229 REV INSTALLATION GUIDE Filcoten Infra 4 and 5 mm INSTALLATION 1. Drainage outlets 2. Installation 3. Installing the vandal-proof lock (optionnal) Table 1 : Trench dimensions Figure 1 : Typical trenches Figure 2 : Positioning the expansion joints Figure 3 : Tees and elbows (optional) 02.2018

Upload: vanhanh

Post on 24-Jun-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: INSTALLATION GUIDE - Soleno RE INSTALLATION GUIDE Filcoten Infra 4 and 5 mm INSTALLATION 1. Drainage outlets 2. Installation 3. Installing the vandal-proof lock (optionnal) Table 1

229REV

INSTALLATION GUIDEFilcoten Infra 4 and 5 mm

INSTALLATION1. Drainage outlets

2. Installation

3. Installing the vandal-proof lock (optionnal)

Table 1 : Trench dimensions

Figure 1 : Typical trenches Figure 2 : Positioning the expansion joints

Figure 3 : Tees and elbows (optional)

02.2018

Page 2: INSTALLATION GUIDE - Soleno RE INSTALLATION GUIDE Filcoten Infra 4 and 5 mm INSTALLATION 1. Drainage outlets 2. Installation 3. Installing the vandal-proof lock (optionnal) Table 1

REV

STEP 1DRILLING THE DRAINAGE OUTLETS

DRILLING THE SIDE CONNEXTION WELL OPENING (IF REQUIRED)

AND/OR DRILLING THE VERTICAL CHANNEL OUTLET (IF REQUIRED)

1a. Using a hole saw, drill an opening

in order to install the vertical channel outlet.

1a. Using a concrete drill bit, drill small holes

following the guide which is appropriate

for your installation.

1b. Insert the vertical channel outlet above

the opening and seal.

1b. Using a cold chisel, clear the side con-

nection well opening.

02.2018

Page 3: INSTALLATION GUIDE - Soleno RE INSTALLATION GUIDE Filcoten Infra 4 and 5 mm INSTALLATION 1. Drainage outlets 2. Installation 3. Installing the vandal-proof lock (optionnal) Table 1

REV

STEP 2INSTALLATION

2c. Pour a concrete slab if the clearance be-

tween the base of the channel and the

bottom of the trench exceeds 125 mm

(5 in) and let it harden.

2d. Determinethefinalelevationlevelofthe

top of the corner bracket using a chalk

lineoralaserlevel.Thefinalelevation

level must be 3 mm to 5 mm (1/8 in to

3/16in)lowerthanthefinishedsurface.

2a. Dig the trench in accordance with

Table 1.

2b. Determine the outlet type: lateral for

side connection well, vertical for channel

or horizontal for the end of channel with

end plate with outlet used.

02.2018

Page 4: INSTALLATION GUIDE - Soleno RE INSTALLATION GUIDE Filcoten Infra 4 and 5 mm INSTALLATION 1. Drainage outlets 2. Installation 3. Installing the vandal-proof lock (optionnal) Table 1

REV

Chalk line

Embedment of the base

Paver, block or brick

(optional)

Slab (optional)

Placethefirstdrainagechannelbypushingits

base in the concrete clump, until the angle cor-

ner reaches the desired level.

Method #1:

Place clumps of concrete having a consistent

texture against the channel joints.

Method #2:

Add concrete pavers or bricks against the

channel joints. Embed these leveling blocks

in concrete having a consistent texture.

or

2e. Preparation for levelling: Two suggested methods

2f. Installation and levelling

02.2018

Page 5: INSTALLATION GUIDE - Soleno RE INSTALLATION GUIDE Filcoten Infra 4 and 5 mm INSTALLATION 1. Drainage outlets 2. Installation 3. Installing the vandal-proof lock (optionnal) Table 1

REV

2g. Install the other drainage channels. Let

the concrete embedment harden at the

base of the channels prior to pouring the

finalconcrete.

2i. It is essential that the grates be installed

in the drainage channels and covered

withaplasticfilmorprotectivetape

duringtheconcretepour.Backfillthe

bottom and sides of the trench, in accor-

dance with Figure 1. Take care to spread

the concrete evenly.

2h. Apply a concrete sealer at the joints be-

tween each channel.

2j. Unpack the grates and reinstall them.

Addthefinishcoating,whereapplicable.

02.2018

Page 6: INSTALLATION GUIDE - Soleno RE INSTALLATION GUIDE Filcoten Infra 4 and 5 mm INSTALLATION 1. Drainage outlets 2. Installation 3. Installing the vandal-proof lock (optionnal) Table 1

REV

3a. Insert the vandal-proof lock under the grate.

3c. Insert the grate into the channel.

