Implementing Material Resource Efficiency practices and Logistics
Malcolm WaddellConstruction Project Manager
MRE Guide Material Logistics Plans Reverse Logistics
![Page 2: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse](https://reader033.vdocuments.mx/reader033/viewer/2022051412/55165a21550346b2068b5c44/html5/thumbnails/2.jpg)
MRE Guide for Regeneration and Major Project Support
![Page 3: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse](https://reader033.vdocuments.mx/reader033/viewer/2022051412/55165a21550346b2068b5c44/html5/thumbnails/3.jpg)
Regeneration
Linking the demolition and new-build stages to maximise resource efficiency.
WRAP regeneration guideBrings together:ICE Demolition ProtocolUsing reclaimed materialsGood practice site waste
managementIncreasing recycled content
![Page 4: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse](https://reader033.vdocuments.mx/reader033/viewer/2022051412/55165a21550346b2068b5c44/html5/thumbnails/4.jpg)
Current Projects
• England• Moss Side, Manchester• Loam Pit Vale, Lewisham
• Scotland• Bishopsbriggs, Glasgow• Raploch, Stirling• Clyde Gateway• Dumfries and Galloway
![Page 5: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse](https://reader033.vdocuments.mx/reader033/viewer/2022051412/55165a21550346b2068b5c44/html5/thumbnails/5.jpg)
Ongoing Work
Major Project Support– Work is being contracted.– Further five projects– Varied size and sector across England and
Wales– Client and Contractor Campaign Support
![Page 6: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse](https://reader033.vdocuments.mx/reader033/viewer/2022051412/55165a21550346b2068b5c44/html5/thumbnails/6.jpg)
Material Logistics Plans
![Page 7: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse](https://reader033.vdocuments.mx/reader033/viewer/2022051412/55165a21550346b2068b5c44/html5/thumbnails/7.jpg)
Material Logistics Plans
A tool to manage all materials from project conception through to demobilisation and completion.
Key aspects:Setting objectives and KPIs for
efficient material useMinimisation of materials through
attention to specifications, delivery & storage, handling & use, disposal
Identifying lessons learnt and best practice.
![Page 8: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse](https://reader033.vdocuments.mx/reader033/viewer/2022051412/55165a21550346b2068b5c44/html5/thumbnails/8.jpg)
Participating developments & projects
Leith Docks, Western and Granton Harbour on Edinburgh Waterfront
CaltongateCentral Edinburgh
![Page 9: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse](https://reader033.vdocuments.mx/reader033/viewer/2022051412/55165a21550346b2068b5c44/html5/thumbnails/9.jpg)
Participating developments & projects
Carmel CollegeSt Helens
Tubney BarnNear Oxford
Kennet IslandReading
![Page 10: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse](https://reader033.vdocuments.mx/reader033/viewer/2022051412/55165a21550346b2068b5c44/html5/thumbnails/10.jpg)
Participating projects
Farringdon StationCentral London
CrossrailMaidenhead - London - Essex - Kent
![Page 11: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse](https://reader033.vdocuments.mx/reader033/viewer/2022051412/55165a21550346b2068b5c44/html5/thumbnails/11.jpg)
Participating projects
Central St GilesCentral London
The Dartford HubDartford
HolboroughNear Maidstone
![Page 12: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse](https://reader033.vdocuments.mx/reader033/viewer/2022051412/55165a21550346b2068b5c44/html5/thumbnails/12.jpg)
A cross section
• Any type of project Housing - commercial - retail - public - schools
- transport - infrastructure
• Any size of project £ 16 billion - £600k
• Any location City centre - urban - rural
![Page 13: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse](https://reader033.vdocuments.mx/reader033/viewer/2022051412/55165a21550346b2068b5c44/html5/thumbnails/13.jpg)
How can material logistics help?
