain, so while the dimensions don’t match, moment and

strain are related to each other in a linear fashion. Similarly for the x-axis, since the trucks

maintained a constant speed while driving across the bridge, the values of time were used to

determine the load position with the simple velocity equation with no acceleration. Therefore,

with those two ideas in mind, simply comparing the shape of the influence lines was sufficient

Page 68: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

5

for confirming the Larsa model. To further confirm the model, the locations of maximum

response were compared. In the model, the maximum positive moment is predicted at a position

of 1020 ft, while the maximum positive strain obtained from the load test occurred at 1005 ft.

When looking at the entire mainspan of the bridge, which is 1525 ft, a difference of 15 ft was

certainly within acceptable error ranges.

Symmetry of the VGCS was checked with the results of the Truck Test, which was

important because knowing that the bridge behaves symmetrically confirms that the bridge was

built as according to the plans and that the bridge was in fact designed with the Northbound side

of the bridge the same as the Southbound side of the bridge. In order to check symmetry, three

dynamic load cases were analyzed: Load Cases 6.2, 7.2 and 9.2. Plots of Microstrain vs. Time

was generated and showed, as expected, that the results for Northbound gages when the trucks

were on the Northbound side of the bridge matched quite well with the results for Southbound

gages when the trucks were on the Southbound side of the bridge.

The principle of superposition was also checked with the results of the Truck Test. In

order to check superposition, the same load cases as used for checking symmetry were used.

Based on the principle of superposition, adding the strain response for gage SBFL when the

Southbound side of the bridge was loaded (SBFLSB) to the strain readings for gage SBFL when

the Northbound side of the bridge was loaded (SBFLNB) was equal to the strain for gage SBFL

when both sides of the bridge were loaded (SBFLBB). Similarly, gages STFL, NBFL and NTFL

were analyzed, adding the maximum positive strain response for BFL gages and the maximum

negative strain response for TFL gages: the difference between the sum of the individual

responses and the response from both sides being loaded was 3με for NBFL. This error is small

and confirms that the principle of superposition holds for the bridge under the loads during the

truck test.

8.5 Model Calibration

The objective was to utilize a sparse, relatively inexpensive instrumentation array to

measure response for plan truck load test, and use this measured response to verify design

assumptions and to complete the baseline progressive calibration of the finite element model.

Page 69: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

6

From the available pseudo static tests, Nimse used the bridge measured response for

model calibration (Nimse, 2007). All the gage responses were studied and compared with the

strains calculated from the model (model output).

The design model, as well as, the model that was proposed by Nimse (Nimse, 2007),

were based on the assumption of linear behavior. The measured response returned back to zero

once the load has passed off the bridge. the response was continuous and without any

discontinuity. Hence, this confirms that the proposed model (Nimse, 2007) was a linear model

and the model analysis was linear analysis which confirms that the bridge behaves linearly in the

load range it was exposed. In addition the Design assumption of symmetrical response was also

confirmed.

It was also concluded that the non-structural component such as the ODOT traffic barrier do not

contribute to the cross-sectional stiffness as assumed.

Another feature of the VGCS bridge design is that it has redundancy built into it. It was

confirmed in both the measured response and model results that the bridge can operate with a

missing stay.

With close correlation between the model output and the measured response it can be

concluded that the VGCS finite element model has been progressively calibrated and the load

ratings generated using this model are baseline ratings. The model, which captured baseline

information and was progressively calibrated, is very robust, can handle a variety of loading and

boundary conditions and, hence, can serve as a reliable maintenance tool.

8.6 Conclusion

The Truck Test was planned and run with two main goals in mind. One goal was to

obtain baseline readings of the bridge so that future load tests could be run and the two sets of

data could be compared. Comparing the data sets will be useful when assessing the health of the

bridge, as increased levels of strain could indicate a loss of structural integrity such as excessive

concrete cracking, or post-tensioning strand deterioration. The other main goal of the Truck Test

was to confirm the Larsa model. By comparing the influence lines with the dynamic loading

data, the model was confirmed. This confirmed model can be used in the future to predict

stresses, strains or moments for any load configurations for future truck tests. The model could

also be calibrated in the future to account for structural deficiencies found during future truck

Page 70: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

7

tests. With a model calibrated for structural deficiencies, it would be possible to look at any

point in the bridge and determine if there were any sections which were overstressed, or could

potentially become overstressed if further deterioration occurred. Thus, the health of the bridge

could be monitored over time and structural repairs could be suggested based on any

deterioration found either through visual inspection or by increases in strains from a truck load

test (Nimse, 2007).

References

1. Bosworth, K. J. 2007. “Health monitoring of the veterans' glass city skyway: vibrating wire

strain gage testing, study of temperature gradients and a baseline truck test.” Master’s thesis,

The University of Toledo.

2. Nimse, P.S., 2007, “Calibrated Baseline Model of a Large Cable-Stayed Bridge.” Ph. D.

Dissertation, The University of Toledo.

Page 71: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

1

Chapter 9 Delta Frame Monitoring and Calibration

9.1 Introduction

Delta frames are critical elements in the structure of the VGCS cable stayed bridge. They

are triangular elements which carry live and dead loads from the twin box segments (Fig. 9.2) to

the stay cables. The VGCS delta frames were difficult to model because of their geometry,

changing boundary conditions associated with various construction stages and also since they

were subjected to heavy post tensioning. This led to two basic problems: development of an

accurate finite element model and potential cracking during post-tensioning, handling and

erection. Also, because the delta frame model was to be used in a larger model of the entire

bridge, an accurate model was essential. On the other hand, development of cracks may have

resulted in maintenance problems and would have shortened the service life of the delta frames.

These problems were resolved using a sparse instrument array.

This chapter will address four important sections associated with the delta frame: 1) basic

delta frame instrumentation and data collection, 2) comparative analysis of measured data

against design calculations, 3) monitoring of the delta frame and develop a calibrated finite

element model of the delta frame, and 4) measuring the changes in strain in the delta frame lower

chord due to two events: the tensioning of the DF-4 tendon and the stressing of the stay.

Figure 9.1 Bridge cross-section at stay anchorage point. Delta frame and two box

segments

Page 72: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

2

9.2 Basic Delta Frame Instrumentation and Data Collection

Delta frame no.18B (the eighteenth delta frame on the back span) was selected for

instrumentation since it was among the first to be cast (Fig. 9.2). The gages used were vibrating

wire gages model 4200 (embedment) and 4911 (sister bar) manufactured by Geokon (Geokon,

1997). Both the models came equipped with built-in thermistors for temperature monitoring and

thermal correction. The gages were located in regions of expected high tensile strains in the

bottom chord based on a centroidal deflected shape generated by a two dimensional model

simulating tendons DF1 through DF3 post-tensioning effects.

The gage output includes the effects of axial and bending forces. Because the crucial

piece of information to be acquired was the tensile strain and cracking was a possibility, one

gage of each type was put at the same vertical elevation at each section.

Figure 9.2 Main span of VGCS with location of delta frame 18B (looking west)

To minimize cost, only two gages were placed at each instrumented section. Since both

gages were at the same elevation, their readings were not independent. This meant the gages can

not independently capture the axial and bending force at a section. Therefore, the finite element

model must capture the internal forces and overall behavior. Thus, the gage configuration

selected is a sparse economic array that captured the desired strains, had sufficient redundancy,

and had the potential to be used to verify the finite element model.

Page 73: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

3

Data was continuously collected beginning the day when the delta frame was cast. This

data was collected at 15 minute intervals. The strain data was also collected at 15-minute

intervals during the initial post-tensioning and at one-minute intervals during for the final post-

tensioning. The collected data was transferred to a laptop computer which was hooked to the data

logger on visits to the casting yard, mostly coinciding with battery changes.

9.3 Monitor the delta frame and develop a calibrated finite element model of the delta

frame

Nimse (2007) utilized Larsa 4D [Larsa, 2007] to simulate the staged post-tensioning DF1

to DF3 and the construction sequence and subsequent final post-tensioning. Only beam elements

were used to develop these models since Larsa can incorporate tendons only with beam

elements. The structural information, including geometry, section properties, material properties

for both concrete, non-prestressed and post-tensioning steel, and tendon geometry was derived

from the as-built construction drawings. The construction event timings came from the post-

tensioning logs and information provided by the contractor. The global torsional degree of

freedom, rotation about the x axis, was released.

Since the short-term elastic strains used for calibration reflect only the change in response

of the delta frame for individual post-tensioning events, only member stiffnesses were involved

in the analysis. Member mass and long term effects had no influence.

Fig. 9.3 shows the model developed for the initial post-tensioning phase. The supports

were provided at the three locations, two on the bottom chord beam elements (Y, Z translation

constrained) and one at the top most point (x translation constrained). Each of the post-

tensioning stages DF1 to DF3 was set as a construction stage and Larsa stage construction

analysis was carried out.

Effects of parameters, such as the stiffness of the members, used to simulate the stay

anchor block and the tendon anchor block were observed. These particular elements of the delta

frame were critical to simulate observed response since the load from post tensioning goes to the

bottom chord through these elements. It was found that rigid beam elements with dimensions

summing up to that of the 3D block geometry, (Fig. 9.3) were able to simulate the behavior

matching the measured response. A short study on how different combinations of support

Page 74: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

4

constraints simulated in the model affected the comparison between the analytical data and the

measured response was done before arriving at the final support conditions.

Figure 9.3 Delta frame model for initial post tensioning

9.4 Comparative Analysis of Measured Data against Design Calculations

In correlating the analytical output from the models with the recorded data, the following

assumptions were made:

1) The strains were recorded at the gage location which was measured at the center of the

gage. Though the sister and vibrating wire gages integrate the strain over their lengths the

assumption is only strictly valid as long as the bending moment diagram is linear over the

length of the gage and acceptable linearity was verified by the finite element model.

2) The contribution of time dependent effects in concrete like creep, shrinkage and

relaxation are negligible over few hours duration of post-tensioning of tendons DF2-

DF3-DF1and DF4.

3) Plane sections remain plane before and after post-tensioning.

4) Concrete is homogenous.

The stresses obtained from the Larsa model were converted to strains and were compared

with the measured data. As explained in the data reduction section, the short term effects, the

initial and final post-tensioning were considered separately. For initial post-tensioning, the datum

was selected as a strain level just before the DF2 post-tensioning was started and the final

reading corresponded to a strain level when DF1 stressing was completed. Therefore, the isolated

strain values have the cumulative effect of DF2 to DF1 stressing. Then changes (parametric

changes such as member stiffness and support conditions) were made in the model so as to get a

better fit between the actual and analytical strains. Once an acceptable match was obtained this

Page 75: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

5

model was made a part of the second phase model with other bridge elements and a similar

procedure was followed.

The comparison between measured strains and model output (analytical strains) showed a

good correlation. Once the model was calibrated, the centroidal forces were used to calculate the

surface strains for both stages of post tensioning.

Since total strain levels were required to be checked against cracking, corresponding dead

load strains were added to both ends of initial post-tensioning and final post-tensioning strains.

Samples of concrete were taken while the delta frame was being cast. The average compressive

strength was found to be 7813 psi and modulus of rupture as 802 psi when tested at the

University of Toledo. The compressive strength was used to calculate modulus of elasticity for

the initial post tensioning whereas for final post tensioning the modulus was calculated based on

CEB-FIP90 [ - code equations. The results showed the

strain level verification for initial and final post tensioning events. They also showed surface

strains from the calibrated model for locations other than the gage location. These additional

locations are shown in Fig. 9.1. The delta frame was also inspected [Nims, D.K., 2006] in the

field after the initial post-tensioning and after the second post tensioning for cracks. No cracks

were found.

9.5 Measuring the changes in strain in the delta frame lower chord due to two events:

the tensioning of the DF-4 tendon and the stressing of the stay

Nimse (2007) studies the response of delta frame post tensioning after reducing the data

to isolate response of each of the post tensioning stages. DF2, which lies in the same vertical

plane as gages 18BSNTO, 18BVSTO and 18BSSBI, was tensioned; these gages went in

compression due to the moment about the vertical axis (Myy). Whereas, the gages on the positive

z-axis were in tension due to moment Myy. DF2 is in the arm on the south bound side of the delta

frame, but similar effects were seen in the north bound arm. The difference was that the change

in strain was smaller on the north bound side. Thus, DF2 tensioning created an asymmetric stress

field. When DF3, which runs through both the north and south bound arms and lies on the

positive side of the z-axis (Fig. 9.5), was tensioned it had similar effects. Even after DF3 was

tensioned, the delta frame was still asymmetrically post tensioned. Since DF3 goes from one

tendon anchor block to the other, it also pushed the stay anchor block (Fig. 9.4) down and the

Page 76: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

6

load was transferred through the V-strut to the central part of the bottom chord bending it

downwards.

Figure 9.4 Delta frame with tendons. Plan view [Carballo et. el. 2006]

Figure 9.5 A typical pair of instrumented segments with approximate gage locations (cross-

section, facing north)

Page 77: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

7

Figure 9.6 Plan view of delta frame bottom chord

As a result, the four gages near the V-strut showed tension and the gages at the tendon

anchor blocks showed compression. The tensioning of DF1 led to symmetry in stress field due to

post-tensioning. All four gages at the anchor blocks were in compression and all four gages in

the center were in tension. This agreed with the shape predicted before tensioning. After DF-1, 2

and 3 were tensioned the delta frame was laid on its side in the casting yard for eighteen months.