3e. Using a 5-mm Allen wrench, tighten the screw to expand the lock and thus prevent removal of the grate.

3b. Press on the lock until it fits completely between the clips.

3d. Press the grate until the clips reach the recesses inside the channel.

STEP 3INSTALLING THE VANDAL-PROOF LOCK (OPTIONAL)

02.2018

Page 7: INSTALLATION GUIDE - Soleno RE INSTALLATION GUIDE Filcoten Infra 4 and 5 mm INSTALLATION 1. Drainage outlets 2. Installation 3. Installing the vandal-proof lock (optionnal) Table 1

REV

Load Classes

A 15 kN B 125 kN C 250 kN D 400 kN E 600 kN F 900 kN

Channel width (mm)

100150 200

300 100150 200

300 100150 200

300 100150 200

300 100150 200

300 100150 200

300

Xmin

(mm) 100 150 200 100 150 200 150 200 250 150 200 300 200 250 300 200 250 300

Zmin

(mm) 100 150 200 100 150 200 150 200 250 150 200 300 200 250 300 200 250 300

Ymin

(mm) Total height of the channel

Re-bar Not requiredTreillis of 10 m

200 mm x 200 mm

TABLE 1TABLE TRENCH DIMENSIONS ACCORDING TO THE LOAD CLASSES OF THE INSTALLATION*

02.2018

X

Y

Z

3 to 5 mm(0.12 to 0.2 in)

Y

Z

X

3 to 5 mm(0.12 to 0.2 in)

X

*The load class of the installation is governed by the lowest component. For example, an installation of a Class F channel with a Class C grate will have a global load Class C.

CHANNEL SIDE CONNECTION WELL

Page 8: INSTALLATION GUIDE - Soleno RE INSTALLATION GUIDE Filcoten Infra 4 and 5 mm INSTALLATION 1. Drainage outlets 2. Installation 3. Installing the vandal-proof lock (optionnal) Table 1

REV 02.2018

EDGE / ASPHALT

FIGURE 1TYPICAL FILCOTEN INFRA TRENCHES 4 mm AND 5 mm

CONCRETE / ASPHALT

PAVERS / ASPHALT

Concrete edge

Paver

Granular layer

Sub-foundation

Concrete embedment

Bitumunous coating

Bituminous sealing tape

Finishing layer - asphalt

Upper foundation

Lower foundation

X

Z

3 to 5 mm(0.12 to 0.2 in)

Concrete embedment

Longitudinal expansion joint*

Concrete slab

Sub-foundation

Load-resistant concrete slab

Bituminous sealing tape

Finishing layer - asphalt

Upper foundation

Lower foundation

X

Z

X

Re-bar, see Table 1* Longitudinal expansion joints shall

be provided over the total length of the channel project.

3 to 5 mm(0.12 to 0.2 in)

Note 1 : For the installation of the paver in direct contact with the channel, using a concrete adhesive, make sure to adhere the first row of pavers to the channel and on the width X*, to adhere the horizontal side of the pavers to concrete and the vertical sides of the paving stones one on each other.

See Note 1

Paver

Sub-foundation

Concrete embedment

X

Z

X

Bituminous sealing tape

Finishing layer - asphalt

Upper foundation

Lower foundation

3 to 5 mm(0.12 to 0.2 in)

* If the paver width exceeds the width X, adjust the width X to match the width of the paver.

Page 9: INSTALLATION GUIDE - Soleno RE INSTALLATION GUIDE Filcoten Infra 4 and 5 mm INSTALLATION 1. Drainage outlets 2. Installation 3. Installing the vandal-proof lock (optionnal) Table 1

REV

ON SITE, IT IS POSSIBLE TO MAKE TEES AND ELBOWS, IF REQUIRED. CONTACT YOUR SOLENO REPRESENTATIVE FOR QUESTIONS REGARDING YOUR PROJECT.

FIGURE 3 TEES AND ELBOWS (OPTIONAL)

FIGURE 2POSITIONING THE EXPANSION JOINTS

02.2018

LONGITUDINAL EXPANSION JOINTS SHALL BE PROVIDED OVER THE TOTAL LENGTH OF THE CHANNEL PROJECT.

THE TRANSVERSE JOINTS SHOULD BE INSTALLED EVERY 5 METERS WHEN THE CONCRETE IS IN DIRECT CONTACT WITH THE CHANNELS.

TRANSVERSE EXPANSION JOINTINSTALLED WHEN CONCRETE IS IN CONTACT WITH THE CHANNEL

Note : A transverse expansion joint must be provided every 5 meters at the junction between two channels.

Concrete sealer

Channel (1 m)

Transverse expansion joint

Concrete embedment

5 m(15,5 ft)