• Efficient construction• Reduced transport and associated CO2• Reduced productivity loss• Improved health & safety• Reduced damaged by:
Weather Bad storage conditions Unnecessary movements Poor handling
![Page 14: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse](https://reader033.vdocuments.mx/reader033/viewer/2022051412/55165a21550346b2068b5c44/html5/thumbnails/14.jpg)
Strategies
• Just-in-time• On site logistics specialists• Construction consolidation centres• Off-site manufacture• 4th party logistics• On-site marketplaces• IT solutions
![Page 15: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse](https://reader033.vdocuments.mx/reader033/viewer/2022051412/55165a21550346b2068b5c44/html5/thumbnails/15.jpg)
Traditional transport to site
Site
• Many separate deliveries• Un-coordinated arrivals • Risk of congestion on site and at gates• Many half empty lorries or …• Consignments too large• High stock levels on site• Empty return journeys• High traffic flow - high CO2
![Page 16: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse](https://reader033.vdocuments.mx/reader033/viewer/2022051412/55165a21550346b2068b5c44/html5/thumbnails/16.jpg)
Construction Consolidation Centres CCC
Site
Concrete, steelwork, very large items, and full vehicle loads when required, go directly to site
• Contractors deliver to CCC
• Mixed loads from CCC• Daily deliveries - JIT• Logistics operator runs
the CCC• Transport to site • On site handling• Waste removed on
return journeys• Bulked up, compacted
etc at the CCC
![Page 17: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse](https://reader033.vdocuments.mx/reader033/viewer/2022051412/55165a21550346b2068b5c44/html5/thumbnails/17.jpg)
Off site manufacturing OSM
• Controlled manufacturing environment
• Standardisation• Consistent quality• Shorter time on site• Design freeze• Packaging• Transport and Travel• Reduced cost and risk
![Page 18: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse](https://reader033.vdocuments.mx/reader033/viewer/2022051412/55165a21550346b2068b5c44/html5/thumbnails/18.jpg)
WRAP case studiesSpecific case studies examples developed by WRAP looking at:
Volumetric methods – CAD CAM software helps reduce waste <0.6% Pre-fabrication: Pods – post production waste <1%
Pre-cast concrete – Bison have reduced waste to landfill <1% using their system
Timber frame - <2% waste sent to landfill
Light Steel Frame – materials requirements down 5% and wastage reduced from 12% to <1%
![Page 19: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse](https://reader033.vdocuments.mx/reader033/viewer/2022051412/55165a21550346b2068b5c44/html5/thumbnails/19.jpg)
SECTION 1 RESPONSIBLE PERSONS, TRAINING AND COMMUNICATIONSECTION 2 TRAINING AND COMMUNICATIONS PLANSECTION 3 MATERIAL REQUIREMENTSSECTION 4 MATERIALS RECEIPT, STORAGE AND MANAGEMENT SECTION 5 MANAGEMENT OF SUB-CONTRACTORS SECTION 6 SITE MOBILISATION AND CONSTRUCTIONSECTION 7 PROJECT DEMOBILISATION AND COMPLETION SECTION 8 REVIEW
Material Logistics Plan
![Page 20: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse](https://reader033.vdocuments.mx/reader033/viewer/2022051412/55165a21550346b2068b5c44/html5/thumbnails/20.jpg)
Implementation of MLP
Pilot project using WRAP
template
Internal review
Adapt and make part of
co procedures
Programme for co-wide
rollout
Monitor performance, SWMP data
Build own database of
KPIs
Continuous review of KPI and
procedures
Engage with contractors
Phase 1Phase
2Phase
3
Engage with contractors
![Page 21: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse](https://reader033.vdocuments.mx/reader033/viewer/2022051412/55165a21550346b2068b5c44/html5/thumbnails/21.jpg)
Reverse LogisticsWAS620
Efficient use of vehicles visiting site – promoting better waste management
![Page 22: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse](https://reader033.vdocuments.mx/reader033/viewer/2022051412/55165a21550346b2068b5c44/html5/thumbnails/22.jpg)
Materials arrive on site in delivery vehicles, are dropped off, and the vehicle leaves empty
Waste vehicles arrive on site empty and leave full with waste
The reverse logistics concept
A logistics operation that seeks to avoid the empty journeys, and promote the take-back of un-used and wasted materials could have a range of environmental benefits
![Page 23: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse](https://reader033.vdocuments.mx/reader033/viewer/2022051412/55165a21550346b2068b5c44/html5/thumbnails/23.jpg)
The concept
Take-back schemes are becoming more common offerings to UK construction sites
There is a real opportunity here to:
Promote the take-back of unused / waste product and packaging by delivery vehicles
Reduce vehicle movements and mileages associated with material supply and waste management
Reduce the environmental impact of construction
![Page 24: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse](https://reader033.vdocuments.mx/reader033/viewer/2022051412/55165a21550346b2068b5c44/html5/thumbnails/24.jpg)
The Reverse Logistics ModelExcel based model compares current against potential
The model reports the results in terms of:
The proportions of waste, recyclate and back-hauled material
The costs of material purchase, waste management and back-hauling
The number of miles travelled for delivery and waste travelled
The associated carbon footprint
![Page 25: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse](https://reader033.vdocuments.mx/reader033/viewer/2022051412/55165a21550346b2068b5c44/html5/thumbnails/25.jpg)
Current Case Study – North Staffs Hospital (Laing O’Rourke)
![Page 26: Implementing Material Resource Efficiency practices and Logistics Malcolm Waddell Construction Project Manager MRE Guide Material Logistics Plans Reverse](https://reader033.vdocuments.mx/reader033/viewer/2022051412/55165a21550346b2068b5c44/html5/thumbnails/26.jpg)
Any questions?