At the end of the storage period, DF-18B was then shipped to the site and moved into

final position where DF-4 was tightened. DF4 (Fig. 9.4) lies on the centerline in the XZ plane so

tensioning of DF4 had an effect similar to tensioning DF-3. DF-4 compressed the tendon

carrying arms, moving the stay anchor block down relative to the tendon anchor blocks and

induced additional tension in the critical regions of the bottom chord.

The deformation of DF-18B when DF-4 was stressed was constrained because of the

construction supports. At the deck level, the stay anchor block was prevented from moving freely

because of the median slab in place and also since the transverse tendons were stressed (Fig.

9.4). At the bottom of the delta frame, tendon anchor blocks were locked into the segments on

both sides by pouring concrete into the gaps in the keyways making them part of the segment

webs on both sides. Thus, the stiffness of the entire cross-section came into play and the

movement of the delta frame was restricted. Despite these constraints, as expected, the tension in

all the gages increased which was incorporated in the model calibration and the strain

verification process.

Page 78: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

8

9.6 Delta frame – Conclusion

During Nimse (2007) work, a sparse array of instrumentation concentrated in areas of

high strain was used to resolve uncertainties in modeling of a complex element of a cable stayed

bridge. After calibration, the element model was used to verify that there was no cracking before

service. Finally, the calibrated model of the element can be placed confidently in a model of the

overall bridge. Also, the VGCS delta frames were heavily post tensioned during construction,

inducing tension in the bottom chord. This could have potentially lead to development of cracks.

Therefore, the bottom chord of VGCS delta frame 18B was instrumented in a few critical

locations with the highest expected tensile strains to verify strain levels corresponding to critical

post tensioning events. A relatively inexpensive sparse instrument array was installed and the

measured response against the post tensioning events was used to develop a calibrated

component model of the delta frame. First the model was calibrated against initial post

tensioning and then used to generate surface strains for the initial post tensioning plus self

weight. These strains were then checked against the cracking strain. Then this calibrated model

was fit into a complex model of the cross section and the calibration was verified at this stage

against measured response from final post tensioning. Surface strain levels at this stage were also

checked against cracking. It was found that at both stages of post tensioning the surface strains

were well below the cracking level. Since the final loading of the delta frame is stay stressing

which induces compression in the delta frame bottom chord, it can be concluded that the bottom

chord of the delta frame did not crack due to construction loads. This conclusion was also

supported by the visual inspection of the delta frame done during construction.

Since the VGCS Bridge is instrumented for long term monitoring, the calibrated model of

the delta frame which showed good correlation to measured response during the second post-

tensioning was now ready to be used as a component of the full bridge model. Therefore, this

work also contributes towards developing long term maintenance planning of VGCS. Though the

efforts were directed towards expected problems at the VGCS, the verification of delta frame

behavior under various construction arrangements will, provide more support for their use in this

future.

References

1. N s P.S. 2007 “ B s M f L g -S y B g .” Ph. D.

Dissertation, The University of Toledo.

Page 79: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

1

Chapter 10 Use Intermediate Construction Live Loads for Progressive

Calibration

10.1 Introduction

Progressive calibration is calibrating the finite element model developed for intermediate

construction stages against construction loads when the structure geometry is incomplete and the

boundary conditions are changing. Progressive calibration instills more confidence in the use of

the model, as the model is checked for varying structural geometries and loading conditions and,

therefore, is more robust. The model calibration procedure provides an opportunity to capture as-

built procedures and is tuned against a variety of loading and boundary conditions. Generally, the

model is calibrated using the measured response from truck load tests conducted just before the

bridge is opened to traffic.

The process of calibrating the VGCS Bridge began with determining if the data collected

was acceptable. Therefore, the first objective was to study the quality of the data collection

mechanism used for live load tests; and to check the performance of the instrument suite. After

the data quality was confirmed, the test data was used to calibrate the model for construction live

loads. This objective is very important in the context of the ultimate goal of developing a

calibrated finite element model, which is also calibrated “progressively” through construction.

The second sub-objective was to use data collected during these tests to plan the final truck load

tests.

VGCS bridge segments were instrumented during casting and data was acquired

continuously since casting. Therefore, it was a unique opportunity to monitor the measured

response from casting, through storage, then erection and on into service. It was decided to

calibrate the model progressively through construction since the VGCS had a sparse

instrumentation array and only four sections in the bridge are instrumented. There are advantages

to developing a calibrated model progressively. First, calibration during construction provides

useful measurements and analytical results that assist in generating plans for the final truck load

test. It provides a better understanding of quality of the measured response, the effectiveness of

the instrumentation suite, the bridge behavior and it confirms the design assumptions for the

construction loads. This is especially important because the bridge is subjected to some of the

heaviest loads and largest deformations in its life during construction while the bridge stiffness is

reduced and geometry is changing. Finally, the range and variety of construction loads enhance

Page 80: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

2

the calibration of the model by making it more robust. This increases the confidence that the

model can sensitively and accurately reflect future changes. This is very significant since the

final baseline model developed as part of the VGCS monitoring program will be used to monitor

long term changes.

For the VGCS, the first opportunity to progressively calibrate the model against

construction live loads was presented when the segment hauler transported the segments across

the bridge to the tip of the cantilever span as the cantilever advanced. A second opportunity was

available when the Demag AC400 cranes used to hoist and install the segments and the delta

frames onto the cantilever span, were driven off the bridge. This crane withdrawal occurred close

to end of construction, but before closure. This chapter describes these construction live load

tests, the instrumentation response study and development of a calibrated model using these

construction live loads. In the coming sections a study of the response to understand the quality

of measured data and bridge behavior is presented. This is followed by a description of finite

element model calibration.

10.2 Construction Live Load Bridge Model

Fig. 10.1 is a typical isometric elevation of the bridge model developed to simulate the

crane roll-off and segment hauler movement events.

Figure 10.1 Isometric view of the model for segment hauler tests. For crane roll off one stay and

four segments are added and the rest remain the same.

Page 81: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

3

The segment hauler model has 3486 beam elements and 36 cable elements. There were

six spring elements used, two for pier 26 (North Bound (NB) and South Bound (SB)), two for

pier 27 (NB&SB) and two for pier 27A (NB&SB). The stiffnesses assigned were combined

effects of the supporting piers and bearings [IBT, 2005]. In the case of pier 26 and 27, it was a

combination of the concrete permanent pier and the bearing placed on top of it. For pier 27A, it

was a combination of the temporary steel pier and the bearing placed on top of it. For progressive

calibration, it served as an excellent check to insure the structural framework developed to

simulate the stiffness of the bridge and flow of forces matches the actual bridge response to the

construction live loads.

The dynamic load (segment hauler) path was determined by construction arrangements.

Per the construction specification, as far as possible, the loaded segment haulers were supposed

to move along the center of each of the twin box girders. The bridge lane which carries the

dynamic loads was assumed as the width along the center line of the segments.

The static load positions were governed by the location of the instrumented segments.

The only construction live load used for static loads is that of the Demag crane. When the crane

rolled-off the bridge these static tests were conducted. The crane was stopped at instrumented

segments for three to four minutes and data was collected by the vibrating wire gages.

10.3 Test Description

The process of calibration began with determining if the data collected was acceptable.

Therefore, the first objective was to study the quality of the data collected and to check the

performance of the instrument suite. The criteria for data quality checking were 1) the

reproducibility under repeated loadings and 2) any drift during individual tests. The second

objective was to gain some insight into the basic bridge behavior during construction based on

the design assumptions. The assumptions verified were symmetric response and elastic behavior,

which allowed linear superposition. The final objective was that of progressive model calibration

done against test records corresponding to the construction stages.

There were twenty-two test records [Ward, 2007] available related to segment hauler

movement. These corresponded to loaded segment hauler movement from pier 26 to the tip of

the cantilever, as well as for the return trip of the empty segment hauler as the construction

progressed. The test record for the crane roll off was broken down into eight subsets. All of these

Page 82: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

4

tests were studied and it was found that the response was consistent and as expected. Pairs of

tests were selected for reproducibility and symmetry.

To perform the reproducibility check on the data quality, a pair of tests was selected in

which the data was collected when the segment hauler was on the return path after delivering the

segment to the tip of the cantilever span. Data collection started in both the cases when the

segment hauler left the pylon and stopped when the segment hauler drove off the bridge on the

back-span side (north bound or south bound back-span side). It was found that the measured

response of two representative gages, a top flange gage and bottom flange gage, was repeatable.

To verify the symmetric response of the bridge, two tests were performed to confirm that gages

located at comparable locations respond and behave similarly. In the first test, date was collected

when the empty segment hauler moved southward over the southbound back-span from pylon to

the south end. Similarly, the second test monitored the movement of the empty segment hauler

on the northbound span as it moved southward over the back-span. After comparison, it was

concluded that the gage response at comparable locations compared well.

In order to confirm the elastic response of the bridge, as well as check drift of the

embedment electrical resistance strain gages (foil gages), a third test was selected. This test was

performed using the dynamic DAS connected to segment 27NB41. The beginning and ending

values of strain were equal to the noise level as the segment hauler passed from the south end of

the main span to the pylon carrying segment 28NB61. It was concluded that the bridge response

is elastic and there is no drift in the strain gages. Similar tests for drift were done throughout the

testing before and after closure.

Once it was established with reproducibility, symmetry and drift testing that the gage

response was reliable and that the bridge response to these loads is linear, the measured values

were used to fine tune the finite element model.

10.4 Model Calibration

The crane roll-off static and crawl speed loadings are especially important for calibration

since it was possible to script the Terex-Demag AC400 crane roll-off movements and because

the roll-off happened at night when the least amount of construction equipment movement

occurred on the bridge. At predetermined locations, these cranes (one each on NB & SB lanes)

were made to pause for three to five minutes to simulate static loading conditions. On the other

Page 83: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

5

hand, the segment hauler tests were used to obtain continuous measured response to compare

with model output. Segment hauler and crane axle loadings were simulated in the bridge model.

First, crane static positions at 28NB28 & 28SB28 and 27NB41 & 27SB41 were used for

comparing measured and analytical results. It was found that the suggested arrangement of beam

elements and rigid elements (Fig. 10.2) works well to simulate the bridge stiffness. Effect of

support conditions was also studied. Since the approach spans to the south of pier 26 were

already constructed, translational restraint in the longitudinal direction (along the X-axis in the

Figure 10.2 Arrangement of beam elements at stay anchor cross-section (Nimse, 2007)

model) gave good results. To begin with, the restrained conditions used to simulate supports,

temporary pier 27A and permanent pier 26 and 27, were such that they had only compressive

stiffnesses and their magnitudes were as suggested in the reports submitted by IBT (IBT, 2005).

But results obtained using these restrains did not compare well with the measured values. After a

few iterative studies and updating the in-situ support condition details, changes were made to the

model. The spring supports at pier 27A (SB & NB) were provided with constraint in vertical

direction (Z axis), since in-situ, these pier segments were connected to the temporary steel pier

using four PT bars to prevent uplift. Since the permanent piers 26 and 27 had elastomeric

bearings with no provision for uplift, only compressive stiffnesses were used. For the temporary

piers, as well as the permanent piers, the stiffnessess provided by IBT, (IBT, 2005) were found to

give comparable results.

Ward compared the measured data to the analytical data and the model output (Ward

2007). The foil gage response of the instrumented segments for cranes for cranes positioned at

the pylon was used as the datum to calculate the response for cranes at segments 28NB28 &

28SB28. For the cranes positioned at 28NB28 & 28SB28, it can be seen that analytical strains

compared well with measured strain for all the instrumented segments. At 27NB04, the

Page 84: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

6

measured response is well within the range of noise and because of that these readings were not

taken into account while making changes to the model. Similarly, for cranes positioned at

27NB41 & 27SB41 only the response at 27NB41 was used for calibration as the rest of the gage

response was in the noise range. Once again the analytical strains compared well with the

measured response for static load crane load positions, the model output was also verified against

segment hauler moving loads.

10.5 Conclusion

In the initial phase of this work, the foundation for performing progressive calibration

was laid. It assured the quality of the data collected. It verified the design assumptions of

linearity and symmetry. Since the project employed a sparse array of instrumentation, achieving

these objectives was important to prove that the instrumentation array was sufficient for carrying

out model calibration.

The uniqueness was in the progressively calibrated model of the bridge. The design

models available for bridges were underlain by design assumptions, predicted responses to

construction procedures and loads. Such design efforts satisfied the code requirements and had

been found to be sufficient enough to ensure the service life and safety of the structure. But they

lack the sophistication and accuracy required to be useful for maintenance purposes. Whereas a

model developed and calibrated progressively is more responsive to changes since it is fine tuned

with changing geometry, stiffness and against a variety of loading conditions. Satisfactory

verification against all monitored construction stages instills confidence in its future use for

inspection and maintenance purposes.

