inspection report daily, weekly or final - calabasas · inspection report – daily, ... daily...

2
LOS ANGELES BASIN CHAPTER INTERNATIONAL CODE COUNCIL Established 1957 P.O. Box 1099 www.icclabc.org Alhambra, CA 91802 July 11, 2014 3 Forms Page 6 of 19 Inspection Report Daily, Weekly or Final LABC Form 9 Page 1 of _____ Jurisdiction _________________________________ Building Permit Number _____________________ Address_____________________________ Daily Report Weekly Report Final Report General Contractor __________________________ Structural Engineer ____________________ Inspection frequency- check one: Periodic Continuous Type of Inspection - check one: Reinforced Concrete Shotcrete Prestressed Concrete Masonry For any of the above insert Mix Design No. ___________________ PSI: ____________ Welding: High-strength Bolts Epoxy Other Welder Name/s ______________________________ Describe Below Off Site Fabricator ___________________________ _________________ Time present at project; location and description of work inspected: Date (Insert additional pages if necessary) To the best of my knowledge, the work that I have inspected has been completed per the stamped, approved plans and the requirements of the California Building Code pertaining to special inspections. Inspectors Name _________________________________ Date __________ Print Inspectors Signature ______________________________

Upload: truongdat

Post on 23-May-2018

225 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Inspection Report Daily, Weekly or Final - Calabasas · Inspection Report – Daily, ... Daily Report Weekly Report Final Report ... Welding: High-strength Bolts Epoxy Other

LOS ANGELES BASIN CHAPTER

INTERNATIONAL CODE COUNCIL

Established 1957 P.O. Box 1099 www.icclabc.org Alhambra, CA 91802

July 11, 2014 3 Forms Page 6 of 19

Inspection Report – Daily, Weekly or Final

LABC Form 9 Page 1 of _____

Jurisdiction _________________________________

Building Permit Number _____________________ Address_____________________________

Daily Report Weekly Report Final Report

General Contractor __________________________ Structural Engineer ____________________

Inspection frequency- check one:

Periodic Continuous

Type of Inspection - check one:

Reinforced Concrete Shotcrete Prestressed Concrete Masonry

For any of the above insert Mix Design No. ___________________ PSI: ____________

Welding: High-strength Bolts Epoxy Other Welder Name/s ______________________________ Describe Below

Off Site Fabricator ___________________________ _________________

Time present at project; location and description of work inspected: Date

(Insert additional pages if necessary)

To the best of my knowledge, the work that I have inspected has been completed per the stamped, approved

plans and the requirements of the California Building Code pertaining to special inspections.

Inspectors Name _________________________________ Date __________

Print

Inspectors Signature ______________________________

Page 2: Inspection Report Daily, Weekly or Final - Calabasas · Inspection Report – Daily, ... Daily Report Weekly Report Final Report ... Welding: High-strength Bolts Epoxy Other

LOS ANGELES BASIN CHAPTER

INTERNATIONAL CODE COUNCIL

Established 1957 P.O. Box 1099 www.icclabc.org Alhambra, CA 91802

July 11, 2014 3 Forms Page 7 of 19

Inspection Report – Daily, Weekly or Final

LABC Form 9 (Additional Page/s)

Page _____ of _______

To the best of my knowledge, the work that I have inspected has been completed per the stamped

approved plans and the requirements of the California Building Code pertaining to special

inspections.

Inspectors Name _________________________________ Date __________

Print

Inspectors Signature ______________________________