iesl estimate
TRANSCRIPT
-
8/22/2019 IESL Estimate
1/14
A - EXCAVATION & EARTHWORK
Rates for Excavation and Earthwork shall include for:
(a)
(b) Leveling and consolidating where required under slabs or sub-floor layers.
(c) Back filling and well ramming around foundation.
(d)
(e) Any necessary additional excavation for working spaces, planking and strutting etc.
(f) Providing shoring work where necessary.
Item
No.Description Unit Quantity Rate Amount
A-1 Removing top soil to a depth of 150mm and
depositing as directed within the site
sqm 213.00 88.00 18,744.00
A-2 Excavation for foundation in any materialexcept rock requiring blasting, part return fill
in and ram, and surplus dispose within the site
as directed.
cum 87.00 418.00 36,366.00
A-3 Filling under floors with gravel or other
approved quality of filling, spread, watered
and well rammed in 150mm layers (material
not available at site)
cum 259.00 2,554.00 661,486.00
A-4 Anti termite treatment on excavated
foundation and compacted soil under floors
(Should be use Approved Chemicals In
Pesticide Dept ) - Warranty period 10 years
sqm 332.00 385.00 127,820.00
844,416.00
B - MASON
Rates for Masonry work shall include for:
(a) All joggles, clamps, dowels, ties, and templates.
(b) Rough and fair cutting forming splays.
(c) Angles, reveals and returns.
Instructions :
(a) Cement used should be SLS Certified Products for Masonry work
(b) Average crushing strength of 10 blocks shall be not less than 2.8 N/mm2
Item
No.Description Unit Quantity Rate Amount
Rubble Masonry
B-1 150-225mm Random Rubble Masonry in
cement mortar 1:5 above 1 cube
cum 37.60 10,306.00 387,505.60
387,505.60Sub Total - B carried to summary
Trimming sides, keeping clean, leveling, grading and consolidating bottom of bases and trenches etc.
Keeping all excavations free from storm or percolating water to keep excavation dry at all stages of
construction.
Sub Total - A carried to summary
Estimate for the Construction of IESL - NCP Centre Building at
Korakahawewa, Anuradhapura
1
-
8/22/2019 IESL Estimate
2/14
C - CONCRETOR
(a) Grade 25 Recommended Mix 1 : 1 : 3 (20mm)
(b) Grade 20 Recommended Mix 1 : 2 : 4 (20mm)
(c) Grade 15 Recommended Mix 1 : 3: 6 (40mm)
Rate shall include,
(a) Mixing, hoisting, placing and compacting on the surfaces of any material or on formwork.
(b) Forming any construction joint.
(c) Vibrating, curing and protecting concrete surfaces from harmful weather conditions.
(d) Forming sloping on upper surfaces where required.
(e) Grouting the earlier concreted edges.
(f) Making good after removal of formwork.
Instructions
(a)
(b)
(c) Cement used should be SLS certified products approved for concrete.
(d) Reinforcement and formwork paid separately where not mentioned.
Item
No.Description Unit Quantity Rate Amount
C-1 Cement concrete grade 15 above one cube. cum 19.51 12,611.00 246,040.61
C-2 Cement concrete grade 20 in column
foundation, column shaft and plinth beams
using mixer and vibrator - up to first floor
level
cum 25.42 16,360.00 415,871.20
C-3 Cement concrete grade 20 in column shaft
using mixer and vibrator - up to second floor
level
cum 4.92 17,135.00 84,304.20
C-4 Cement concrete grade 20 in slab, beams and
stair case using mixer and vibrator - up to first
floor level
cum 33.20 16,847.00 559,320.40
C-5 Cement concrete grade 20 in lintels
(reinforcement and shuttering paid separately)
using mixer and vibrator - up to first floor
level
cum 1.39 14,840.00 20,627.60
1,326,164.01
Grade of concrete used in the construction and recommended mixes as follows.
Prior approval for any concrete work should be taken from the Engineer.
Sub Total - C carried to summary
Approval for constituent materials and test reports for properties of concrete should be taken from
Quality Control Engineer, Quality Control lab, Kekirawa with contractor's expense.