References

1. Ward R. J., 2007, “Short-term Construction Load Monitoring & Transverse Bending of the

Bottom Slab on the I-280 Veteran’s Glass City Skyway” Master Thesis, The University of

Toledo.

2. Nimse, P.S., 2007, “Calibrated Baseline Model of a Large Cable-Stayed Bridge.” Ph. D.

Dissertation, The University of Toledo.

Page 85: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

1

Chapter 11 Strains in the Bottom Slab

11.1 Introduction

This chapter focuses on the investigation of the strain concentration in the floor slab

behind delta frame anchor block (Wright, 2007); and on the additional strain measurements that

were required in the cantilever span in the bottom slab at the strain concentration regions

between the bottom slab and the walls at two locations in span 28 (Ward, 2007). Prior to the

construction of the VGCS, no research had been done investigating the bottom slab bending

behavior of concrete box girders.

The finite element model created by the construction engineer to analyze the transverse

bending of the main span, showed that there was potential for the bending moments due to the

self-weight of the structure to locally exceed the available strength (see Figure 11.1) before the

application of live load. This could lead to future maintenance issues such as cracking. A

separate analysis performed by the design engineer did not show a potential of exceeding the

available strength.

Testing was elected as a method to resolve the difference in the potential high stress

disagreement and reconcile discrepancies between the construction and design engineer as

described in the remainder of this chapter. It was found through testing that the measured strain

levels were significantly less than yield and no cracking at the bottom of the concrete slab was

observed.

A consultant’s finite element model (IBT 2006) showed a stress concentration behind the

delta frame anchor block occurring in the bottom slab of the delta frame segments. Outputs from

the models indicated that the segment weight and the tensioning force of the DF-4 tendon were

creating a high tensile stresses in the bottom slab behind the anchor block. The area was

instrumented using external vibrating wire strain gages. The strains in the floor slab behind the

anchor block were investigated to compare results with the FEM in question. A key element to

study this behavior was determining the actual strains through experimental testing to validate an

FEM model for the bottom slab and show that the stress pattern behind the delta anchor block

from our FEM makes sense.

Page 86: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

2

Additionally, while performing a check of the proposed construction erection sequence,

concerns arose from finite element modeling that there was a potential for the capacity of the

bottom slab to be exceeded in transverse bending (see Figs 11.2 & 11.3 below). For the

transverse bending of the bottom slab, results of the finite element analyses generated by the

construction engineer and the designer were compared with data collected at various construction

stages to determine whether the predicted levels of stress occurred.

11.2 Strain in Bottom Slab Adjacent to Delta Frame Anchor Block Due to DF-4

Tensioning

Early in 2006, finite element models developed by the consultant retained by the

contractor showed areas of high tensile stress in the bottom slabs of delta frame segments behind

the DF-4 anchor block. These high tensile stresses were from the tensioning of the DF-4 tendon

in combination with the segments self-weight.

Three models of the bridge were developed whose analysis results presented potentially

high stress areas. An outside consultant developed the finite element model of the bridge and

presented its analysis to ODOT which was the first to indicate that the delta frame anchor block

areas are under potential high stress, using the segment dead weight and load from the DF-4

tendon. After receiving the consultant’s analysis, FIGG developed their own finite element

model of the design to confirm the consultant’s model. To better understand the stress path from

the tensioning of the DF-4, a simple model was also developed using the program SAP. It was

not a full-scale bridge model, but rather a system consisting of the bottom slabs of 3 segments,

one being the slab containing the DF-4 anchor block. The boundary conditions placed on the

system were made to simulate the actual restraint of the slab. The segment weight was not used

in the analysis; only the DF-4 effect was placed on the system. This model was developed to see

the stress pattern generated from the tensioning behind the DF-4 anchor block, not to produce a

set of comparable analysis results.

The generated model was used to locate the testing instrumentations using external

vibrating wire strain gages to monitor the strain concentration behind the delta frame anchor

block under the segment weight and the tensioning force of the DF-4 tendon; hence, the area was

instrumented. The three gages were installed in a straight line at varying distances behind the

DF-4 block, slightly offset from the center of the tendon so as to not interfere with the tensioning

Page 87: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

3

procedure. The crack meter was installed next to the strain gage nearest the delta block. The

URT stayed on site monitoring the construction progress while frequently downloading and

monitoring readings to ensure the data collector was ready when the tendon was tightened.

Fig. 11.1 Test Setup (Wright, 2007, Fig. 3.7)

11.3 Strain Due to Transverse Bending

The construction engineer created short, medium, and long span models to check various

loading conditions. Short-span model behavior was governed primarily by longitudinal effects

such as primary bending; however, in the medium to long span models, the transverse bending

behavior of the segments began to surpass the longitudinal effects in some regions. Due to the

support conditions of the segment, it was anticipated that the bottom slab could be forced into an

“S” bend (see Figure 11.3), which would cause high stresses on the top of the bottom slab near

the inside web, and also at the bottom of the bottom slab near the outside web. The transverse

bending behavior was caused by the deflection of the outside wall exceeding the deflection of the

Page 88: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

4

inside wall. Since the segments are supported at the delta frame there is a tendency for sag to

develop between the supports as shown in Figure 11.3.

Figure 11.2 Bottom Slab Transverse Bending Moment caused by Unfactored Dead Load

(Ward 2007, Fig. 4.1)

Global models were generated for the entire bridge using plate elements and rigid beam

elements to model the increased stiffness of corner joints. The global models used by both the

construction engineer and the designer were in agreement, but the local models were not. Local

models were composed of three dimensional volume elements to locally focus on typical

sections of differing lengths ranging from 28-feet to 56-feet long.

Page 89: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

5

Boundary conditions for local models were established using the global models. After

analyzing the structure as a whole, section cuts could be taken at each end of the local models to

be created. From these results, the axial forces, shears, and moments could be applied to the

local model to provide accurate representation as well as maintain global equilibrium. The

refined local models prepared by the construction engineer did not significantly reduce the local

effects of the transverse bending, but did provide for more precise locations where high stress

would occur. With these locations, the URT was able to install gages to monitor the transverse

bending behavior.

Figure 11.4 shows an enlargement of the region where maximum bending moments

where predicted to occur. Although higher values of moment occurred directly behind the delta

frame block, the phenomenon has been investigated during prior research by the URT (Wright,

2007) when the effect caused by post-tensioning the segments together was studied.

Figure 11.3 Self-weight deflection (Ward 2007, Fig. 4.2)

Table 11.1 Algor FEA Legend

-8615.5

-10635.0

9560.0

-537.5

-2557.0

-4576.5

-6596.0

7540.5

5521.0

3501.5

Bending Moment

Tensor X-X (ft·lb/ft)

1482.0

Figure 11.4 Enlarged Transverse Bending Moment

Page 90: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

6

Table 11.1 is the legend that corresponds to the transverse bending moment contours

from the finite element analysis performed by the construction engineer.

The connection between the slab and wall was simulated using approximately very stiff

elements. However, the designer noted that the effects of different values for the stiffness of

these elements had a significant effect in the local analyses. By using rigid elements that are

stiffer, the joints experienced little shear strain and will transmit the entire moment to the bottom

slab. Also, the length of the rigid elements in the corner dramatically affected the results of the

stresses near the wall. Rigid elements that are short tend to approximate a reentrant corner with

theoretically infinite stress. By similar logic, if the corner elements are longer, the stresses near

the corner are trend towards a stress with no stress concentration factor. Results from a

preliminary investigation of the overall self-weight deflection confirmed the general shape of

deflection and moment behavior predicted by the construction engineer.

Analysis results from both the construction and design engineer indicated that the highest

transverse bending strains were predicted midway between the delta frame supports where the

differential sag of the inner and outer wall was the largest. This location actually occurred at the

joint between segments 28SB24 and 28SB25.

Based on the results of the FEA performed by the construction engineer, vibrating wire

strain gages were installed on the bottom slab near the intersection of the inside web and bottom

slab in segments fifteen and twenty five of span twenty eight on the southbound side (28SB15

and 28SB25). The gages were concentrated in the portion of the slab nearest the predicted strain

concentrations. Furthermore, since the largest predicted strains could have exceeded the working

range of the normal vibrating wire strain gages (3000με) a vibrating wire crack meter was

installed near the junction of the wing and bottom slab. The crack meter had a working range of

approximately 3mm. To account for this strain at bottom slab due to self-weight deflection, two

simple models were developed. One model consisted of a simply supported slab subject to its

own dead weight, while the other had fixed boundary condition. In this manner, the worst case

possible between the results was used and the estimation was conservative. Combining the

effect of the self weight deflection with the measured results caused by transverse bending

behavior of the segment can be summed and compared with the overall model results.

Page 91: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

7

In order to investigate what effect live load contributed to the overall stresses in the

bottom slab, the gages installed in segment 28SB25 were set to record data during both the crane

withdrawal test and the full scale truck load tests.

11.4 Research Results and Conclusions

Transverse bending of the bottom slab was monitored in order to reconcile discrepancies

in finite element analyses performed by the construction and design engineers. Vibrating wire

strain gages were installed in the bottom slab of segments to monitor transverse bending. Data

was collected during construction, as well as during the truck load test prior to opening the

VGCS to traffic.

Two research studies focused on investigating the concentration of strain in the bottom

slab of the delta frame by comparing the results of the experimental data to the analysis results

provided by the design engineer.

Wright (2007) investigated strain concentrations in the bottom slab of the VGCS caused

by the post-tensioning tendons used to hold the delta frames in place. Results of the research

monitoring strain levels immediately behind the delta frame tension block following the

tensioning of the DF4 tendon indicated that the strain magnitudes attenuated quickly when

moving away from the zone of predicted response (Wright, 2007).

Ward (2007) studied the transverse bending behavior of the bottom slab by monitoring

the slab prior to installation and after the bridge was completed and opened to traffic.

Experimental results at a construction stage prior to stressing stay 8 were compared with analysis

provided by the designer. Experimental results were higher than predicted by the design

engineer, but less than those predicted by the construction engineer. Strains approaching the

yield for reinforcement (approximately 2000με) were not observed at any point during

construction. Strain magnitudes did not exceed 300με for any of the gages installed on the

bottom slab.

Visual inspection following installation of the instrumented segments, as well as

subsequent segments did not reveal any cracking in the bottom slab in the regions where large

strains were predicted. Strain magnitudes from the gages installed on the bottom slab of

Page 92: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

8

segments 28SB15 and 28SB25 have been independently verified to be accurate by performing

lab calibration of the actual gages used in the field (Bosworth 2007).

In addition, data recorded during live load tests including the crane withdrawal and full

scale truckload tests confirms the assertion that dead load bending behavior dominates the

transverse bending capacity of the bottom slab.

Dead load effects caused by the self-weight of the segments and delta frames are the

predominant factor in determining the capacity of the bottom slab in transverse bending of the

bottom slab.

References

1. Ward R. J., 2007, “Short-term Construction Load Monitoring & Transverse Bending of the

Bottom Slab on the I-280 Veteran’s Glass City Skyway” Master Thesis, The University of

Toledo.

2. Wright, B.W., 2007, “Experimental and Analytical Analysis of Concrete Strain

Concentrations on the I-280 Veterans Glass City Skyway Cable Stayed Bridge.” Master’s

Thesis, The University of Toledo.

3. Bosworth, K.J., 2007, “Health Monitoring of the Veterans' Glass City Skyway: Vibrating

Wire Strain Gage Testing, Study of Temperature Gradients and a Baseline Truck Test.”

Master’s Thesis, The University of Toledo

4. Nimse, P.S., 2007, “Calibrated Baseline Model of a Large Cable-Stayed Bridge.” Ph. D.

Dissertation, The University of Toledo.

Page 93: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

1

Chapter 12: Bridge Long Term Analytical and Experimental Responses

12.1 Introduction

In this chapter, the analytical and experimental stresses from the time of stay stressing

through service life up to the present time are compared. Time history of the analytical stresses

in the contractor’s as-built finite element model for staged construction (BD2) is compared to the

time history of the stresses based on the strain data collected. Representative plots for the

comparison are presented.

Stay cable stressing events have a clear signature in the time history line and the exact time

of each event is recorded in the stay cable stressing log. Table 12.1 shows a portion of the stay

cable stressing log for stay 1.

Table 12.1 Stay 1 Stage 1 Cantilever Stressing Log

Stay 1 Stage 1 Cantilever Stressing Log

Strand

No.

Master Load

Cell (kips) Date Time Comments

1 36.5 2006-7-15 9:55 AM Master Strand

2 35 2006-7-15 10:22 AM

3 34.3 2006-7-15 10:32 AM

Check teeth pattern at stage 2. Check for full

overbite of wedge.

4 34 2006-7-15 11:12 AM

5 33.9 2006-7-15 11:21 AM

6 33.6 2006-7-16 11:31 AM Released sheathing onto the strands.

7 35.4 2006-7-16 11:41 AM

8 34.8 2006-7-16 11:50 AM Measured liftoff.

