INITIALIZATION AND ONGOING ACCEPTANCE
TESTING
![Page 2: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/2.jpg)
In order to use the contractor’s test results for acceptance and payment, ODOT must ensure that the contractor’s test results compare favorably with their own.
Favorable comparability will be determined by means of paired testing of split samples.
![Page 3: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/3.jpg)
INITIALIZATION TESTING
Minimum of 10 tests
1st Lot testing divided into 10 sublots
Optionally, initialization can be made
up of the first 2 lots of 5 sublots
Include plant start-up testing
![Page 4: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/4.jpg)
Each set of asphalt testing includes:
INITIALIZATION TESTING
✓1 AIR VOID TEST
✓1 AC CONTENT TEST
✓3 ROADWAY DENSITY TESTS
![Page 5: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/5.jpg)
At the conclusion of the sampling and associated
testing, a statistical “paired-t test” will be performed by ODOT using the pairs of initialization test data.
![Page 6: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/6.jpg)
If there is a significant bias:
ODOT’s test results will be relied upon until the source of the bias
has been identified and corrected. The lack of bias must then be validated by further “paired-t
testing”
![Page 7: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/7.jpg)
If Independent Evaluation requested:
The Contractor may request evaluation of the testing bias via three-way split sample testing with an independent laboratory.
ODOT will select the independent laboratory.
All initialization testing will be performed by all three laboratories using split samples.
![Page 8: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/8.jpg)
If ODOT testing shows a significant bias:
●The Contractor will not be held responsible for any additional costs
incurred by ODOT in conjunction with the 3-way split-sample testing
●The Contractor’s test results will be relied upon for acceptance and pay
adjustments
![Page 9: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/9.jpg)
If Contractor testing shows a significant bias:
●The Contractor shall reimburse ODOT for any additional costs incurred by
ODOT in conjunction with the 3-way split-sample testing
●ODOT’s test results will be relied upon for acceptance and pay adjustments
![Page 10: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/10.jpg)
If paired-t testing validates the Contractor’s test methods, the Contractor’s test results
will be used for acceptance and pay adjustment subject to:
●ODOT will perform ongoing testing at a minimum frequency of 1 independent test
per lot.
●Ongoing process verification over time will be performed using the F-test and the
t-test.
![Page 11: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/11.jpg)
If ODOT’s testing-bias Control Charts indicate an out-of-control condition
for testing bias:
Both the Contractor and ODOT will immediately investigate the probable
cause.
![Page 12: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/12.jpg)
If the probable cause is identified and corrected or if the resulting bias is, in ODOT’s judgment, not likely to exceed
the Allowable Testing Bias:
Acceptance and pay adjustments will continue to be based on the Contractor’s
results
At ODOT’s discretion, errant test results may be discarded. If replacement test results are
available, they may be substituted for discarded test results
![Page 13: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/13.jpg)
If the probable cause is not corrected or if the resulting bias is, in ODOT’s judgment, likely to exceed the allowable testing bias:
All subsequent testing will be paired testing until the source of the
unaccepatable testing bias is corrected.
During this period, acceptance and pay adjustments will be based on ODOT’s test
results.
![Page 14: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/14.jpg)
GUIDELINES FOR INITIAL VALIDATION OF CONTRACTOR’S TEST METHODS
●A paired test shall consist of 2 separate tests by ODOT and the
Contractor on a split sample
![Page 15: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/15.jpg)
PAIRED TESTING
On split samples test:●Air Voids
●Asphalt Cement Content
For Roadway Densities, perform paired tests on the same cores. The
first lab to test the cores should make sure to oven-dry the cores at
140°F instead of 230°F
![Page 16: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/16.jpg)
GENERAL PROCEDURE
Calculate , the average of thedifferences between the paired tests
pX
STEP 1
![Page 17: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/17.jpg)
Where:
np = Number of paired tests
Xd = ODOT’s individual test result for
Xp = The average of the differencebetween paired tests
Xc = The Contractor’s individual test result for each sample.
each sample.
p
n
1 idc
pn
)X(XX
p
![Page 18: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/18.jpg)
GENERAL PROCEDURE
Calculate Sp, the standard deviation of the differences between the
paired tests
STEP 2
![Page 19: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/19.jpg)
Where:
Sp = The Standard Deviation of the
np - 1 = Degrees of freedom, and
difference between paired tests,
Xc, Xd, np, and Xp as previously defined.
