injector / linac installation current status
DESCRIPTION
Injector / Linac Installation Current Status. Manager-Kathleen Ratcliffe Project Schedule R.M. Boyce Major Partner-Mechanical Fabrication Department Installation Underway!. 2006 Installation. Sector 21. Sector 20. Laser. BC1 Out. Bunch Compressor 1. Vault. X-Band Compressor. L1. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/1.jpg)
112-13 October 2006C.E. Rago
Injector / Linac Installation Current Status
Manager-Kathleen RatcliffeProject Schedule R.M. Boyce
Major Partner-Mechanical Fabrication Department
Installation Underway!
![Page 2: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/2.jpg)
212-13 October 2006C.E. Rago
2006 Installation
Bunch Compressor 1
BC1 Out
X-Band Compressor
L1
Insertion/SAB
Wall
Laser
Sector 20
Sector 21
Vault
![Page 3: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/3.jpg)
312-13 October 2006C.E. Rago
Linac Status
Downtime Installation 8/~20 Weeks of Linac AccessPrep and Removal CompleteInstallation Priority
Linac Housing / Return to A-Line Operation January 07Vacuum Envelope & All Safety SystemsInjection Vault / Laser Schedule and ControlsSLAC Resources / MFD and OthersHardware ReadySystem Schedule / Commissioning
Good Design, Teamwork, Control
![Page 4: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/4.jpg)
412-13 October 2006C.E. Rago
Linac Housing
E-
![Page 5: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/5.jpg)
512-13 October 2006C.E. Rago
BC 1 Out
TD11 (Stopper)
BL11/12
Future EO/BL
Wire Scanner / PMT
![Page 6: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/6.jpg)
612-13 October 2006C.E. Rago
Bunch Compressor 1
4 DipolesBC1 Diagnostics Chambers & Supports
2 Tweeker Quads
![Page 7: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/7.jpg)
712-13 October 2006C.E. Rago
Bunch Compressor 1 Sub-Assembly
![Page 8: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/8.jpg)
812-13 October 2006C.E. Rago
X-Band Compressor
WC 293Removable 60cm X-Band
![Page 9: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/9.jpg)
912-13 October 2006C.E. Rago
The X-band accelerator section
Klystron, modulator being power tested prior to installation.
![Page 10: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/10.jpg)
1012-13 October 2006C.E. Rago
L 1
2ea 9 ½ Ft DLWG
![Page 11: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/11.jpg)
1112-13 October 2006C.E. Rago
![Page 12: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/12.jpg)
1212-13 October 2006C.E. Rago
Linac Accelerator Section Removal
Before
After
Making room for the Insertion, L-1 and L-X regions
![Page 13: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/13.jpg)
1312-13 October 2006C.E. Rago
Insertion / SABBX 02 Dipole
SDMP / Stopper
OTRS1 / ANL
SAB Dipole
![Page 14: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/14.jpg)
1412-13 October 2006C.E. Rago
![Page 15: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/15.jpg)
1512-13 October 2006C.E. Rago
Injection Vault
E-
![Page 16: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/16.jpg)
1612-13 October 2006C.E. Rago
The Injector Vault
Cable plant, vault ready for beamline components.
![Page 17: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/17.jpg)
1712-13 October 2006C.E. Rago
Wall
BBS Radiation Stopper
3 Wire Scanners BX 01 Dipole
![Page 18: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/18.jpg)
1812-13 October 2006C.E. Rago
Heater Phase 1
Heater Table
![Page 19: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/19.jpg)
1912-13 October 2006C.E. Rago
L0A / L0B
L0AL0B
![Page 20: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/20.jpg)
2012-13 October 2006C.E. Rago
L0A on the MMF CMM
![Page 21: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/21.jpg)
2112-13 October 2006C.E. Rago
Gun / GTLLaser Table
Gun
SAB Dipole
![Page 22: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/22.jpg)
2212-13 October 2006C.E. Rago
Gun-to-Linac area
Gun
Laser table
Spectrometer
L0a
GTL
uv
![Page 23: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/23.jpg)
2312-13 October 2006C.E. Rago
The LCLS photocathode electron gun
![Page 24: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/24.jpg)
2412-13 October 2006C.E. Rago
Linac Downtime IssuesBPM feed-through 10-9 He leak
Old problem / New again (~3/23 BPMs On Temporary Hold)
BC 1 Diagnostics2/3 Assemblies close with Fab. SLA BPM is probably late for January.
Late components:BLM 11 (BLM 12 will be in)Toroids (All Locations / Vendor Failure)Vacuum chambers in insertion region. (next slide)
Spool pieces are being fabricated to not prevent Commissioning Start.Scheduled Downtime will be needed to install these components
January : March to support current Commissioning schedule.
![Page 25: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/25.jpg)
2512-13 October 2006C.E. Rago
LCLS Insertion region
Vac Chambers late for January
Linac integrity needed for ESA program in Jan.
Linac beam
LCLS Injection
![Page 26: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/26.jpg)
2612-13 October 2006C.E. Rago
Injector Installation Status
Injector installation has taken second priority to Linac installation.
Injector vault:Floor and cable plant installed
Injector beamline:Accelerator structures, L0a ready, L0b in final bakeRF waveguide needs to go through bakeGun in hot test at Klystron Mfg
2nd gun is in pre-braze cold-test.Vault Supports & Tables waiting DB start.
except for the GTL supports & table
![Page 27: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/27.jpg)
2712-13 October 2006C.E. Rago
Injector Installation Issues
Water system under pressure to make schedule!1 BPM in GTL waiting feedthrough resolution.
Late:Torroids are not delivered from Vendor The GTL stand is out for quote
Estimate it will be here 11/16 for installation 11/20.
Laser table installation begins 11/27 The Gun will be ready by Laser Table install. GTL is late, released for machining.
Working all issues with MFD to expedite schedule. Improve on 2/15/07 Date.
![Page 28: Injector / Linac Installation Current Status](https://reader031.vdocuments.mx/reader031/viewer/2022032612/56812d5c550346895d926861/html5/thumbnails/28.jpg)
2812-13 October 2006C.E. Rago
Some Good Stuff
Good Design with Solid Documentation.
Active Data BaseInterconnect Control
Component Histories
Non-Compliance
Effective Teamwork MFD/MD/KLY/AD
Downstream Linac under design!