Introduction
EnergyServ is a professional services organization specializing in serving a variety of
energy and industrial sectors in the Kingdom of Saudi Arabia and GCC countries.
EnergyServ is partner to group of Egyptian companies under the name of
“The Energy Group (TEG)”.
TEG is an independently owned professional services organization specializing in variety
of energy and utility based services in the Arab Republic of Egypt and the Middle East
Region.
TEG companies websites:
www.egyptrol.com
www.pesco-eg.com
www.powerserv-eg.com
www.econsult-eg.com
EnergyServ through its back-up entities have a diverse portfolio encompasses design,
erection, testing & commissioning & startup, and operation & maintenance activities as
well as a wide pool of experts in different technical and administration fields.
EnergyServ founders enjoy a very strong communication network within the energy &
industrial sectors. This experience helps EnergyServ to serve the regional Market to the
most efficient way.
EnergyServ is fully geared and ready to align with EPC Contractors to support their
operations in the Kingdom of Saudi Arabia and GCC countries in Sourcing technical
manpower in the following areas:
Testing & Commissioning.
Operation & Maintenance.
IBDAA W TAJADDOD
For Contracting
جتـدد و إبـداع مـؤسـسـة
ت للمـقـاوال
20 Oct., 2013 Page 3 of 21
Construction Supervision.
Instruments Calibration.
Detailed Engineering
Equipment Procurement.
Cost Estimating.
RFP preparation
Project Cost and Schedule Control
Our Services and tools can be packaged to meet with the project needs.
EnergyServ has an access to continuously updated energy & industrial professional’s
database with unique qualities that help them execute the required tasks professionally.
Selected through a solid filtering process.
Practiced work in energy projects during the last 20 Years in Middle East.
Previously tested to work together.
Most of them received our training.
When work together under our leadership, our clients take advantage of:
- Reduced conflicts and friction.
- Internally assigned and coordinated tasks.
Positive attitude to act and improve process as required.
Hard working staff used to work under stress.
Familiar with safety procedures and practices.
Deep understanding of energy processes.
Can prepare and execute procedures for the site specific conditions
Can manage others to carry out the procedures.
Can lead the coordination between contractors.
Experience in different energy equipment suppliers:
500/220kV GIS Systems: AREVA T&D., Hyosung, Siemens, ABB, Alstom Grid …etc.
MV&LV SWGR, GCB: ABB, Alstom,…etc.
IBDAA W TAJADDOD
For Contracting
جتـدد و إبـداع مـؤسـسـة
ت للمـقـاوال
20 Oct., 2013 Page 4 of 21
Gas Turbine: GE, Siemens, MHI, Alstom, Ansaldo Energia.
Steam Turbine: GE, Siemens, Ansaldo, Toshiba, Alstom.
Boiler: B&W, CE, Ansaldo Caldaie & HRSG: NEM, Ansaldo Caldaie.
EnergyServ Services:
1- Engineering
EnergyServ perform different forms of engineering, covering basic and detailed
designs for Power Plants, Substations, Industrial Systems and Public services buildings.
EnergyServ integrate efficiently between different engineering disciplines within the
project to end up with reliable documents for the required services.
EnergyServ perform Electrical, Mechanical and Control Systems Field Engineering,
Installation supervision, testing and commissioning according to the highest applicable
standards.
EnergyServ has the capability to offer Mechanical, Electrical and Plumbing (MEP)
Engineering services (HVAC, Fire Fighting, Plumbing, Electrical Power and low current)
that represent a significant planning and cost factor on projects and provide a fully
integrated design solution that are delivered on time, on budget and embraces the
latest technology.
IBDAA W TAJADDOD
For Contracting
جتـدد و إبـداع مـؤسـسـة
ت للمـقـاوال
20 Oct., 2013 Page 5 of 21
a. Electrical Engineering
Equipment General Arrangement.
Single and Three Line Diagrams.
Power system analysis and calculations using (ETAP) software.