In the log, the master cell force, the date, time and tensioning event are clearly defined. The

tensioning events are also phases in the finite element model so matching the measured strains to

the analytical stresses for these events is straightforward. Then the measured strains are

transformed to measured stresses and the time series of experimental stresses are compared to the

time series of the analytical stresses.

Page 94: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

2

12.2 Analytical stresses

Bridge Design II (BD2) (Interactive Design Systems, 2011) is the finite element software

used for long term modeling from casting construction through service. It is specifically designed

for staged construction of pre- and post-tensioned segmental concrete and cable stayed bridges.

The model used here to find the construction and long term stresses due to permanent loads is the

as-built model developed by International Bridge Technologies for the VGCS contractor. It has

been accepted by Figg and ODOT. During construction the model includes temporary

construction loads as well as other static loads such as deadweight and stay and tendon forces.

During service, all permanent gravity loads and stay and tendon forces are considered.

BD2 defines every construction stage as a corresponding BD2 Phase. Stresses for all

loading conditions can be evaluated at any phase. Stressing, distressing and restressing are

specifically addressed as BD2 phases.

Figure 12.1 Bridge Designer II interface

Figure 12.1 shows the BD2 interface when the database of VGCS was running. The

geometry of VGCS can be viewed in elevation or plan.

Page 95: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

3

The principle task of this study is to understand the long-term behavior of VGCS based on

the comparison of the analytical stress and experimental stress. Since the steady state condition

was of interest, the analytical stress did not consider the temperature gradient. Hence, some

deviation from measured can be attributed to temperature effects.

When necessary, a new construction phase corresponding to the time of data collection was

defined. No changes in the model or loading were made. The new phases simply calculated the

bridge data at required points in time.

Once the new phase is set up, the BD II can evaluate the results of stresses at each segment.

Table 12.2 shows the stress results at bottom of Segment 2806 from day 358 to day 2861. I and J

represent the south and north end of each segment. Segment 306 of the BDII model represents

segments 2806NB and 2806 SB of the bridge. Because the strain gage is near the middle of the

segment, the analytical stress used for comparison is the average of the stresses at the I and J

ends.

Table 12.2 Analytical Stress in Segments 2806NB and 2806SB (kips/ft2)

Date Events

BDII

Seg. bottom

Analytical

Stress at

Bottom

(k/ft2)

I J

2/6/2007

PHASE 4540 (CLOSE MAIN SPAN

AND CAST MEDIAN IN SP29) 306 -147.3 -137.0 -142

2/11/2007

PHASE 4560 (DEACTIVATE PIER

27A) 306 -130.5 -117.6 -124

2/26/2007

PHASE 4580 (REMOVE

MISCELLENEOUS LOADS AT

PYLON) 306 -123.6 -110.8 -117

6/6/2007 PHASE 4600 (Day1460) 306 -146.9 -131.7 -139

*6/24/2007 PHASE 4640( Day 1478) 306 -154.4 -138.6 -146

12/1/2008 PHASE 4650( Day 2000) 306 -183.9 -165.2 -174

1/21/2010 PHASE 4680 (DAY 2415) 306 -182.3 -164.0 -173

3/20/2011 PHASE 4690 (DAY 2840) 306 -181.6 -163.0 -172

Page 96: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

4

12.3 Experimental Strain to Stress Transformation

The experimental stresses are evaluated from the strain data collected during the long-term

monitoring. Based on the elastic relation between stress and strain, experimental stress was

calculated from:

i=Eii - E00 (12.1)

where

i …………………………Experimental stress at construction phases and today

iE…………………………Modulus of elasticity at construction phases and today

i ………………………….Strain data at construction phases and today

0E…………………………Initial modulus of elasticity at an age of 28 days

0 ………………………….Initial strain data at an age of 28 days

In this equation, Young’s Modulus varies with time. The values used were calculated by

BD2 as shown in Figure 12.2, a model developed by Fru-Con utilizing FIP-CEB model code

1990 to simulate the time dependent behavior. This equation can be written to include many

steps in the time history of the segment (Branson, 1977). However, because of the long interval

between casting and erection, one step is sufficient in the present analysis. The strain data were

collected at each instrumented segment. During the long-term monitoring, there are not enough

available strain data at the casting yard. Thus, the initial strain data for each gage needs to be

evaluated with the help of BD 2.

analytical,i=Eii - E00 (12.2)

Using equation 12.2, the initial strain, 0, can be evaluated after substituting the Young’s

Moduli, strain i and an analytical stress from BD2.

Figure 12.1 shows the variation of Young’s Modulus with time. Since Young’s Modulus

(E) varies much more slowly after the first of 28 days. E0 at the age of 28 days 724,000 kips/ft2

(5,030 ksi) was defined as an initial value for the strain to stress transformation.

Page 97: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

5

0 500 1000 1500 2000 2500 3000 3500 40003.5

4

4.5

5

5.5

6

6.5

7

7.5

8

8.5x 10

5

Figure 12.2 Young’s Modulus (kips/ft2) vs. time (days) from BD2 model

The strain data can be obtained at each construction phase (BD2) by comparing the model

stages to the construction log.

Table 12.3 Experimental Stress of Segment 2806NB (kips/ft2)

Date Events

Experi-

mental

Strain

(bottom)

Initial Strain

( 28 Days

after casting)

E

Modulus

From BD2

Initial

E

Modulus

Exper-

imental

stress

Analytical

stress

8/18/

2006

PHASE 125

(STRESS STAY

4A&B - STAGE

1 DAY1186)

1948 2150 734112 723948 -126 -142

6/6/

2007

PHASE 4600

(Day1460) 1857.6 2150 769841 723948 -126 -139

12/1/

2008

PHASE 4650

(Day 2000) 1704.6 2150 800481 723948 -175 -174

1/21/

2010

PHASE 4680

(DAY 2415) 1681 2150 825456 723948 -169 -173

3/20/

2011

PHASE 4690

(DAY 2840) 1621 2150 825456 723948 -219 -172

Page 98: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

6

12.3 Representative Analytical vs. Experimental Stress Comparisons

Fig 12.3 Experimental stress and analytical stress (kips /ft2) at the bottom of segment 2806SB

(Feng 2010)

Fig 12.4 Experimental stress and analytical stress (kips /ft2) at the top of segment 2806NB

(Feng 2010)

Page 99: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

7

Fig 12.5 Experimental stress and analytical stress (kips /ft2) at the bottom of segment 2828NB

(Feng 2010)

Fig 12.6 Experimental stress and analytical stress (kips /ft2) at the top of segment 2828NB

(Feng 2010)

Page 100: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

8

Fig 12.7 Experimental stress and analytical stress (kips /ft2) at the bottom of segment 2704NB

(Feng 2010)

Fig 12.8 Experimental stress and analytical stress (kips /ft2) at the bottom of segment 2704SB

(Feng 2010)

Page 101: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

9

Fig 12.9 Experimental stress and analytical stress (kips /ft2) at the top of segment 2704NB

(Feng 2010)

Fig 12.10 Experimental stress and analytical stress (kips /ft2) at the bottom of segment

2741NB (Feng, 2010)

Page 102: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

10

The stress comparisons at segment 2806 and segment 2828 show a good match in trend and

a reasonable match in value.

Fig 12.11 Experimental stress and analytical (kips /ft2) stress at the top of segment 2741NB

(Feng, 2010)

Segments 2704 and 2741 have few available experimental data during construction. But the

experimental stress comparison between the northbound and southbound segments are a good

match with each other and the experimental stresses present a good fit with analytical stress for

BD2 model.

12.4 Summary of Results

This study verifies that the instrumented segments of VGCS behave as expected for the

period studied.

References

1. Qiao C., 2009, “Analytical and Experimental Stress during Construction of the Veteran’s

Glass City Skyway” Master Thesis, The University of Toledo.

Page 103: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

11

2. Feng X., 2010, “Nondestructive load testing of the Veteran’s Glass City Skyway” Master

Thesis, The University of Toledo.

3. Branson, D., 1977, “Deformation of Concrete Structures”, McGraw-Hill.

4. IDS 2011, Interactive Design Systems, Inc., Bridge Designer II, http://www.ids-soft.com/

5. Yi G., 2011, “Long-term Behavior of the Veteran’s Glass City Skyway Cable Stayed Bridge”

Master Thesis, The University of Toledo.

Page 104: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

1

Chapter 13: Load Rating

13.1 Load Rating Procedure

In this study, the allowable stress (ASR) load rating method was used to evaluate the

inventory load rating factor for analytical and experimental stresses. The following load-rating

equation was used for the load rating of the concrete in each of the instrumented segments.

Effect Load Live

Effect Load DeadCapacity AllowableFactor Rating Load

(Eq. 13.1)

Previous work done by Mr. Bosworth (2007) and Mr. Feng (2010)confirmed that the VGCS

behaves symmetrically. This is illustrated in Figure 13.1.

0 20 40 60 80 100 120 140-15

-10

-5

0

5

10

Time (s)

Data

of

str

ain

gage

Truck Load Test

TruckNBGageNB

TruckSBGageSB

Fig 13.1 NBFL with Northbound loaded and SBFL with Southbound loaded

A good match of the strain comparison (Qiao, 2009) and good match of the stress

comparison as shown in chapter 12 (Figures 12.3 thru 12.11) for each pair of segments

throughout construction verified that dead load effects from the two sides of the bridge are

similar during service (Feng, 2010).

Thus, because of the verified symmetry of the VGCS, this study only evaluates the live load

effect for the northbound segments.

Page 105: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

2

13.2 Development of the Unit Influence Line

To evaluate the live load effect for VGCS, the unit influence line (UIL) need to be

generated by the finite element model (LARSA) and truck load tests. Here the unit influence line

from the LARSA model with the unit influence line derived from the dynamic truck load test. In

the following exercise, the unit load considered is the truck configuration.

Fig 13.2 Second truck load test configuration 16

Fig 13.2 is configuration 16 of the second truck load test. (Four trucks moving north bound

across the main span of VGCS).

20 40 60 80 100 120 140 160 180-10

-8

-6

-4

-2

0

2

4

6

8

Time (s)

Str

ain

gage

dat

a (m

icro

stra

in)

Truck Load Test

Fig 13.3 Data at segment 2806NB measured from the truck load test configuration 15

Page 106: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

3

Figure 13.3 is the strain data for the gage embedded in the middle of the floor at segment

2806 measured from truck load test configuration 16.

The following equations are used to convert this curve to an influence line:

E

x

My

I

xEIM

Wy

Where,

y is the moment arm, or distance of the gage from the neutral axis of the segment

W is the total weight of truck loads

v is the velocity of the live loads in the truck load test

Table 13.1 Geometry properties of segment 2806 from LARSA model

Location Element No. Ix Neutral axis(in) Modulus of Elasticity

(lb/in2)

NBseg2806 20089 39885495 99.67 5098000

Table 13.2 Truck weight information for the four trucks used in second truck load test

Northbound

Truck No. T2643 T2580 T2840 T2739

Truck Type Double Axle Double Axle Double Axle Single Axle

Gross Weight (lb) 45480 47570 46540 27620

For truck load test, all the geometric properties of segment come from the LARSA model.

By using the equations above, the strain time history can be converted to influence line.

Figure 13.4 is the influence line evaluated by strain data from truck load test; whereas figure

13.5 is the influence line obtained from LARSA model at segment 2806. These two curves show

a good match. The maximum value of negative moment from Figure 13.4 is -17.56 kip-ft, and

the maximum value of negative moment from Figure 13.5 is -19.00 kip-ft. The difference

M: Moment Eq. (13.4)

σ: Stress Eq. (13.3)

ε: Strain Eq. (13.2)

Page 107: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

4

between the maximum values of negative moment from Fig. 13.4 and Fig. 13.5 is 7.5%. Thus,

the LARSA model is able to effectively to simulate the structure’s response to live load.

200 400 600 800 1000 1200

-15

-10

-5

0

5

10

span (ft)

Monent

Truck Load Test

Fig 13.4 Converted influence line

Fig 13.5 Influence line from LARSA for segment 2806

Page 108: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

5

From configuration 5 and configuration 17 (figure 13.6 and 13.7 respectively) of second

truck load test (Eight trucks across the main span of VGCS), the strain data can be converted to

the experimental influence line and integrated with the analytical influence line.

Fig 13.6 Second truck load test configuration 5

Fig 13.7 Second truck load test configuration 17

Figures 13.8~13.11 compares the analytical and experimental influence lines for each

instrumented segment.

Page 109: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

6

0 200 400 600 800 1000 1200

-20

-15

-10

-5

0

5

10

span (ft)

Monent (kip

*ft)

Experimental influence line and Analytical influence line

Analytical influence line

Experimental influence line

Fig 13.8 Integrate influence line for segment 2806

0 200 400 600 800 1000 1200

0

10

20

30

40

50

span (ft)

Monent (kip

*ft)

Experimental influence line and Analytical influence line

Analytical influence line

Experimental influence line

Fig 13.9 Integrate influence line for segment 2828

Page 110: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

7

0 200 400 600 800 1000 1200-30

-25

-20

-15

-10

-5

0

5

10

span (ft)

Monent

(kip

*ft

)

Experimental influence line and Analytical influence line

Experimental influence line

Analytical influence line

Fig 13.10 Integrate influence line for segment 2704

0 200 400 600 800 1000 1200

-10

0

10

20

30

40

50

span (ft)

Monent (kip

*ft)

Experimental influence line and Analytical influence line

Analytical influence line

Experimental influence line

Fig 13.11 Integrate influence line for segment 2741

Page 111: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

8

13.3 Live Load Effect

At inventory level, we just consider the design service live loads. The bridge was designed

to handle HS25 live load, as well as two other loadings: Michigan grain truck II and III, one per

traffic direction, (with HS25s in the other lanes), and single military. Following the AASHTO

Bridge Design Manual, the HS25 lane load is suggested as 0.8 kip/ft2 for each lane.

