IMPROVEMENTS ARE DOWN THE ROAD
OCTA.NET/SOUTHCOUNTY
CONSTRUCTIONBEGINS
MID2019
To address freeway travel demand, OCTA in partnership with Caltrans District 12 is implementing the San Diego Freeway (I-5) Widening project from SR-73 to El Toro Road in southern Orange County.
PROJECT IMPROVEMENTS
FOR MORE INFORMATION
OCI5SOUTHCOUNTY @SOUTHOC5INFOOCTA.NET/SOUTHCOUNTY
PROJECT FUNDINGCONSTRUCTION SEGMENTS
Sienna SegmentOso Pkwy to Alicia Pkwy
Mid-2019—Late 2023
Orange SegmentSR-73 to Oso Pkwy
Early 2020—Early 2025
Palm SegmentAlicia Pkwy to El Toro Rd
Mid-2020—Mid-2024
Voter Approved Nov. 2006
*All pictures shown are for illustration purposes only.
*Schedule subject to change
SEGMENT OVERVIEWNew northbound and southbound general purpose lanes help keep south Orange County moving. The improvements provide connectivity to local communities, businesses and schools, including Mission Viejo High School.
Oso Parkway to Alicia ParkwaySIENNA SEGMENT Estimated Construction Schedule: Mid-2019 to Late 2023
ANTICIPATED CONSTRUCTION SCHEDULE
2019 2020 2021 2022 2023 2024 2025
BEGINS ENDS
La Paz Rd
Muirlands Blvd
Marguerite Pkwy
La P
az R
d
Alici
a Pk
wyAl
icia
Pkwy
Cabot Rd
Paseo
De Vale
ncia
Oso Pkw
y
Oso Pkw
y
LAGUNA HILLS
MISSION VIEJO
MISSION VIEJO
LomarenaElementarySchool
ValenciaElementarySchool
Mission ViejoHigh School
Linda VistaElementarySchool
Mission ViejoCountry Club
*Map is not to scale
Interchange Improvement Segment BoundariesPROJECTLEGENDLa Paz Road interchange
DETAILS LENGTH: 2.6 milesADJACENT CITIES: Mission Viejo, Lake Forrest & Laguna HillsTOTAL ESTIMATED COST: $191 million
• Increase capacity / improve mobility• Add general purpose lane, northbound and southbound from Oso to Alicia Parkways
• Convert carpool lanes to continuous access• Add new and re-establish auxiliary lanes, improving operations
• Reconstruct La Paz Road interchange• Modify six on-and off-ramps at Oso Parkway• Add new sound and retaining walls
ROADWAY
STRUCTURE
OPERATIONAL
CONSTRUCTIONBEGINS
MID2019
SR-73 to Oso ParkwayORANGE SEGMENT
Marguerite Pkwy
Avery Pkwy
Cabo
t Rd Crow
n Valle
y Pkwy
Crow
n Va
lley
Pkwy
Pase
o de
Col
inas
Oso
Pkwy
MISSION VIEJO
LAGUNA NIGUEL
LAGUNA HILLS
Saddleback College
ViejoElementarySchool
The Center atRancho Niguel
ArroyoTrabucoGolf Club
The Shops at
Mission Viejo
MissionHospital
OCLine
MissionViejoCountry Club
*Map is not to scale
Kaleidoscope
73
73
ANTICIPATED CONSTRUCTION SCHEDULE
2019 2020 2021 2022 2023 2024 2025
BEGINS ENDS
Interchange ImprovementSegment BoundariesProject Boundary
PROJECTLEGEND
Estimated Construction Schedule: Early 2020 to Early 2025
SEGMENT OVERVIEWNew general purpose lanes in both directions allow access to local shops and restaurants, as well as healthcare and educational facilities. Commuters can also connect to Metrolink’s Laguna Niguel/Mission Viejo station.
DETAILS LENGTH: 2.1 milesADJACENT CITIES: Mission Viejo, Laguna Hills, Laguna Niguel & San Juan CapistranoTOTAL ESTIMATED COST: $191 million
• Increase capacity / improve mobility• Add general purpose lane, northbound and southbound from Avery to Oso Parkways
• Convert carpool lanes to continuous access• Add new and re-establish auxiliary lanes, improving operations
• Reconstruct and improve Avery Parkway interchange• Modify four on- and off-ramps at Crown Valley• Add new retaining walls
ROADWAY
STRUCTURE
OPERATIONAL
Oso Parkway interchange
Alicia Parkway to El Toro RoadPALM SEGMENT Estimated Construction Schedule: Mid-2020 to Mid-2024
ANTICIPATED CONSTRUCTION SCHEDULE
2019 2020 2021 2022 2023 2024 2025
BEGINS ENDS
Segment BoundariesProject BoundaryPROJECTLEGEND
Rockfield Blvd
Paseo DeValencia
los A
lisos
Blvd
El Toro Rd
Ridge Rte Dr
Lake
Fores
t Dr
Lagun
a Hills
Dr
Moulton Pkwy
El To
ro R
d
LAGUNA WOODS
LAGUNAHILLS
MISSIONVIEJO
LAKE FOREST
MemorialCareSaddlebackMedical Center
The Arbor
Laguna WoodsCity Hall
Alicia
Pkw
y
Muirlands Blvd
Muirlands Blvd
Alici
a Pk
wy
La P
az R
d
Laguna Hills MallLaguna Woods
Golf Club
Lake ForestGolf and
Practice Center
*Map is not to scale
SEGMENT OVERVIEWThe projects adds a general purpose lane and extends a second carpool lane in both directions. Lake Forest and Laguna Hills shops and restaurants are accessible, as well as MemorialCare Saddleback Medical Center.
DETAILS LENGTH: 1.8 milesADJACENT CITIES: Lake Forest, Laguna Hills & Laguna WoodsTOTAL ESTIMATED COST: $166 million
• Increase capacity / improve mobility• Widen freeway, northbound and southbound• Extend second carpool lane between Alicia Parkway and El Toro Road
ROADWAY
• Reconstruct Los Alisos Boulevard bridge• Add new retaining and sound walls• Modify six on-and off-ramps
STRUCTURE
• Convert carpool lanes to continuous access• Add new and re-establish auxiliary lanes, improving operations• Install new overhead signs
OPERATIONAL
Alicia Parkway interchange
LAKE FOREST
MISSION VIEJO
LAGUNA WOODS
ALISO VIEJO
LAGUNA NIGUEL Avery Pkwy
Crown Valley Pkwy
Oso Pkwy
La Paz Road
Alici
a Pk
wy
El To
ro R
d
LAGU
NA H
ILLS
PROJECTLEGEND
Project Boundary
Interchange ImprovementsOrange Segment - Early 2020 to Early 2025Sienna Segment - Mid-2019 to Late 2023
Palm Segment - Mid-2020 to Mid-2024
*Map is not to scale
Fernando ChavarriaOCI5SOUTHCOUNTY @SOUTHOC5INFO
OCTA.NET/SOUTHCOUNTY
73
73
CONSTRUCTIONBEGINS
MID2019
[email protected] 714-560-5306Logan Selleck
[email protected] 714-560-5573
Orange County Transportation AuthorityPublic Outreach RM 738550 S. Main St.P.O. Box 14184Orange, CA 92873-1584
*Schedule subject to change