improved set-up time delivers operational success

1
Find out more about the Xiamen plant’s continuous improvement successes here: traccsolution.com/resources/improved-setup-time/ infographic TRACC CASE STUDY Financial gains totalled RMB 500 000 with a three-month return on investment, and SCMC has made an across-the-board decision to also introduce TRACC at the Suzhou and Beijing sites. Following considerable success at its Dongguan plant, China’s Coca-Cola Supply Chain Management Company (SCMC) decided to introduce TRACC Best Practices to the Xiamen plant. Improved set-up time delivers operational success The plant’s key driver for rolling out TRACC was set-up time reduction. Before the roll-out, product set-up time at Xiamen took approximately 12 hours, which had a negative impact on net time utilisation. 12 hrs STR adoption was not an easy process. The turning point came when the front-line operators became involved and engaged in the plant-wide CI effort. This resulted in a highly motivated workforce and significant results were achieved within the first 12 months of implementation. Set-up time reduction became an internal benchmark for other SCMC sites to follow as the product set-up time dropped from 12 hours to just 4 hours. 4 hrs

Upload: tracc-value-chain-improvement-solution

Post on 22-Jan-2018

80 views

Category:

Business


2 download

TRANSCRIPT

Page 1: Improved set-up time delivers operational success

Find out more about the Xiamen plant’s continuous improvement successes here: traccsolution.com/resources/improved-setup-time/

infographicTRACC CASE STUDY

Financial gains totalled RMB 500 000 with a three-month return on investment, and SCMC has made an across-the-board decision to also introduce TRACC at the Suzhou and Beijing sites.

Following considerable success at its Dongguan plant, China’s Coca-Cola Supply Chain Management Company (SCMC) decided to introduce TRACC Best Practices to the Xiamen plant.

Improved set-up timedelivers operational success

The plant’s key driver for rolling out TRACC was set-up time reduction. Before the roll-out, product set-up time at Xiamen took approximately 12 hours, which had a negative impact on net time utilisation.

12 hrs

STR adoption was not an easy process. The turning point came when the front-line operators became involved and engaged in the plant-wide CI effort.

This resulted in a highly motivated workforce and significant results were achieved within the first 12 months of implementation.

Set-up time reduction became an internal benchmark for other SCMC sites to follow as the product set-up time dropped from 12 hours to just 4 hours.

4 hrs