A New Bridge Proposal Taylor’s University Lakeside Campus
Foundation in Natural and Built Environments
Introduction to the Construction Industry [QSB 30105]
Assignment 3
The Project Brief
Name: Pang Khai Shuen Name: Yong Yu Joon
Student ID: 0318423 Student ID: 0318299
Introduction to the Site:
The site measures about 9m x
30m and is located at the lake in
Taylor’s University Lakeside
Campus. The lake measures 5.5
acres and is man made with the
construction of the Lakeside
Campus.
Site Analysis:
Accessibility:
The boardwalk is usually not utilised because it is hard to reach and does not lead to any other
places. Building the bridge will help to draw people in as it will lead to the commercial block.
Walkability:
Before Construction
Students from Block C, D and E have to take a long
walk to reach the commercial block. To get to the
opposite, the average time needed is 5 minutes.
After Construction:
Students can now access the boardwalk
and reach the commercial block via the
bridge. This will shorten the time needed
to around 1 minute
Suggestion and Proposal:
It is hereby proposed to build a food and beverage bridge from Block E of
Taylor’s University Lakeside Campus to Commercial Block.
The bridge is a 30m long suspension bridge, with 6m width at the narrow point and
9m width at the bulging point. There are 8 suspension points on the bridge as
indicated in the following drawing.
The bridge is split into 3 segments, and each segment has a 6m x 4m capsule that can
be rented as cafes. There are also 3m x 1m tables accompanied by 6 chairs between
each capsule. Each capsule will be fitted with 2 sliding doors to prevent space
wastage by the door arc.
The main material for this bridge is tempered glass. 22mm glass is used for the
flooring, 1.2m high 12mm glass is used for the steel railing, 8mm glass is used for the
capsule wall, and 12.38mm laminated glass is used for the capsule canopy.
This bridge will serve as a new walkway for students and staffs in the university, and
also provide a new location for food and beverage.
Rationale and benefits:
a. Benefits to client:
i. Earns extra income as stalls on the bridges can be rented, generating
extra income.
b. Benefits to students: i. Provides a new location for students to spend extra time.
ii. Provides better access for students to the Commercial Block.
iii. Provides new alternatives of food and beverages for students.
c. Benefits to the Campus: i. Increases campus value.
ii. Enhances the lake view.
iii. Improves walkability around the campus.
PKS JURUUKUR BAHAN
Item
Description
Unit
Quantity
Rates Amount
RM RM
A.
B.
C.
D.
E.
SUSPENSION BRIDGE
OVERALL STRUCTURAL WORKS
ELEMENT NO.1: SUSPENSION
STRUCTURE
Vibrated reinforced concrete Grade 35 as
described in:-
Pillar
Footing
Beam
High Tensile Steel Bar Reinforcement as
described in:-
High Tensile Steel Bars
Suspension Cables
M3
M3
M3
Kg
Kg
50
250
150
45,000
20,000
220.00
220.00
220.00
3.50
10.00
11 000.00
55 000.00
33 000.00
157 500.00
200 000.00
Total to overall summary page 456 500.00
DOCUMENTE/4 – BILLS OF QUANTITIES
PKS JURUUKUR BAHAN
Item
Description
Unit
Quantity
Rates Amount
RM RM
A.
B.
C.
D.
SUSPENSION BRIDGE
OVERALL STRUCTURAL WORKS
ELEMENT NO.2: MAIN STRUCTURE
22mm Thick tempered glass 30% of blue tint
as described in Manufacture Specification:-
Flooring
1.2m High 12mm Thick tempered glass 30%
of blue tint with stainless steel railing design
as described in Manufacture Specification:-
Railing
8mm Thick tempered glass 30% blue tint as
described in Manufacture Specification:-
Walls
12.38mm Thick laminated glass (colour to be
selected by Client) completed with Hollow
Mild Steel section painted with white Powder
Coated as described in Manufacture
Specification:-
Canopy
M2
M2
M2
M2
250
72
180
72
560.00
450.00
327.00
625.60
140 000.00
32 400.00
58 860.00
46 987.20
Total to overall summary page 278 238.20
DOCUMENTE/4 – BILLS OF QUANTITIES
PKS JURUUKUR BAHAN
Item
Description
Unit
Quantity
Rates Amount
RM RM
A.
SUSPENSION BRIDGE
OVERALL STRUCTURAL WORKS
ELEMENT NO.3: DOORS
Supply, delivery to site and install the
following door as described all to the
approval and satisfaction of Client
Aluminium Glass Door
6mm Thick approved aluminium glass sliding
door overall size 1800 x 2100mm high in double
leaf all as per “Door Schedule” (Type SD1)
No.
6
1450.00
8700.00
Total to overall summary page 8700.00
DOCUMENTE/4 – BILLS OF QUANTITIES
PKS JURUUKUR BAHAN
Item
Description
Unit
Quantity
Rates Amount
RM RM
A.
B.
C.
D.
E.
F.
G.
SUSPENSION BRIDGE
OVERALL STRUCTURAL WORKS
ELEMENT NO.4: MECHANICAL &
ELECTRICAL WORKS
Cold Water Piping C/W all accessories
50mm Diameter HDPE pipe PN 20
20mm Diameter HDPE pipe PN 20
Waste Water Piping
150mm Diameter HDPE pipe PN 10
Multimedia Supply
“Amphenol Spectra Strip” 30.5m Length Fibre
Optic Ribbon 12 x 125µm cables with orange
PVDF jacket
Electrical Supply
3 Phase Power Supply from TNB BHD c/w all
necessary cabling, steel trunking, internal
wiring works and power points
3 phase cable (Lump Sum)
Internal wiring works (Lump Sum)
Power point (Lump Sum)
M
M
M
No.
40
25
40
1
50.00
40.00
75.00
5500.00
2000.00
1000.00
3000.00
5500.00
20 000.00
5000.00
1000.00
Total to overall summary page 37 500.00
DOCUMENTE/4 – BILLS OF QUANTITIES
PKS JURUUKUR BAHAN
Item
Description
Unit
Quantity
Rates Amount
RM RM
SUSPENSION BRIDGE
OVERALL SUMMARY
Element No. 1: Suspension Structure
Element No. 2: Main Structure
Element No. 3: Door
Element No. 4: Mechanical and Electrical
Works
456 500.00
278 238.00
8700.00
37 500.00
Total Overall Cost 780 938.00
DOCUMENTE/4 – BILLS OF QUANTITIES