Protection relays setting.
Voltage drop calculations.
Raceway details and numbering.
IBDAA W TAJADDOD
For Contracting
جتـدد و إبـداع مـؤسـسـة
ت للمـقـاوال
20 Oct., 2013 Page 6 of 21
Cable trays routing.
Grounding system detailed design.
Cable sizing, routing and cable lists.
Lighting calculations in DIALUX.
Installation typical designs.
Interconnection diagrams.
Fire Alarm Systems, CCTV and Sound Systems.
Material takes off “MTO” for electrical material.
Preparation of electrical specifications for industrial projects.
Preparation of tender RFP (Request for Proposal) documents technical and
commercial sections.
Electrical systems design review.
b. Instrument and control systems engineering.
Participation with Mechanical Discipline in P&IDs Design.
Input / Output lists.
Instrument Lists.
Logic Diagrams for On-Off Controls.
IBDAA W TAJADDOD
For Contracting
جتـدد و إبـداع مـؤسـسـة
ت للمـقـاوال
20 Oct., 2013 Page 7 of 21
Functional Block Diagrams for Closed Loop Controls.
Instrument Data Sheets.
Instrument hook-up Details and Material Take Off.
Level Setting Diagrams.
I&C systems design review.
c. Mechanical Engineering
Equipment Sizing / System Sizing Calculations.
Piping & Instrumentation Diagrams (P&IDs).
Piping System Detailed Design (Sizing, Fitting Detailing, Pressure Drop).
Layout and General Arrangements.
Piping isometrics and fabrication details.
Pipe Routing and Supports.
3D Modeling using (PDMS) program.
Medical and Waste Anesthetic Gas and Vacuum Systems.
Heating, ventilation and air condition (HVAC) systems.
Energy Modeling.
LPG Systems.
Material takeoff.
Mechanical Equipment Specifications.
Mechanical systems design review.
d. Fire Fighting
Clean Agent Suppression.
Pre-action Systems.
Automatic sprinkler system.
Water mist Systems.
Diesel and Electric Fire Pumps.
IBDAA W TAJADDOD
For Contracting
جتـدد و إبـداع مـؤسـسـة
ت للمـقـاوال
20 Oct., 2013 Page 8 of 21
Early Detection and Suppression Systems.
Automatic and Manual.
Standpipe Systems.
e. Plumbing Engineering
Building Plumbing, Drain, Waste, and Vent Systems.
Medical and Waste Anesthetic Gas and Vacuum Systems.
Water Conservation and Recovery, Rainwater Harvesting.
2- Construction and Procurement
The construction has been one of the essences of EnergyServ activities. We have the
resources and knowledge to participate in energy & industrial construction projects;
we are familiar with construction regulations and labor laws.
EnergyServ has the capability to cover the supplying, installing, testing, repairing and
recondition most types of electromechanical, instruments and control systems
including:
Boiler components
Process piping
IBDAA W TAJADDOD
For Contracting
جتـدد و إبـداع مـؤسـسـة
ت للمـقـاوال
20 Oct., 2013 Page 9 of 21
Valves
Pumps
Motors
Tanks, and vessels
Centrifuges
Fans and blowers
Compressors
Gear boxes
Fire protection systems
Pneumatic fittings / cylinders
Valves / pumps / seals Insulation
lubricants and coating
Heat exchangers
Transformers
Motors
Generators
Lighting systems
Distribution panels
Switchgear
Telecommunications
Security Systems
Pressure / Differential Pressure Instrumentation
Temperature Instrumentation
Flow Instrumentation
Level Instrumentation
IBDAA W TAJADDOD
For Contracting
جتـدد و إبـداع مـؤسـسـة
ت للمـقـاوال
20 Oct., 2013 Page 10 of 21
3- Commissioning and Start-Up
EnergyServ perform electrical, mechanical and control systems field engineering,
installation supervision, testing and commissioning according to the highest standards
in energy & and Industrial Systems.
