30 min Update w/WorkStream PM and SMEs Lync or Live Line by Line of Tasks Due Dozens of Workstreams Wednesday – Friday Preferred If Negative Slack, Review of Path in Meeting and Implore team for Cr ash Opportunitie s After meeting report of un-statused tasks, Critical Path if needed and Issues Program Level Review of All Workstreams, with TL, Negative Slack Paths, Low SPI Sources (if applicable) Additional Scrub for Needed Status and Negative Path Improvements Post to Customer Accessib le Share Site Decisi on on Postin g Prepare weekly Zip Program MPP Zip Package Friday or as agreed Integra ted Master Schedul e Review

Upload: fekovach

Post on 15-Jun-2015

50 views

Category:

Documents


1 download

DESCRIPTION

IMS Review Cycle

TRANSCRIPT

Page 1: IMS Review Cycle

30 min Update w/WorkStream PM and SMEs

Lync or Live Line by Line of Tasks

Due

Dozens of Workstreams

Wednesday – Friday Preferred

If Negative Slack, Review of Path in

Meeting and Implore team for

Cr ash Opportunities

After meeting report of un-

statused tasks, Critical Path if needed and

Issues

Program Level Review of All Workstreams,

with TL, Negative Slack Paths, Low

SPI Sources (if applicable)

Additional Scrub for Needed Status and

Negative Path Improvements

Post to Customer Accessible Share Site

Decision on

Posting

Prepare weekly Zip Program MPP Zip Package

Friday or as agreed

Integrated Master Schedule Review Cycle