2
-
8/22/2019 IESL Estimate
3/14
D - FORMWORK
Rates for formwork shall include for:
(a)
(b) Erecting, Striking off and cleaning of formwork.
(c) Rubbing down, filling and making good the surface of concrete after removal of formwork.
Instructions
(a)
Item
No.Description Unit Quantity Rate Amount
D-1 12mm Plywood shuttering for slab, beams and
staircase including dismantling - up to first
floor level
sqm 280.19 1,264.00 354,160.16
D-2 12mm Plywood shuttering for column shaft
including dismantling - up to first floor level
sqm 97.20 1,425.00 138,510.00
D-3 12mm Plywood shuttering for column shaft
including dismantling - up to second floor
level
sqm 97.20 1,470.00 142,884.00
D-4 Shuttering for plinth beams and lintels
including dismantling - up to first floor level
sqm 39.18 942.00 36,907.56
D-5 Shuttering for lintels including dismantling -
up to second floor level
sqm 8.66 1,091.00 9,448.06
681,909.78Sub Total - D carried to summary
All framing, propping, bracing, cutting angles, bolting, wedging, cleaning, wetting and treating
before pouring concrete.
All the formwork for slabs should be done in such a way that it is good enough to apply a layer of
skim coat or suitable pillar and painting, without soffit plastering.
3
-
8/22/2019 IESL Estimate
4/14
E- REINFORCEMENT
Rates for Reinforcement shall include for:
(a) Rolling margin and waste.
(b) Bending, cutting, fabricating, hoisting, and placing in position.
(c) Holding and supporting including temporary fixing supports, hangers.
(d) Cleaning and wire brushing.
(e) All spacing, laps etc. in reinforced steel other than design laps.
(f)
Instructions
(a) Inevitable laps should be measured.
(b) Unless otherwise specified laps to be 50 times the diameter of the bar.(c)
(d)
(e)
Item
No.Description Unit Quantity Rate Amount
E-1 Tor steel rods reinforcing in Column
foundation and plinth beams up to DPC,
bent to shape laid in position and tied with G.I.
Wire as directed
M.Ton 1.83 202,614.00 370,783.62
E-2 Tor steel rods reinforcing in columns, beams,
slabs and lintels up to first floor levelbent to
shape laid in position and tied with G.I. Wire
as directed
M.Ton 4.40 209,814.00 923,181.60
E-3 Tor steel rods reinforcing in columns, beams,
slabs and lintels up to second floor level bent
to shape laid in position and tied with G.I.
Wire as directed
M.Ton 0.83 216,294.00 179,524.02
E-4 Mild steel rods, shape into stirrups and laid in
position and tied with GI wires as directed - upto first floor level
M.Ton 0.36 208,854.00 75,187.44
1,548,676.68Sub Total - E carried to summary
Reinforcements should be CN, GTB or LANWA. Tensile strength of reinforcements should be tested
if requested, from the institution where specified by the Engineer with contractor's expense.
Some trade names are used only for the purpose of indicating the minimum level of quality and
standards.
Tensile strength of Tor Steel should be not less than 460 N/mm2 and Mild Steel should be not less
than 250 N/mm2
Preparation, supplying & binding of cover blocks such that specified cover is maintained at outer-
most rod.
4
-
8/22/2019 IESL Estimate
5/14
F - BRICK LAYER
Rates for Brickwork shall include for:
(a) Wetting well all the surfaces of the bricks before using.
(b) Plumbing angles.
(c) Normal straight cuttings.
(d) Ranking of joints for plastering.
(e) All the necessary scaffolding.
(f) Ranking of joints for plastering.