Table 13.3 HS-25 Truck Load Moment Effect for Segment 2806

Positive LL Moment

span Influence Line (kip-ft) Axle load Cumulative Truck Load

Moment (HS-25×8) (kip-ft)

646 7.3 10 587

660 12.6 40 4632

674 5.5 40 6379

Negative LL Moment

span Influence Line (kip-ft) Axle load Cumulative Truck Load

Moment (HS-25×8) (kip-ft)

806 -24.2 10 -1939

820 -24.5 40 -9772

834 -24.4 40 -17566

Table 13.4 Lane Load Effect for Segment 2806

Lane Load Moment (kip-ft) Lane Load Moment × 8

Positive 716 5730

Negative -6175 -49402

Tables 13.3 and Table 13.4 present the analytical HS-25 truck load effect and lane load

effect for segment 2806 evaluated by the integration of the influence line.

According to AASHTO 17th

edition (2002), Section 3.8.2.1, the impact factor for live loads shall

be determined by the formula:

125L

501 IM

(Eq. 13.5)

Where, IM : live load impact factor

L: the loaded length. For continuous spans: the length of span under consideration for

positive moment, and the average of two adjacent loaded spans for negative moment.

Page 112: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

9

The impact factor was calculated and reported in table 13.5 for northbound segments for

both positive and negative moments.

Table 13.5 Impact Factor for Segments 2806, 2828, 2704, and 2741

Segment Impact Factor (IM)

Positive Moment Negative Moment

NB2806 1.07 1.07

NB2828 1.07 1.07

NB2704 1.07 1.1

NB2741 1.07 1.1

The lane load moment effect is shown in table 13.6 due to the lane load effect, while the

adjusted truck moment is shown in table 13.7 due to the truck load effects.

Table 13.6 Lane Load Effect including Impact Factor for Segment 2806

Lane Load

Moment

(kip-ft)

Total Lane Load

Moment (kip-ft) = Lane

Load Moment × 8

Impact

Factor (IM)

Total Lane Load Moment (kip-ft) ×

IM

Positive 5730 1.07 Positive 6131

Negative -49402 1.07 Negative -52860

Table 13.7 Adjusted Truck Load Moment Effect including Impact Factor and Multiple Lane Factor

(0.75) for Segment 2806

Truck Load

Moment

(kip-ft)

Cumulative Truck

Load Moment

(kip-ft)

(table 13.3)

Impact

Factor (IM)

Adjusted Truck Load Moment (kip-ft) =

Cumulative Truck load Moment × IM × 0.75

Positive 6379 1.07 Positive 5119

Negative -17566 1.07 Negative -14097

For maximum positive moment, only one concentrated load shall be used per lane,

combined with as many spans loaded uniformly as are required to produce maximum moment.

For the determination of maximum negative moment in the design of continuous spans, however,

AASHTO Section 3.11.3 specifies that the lane load shown shall be modified by the addition of a

second concentrated load of equal weight placed in one other span in the series in such position

to produce the maximum effect.

Per AASHTO figure 3.7.6B, the additional concentrated load shall be 18 kips for HS20

loading. Since HS25 loading is being considered in this analysis, the 18 kips concentrated load

Page 113: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

10

must be scaled up by 1.25 multiplier. Hence the proportioned 22.5 kips concentrated load is to be

added to the lane load, plus another 22.5 kips concentrated load on other side of support for any

sensor locations governed by negative moment. The total resulting positive and negative

moments from a 22.5 kips point load, are shown in table 13.8 and 13.9 respectively.

Table 13.8 Point Load 22.5 kips Positive Effect at Maximum Influence Line of Two Adjacent

Spans for Segment 2806

Positive LL Moment

1st

span

Influence Line

(kip-ft)

Point

load

Moment (22.5K×8)

(kip-ft)

200 2.4 22.5 432

Positive LL Moment

2nd

span

Influence Line

(kip-ft)

Point

load

Moment (22.5K×8)

(kip-ft)

660 12.6 22.5 2275

Total = Worst Case 2275

Table 13.9 Point Load 22.5 kips Negative Effect at Maximum Influence Line of Two Adjacent

Spans for Segment 2806

Negative LL Moment

1st span

Influence Line

(kip-ft)

Point

load

Moment (22.5K×8)

(kip-ft)

530 -5.3 22.5 -954

Negative LL Moment

2nd

span Influence Line (kip-ft)

Point

load Moment(22.5K×8) (kip-ft)

820 -24.5 22.5 -4406

Total = Add Both Cases -5360

Per AASHTO Section 3.12.1, a reduction in load intensity may be considered where

maximum stresses are produced in any member by loading a number of traffic lanes

simultaneously; therefore, a 75 percent reduction of the live loads may be used for four lanes or

more in view of the improbability of coincident maximum loading. Therefore, table 13.10 shows

the application of a multiple lane factor equal to 0.75 and the segment corresponding impact

factor (from table 13.5) to the cumulative moment effects of lane load and the 22.5 kips point

load from table 13.8 and 13.9 respectively.

Page 114: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

11

Table 13.10 Adjusted Lane Moment Effects of Lane Load plus a 22.5 kips Point Load including

Impact Factor and Multiple Lane Factor (0.75) for Segment 2806

(a) Lane Load

Moment (kip-ft)

(b) Lane

Load Moment

(kip-ft) × 8

lanes

(c) Point

Load LL

Moment

(kip-ft)

(d) Cumulative Lane

Moment = Lane Load

Moment (b) + Point

Load Moment (c)

(kip-ft)

(e) Adjusted Lane

Moment Effects =

Cumulative Lane

Moment (d) × IM × 0.75

(kip-ft)

Positive 716 5730 2275 8005 6424

Negative -6175 -49402 -5360 -54762 -43947

Tables 13.11 shows the calculated stresses due to the adjusted lane moment effects due to

the lane load and the point load from table 13.10. However, table 13.12 shows the calculated

stresses due to adjusted truck load moment effect from table 13.7. By comparing the live lane

load stresses (table 13.11) and the live truck load stresses (table 13.12) for Segment 2806; it is

evident that the live lane load stresses are critical and govern in this case. This is also valid for

the other three segments: 2828, 2704, and 2741.

Table 13.11 Live Lane Load Stresses for Segment 2806

Stresses due to Adjusted Lane Moment Effects (e) from table 13.10 (Segment 2806)

M (kips-in) y (in) Ix (in4) Stress (ksi)

Tension on bottom 77,092 100 39,885,495 0.19

Compression on bottom -527,359 100 39,885,495 -1.32

Compression on top 77,092 46 39,885,495 -0.09

Tension on top -527,359 46 39,885,495 0.61

Table 13.12 Live Truck Load Stresses for Segment 2806

Stresses due to Adjusted Truck Load Moment Effect from table 13.7 (Segment 2806)

M (kips-in) Y (in) Ix (in4) Stress (ksi)

Tension on bottom 76,549 100 39,885,495 0.15

Compression on bottom -210,794 100 39,885,495 -0.42

Compression on top 76,549 46 39,885,495 -0.07

Tension on top -210,794 46 39,885,495 0.20

Page 115: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

12

13.4 Load Rating Procedure

Load rating defines the maximum live load capacity of a bridge. In this study, the

experimental and analytical inventory load rating for the concrete in compression will be

evaluated by the Allowable Stress Rating Method for concrete. The general idea for analytical

load rating is: Load rating factor = (Allowable capacity - Dead load effect) / Live load effect.

The allowable compressive stress of prestressed concrete is -691.2 kip/ft2 (-4.80 ksi), which

comes from design company Figg’s database. The prestressed concrete was specified as fc’

= 8000 psi, which has allowable compressive stress of 0.6 fc’ and allowable tensile stress of

'3 cf according to AASHTO Specification 9.15.2.1.

For the experimental dead load effect, actual stress at day 2840 (03/20/2011) will be used

from the long-term monitoring of VGCS (Yi, 2011).

The influence line can describe the live load effect at each segment by the equation:

x

My

I

Tables 13.13 thru 13.16 shows a load rating comparison among the design, analytical and

experimental results.

Table 13.13 Analytical Load Rating and Experimental Load Rating for Segment 2806

Load Rating For Segment 2806 NB

Stress Seg. 2806NB Location Allowable

Stress (ksi)

Dead Load

Effect (ksi)

Live Load

Effect (ksi)

Load

Rating

LR

Compression Analytical Bottom -4.8 -1.2 -1.32 2.7

Compression Analytical Top -4.8 -1.9 -0.09 32.7

Tension Analytical Bottom 1.03 -1.2 0.19 11.5

Tension Analytical Top 1.03 -1.9 0.61 4.8

Compression Experimental Bottom -4.8 -1.5 -1.12 2.9

Compression Experimental Top -4.8 -2 -0.08 34.2

Tension Experimental Bottom 1.03 -1.5 0.18 14.2

Tension Experimental Top 1.03 -2 0.52 5.9

(Eq. 13.6)

Page 116: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

13

Table 13.14 Analytical Load Rating and Experimental Load Rating for Segment 2828

Load Rating For Segment 2828 NB

Stress Seg. 2828NB Location Allowable

Stress (ksi)

Dead Load

Effect (ksi)

Live Load

Effect (ksi)

Load

Rating

LR

Compression Analytical Bottom -4.80 -2.00 -0.52 5.4

Compression Analytical Top -4.80 -1.60 -0.72 4.5

Tension Analytical Bottom 1.03 -2.00 1.56 1.9

Tension Analytical Top 1.03 -1.60 0.24 10.9

Compression Experimental Bottom -4.8 -2.9 -0.37 5.1

Compression Experimental Top -4.8 -2.2 -0.88 3.0

Tension Experimental Bottom 1.03 -2.9 1.91 2.1

Tension Experimental Top 1.03 -2.2 0.17 18.8

Table 13.15 Analytical Load Rating and Experimental Load Rating for Segment 2704

Load Rating For Segment 2704 NB

Stress Seg. 2704NB Location Allowable

Stress (ksi)

Dead Load

Effect (ksi)

Live Load

Effect (ksi)

Load

Rating

LR

Compression Analytical Bottom -4.8 -1.7 -1.59 2.0

Compression Analytical Top -4.8 -1 -0.26 14.6

Tension Analytical Bottom 1.03 -1.7 0.57 4.8

Tension Analytical Top 1.03 -1 0.73 2.8

Compression Experimental Bottom -4.8 -1.5 -1.75 1.9

Compression Experimental Top -4.8 -1.6 -0.24 13.4

Tension Experimental Bottom 1.03 -1.5 0.52 4.9

Tension Experimental Top 1.03 -1.6 0.81 3.3

Table 13.16 Analytical Load Rating and Experimental Load Rating for Segment 2741

Load Rating For Segment 2741 NB

Stress Seg. 2741NB Location Allowable

Stress (ksi)

Dead Load

Effect (ksi)

Live Load

Effect

(ksi)

Load

Rating

LR

Compression Analytical Bottom -4.80 -0.9 -0.53 7.3

Compression Analytical Top -4.80 -2.1 -0.58 4.7

Tension Analytical Bottom 1.03 -0.9 1.25 1.5

Tension Analytical Top 1.03 -2.1 0.24 12.8

Compression Experimental Bottom -4.8 -1.1 -0.77 4.8

Compression Experimental Top -4.8 -2.2 -0.66 3.9

Tension Experimental Bottom 1.03 -1.1 1.43 1.5

Tension Experimental Top 1.03 -2.2 0.35 9.1

Page 117: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

14

13.5 Load Rating Summary

The analytical and experimental influence lines have a good fit. Therefore, the load rating

values in the analytical and experimental results are in agreement. It is noteworthy to mention

that there are slight differences in some load rating values when the peaks of analytical and

experimental influence lines occur within several feet from each other in the same span;

however, differences are hardly noticeable and are rather insignificant. The calculated load rating

from the analytical and the experimental tests should be close to what was intended in the design.

References

1. Bosworth, K.J., 2007, “Health Monitoring of the Veterans' Glass City Skyway: Vibrating

Wire Strain Gage Testing, Study of Temperature Gradients and a Baseline Truck Test.”

Master’s Thesis, The University of Toledo.

2. Qiao C., 2009, “Analytical and Experimental Stress during Construction of the Veteran’s

Glass City Skyway” Master Thesis, The University of Toledo.

3. Feng X., 2010, “Nondestructive load testing of the Veteran’s Glass City Skyway” Master

Thesis, The University of Toledo.

4. AASHTO 17th

edition (2002), Standard Bridge Design Manual.

