inside battery limits man-hour report - compass · pdf fileinside battery limits man-hour...

1
Inside Battery Limits Man-Hour Report: Installation / Benchmark Man-hours for “Process” related Carbon Steel Pipe from recently completed Refinery / LNG / Chemical Projects located in US Gulf Coast (Texas): Inside Battery Limits (ISBL) A-53 Carbon Steel Pipe Fabrication (at a Pipe Fabrication Shop) & Erection M-H’s, includes testing. Assumes Pipe is 20’ off grade: Add 7.5% to above for height 25’ to 50’ • Add 12.5% to above for height 50’ to 100’ COMPASS INTERNATIONAL (215) 504 9777 www.compassinternational.net [email protected] View our annual cost estimating yearbooks at www.compassinternational.net If you have any questions or comments on this benchmark report please contact:: John G. McConville, CCP • Operations Director - Compass International •Telephone in the USA (609) 577 4505 • [email protected] • www.compassinternational.net Carbon Steel A-53 Pipe Diameter Schedule 40 Schedule 40 Schedule 40 Schedule 40 Minimum M-H’s per LF (Good Productivity) Maximum M-H’s per LF (with less than Average to Poor Productivity) Minimum M-H’s per M (Good Productivity) Maximum M-H’s per M (with less than Average to Poor Productivity) 2 0.88 1.98 2.89 6.51 4 1.54 3.47 5.06 11.39 6 1.87 4.20 6.12 13.78 8 2.44 5.49 8.00 18.01 10 2.57 5.79 8.44 18.99 12 2.70 6.09 8.87 19.96 14 3.19 7.17 10.45 23.51 16 3.48 7.82 11.40 25.66 18 3.72 8.37 12.20 27.45 20 4.12 9.28 13.52 30.43 22 4.29 9.64 14.05 31.62 24 4.45 10.01 14.59 32.82

Upload: lytuyen

Post on 07-Feb-2018

247 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Inside Battery Limits Man-Hour Report - Compass · PDF fileInside Battery Limits Man-Hour Report: Installation / Benchmark Man-hours for “Process” related Carbon Steel Pipe from

Inside Battery Limits Man-Hour Report:Installation / Benchmark Man-hours for “Process” related Carbon Steel Pipe from recently completed Refinery / LNG / Chemical Projects located in US Gulf Coast (Texas):

Inside Battery Limits (ISBL) A-53 Carbon Steel Pipe Fabrication (at a Pipe Fabrication Shop) & Erection M-H’s, includes testing. Assumes Pipe is 20’ off grade:

Add 7.5% to above for height 25’ to 50’ • Add 12.5% to above for height 50’ to 100’

COMPASS INTERNATIONAL(215) 504 [email protected]

View our annual cost estimating yearbooks at www.compassinternational.net

Similar building as above constructed in following Countries:

For additional location factors refer to Compass International’s 2015 Global Construction Yearbook (15th Edition) or visit http://www.compassinternational.net/product/2015-global-construction-costs-yearbook/Please send us an e mail if you would like an excel spreadsheet for this cost model.

1 Brazil Uberaba 0.88 $248 $2,6702 China Wuhan 0.85 $240 $2,5793 France Nantes 0.97 $274 $2,9434 Germany Bremen 0.98 $276 $2,9745 India Jamshedpur 0.86 $243 $2,6106 Italy Turin 0.94 $265 $2,8527 Mexico Tampico 0.85 $240 $2,5798 Norway Bergen 1.05 $296 $3,1869 Spain Bilbao 0.92 $259 $2,79210 Sweden Malmo 1.05 $296 $3,18611 Switzerland Fribourg 1.06 $299 $3,21612 Turkey Izmir 0.90 $254 $2,73113 UK Bristol 1.02 $288 $3,09514 USA Trenton, NJ 1.00 $282 $3,036

# COUNTRY CITY LOCATION FACTOR $ COST PER SQUARE FOOT $ COST PER M2

If you have any questions or comments on this benchmark report please contact::

John G. McConville, CCP • Operations Director - Compass International •Telephone in the USA (609) 577 4505 • [email protected] • www.compassinternational.net

Carbon Steel A-53 Pipe Diameter Schedule 40 Schedule 40 Schedule 40 Schedule 40

Minimum M-H’s per LF (Good Productivity)

Maximum M-H’s per LF (with less than Average to Poor

Productivity)

Minimum M-H’s per M (Good Productivity)

Maximum M-H’s per M (with less than Average to Poor

Productivity)

2 0.88 1.98 2.89 6.514 1.54 3.47 5.06 11.396 1.87 4.20 6.12 13.788 2.44 5.49 8.00 18.01

10 2.57 5.79 8.44 18.9912 2.70 6.09 8.87 19.9614 3.19 7.17 10.45 23.5116 3.48 7.82 11.40 25.6618 3.72 8.37 12.20 27.4520 4.12 9.28 13.52 30.4322 4.29 9.64 14.05 31.6224 4.45 10.01 14.59 32.82