Instructions :
(a) Cement used should be SLS Certified Products for Masonry work
(b) Average crushing strength of 10 bricks shall be not less than 7.0 N/mm2
Item
No.Description Unit Quantity Rate Amount
F-1 Arch, segmental, brick in cement sand 1:3,
including plumbing angles, normal straight
cutting, forming rebated reveals and raking of
joints for plastering
cum 1.62 15,497.00 25,105.14
F-2 225mm thick brick work in cement - sand
mortar 1:8 (up to first floor level)
cum 28.29 11,923.00 337,301.67
F-3 225mm thick brick work in cement - sand
mortar 1:8 (up to second floor level)
cum 32.11 12,447.00 399,673.17
F-4 Brick 112mm thick in cement - sand mortar
1:5 (up to first floor level)
sqm 21.88 1,440.00 31,507.20
793,587.18
G - PLASTERER
Rates for wall finishing shall include for:
(a) Temporary rules, screeds, ground etc.
(b) Ranking out joints of brickwork and backing concrete surface for forming key.
(c) Joints between different surfaces.
(d) Forming arises and stopping against joinery work, metal work etc.
(e) Making good around pipes, sanitary fittings and fixtures.
(f)
(g)
(h) Cement used should be SLS Certified Products for masonry work.
Sub Total - F carried to summary
Straight cutting and raking cutting holes, notching and other sundries Labour of a like nature.
Preparing sample panel of different finishes described below for the approval of the Engineer. Each
panel not less than 0.5 m2 in area.
5
-
8/22/2019 IESL Estimate
6/14
Item
No.Description Unit Quantity Rate Amount
G-1 D.P.C., 20mm thick, in cement-sand mortar
1:2 finished with two coats of hot tar applied at
the rate of 0.25 liters per sqm. for each coat
sqm 33.10 787.00 26,049.70
G-2 20mm thick plinth plaster in 1:3 cement - sand
mortar finished smooth with neat cement
floating.
sqm 21.30 637.00 13,568.10
G-3 Cement plastering with 1:5 mix, 15mm thick
finished semi rough in external walls - up to
first floor level
sqm 127.49 413.00 52,653.37
G-4 Cement plastering with 1:5 mix, 15mm thick
finished semi rough in external walls - up to
second floor level
sqm 120.51 451.00 54,350.01
G-5 Cement plaster with 1:5 mix, 15mm thick
finished smooth with skim coat in internal
walls - up to first floor level
sqm 239.91 582.00 139,627.62
G-6 Cement plaster with 1:5 mix, 15mm thick
finished smooth with skim coat in internal
walls - up to second floor level
sqm 107.62 642.00 69,092.04
G-7 Reveals or plaster band 150mm wide in walls
with cement lime and sand 1:1:5 mix finished
to match existing
Lm 101.75 226.00 22,995.50
G-8 Finish smooth soffit of slab by applying skim
coat - up to first floor level
sqm 139.04 282.00 39,209.28
G-9 15mm thick plaster to R.C.C. columns, beams
and soffit of slab in cement - sand 1:3 mix
including floating with lime putty - up to first
floor level
sqm 160.62 636.00 102,154.32
G-10 15mm thick plaster to R.C.C. columns, beams
and soffit of slab in cement - sand 1:3 mix
including floating with lime putty - up to
second floor level
sqm 87.48 708.00 61,935.84
581,635.78Sub Total - G carried to summary
6
-
8/22/2019 IESL Estimate
7/14
H - PAVIOR
Rates for paving and tiling shall include for:
(a) Preparing surfaces of concrete / brick to receive rendering plaster bedding etc.
(b) Joints between different surfaces.
(c) Finishing to slopes and cross falls.
(d) Straight cutting and waste of tiles and other types of floor finishes.
(e) Protecting finished surfaces.
(f) For temporary rules, screeds, ground etc.
(g) All normal cutting arises, rounded edges, bedding and pointing.
(h) Slope should be maintained to a suitable direction to flow the water towards out side.(i) Expansion joints so that no cracks propagated.