5. IDS 2011, Interactive Design Systems, Inc., Bridge Designer II, http://www.ids-soft.com.

6. Yi G., 2011, “Long-term Behavior of the Veteran’s Glass City Skyway Cable Stayed Bridge”

Master Thesis, The University of Toledo.

Page 118: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

1

Chapter 14 Stay Vibration

14.1 Introduction

This chapter focuses on the stay testing program that was employed on this project

(Kangas, 2009). Several experiments were performed during various stages of construction to

determine the capability of using traditional vibration techniques to estimate cable tensions with

the non-traditional cable sheathing system of this structure. The stays on this bridge use a

stainless steel cover pipe instead of a more traditional high density polyethylene (HDPE) sheath

utilized on other stay bridges. Also, following recent trends, the stays at this bridge are built

without the use of grout for the purposes of inspection and, if necessary, replacement. The cables

are aligned in a single plane and use a semi-harp arrangement. The cables consist of 82 to 156

epoxy-coated strands which are enclosed within a stainless steel cover pipe. There are 40 cables

on the bridge with cable lengths varying from 28 to 200 m. The stays are numbered from 1 to 20,

starting at the tower and extending towards the abutment and labeled A for the approach span or

B for the back span. Fig. 14.1 shows a basic overview for this bridge.

Figure 14.1 Plan View of VGCS Bridge (Kangas, 2009)

Page 119: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

2

The cables at VGCS continuously pass through the pylon and terminate at the deck level.

Although there are 20 total cables on this bridge, each span is considered to have unique cable

motion resulting in 40 cable legs. This bridge is one of two cable-stayed bridges, along with the

Penobscot Narrows Bridge, that uses this innovative cradle system to eliminate anchorages in the

pylon (Figg, 2007). Each strand passes through its own individual stainless steel sleeve in the

cradle assembly and is housed within stainless steel sheathing for its free length.

14.2 Cable Vibration and Force Estimation

To estimate cable force, cable vibrations are measured by placing accelerometers on the

cable’s protective cover pipe which is assumed to move in unison with the internal wire strands.

The measured vibrations are used to create auto-correlation functions, calculated only using the

positive time lags and therefore only retains information pertaining to the positive (stable) poles.

These identified correlations are subsequently used as basis functions within a stochastic

subspace identification algorithm to extract the eigenfrequencies of the cable’s measured

response. Figure 14.2 shows a typical measured cable acceleration and its corresponding auto-

correlation used to identify cable resonant frequencies. To identify the resonant cable

frequencies, the stochastic algorithm computes eigenfrequencies for varying model orders. The

returned eigenfrequencies that are consistent for various model orders are selected for calculation

of cable force. Figure 14.3 shows an example of the eigenfrequencies estimated by the subspace

algorithm compared against the power spectrum created the positive correlation lags. The

simplest model to describe a member under tension assumes it behaves like a taut string and is

described by the following equation:

Taut String Equation: (Equation 14.1)

where fsn is the nth harmonic frequency of vibration (Hz), T, m and L are string tension (N), cable

mass (kg/m), and cable free length (m), respectively.

This taut string approximation is not completely accurate for stay cables which have a

degree of bending stiffness (EI), and cable sag associated with them, where sag is represented by

Page 120: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

3

the parameter sag-extensibility (2). Mehrabi (1998) accounted for these parameters within the

following equation to describe the in-plane resonant frequencies:

Stay with Sag Equation: (Equation 14.2)

where: (Equation 14.3)

fEI

n is the measured frequency of the nth harmonic (Hz)

fSn is the equivalent-taut string frequency of the nth harmonic (Hz)

is the dimensionless parameter related to the bending stiffness

The method for tension estimation implemented within this research follows the two-step method

outlined by Peeters (2003) where non-linear least squares is used to simultaneously estimate

and fS

1 from the identified cable frequencies, which are assumed to behave like fEI

n in Equation

14.2. Knowing the cable length (L) and mass per unit length (m), the estimate of fS

1 can be used

to calculate cable force according to Equation 14.1.

Page 121: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

4

Figure 14.2 Acceleration (top) and auto-correlation (bottom) (Kangas, 2009)

Figure 14.3 Cable eigenfrequencies (Kangas, 2009)

Page 122: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

5

14.3 Baseline Stay Tests before Installation of Cable Dampers - 3/12/2007

Under contract with the Ohio Department of Transportation (ODOT), there was an

ongoing mutual dialogue and data sharing agreement between the University of Cincinnati

Infrastructure Institute (UCII) and the CTL Group. The results shown in this section are based on

data recorded by the CTL Group and processed with algorithms developed by UCII. Tables 14.1

and 14.2 show the cable lengths, measured fundamental frequencies, lift-off forces supplied by

the erection engineer and calculated forces assuming a uniformly distributed sheath for each of

the 40 stays at VGCS. Lift-off measurements are typically employed during stay installation (or

in later inspections) where each (or several) strand are hydraulically lifted off their anchorage in

order to directly measure their tensile force. These calculated forces are as much as 40% lower

than measured lift-off forces requiring sheath/strand interaction to again be quantified based on

lift-off readings. Sheath participation factors were calculated for all the cables and these

calculated sheath participation factors are also plotted against cable length in Figure 14.4. From

this figure, it is apparent that the sheath participation factors decrease as the cable length

increases (or as cable inclination decreases). These participation factors approach a value of one

as cable length increases indicating that the distribution of sheath mass approaches a uniform

distribution for the longer cables.

Page 123: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

6

Figure 14.4 Sheath participation factors identified before damper installation (Kangas, 2009)

Table 14.1 Frequencies & Forces for Approach Stays before damper installation (Kangas, 2009)

Page 124: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

7

Table 14.2 Frequencies & Forces for Back Stays before damper installation (Kangas, 2009)

14.4 Baseline Stay Tests after Installation of Cable Dampers - 6/16/2009

The preliminary tests performed at VGCS have shown the estimated tensions have been

consistently underestimated as a result of a non-uniform distribution of sheath mass. This

underestimation seems to be heavily influenced by cable angle; as the stay inclination decreases

the sheath mass becomes more uniformly distributed and vibration-based tension estimates

approach the values from lift-off readings. After installation of the cable dampers at VGCS, a

final series of stay measurements were conducted. Lift-off tension readings were not available at

the time of testing, so cable forces were assumed to be constant between these stays tests and the

set of experiments before the dampers were installed.

Table 14.3 compares the fundamental frequency measured at each stay before and after

dampers were installed. These cable frequencies are very close and there is a subtle upward shift

in frequencies after the installation of the dampers (except for Cables 1A and 1B, which are the

shortest cables with highest degree of cable inclination). Using the identified cable frequencies,

Page 125: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

8

sheath participation factors were calculated and are shown in Figure 14.5. Unlike the previous

experiments, from the measurements taken here a majority of the cables have a sheath

participation factor close to unity. It is hypothesized that this reflects the change in cable state

now that the stays are in their final configuration and the bridge is open to service; further, with

the elimination of the temporary spacer, the distribution of sheath mass along the free length of

the cable has approached a more uniform distribution.

Figure 14.5 Sheath participation factors identified after damper installation (Kangas, 2009)

Page 126: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

9

Table 14.3 Comparison of Stay Frequencies Before/After Damper Installation (Kangas, 2009)

14.5 Research Results and Conclusions

Stay vibration tests were performed during multiple stages of cable erection of the

Veteran’s Glass City Skyway Bridge. The stays at VGCS have unique structural characteristics

that posed challenges to traditional vibration-based force estimation. Unlike the high density

polyethylene sheathing system often incorporated on cable stayed bridges, the relative stiffness

of the stainless steel cover pipe prevents the sheath and strands from making contact except at a

limited number of locations. The sheath can account for approximately 25% of the total cable

mass and its influence needed to be taken into account for accurate estimation of cable tension.

After refining the cable force formulation based on field test observations, future vibration-based

force estimations can be implemented in lieu of lift-off measurements.

References

1. Figg, 2007, Figg Bridge Engineers, Charles Pankow Award for Innovation, American

Society of Civil Engineers (ASCE), April

2. S. Kangas, A. Helmicki, V. Hunt, R. Sexton, J. Swanson, "Identification of Cable Forces on

Cable-Stayed Bridges: A Novel Extension of the MUSIC Algorithm", Experimental

Page 127: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

10

Mechanics Journal, Society for Experimental Mechanics (SEM), Volume 50, Number 7, pp.

957-968, 2010.

3. S. Kangas, “Modeling and Ambient Vibration Monitoring of Cable-Stayed Bridges,”

Dissertation, University of Cincinnati, 2009.

4. Mehrabi, A., and Tabatabai, H. Unified finite difference formulation for free vibration

of cables. Journal of Structural Engineering 124, 11 (1998), 1313–1322.

5. Peeters, B., Couvreur, G., Razinkov, O., Kundig, C., Der Auweraer, H. V., and

Roeck, G. D. Continuous monitoring of the øresund bridge: System and data analysis.

In Proceedings of International Modal Analysis conference (IMAC) (2003).

6. R. Sexton, S. Koganti, A. Helmicki, V. Hunt, and J. Swanson, “Aspects of Health Monitoring

for Cable Stay Bridges,” Proceedings of ASNT Structural Materials Technology VI: An NDT

Conference, Columbus, OH, October, 2005.

Page 128: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

1

Chapter 15 Modal Analysis

15.1 Introduction

This chapter focuses on the operational modal analysis program that was employed on

this project (Chauhan, 2008). The magnitude and direction of structural vibrations may be

monitored/measured at critical locations through the use of mounted accelerometers to identify

the characteristic modal shapes and frequencies of the bridge. Monitoring structural vibrations at

such locations for several long time periods (20-30 minutes) throughout the course of 1-2 days

should be sufficient to capture important vibration response characteristics of the bridge.

Sensors are easily mounted and the bridge is left open to traffic for the duration of the test. Live-

load inputs from passing vehicles as well as the wind are used to induce structural vibration.

Separate characterization of wind inputs to the structure are typically captured through

synchronization with the weather station installed at the site.

From such data, it can be assessed whether vibration magnitude and/or frequency is of

concern to the health or use of the bridge. Identification of vibration-critical regions in this

manner may consequently provide information that can assist in assessing the performance of

damping systems which, by reducing vibration contribute toward increasing the serviceable life

of the structure. In addition, this vibrational data can be analyzed to characterize the dynamic

mechanisms of bridge articulation. Such analysis is essential for a comprehensive calibration of

FEM models.

15.2 Test Set-up, Data Acquisition and Data Processing

Figure 15.1 shows the test set-up layout. The sensor grid used for the test is much coarser

in comparison to the one used for the US Grant Bridge and thus it is expected that some of the

modes might appear to be similar (poor observability). A total of 10 sensors are used, 5 on each

side of the parapet. The sensor lines extend from the back span side to the front span side with 8

sensors on one side of the pylon and 2 on the other as indicated. The sensor line extends 500m

from Cable 14B on the back span to 6A on the front span. Note that notations A and B are for

front and back spans respectively. Figure 15.2 shows one of the accelerometers glued on the

Page 129: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

2

bridge superstructure. The data acquisition parameters for the test were set as following:

sampling rate 40 Hz, frequency range 0 – 15 Hz, and test duration 20 minutes. The bridge was

partially opened to public and one lane of traffic was open during the test.

Figure 15.1 OMA Test Set-Up Layout for the VGCS Bridge (Chauhan, 2008)

Page 130: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

3

Figure 15.2 Typical accelerometer set up for the VGCS Bridge OMA test (Chauhan, 2008)

A block size of 2048, along with the application of Hanning window and 66.67 %

overlap was used for processing the output time histories to obtain the power spectra. The

autopower plot of individual channels is shown in Figure 15.3. The plot indicates the presence of

at least 6 modes below 1.4 Hz frequency range. Further analysis also indicated the presence of

two close modes around 1 Hz in addition to the modes indicated by the Autopower plot.

Page 131: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

4

Figure 15.3 Autopower spectrum of individual channels (VGCS Bridge) (Chauhan, 2008)

15.3 Modal Parameter Estimation

Table 15.1 shows the modal parameters obtained using custom algorithms developed at

the University of Cincinnati. The modal frequencies obtained using two algorithms match well.

However, the damping estimates differ due to their dependence on a number of factors which are

algorithm specific. Damping for the mode at 1.66 Hz (highlighted in green) is not estimated

using the Enhanced Frequency Domain Decomposition (EFDD) algorithm as its spectral bell

curve could not be identified properly at this frequency.

Page 132: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

5

Table 15.1 Modal Parameter Estimates (VGCS Bridge) (Chauhan, 2008)

15.4 Finite Element (FE) Model Comparison

A finite element model of the bridge was developed and analyzed to compute the modal

frequencies and the mode shapes. The modal frequencies and the mode shapes are listed in Table

15.2 along with the corresponding operational modal analysis results. It should be noted that

most of these modes are vertical bending modes. Thus, the sensor layout for the final

superstructure test was chosen in a manner that ensured the observation of these critical modes.

Note that most of the early flexural modes for the FE model have been validated by field tests.