1n
XX(XS
p
n
1i
pdc
p
p
2)
![Page 20: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/20.jpg)
GENERAL PROCEDURE
Calculate tp, the paired-t teststatistic
STEP 3
![Page 21: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/21.jpg)
Where:
tp = The paired-t test statistic, andnp, Xp, and Sp as previously
defined. The vertical lines on either side of the equation indicate the need to take the ABSOLUTE VALUE of the
equation
Simply put, if the result of the calculation is NEGATIVE, change it to
a POSITIVE number
p
p
pp S
Xnt
![Page 22: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/22.jpg)
GENERAL PROCEDURE
Obtain the critical t-value, tcrit, from Table 1 in Appendix A
using np-1 degrees of freedom
STEP 4
![Page 23: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/23.jpg)
GENERAL PROCEDURE
Compare the calculated paired-t statistic (tp) to the critical t-value tcrit
STEP 5
If tp is less than tcrit, there is no statistically significant bias
If tp is more than tcrit, there is a statistically significant bias
![Page 24: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/24.jpg)
Compare the testing bias (Xp) to the associated allowable testing bias (ATB) from
the table in Appendix A:
If tp is more than tcrit
:
AC Quality Char. ATB Units
AC Content ± 0.15 % by weight Air Voids ± 0.50 % by volume
Roadway Density ± 0.50 % of Gmm
Note: ATB’s for aggregates are for control charts and
information only.
![Page 25: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/25.jpg)
If the magnitude of Xp is less than the magnitude of the corresponding ATB, the Contractor’s bias is statistically,
but not practically significant.
Contractor test results shall then be relied upon for acceptance and pay
adjustments
![Page 26: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/26.jpg)
If the magnitude of Xp is greater than or equal to the magnitude of the
corresponding ATB, the Contractor’s bias is practically significant and unacceptable.
Contractor test results shall not be relied upon until certified by a qualified
independent calibration specialist and validated through further paired-t testing.
![Page 27: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/27.jpg)
EXAMPLE - % Air Voids
TEST #
1 2 3 4 5 6 7 8 9
10
Xc 4.14.24.95.85.04.83.75.14.9
4.5
Xd 3.94.45.46.05.14.53.95.44.7
4.7
![Page 28: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/28.jpg)
Step 1 – Average DifferencesTEST #
1 2 3 4 5 6 7 8 9
10
Xc 4.14.24.95.85.04.83.75.14.9
4.5
Xd 3.94.45.46.05.14.53.95.44.7
4.7
Xc - Xd
0.2
-0.2-0.5-0.2-0.10.3
-0.2-0.3
0.2-0.2
Xp = -0.1
![Page 29: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/29.jpg)
Step 2 – Standard DeviationTEST #
1 2 3 4 5 6 7 8 9
10
Xp -0.1-0.1-0.1-0.1-0.1-0.1-0.1-0.1-0.1
-0.1
Xc - Xd - Xp 0.3
-0.1-0.4-0.1
0.00.4
-0.1-0.2
0.3-0.1
Xc - Xd
0.2
-0.2-0.5-0.2-0.10.3
-0.2-0.3
0.2-0.2
(Xc - Xd - Xp)2 = 0.58
(Xc - Xd - Xp)2
0.090.010.160.010.000.160.010.040.09
0.01
![Page 30: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/30.jpg)
Sp = 0.25386
1n
XX(XS
p
n
1i
pdc
p
p
2)
110
0.58Sp
![Page 31: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/31.jpg)
tp = 1.246
p
p
pp S
Xnt
0.25386
0.1-10tp
![Page 32: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/32.jpg)
Degrees ofFreedom(np – 1)
Criticalt-value
(tcrit)
9.925
3.250
23 5.8414 4.6045 4.0326 3.7077 3.4998 3.3559
3.16910
![Page 33: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/33.jpg)
tp = 1.246 < tcrit = 3.250
Since tp < tcrit, there is no statistical bias. Therefore the contractor’s
tests on this quality characteristic are valid and will be relied upon for acceptance and pay adjustments.
![Page 34: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/34.jpg)
ONGOING VALIDATION OF CONTRACTOR’S TEST METHODS
![Page 35: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/35.jpg)
GUIDELINES FOR ONGOING VALIDATION OF CONTRACTOR’S TEST METHODS
●Ongoing process verification over time will be performed using the F-test
and the t-test.
●The F-test provides a method for comparing the variances of the two data
sets.
● The t-test provides a method for comparing the means of the two data
sets.
![Page 36: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/36.jpg)
Contractor
Department
One independent
Contractor: Collect samples to split and test ¼, discard ¼, store 2nd half.