(j) Tiles should be approved by the Architect
Item
No.Description Unit Quantity Rate Amount
H-1 Tile glazed 200x200mm, Sri Lankan made of
approved type and colour, with all specials,
supplied and fixed to wall including raking
plaster and bedding in cement mortar 1:2, with
tile beadings on top and edges - Ground floor
sqm 26.46 3,228.00 85,412.88
H-2 Homogeneous Floor tile, 300x300mm, Sri
Lankan made, nonskid pattern of approvedtype and colour supplied and laid including
plaster bedding 1:2 with skirting and tile
beadings on top - Ground floor
sqm 208.44 3,302.00 688,268.88
H-3 Homogeneous Floor tile, 300x300mm, Sri
Lankan made, nonskid pattern of approved
type and colour supplied and laid including
plaster bedding 1:2 with skirting and tile
beadings on top - First floor
sqm 161.77 3,333.00 539,179.41
H-4 Skirting 25x100mm in 1:5, projected or flush
with walls and including forming groove
lm 101.66 177.00 17,993.82
1,330,854.99Sub Total - H carried to summary
7
-
8/22/2019 IESL Estimate
8/14
I - IRON WORK
Rates for Metal work shall include for:
(a) To make good ground at balusters on completion.
(b) Welding where necessary.
(c) Wire brush and clean metal surfaces prior to painting.
(d) All fabricating work handling, hosting, fitting and fixing in position.
(e) Preparing surfaces and painting as specified or directed.
Item
No.Description Unit Quantity Rate Amount
I-1 Roof Works 2,000,000.00
2,000,000.00
J - PAINTER AND DECORATOR
Rates for painting shall include for:(a) Preparation of surfaces, cleaning down.
(b) Smoothing, knotting, stopping etc.
(c) Protecting floors and fittings etc.
(d) Removing and replacing doors furniture and cleaning upon completion.
(e) Providing samples and specification of all paints to be used in the works.
(f) Providing painting to an approved colour scheme design.
(g) All the paints are to be done up to the manufacturers specification.
(h)
Item
No.Description Unit Quantity Rate Amount
J-1 Prepare and apply one coat of Alkali resistant
primer and two coats of emulsion paint to
walls - up to first floor level
sqm 237.91 288.00 68,518.08
J-2 Prepare and apply one coat of Alkali resistant
primer and two coats of emulsion paint to
walls - up to second floor level
sqm 107.62 315.00 33,900.30
J-3 Prepare and apply one coat of Alkali resistant
primer and two coats of emulsion paint soffit
of slabs - up to first floor level
sqm 127.49 296.00 37,737.04
J-4 Prepare and apply one coat of Alkali resistant
primer and two coats of emulsion paint to
soffit of slabs - up to second floor level
sqm 120.51 323.00 38,924.73
J-5 Water - Proofing of Bathrooms with approved
materials as per Instructions
sqm 30.06 341.00 10,250.46
189,330.61
Preparation sample panels of different finishes for the approval of the Engineer. Each panel not less
than 0.5 sqm in area.
Provisional Sum
Sub Total - I carried to summary
Sub Total - J carried to summary
8
-
8/22/2019 IESL Estimate
9/14
K - PLUMBER
Rates for Plumbing shall include for:
(a)
(b) Testing installations on completion.
(c) Chasing in brickwork / block work / concrete floor / concrete columns and make good.
(d) Fixing pipes to brickwork / block work.
(e) Solder rivets, screws, nails, clips, brackets, straps etc.
(f) Testing installations on completion.
(g) Sterilization, of Drinking water pipes on completion.
FIXTURES, APPLIANCES AND EQUIPMENT
Rates for sanitary fixtures shall include for:
(a) Installation complete with plugs.
(b) Grated waste outlets.
(c) Brackets and all fixings including jointing to pipes.
Instructions
(a)
(b)
(c) All the UPVC pipes to be SLS certified products.
(d)
Item
No.Description Unit Quantity Rate Amount
K-1 Plumbing and Sanitory works 500,000.00
500,000.00
Excavation of trenches for services, pipes or drain pipes shall include for deepening and widening as
necessary to enable the barrels of pipes, ducts etc. to rest on firm ground and to facilitate jointing .
Prior approval from the architect should be taken for all the sanitary fittings and accessories.
Guarantee certificates of fittings should be submitted to the Department with the bills. No payment is
done without bills.