Page 133: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

6

Table 15.2 Frequency Comparison of OMA and FEM Results (VGCS Bridge) (Chauhan, 2008)

15.5 Research Results and Conclusions

In past, operational modal analysis has been shown to give good results with both

analytical and lab based experimental data. In this study, the performance of these algorithms has

been further analyzed by means of studies conducted on a cable stayed bridge. The modal

parameter estimates obtained are shown to have comparative results with respect to at least two

algorithms. In certain cases, the mode shapes appear to be similar. One of the reasons for this is

the limited spatial resolution, which gives rise to observability related issues. However, with the

help of the available knowledge in terms of the FE model, all the important modes have been

estimated properly. Thus the study underlines the two key points of modal analysis in general

that 1) its always good to have some a priori information available, and 2) the importance of

good test planning, set up and good data acquisition because the parameter estimation algorithm

is only as good as the data collected.

References

1. S. Chauhan, “Parameter Estimation and Signal Processing Techniques for Operational Modal

Analysis,” Dissertation, University of Cincinnati, 2008.

2. S. Chauhan, A. Helmicki, V. Hunt, J. Swanson, J. Saini, S. Kangas, D. Nims, R. Allemang,

“Application of OMA-EMIF Algorithm to Cable Stayed Bridges,” Proceedings of

International Seminar on Modal Analysis (ISMA), Leuven, Belgium, 2008.

3. R. Sexton, S. Koganti, A. Helmicki, V. Hunt, and J. Swanson, “Aspects of Health Monitoring

for Cable Stay Bridges,” Proceedings of ASNT Structural Materials Technology VI: An NDT

Conference, Columbus, OH, October, 2005.

Page 134: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

1

Chapter 16 Website Design and Documentation

16.1 Introduction

This chapter focuses on the long term instrumentation package, data collection system

and web site which is used to monitor and evaluate the long term environmental effects on the

structure. This system provided ODOT, UT and UCII the ability to plot strain and temperature

information about the bridge in a data-form which can easily be plotted over periods of time for

multiple locations. (1)

The system starts with sensors installed in specific locations on the bridge which all attach to a

central data logger located near the bridges tower in a protected, temperature controlled metal

cabinet. This data logger collects and stores the sensor readings for collection from a data

processing system. A computer in the UCII laboratory was setup with customized data-logger

software to make scheduled downloads of this sensor data. These scheduled processes trigger

various sets of programs to then load the collected data into a database for further analysis or

plotting from web sites. With the data loaded into a database, ODOT, UT and UCII can plot

sensor information from any web accessible device via a simple web browser. The ability to run

programs on recently collected sensor data also provides the ability to alert the authorities of

events if necessary. A diagram of the overall system described above is shown in Figure 16.1.

Figure 16.1: Complete Monitor System Diagram

Page 135: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

2

16.2 Instrumentation

The current system contains a Campbell Scientific (2) CR10X data-logger, AM16/32 Relay

Multiplexers, an NL100 Network Link interface, a Geokon Vibrating Wire Digital Signal

Processor (DSP) interface and 64 Geokon (3) Vibrating Wire Gages (VWG) embedded in the

concrete.

A total of 64 vibrating wire embedded strain gages are installed, 8 for each lane as shown in

Figure 16.2 (16 at each location) and 4 locations. Figure 16.2 is a schematic showing the gage

layout inside one lane of each of the 4 locations on the bridge where sensors are installed.

Figure 16.2: Segment Sensor Locations

16.3 Data Collection

The data collection and storage portion of the monitoring system is setup to take measurements

every 30 minutes and store that information for download. Once stored by the data logger, the

data is then ready for collection which can be carried out various ways. The remote collection of

data from the bridge is done using a dedicated computer with a dedicated internet connection

which links to the NL100 device located at the bridge. Scheduling the automatic collection of the

data is done using the LoggerNet software provided by Campbell Scientific.

Page 136: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

3

The bridge health monitor incorporates a standard process for formatting and warehousing the

collected data from the bridge. In order for the data downloaded from the CR10X to integrate

into a database, some custom programs were developed for pushing the sensor data into a

MySQL (4) database. This custom program gets initiated by LoggerNet and also archives the

raw sensor data collected from the CR10X data-logger.

Making the collected data accessible via the web means warehousing the data in a database.

This not only makes the data accessible but also makes sections or slices of specific data easily

attainable. The database design was based on requirements of typical requests of the sensor data

and how to respond most efficiently and quickly. The database resides on servers at the UCII

laboratory which run the MySQL database server software. Since the data is pushed

immediately after each collection sequence, the database always maintains the latest sensor data

and can be used for real time monitoring of the bridge.

16.4 Website

The front door of this project is the web site which provides the tool for monitoring the bridge’s

health. Not only does the site provide the health monitoring but also provides information about

all the equipment used and locations of installed sensors. To make navigating the site easy for

the targeted audience, its design was based on the ODOT home page (5). The web site’s main

sections include equipment information, information on the installation of the equipment and the

monitoring system hardware. The navigation through the site is accomplished with a standard

set of links on the left side that are always present. These links take you to the main sections of

the web site and back to the main description page. The entire website is inaccessible by the

general public and requires authorization by a username and password. Since the website is part

of an ODOT funded project and was developed for UT and UCII researchers and ODOT staff to

view, the website is limited to those personnel.

The monitor section of the web site is the most interactive and important section of the monitor

and allows for plotting and analysis of sensor readings. The goal here was to provide a user-

friendly interface to plot the strain readings but also includes a schematic of gage locations, a

user input page, and an interactive plotting utility.

Page 137: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

4

Figure 16.2 shows the schematic used on the monitor page and Figure 16.3 is a screen shot of the

rest of the monitor page where the user interaction takes place. As shown the sensors installed

on the bridge are listed on the left, which can be selected for plotting on a graph during a

specified time frame. Temperature can also be plotted by selecting the check box next to it

instead of Stress or Strain. The Strain vs. Temperature can be plotted for a particular gage but

for this type of plot only one gage can be selected at a time. Once all of the desired parameters

are chosen, the “Graph” button is selected to produce the plot based these selections. A

maximum of eight sensors can be plotted and each is plotted in different colors. You can also

export the data to a file which is formatted using the comma separated value (CSV) format for

use in other programs, such as Microsoft™ Excel by selecting the “Export” button.

Figure 16.3: Monitor Web Site

Figure 16.4 are plots from the web site showing on the left a strain plot and on the right a

temperature plot. Both plots are for two sensors which as can be seen in the temperature plot

read the same temperature values.

Page 138: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

5

Strain (μE) Temperature (°F)

Figure 16.4: Web Monitor Sample Plots

16.5 Conclusion

This automated long-term health monitoring system is customizable and modular thus making it

possible to add additional gages or other data driven devices. One main reason is the utilization

of the existing manufacturer’s software (in this case Campbell Scientific) in a customized

fashion. The use of open-source software and web standards also makes the system open and

easy for future customizations and additions. Currently the system consists of the following

modules: data measurement, data collection and storage, and the web interface.

The data collection and warehousing of gage readings means not only can officials do further

analysis of the bridges health but a historical archive of bridge performance is recorded. Plotting

of strain data for multiple sensors over varying time frames means ODOT, UT and UCII can

further analyze the health of certain sections or the bridge as a whole over seasonal changes.

High speed connectivity allows for more frequent data collection which enables close to real

time monitoring of the bridge and conditions like cold weather or icing. This also allows for a

close to real time model of the bridge for possible fault detection and the ability to automatically

send warning notifications.

References

1. G. Kimmel, J. Kumpf, V. Hunt, J. Swanson, A. Helmicki, “Automated Health Monitoring of

an Aged and Deteriorated Truss,” Proceedings of ASNT Fall Conference and Quality Testing

Show, Columbus, OH, October, 2009.

2. Campbell Scientific: dataloggers, data acquisition systems, weather stations, Campbell

Scientific Inc, 2012, http://www.campbellsci.com/.

Page 139: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

6

3. Geokon Instrumentation, Geokon Inc., 2012, http://geokon.com/.

4. MySQL:: The world’s most popular open source database, Oracle Corporation, 2012, http://mysql.com/.

5. The Ohio Department of Transportation, The Ohio Department of Transportation, 2010,

http://www.dot.state.oh.us/.

Page 140: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

1

Chapter 17: Conclusions and Future Work

This project has focused on the instrumentation, monitoring and testing of the

main span unit of the VGCS, one of Ohio’s first long-span, cable-stayed bridges and one

of only a few dozen such bridges in service in the nation. This effort looked at five main

areas: (1) health monitoring; assessment of the changes in force distribution and bridge

condition during erection and early service, (2) verification of design assumptions during

erection, (3) investigation of the unique design features which have been incorporated

into the VGCS, (4) investigation into the unique erection features and sequencing which

will be used during its construction, and (5) investigation of stay cable vibration which is

a general, unresolved issue for bridges of this type.

Based on the findings discussed in the previous chapters of this report, specific

conclusions and recommendations can be offered as follows.

A health monitoring system for the bridge was designed, planned, and

implemented for the Veteran’s Glass City Skyway bridge, with data collection and

archival throughout its construction and ultimately an automated, user-friendly interface

on a dedicated website. The primary criteria for selecting the segments to be instrumented

was the predicted stresses and rating factors using the analytical data provided by the

designer. An addendum to the plans was prepared to document the items to be installed

by the contractor (e.g., conduit, junction boxes, main data cabinet, phone service, power

outlets, etc.), the general plan for instrumentation and testing, the required access to the

site and casting yard by the university research team (URT), the requirements for

notification during construction, and the protection of instrumentation, wiring, and data

acquisition equipment. Once gages were installed on the rebar cage of the segments, the

lead wires were routed to the inside parapet and protected from the elements by using

trash bags and a white NEMA 4 box. Initially, each segment was handled independently

(e.g., in the casting yard), but ultimately both northbound and southbound segments were

combined at one multiplexer after their installation on the bridge. As per the plans, the

contractor installed conduit along the length of the parapet, mounted the white boxes to

the side of the parapet, installed the main data cabinet near the pylon, and connected all

Page 141: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

2

these together to enable one common architecture for the health monitoring system. This

will be facilitated by the web application which will provide the ability to check the

status, plot and access all sensor data from the instrumentation backbones. This will also

provide the research group the information needed to assess the equipment and system

performance and validate any research findings or conclusions.

An extensive component of the project involved the use and development of

analytical and FE models of the structure for a variety of reasons. Since a cable stayed

bridge may exhibit a complex nonlinear behavior, it necessitates that all the assumptions

made during the design stage be verified. Above all, if the cable stayed bridges is made of

concrete segments whose behavior is inherently time dependent it adds to the problem of

predicting a response. It was concluded from the literature that assumptions and choices

like the kind analytical precision required, that is 2D or 3D analysis, use of particular

type of finite element for elements like segments and cables, material property

representation in the model and assumption regarding the way the bridge is going to

behave at the connections go a long way towards determining the validity of the model.

These assumption might speed up the analysis and may be acceptable at the design stage

but they need to be verified before they could be use to generate quantitative data to be

used for maintenance. For the proposed study, reviewing previous literature research

efforts have yielded significant information that will used to develop initial models in

such a way that they will require minimum changes afterwards to calibrate them. Also

keeping in mind that the instrumentation suite employed for VGCS is a sparse one, it was

decided to progressively calibrate the model, that is, make changes to the model

parameters such as stiffness and support conditions so that the model output correlates

well with the measured data even for intermediate stages of construction. This was done

to instill confidence in the use of the model as a maintenance tool.

Another component of the project involved the installation of gaging whose data

was used, in part, to track stresses and loadings developed during construction/erection.

Total 64 vibrating wire strain gages were installed in eight segments at four cross sections

to monitor the long-term behavior of this bridge. Data from these gages has been

collected since the casting date of each segment. A method of assembling the time line

Page 142: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

3

was developed, a Matlab program was written to combine the strain time history line for

the data of one strain gage, and the experimental stresses were compared to analytical

stresses calculated by the contractor.

From the sample study of the time history line from 28NB28BFL, a good match

between construction events from the construction log and health monitoring strain gage

data was observed. Other gages’ data also showed a good fit to construction events.

These good matches indicated that the gages worked properly during construction, and

the data from these gages is an accurate reflection of the actual strains in the bridge.

By checking the gages at the same elevation located in the same longitudinal

position, the assumption of a two dimensional model, where there is little bending about

the vertical axis was verified. Based on this verification, information from one top and

bottom gage in each cross section is concluded to be representative for the local load

condition.

The next step was using the strain gage data to derive experimental stress time

histories to compare them to the construction finite element analyses. To calculate

converted stress time histories, the initial strain and modulus of elasticity are required.

The initial strain for each gage can be obtained from the strain time history on the casting

date. The modulus of elasticity can be assumed to be a constant because the construction

procedure did not take too long time and thus influence the modulus of elasticity much.

By following this research procedure, the comparisons between analytical stress

and experimental stress for selected gages were done.

Above all, this work supplied a convincing confirmation of both the accuracy of

the gage monitoring process and the finite element analysis used in the design and

construction of the VGCS.