ODOT: Collect one sample per lot, independent of Contractor’s samples.
Test ¼, discard ¼, store 2nd half.
![Page 37: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/37.jpg)
GUIDELINES FOR ONGOING VALIDATION OF CONTRACTOR’S TEST METHODS
●First two lots do not yield enough data for F-test and t-test.
●These lots will be validated by comparing to D2S limits.
● If │Xc – Xd │≤ D2S limit, assumed from same population – Contractor’s accepted.
● If │Xc – Xd │> D2S limit, assumed from different populations – ODOT’s used.
![Page 38: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/38.jpg)
D2S LIMITS
Quality Characteristic D2S Limits
Asphalt Cement Content 0.30%
Air Voids (Lab Molded) 1.40%
Roadway Density 1.40%
![Page 39: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/39.jpg)
THIRD - FIFTH LOT AFTER INITIALIZATION
●Using the F-test and t-test for process verification.
●Use all data after Initialization, including that used for D2S comparisons.
● By third lot after Initialization there should be 15 contractor results and 3
ODOT results.
![Page 40: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/40.jpg)
SIXTH LOTS & FOLLOWING AFTER INITIALIZATION
●Still using the F-test and t-test for process verification.
●Use the current lot results plus the previous four for a total of five lots.
● Each of these analyses should include 25 contractor results and 5 ODOT results.
![Page 41: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/41.jpg)
F-test● Calculate the mean of each test set.
c
cc
n
XX
d
dd
n
XX
Xc = the mean of the Contractor’s results
Xd = the mean of the Department’s results
Xc = individual Contractor result
Xd = individual Department result
nc = the number of Contractor results
nd = the number of Department results
![Page 42: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/42.jpg)
F-test● Calculate the variance of each test
set.
nc - 1 = degrees of freedom of Contractor results
= the variance of the Contractor’s results2cs
nc - 1 = degrees of freedom of Department results
= the variance of the Department’s results2ds
1n
)XX(s
c
2cc2
c
1n
)XX(s
d
2dd2
d
![Page 43: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/43.jpg)
F-test● Calculate the F-statistic.
Use the larger of the variances in the numerator so that the F-statistic is always greater than one.
2d
2c
s
sF
2c
2d
s
sF or
![Page 44: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/44.jpg)
Compare the calculated F-statistic to the critical F-value Fcrit
If F is less than Fcrit, the data is assumed from the same population.
If F is more than Fcrit, the data is assumed from a different population
F-test Determine Fcrit from the F-distribution
table using a 0.01 significance level
![Page 45: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/45.jpg)
t-test
● Calculate the pooled variance, .
Where nc + nd - 2 = pooled degrees of freedom
2ps
2nn
1)(ns1)(nss
dc
d2dc
2c2
p
![Page 46: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/46.jpg)
t-test● Calculate the t-statistic.
d
sp
c
2p
dc
n
s
n
s
XXt
![Page 47: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/47.jpg)
Compare the calculated t-statistic to the critical t-value tcrit
If t is less than tcrit, the data is assumed from the same population.
If t is more than tcrit, the data is assumed from a different population
t-test Determine tcrit from the t-distribution
table using a 0.01 significance level and the pooled degrees of freedom
![Page 48: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/48.jpg)
Both the F-test and the t-test must show the results to be from the same population to
continue accepting the Contractor’s results
![Page 49: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/49.jpg)
If either test shows the results to be from different
populations, ODOT will test the remaining half of
the Contractor’s split samples for acceptance until the reason for the difference is resolved.
![Page 50: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/50.jpg)
EXAMPLE - % Asphalt Content1st Lot after Initialization – D2S Limits
Test # Xc Xd
11 4.18 4.08
12 4.37
13 4.27
14 4.19
15 4.21
After initialization, ODOT and Contractor samples are no longer split
samples but obtained independently
![Page 51: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/51.jpg)
Step 1: Compute Averages
Test # Xc Xd
11 4.18 4.08
12 4.37
13 4.27
14 4.19
15 4.21
Avg. 4.244 4.08
![Page 52: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/52.jpg)
Step 2: Compute D2S Comparison
S2DX-X dc
30.008.4244.4 - (D2S=0.30 from
Appendix A Part 2 for Asphalt Cement content)
True 30.0164.0
● Since is true, we assume that the test results come from the same population.
The Contractor’s results are accepted.