Some trade names are used only for the purpose of indicating the minimum level of quality and
standards.
Sub Total - K carried to summary
Provisional Sum
9
-
8/22/2019 IESL Estimate
10/14
L - DRAINLAYER
Rates for underground drainage shall include for:
(a) Short lengths, joints and cutting at Manholes.
(b) Cutting and fixing pipe work to fittings.
(c) Testing.
(d) Grading to slopes and falls.
Item
No.Description Unit Quantity Rate Amount
L-1 Drainlayer 500,000.00
500,000.00
Provisional Sum
Sub Total - L carried to summary
10
-
8/22/2019 IESL Estimate
11/14
M - ELECTRICAL INSTALLATION
Rates for Electrical Installations shall include for:
(a) All necessary conduits, cables, fittings, screws, nails clips, brackets straps, and the like.
(b) Giving notices, obtaining permits, paying fees etc.
(c) Provision of drawings or circuit diagrams etc.
(d) Labeling switch and switches or other fittings.
(e) Providing samples of switches or other fittings.
(f) Earthening and testing installation as required.Instructions
(a)
(b) All electrical installation shall be for 400 volts / 230 volts 50 Hz.
(c)
(d) No joints are permitted in the runs of cables.
(e) Fixing heights from finished floor level, unless directed otherwise shall be as follows,
Main switches (switch fuses) - 1.5 m Distribution boards - 1.7 m
Lamp fittings - 2.4 m Ceiling fans - 2.5 m
Switches and fan regulators - 1.4 m Socket outlets - 0.2 m(f) Current operated ELCBs.
(g) Earth resistance shall be less than 5 Ohms, tested on a dry day.
(h) All fan regulators to be earthen.
(i)
Item
No.Description Unit Quantity Rate Amount
M-1 Electrical Installation 6,100,000.00
6,100,000.00
Some trade names are used only for the purpose of indicating the minimum level of quality and
standards.
Before conduit pipes are laid on concrete floor slabs, a conduit layout drawing shall be prepared by
the contractor for the approval of consultant.
5 Amp final sub-circuits shall be carried out by the looping-in method.
Sub Total - M carried to summary
Provisional Sum
11
-
8/22/2019 IESL Estimate
12/14
12
-
8/22/2019 IESL Estimate
13/14
N - Aluminium Work
Specifications
(a) All the Aluminium members used for work should have following properties
1. Temper - T5
2. Tensile Strength - 155 Mpa
3. Elongation - 7% (Minimum)
(b) Surface Treatment to be done to get following thicknesses
1. Anodizing - Coating Thickness - 10-15 Microns
2. Powder Coating - Coating Thickness - 60-80 Microns
(c) Glass should be float with thickness 5 mm
ItemNo.
Description Unit Quantity Rate Amount
N-1 Powder coated Aluminium Doors & Windows 1,700,000.00
1,700,000.00
Provisional Sum
Sub Total - N carried to summary
13
-
8/22/2019 IESL Estimate
14/14
ITEM NO DESCRIPTION AMOUNT
A SUB TOTAL A - EXCAVATOR 844,416.00
B SUB TOTAL B - MASON 387,505.60
C SUB TOTAL C - CONCRETOR 1,326,164.01
D SUB TOTAL D - FORMWORK 681,909.78
E SUB TOTAL E- REINFORCEMENT 1,548,676.68
F SUB TOTAL F - BRICKLAYER 793,587.18
G SUB TOTAL G - PLASTERER 581,635.78
H SUB TOTAL H - PAVIOR 1,330,854.99
I SUB TOTAL I - I RON WORK 2,000,000.00
J SUB TOTAL J- PAINTER AND DECORATOR 189,330.61
K SUB TOTAL K- PLUMBER 500,000.00
L SUB TOTAL L- DRAIN LAYER 500,000.00
M SUB TOTAL M- ELECTRICAL INSTALLATION 6,100,000.00
N SUB TOTAL N- ALUMINIUM WORK 1,700,000.00
TOTAL 18,484,080.63
Prepared by :
SUMMARY