The following actions are recommended for further data review:

Page 143: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

4

The modulus of elasticity as a time dependent coefficient should be

studied in the future to generate a more accurate experimental stress time history line for

a long time comparison and prediction.

The continuous database of collected strain needs to be updated to the

current time. Based on this database, the long-term monitoring, the future load condition

prediction, and load rating can be correlated with the contractor’s or another model.

The zero strain estimate for each strain gage is inherently uncertain. The

method of determining the zero strain should be more fully developed to minimize the

uncertainty

Other factors, such as temperature and geometry, which could influence

the reduction of the strain gage data needs to be studied in the future to get a more

accurate result.

Based on future truck testing and improving the accuracy of the long term strain

data reduction, improved estimates of the short term and long term stresses can be made.

These estimates of live load and dead load stresses can be used to establish an

experimental load rating.

Temperature gradients in the VGCS were also studied with two main goals: to

preliminarily assess if the bridge behaves as the AASHTO Code predicts, and to lay the

foundation for future studies of temperature gradients. Results of the maximum and

minimum temperature gradients in Segment 26NB14 were plotted for October,

November, December of 2005 and January, February, March, April and September of

2006. It should be noted that the accuracy of the thermistors is +/- 0.5ºC, or +/- 0.9ºF.

This amount of error could have a significant effect on the shape of the temperature

gradients, as will be seen in the following figures, as often the range of temperatures for a

temperature gradient was at most 8ºF. Depending on which way the individual

thermistors err, the range of 8ºF could easily decrease to almost 6ºF or increase to nearly

10ºF.

Page 144: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

5

Plots of the Positive Temperature Gradients were fairly consistent for most of the

eight months of collected data. This consistency was in the shape of the gradient, while

the actual temperatures varied. Consistency, however, was not the only attribute to

observe from the temperature gradients; comparison of the actual gradients to the design

gradient was done as well. It was found by inspecting the plots that the actual gradients

follow and typically fall within the design gradient. One interesting similarity in the

positive temperature gradient plots is that one or two of the upper gages, Gage VTHL and

VTHT, was consistently colder than the bottom slab gage VBEL. This anomaly could be

explained by the gage being located in a spot where it is surrounded by more concrete

than other gages and that at the time of the maximum positive temperature gradient

occurring the concrete immediately surrounding the gage did not have sufficient time to

warm up as did gage VBEL. Lastly, the upper-most gages all fell within the design code,

reaching upwards of 8ºF warmer than gage VBEL, while the design code temperature

difference is 11ºF for the cross section at the height of those gages.

Plots of the negative temperature gradients were not as consistent as the positive

temperature gradients, however, they were still insightful. Plots for two of the eight

months of negative temperature gradients followed the general idea of the top slab being

colder than the bottom slab, while the other six months actually were positive

temperature gradients, indicating that negative temperature gradients never occurred

during those months. Looking at the temperature difference in December between the

coldest top slab gage and gage VBEL, it was found that this value was within the

specified code value of 3.3ºF. However, in November, the gradient was not a maximum

between the top-most gage and gage VBEL, it was between the one upper gage and the

top-most gage. This could be explained in a similar way as in the positive temperature

gradients when the gage is takes longer to be affected by temperature changes since it is

embedded deeper in concrete than other gages.

Based on the results from the small set of data used, it can be said that the VGCS

behaves within reason to the AASHTO Design Code. Sometimes the gradient didn’t

follow the code so well, as seen with the variability in even the well-behaved positive

temperature gradients, or the two negative temperature gradients that occurred. However,

Page 145: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

6

taking into consideration the error of the thermistors, the variability of temperature

cycles, the fast-changing weather patterns of northwest Ohio and the small data set

available, the results were reasonable enough to say that the study of temperature

gradients is a valuable pursuit. Based on the confirmation of the thermistors and the

preliminary results from eight months of temperature data, it is recommended that

temperature gradients in the instrumented bridge segments are studied for long periods of

time, on the order of years.

The fact that only two of the eight months produced negative temperature

gradients underlines the importance of studying temperature gradients and analyzing

several years’ worth of data versus several months and that negative temperature

gradients do not occur very often.

A series of two sets of truckload tests was conducted on the structure. These were

planned and run with two main goals in mind. One goal was to obtain baseline readings

of the bridge so that future load tests could be run and the two sets of data could be

compared. Comparing the data sets will be useful when assessing the health of the bridge,

as increased levels of strain could indicate a loss of structural integrity such as excessive

concrete cracking, or post-tensioning strand deterioration. The other main goal of the

Truck Test was to confirm the Larsa model. By comparing the influence lines with the

dynamic loading data, the model was confirmed. This confirmed model can be used in

the future to predict stresses, strains or moments for any load configurations for future

truck tests. The model could also be calibrated in the future to account for structural

deficiencies found during future truck tests. With a model calibrated for structural

deficiencies, it would be possible to look at any point in the bridge and determine if there

were any sections which were overstressed, or could potentially become overstressed if

further deterioration occurred. Thus, the health of the bridge could be monitored over

time and structural repairs could be suggested based on any deterioration found either

through visual inspection or by increases in strains from a truck load test.

During the first phase of this project a delta frame was instrumented and

monitored. A sparse array of instrumentation concentrated in areas of high strain was

Page 146: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

7

used to resolve uncertainties in modeling of a complex element of a cable stayed bridge.

After calibration, the element model was used to verify that there was no cracking before

service. Finally, the calibrated model of the element can be placed confidently in a model

of the overall bridge. Also, the VGCS delta frames were heavily post tensioned during

construction, inducing tension in the bottom chord. This could have potentially lead to

development of cracks. Therefore, the bottom chord of VGCS delta frame 18B was

instrumented in a few critical locations with the highest expected tensile strains to verify

strain levels corresponding to critical post tensioning events. A relatively inexpensive

sparse instrument array was installed and the measured response against the post

tensioning events was used to develop a calibrated component model of the delta frame.

First the model was calibrated against initial post tensioning and then used to generate

surface strains for the initial post tensioning plus self weight. These strains were then

checked against the cracking strain. Then this calibrated model was fit into a complex

model of the cross section and the calibration was verified at this stage against measured

response from final post tensioning. Surface strain levels at this stage were also checked

against cracking. It was found that at both stages of post tensioning the surface strains

were well below the cracking level. Since the final loading of the delta frame is stay

stressing which induces compression in the delta frame bottom chord, it can be concluded

that the bottom chord of the delta frame did not crack due to construction loads. This

conclusion was also supported by the visual inspection of the delta frame done during

construction.

Since the VGCS Bridge is instrumented for long term monitoring, the calibrated

model of the delta frame which showed good correlation to measured response during the

second post-tensioning was now ready to be used as a component of the full bridge

model. Therefore, this work also contributes towards developing long term maintenance

planning of VGCS. Though the efforts were directed towards expected problems at the

VGCS, the verification of delta frame behavior under various construction arrangements

will, provide more support for their use in this future.

In the initial phase of this work, the foundation for performing progressive

calibration was laid. It assured the quality of the data collected. It verified the design

Page 147: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

8

assumptions of linearity and symmetry. Since the project employed a sparse array of

instrumentation, achieving these objectives was important to prove that the

instrumentation array was sufficient for carrying out model calibration.

The uniqueness was in the progressively calibrated model of the bridge. The

design models available for bridges were underlain by design assumptions, predicted

responses to construction procedures and loads. Such design efforts satisfied the code

requirements and had been found to be sufficient enough to ensure the service life and

safety of the structure. But they lack the sophistication and accuracy required to be useful

for maintenance purposes. Whereas a model developed and calibrated progressively is

more responsive to changes since it is fine tuned with changing geometry, stiffness and

against a variety of loading conditions. Satisfactory verification against all monitored

construction stages instills confidence in its future use for inspection and maintenance

purposes.

Transverse bending of the bottom slab was monitored in order to reconcile

discrepancies in finite element analyses performed by the construction and design

engineers. Vibrating wire strain gages were installed in the bottom slab of segments to

monitor transverse bending. Data was collected during construction, as well as during the

truck load test prior to opening the VGCS to traffic.

Two research studies focused on investigating the concentration of strain in the

bottom slab of the delta frame by comparing the results of the experimental data to the

analysis results provided by the design engineer.

Wright investigated strain concentrations in the bottom slab of the VGCS caused

by the post-tensioning tendons used to hold the delta frames in place. Results of the

research monitoring strain levels immediately behind the delta frame tension block

following the tensioning of the DF4 tendon indicated that the strain magnitudes

attenuated quickly when moving away from the zone of predicted response.

Page 148: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

9

Ward studied the transverse bending behavior of the bottom slab by monitoring

the slab prior to installation and after the bridge was completed and opened to traffic.

Experimental results at a construction stage prior to stressing stay 8 were compared with

analysis provided by the designer. Experimental results were higher than predicted by the

design engineer, but less than those predicted by the construction engineer. Strains

approaching the yield for reinforcement (approximately 2000με) were not observed at

any point during construction. Strain magnitudes did not exceed 300με for any of the

gages installed on the bottom slab.

Visual inspection following installation of the instrumented segments, as well as

subsequent segments did not reveal any cracking in the bottom slab in the regions where

large strains were predicted. Strain magnitudes from the gages installed on the bottom

slab of segments 28SB15 and 28SB25 have been independently verified to be accurate by

performing lab calibration of the actual gages used in the field.

In addition, data recorded during live load tests including the crane withdrawal

and full scale truckload tests confirms the assertion that dead load bending behavior

dominates the transverse bending capacity of the bottom slab.

Dead load effects caused by the self-weight of the segments and delta frames are

the predominant factor in determining the capacity of the bottom slab in transverse

bending of the bottom slab.

In this chapter, the analytical and experimental stresses from the time of stay

stressing through service life up to the present time are compared. Time history of the

analytical stresses in the contractor’s as-built finite element model for staged construction

(BD2) is compared to the time history of the stresses based on the strain data collected.

Representative plots for the comparison are presented.

Stay cable stressing events eave a clear signature in the time history line and the

exact time of each event is recorded in the stay cable stressing log. This study can verifies

that the instrumented segments of VGCS behave as expected for the period studied

Page 149: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

10

In another aspect of this study, the allowable stress (ASR) load rating method was

used to evaluate the inventory load rating factor for analytical and experimental stresses.

This work utilized results obtained from both models, long term monitoring results and

truckload testing.

Stay vibration tests were also performed during multiple stages of cable erection

of the Veteran’s Glass City Skyway Bridge. The stays at VGCS have unique structural

characteristics that posed challenges to traditional vibration-based force estimation.

Unlike the high density polyethylene sheathing system often incorporated on cable stayed

bridges, the relative stiffness of the stainless steel cover pipe prevents the sheath and

strands from making contact except at a limited number of locations. The sheath can

account for approximately 25% of the total cable mass and its influence needed to be

taken into account for accurate estimation of cable tension. After refining the cable force

formulation based on field test observations, future vibration-based force estimations can

be implemented in lieu of lift-off measurements.

In past, operational modal analysis has been shown to give good results with both

analytical and lab based experimental data. In this study, the performance of these

algorithms has been further analyzed by means of studies conducted on a cable stayed

bridge. The modal parameter estimates obtained are shown to have comparative results

with respect to at least two algorithms. In certain cases, the mode shapes appear to be

similar. One of the reasons for this is the limited spatial resolution, which gives rise to

observability related issues. However, with the help of the available knowledge in terms

of the FE model, all the important modes have been estimated properly. Thus the study

underlines the two key points of modal analysis in general that 1) its always good to have

some a priori information available, and 2) the importance of good test planning, set up

and good data acquisition because the parameter estimation algorithm is only as good as

the data collected.

This automated long-term health monitoring system for bridges is highly

customizable and modular thus making it possible to add additional gages or other data

driven divices. One main reason is the utilization of the existing manufacturer’s software

Page 150: Instrumentation of the Maumee River Crossing...Instrumentation of the Maumee River Crossing Arthur J Helmicki, Ph.D. Professor, University of Cincinnati Infrastructure Institute, School

11

in a customized fashion. The most important and potential stopping point for such a

system is remote connectivity but with modern devices such as cell phones even fairly

remote locations can be connected. The use of open-source software and web standards

also makes the system more apt to future customizations and additions. Currently the

system consists of the following modules: data collection, data analysis and storage, and

the web interface.

The data collection and warehousing of gage readings means not only can

officials do further analysis of the bridges health but a historical archive of bridge

performance is recorded. Plotting of strain data for multiple sensors over varying time

frames means ODOT and UCII can further analyze the health of certain sections or the

bridge as a whole over seasonal changes. High speed connectivity allows for more

frequent data collection which enables close to real time monitoring of the bridge and

conditions like cold weather or icing. This also allows for a close to real time model of

the bridge for possible fault detection and warning.

To summarize, based on the discussion above, this project sought to implement

and operate an appropriate instrumentation and field testing program to support

management of the VGCS through construction and on into its service life. This program

augments the traditional visual inspection program to provide objective, quantitative data

for use by ODOT in assessing the status of the structure. There is value in continuing to

collecting, archive and analyze the strain data from the bridge. The data will give insight

into how the bridge is ageing and ascertain that the actual long term behavior is that

expected during design.