D2SX- dc X
![Page 53: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/53.jpg)
EXAMPLE - % Asphalt Content2nd Lot after Initialization – D2S Limits
Test # Xc Xd
12 4.21
16 4.14
17 4.27
18 4.21
19 4.14
20 4.27
![Page 54: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/54.jpg)
Step 1: Compute Averages
Test # Xc Xd
12 4.21
16 4.14
17 4.27
18 4.21
19 4.14
20 4.27
Avg. 4.206 4.21
![Page 55: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/55.jpg)
Step 2: Compute D2S Comparison
30.021.4206.4 -
True 30.0004.0
● Since is true, we assume that the test results came from the same population.
The Contractor’s results are accepted.
D2SXX dc
S2DX-X dc (D2S=0.30 from
Appendix A Part 2 for Asphalt
Cement content)
![Page 56: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/56.jpg)
EXAMPLE - % Asphalt Content3rd Lot after Initialization – Begin F & t
Test #
Xc XdTest
#Xc
Test #
Xc
11 4.18 4.08 16 4.14 21 4.19
12 4.37 4.21 17 4.27 22 4.21
13 4.27 4.11 18 4.21 23 4.14
14 4.19 19 4.14 24 4.00
15 4.21 20 4.22 25 4.50
![Page 57: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/57.jpg)
Step 1: Compute Mean for Each Set
c
cc
n
XX
d
dd
n
XX
4.224.219333315
63.29Xc
4.134.13333333
12.40Xd
![Page 58: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/58.jpg)
Step 2: Compute s2 (Variance) for Each Set
1n
)XX(s
c
2cc2
c
1n
)XX(s
d
2dd2
d
![Page 59: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/59.jpg)
Step 3: Compute sc2
Test # Xc(Xc-Xc)2
11
12
4.08
4.21
0.0025
0.0064
Sum
Sum/(nc-1)
25 4.50 0.0784
63.29 0.1797
0.1797 / (15-1)
0.01284sc2
Xc ≈ 4.22
![Page 60: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/60.jpg)
Step 4: Compute sd
Test # Xd (Xd-Xd)2
11 4.08 0.0025
12 4.21 0.0064
13 4.11 0.0004
Sum 0.0093
Sum/(nd-1)
0.0093/(3-1)
sd 0.00465
2
2
Xd ≈ 4.13
![Page 61: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/61.jpg)
Step 5: Compute F-statistic
2d
2c
s
sF
2c
2d
s
sF or
F NumeratorDenominat
orResult
1 0.01284 0.00465 2.76
2 0.00465 0.01284 0.36
Note: Pick F with largest numerator (highest result).
![Page 62: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/62.jpg)
Step 6: Pick Fcrit from F-distribution (2-tailed, =0.01) Table
n-1 13 14 15
2 199 199 199
3 43.3 43.2 43.1
n-1 2 3
13 8.19 6.92
14 7.92 6.68
15 7.70 6.48
For this example, contractor variance
was in the numerator with 14 degrees of
freedom and ODOT’s variance was in the denominator with 2
degrees of freedom. Read the table like this
Not like this!
![Page 63: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/63.jpg)
Step 7: Perform F-test
● Since F-test is true, we must perform
the T-test.
● Had F-test been false, the tests would not have come from the same population. The
Contractor’s results would not be accepted.
F ≤ Fcrit ? 2.75 ≤ 199 = True
![Page 64: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/64.jpg)
Step 8: Compute Pooled Variance
2ps
2nn
1)(ns1)(nss
dc
d2dc
2c2
p
2315
1)0.00465(31)-0.01284(15S2
p
0.0118s2p
![Page 65: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/65.jpg)
Step 9: Compute t-statistic
d
sp
c
2p
dc
n
s
n
s
XXt
30.0118
150.0118
4.134.22t
1.31t
Note: Without rounding, t ≈ 1.25.
![Page 66: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/66.jpg)
Step 10: Pick tcrit from t-distribution (2-tailed, =0.01) Table
DF tcrit
15 2.947
16 2.921
17 2.898
• Degrees of freedom = nc + nd – 2
DF = 15 + 3 – 2 = 16
![Page 67: INITIALIZATION AND ONGOING ACCEPTANCE TESTING. In order to use the contractors test results for acceptance and payment, ODOT must ensure that the contractors](https://reader035.vdocuments.mx/reader035/viewer/2022062619/551570e2550346486b8b4eec/html5/thumbnails/67.jpg)
Step 11: Perform t-test
● Since both t-test and F-test are true, we assume
that the test results came from the same population. The Contractor’s results are
accepted.
t ≤ tcrit ? 1.31 ≤ 2.921 = True