EnergyServ prides itself as a company specialized in Commissioning Services, as it has
the following advantages in this area:
Ability to take fast response to clients’ requests.
Use of seasoned office support commissioning specialists in selection of suitable
candidate for each post considering the harmony during the selection based on
previous knowledge of personnel in previous jobs, etc.
Continuous communication with the team during execution to assure teamwork
spirit and best performance to Client.
Assuring high level of staff loyalty.
Ability to provide procedures, advice & trouble-shooting assistance.
Can familiarize the team before dispatching them to site.
IBDAA W TAJADDOD
For Contracting
جتـدد و إبـداع مـؤسـسـة
ت للمـقـاوال
20 Oct., 2013 Page 11 of 21
4- QA/QC Testing and Inspection
EnergyServ has a wide range of testing, analysis and inspection services onshore as
well as offshore applied in energy & industrial systems.
EnergyServ has the capability to provided services range from standard Non
Destructive Testing to complete inspection programs and specialized inspection
techniques.
EnergyServ inspectors are certified as a minimum and all personnel will be regularly
trained by our all-round certified level III inspector. Most inspectors have additional
qualifications or degrees on top of this.
EnergyServ quality assurance / inspection programs whether a testing, analysis,
QA/QC, NDT, boiler inspection, welding inspection services at vendor’s facility or on-
site construction include:
Supplier quality surveillance / expediting services.
Complete turnover documentation compilation and review.
Provide QA/QC inspectors, welding inspectors for the project.
Structural fabrication, installation welding Inspection.
Process piping fabrication and installation Inspection.
Welding procedure qualification review.
Weld inspection Level 2 & Level 3 personnel.
Vendor fabrication inspection.
Vendor quality surveillance.
Visual inspection of process piping systems line check, skids, pressure vessels,
tanks, and structurals.
Hydro testing witnessing & sign off.
Magnetic Particle and Dye Penetrant Testing.
Ultrasonic thickness survey and hardness testing
IBDAA W TAJADDOD
For Contracting
جتـدد و إبـداع مـؤسـسـة
ت للمـقـاوال
20 Oct., 2013 Page 12 of 21
5- Field Instrument Calibration
EnergyServ has a mobile calibration laboratory with capability of calibrating water, air,
steam, gas and fuel pressure and temperature measuring instruments.
EnergyServ calibration laboratory can be moved easily to our client’s erection site with
our calibration specialists to support and cover all pressure, temperature and
electromechanical systems calibration needs.
EnergyServ offers expert instrument calibration services for all types of pressure,
temperature and electrical measuring instruments. Extensive methodology
experience is applied to every calibration we perform to assure compliance to the
applicable standards of our clients industry.
6- Manpower Sourcing
EnergyServ has a specialized pool of experts and adequate in different technical fields
“categories”. We use this database of professionals to select suitable candidates to
each task we undertake. Utilizing a large pool of CVs for power sector individuals
continuously updated and accessible at our webpage
http://www.energy-serv-sa.com/ManpowerSourcing.php
IBDAA W TAJADDOD
For Contracting
جتـدد و إبـداع مـؤسـسـة
ت للمـقـاوال
20 Oct., 2013 Page 13 of 21
7- Operation and Warranty Stage
EnergyServ has the expert and adequate operation & maintenance team capable of
taking the responsibility of taking over the operational phase and represent the EPC
contractor during warranty phase and up to turning over to Owner. During this phase,
the following activities would take place:
Conduct periodic checks and accordingly issue Daily/ Weekly/ Monthly reports.
Monitor the scope of supply equipment operation and maintenance to identify
any improper operation or maintenance activity. Notify the Owner of improper
operation or maintenance.
Direct interface with the owner in identifying warranty issues and coordinate
between owner and our client (Contractor) to resolve them.
Provide instructions to owner operators related to equipment usage.
IBDAA W TAJADDOD
For Contracting
جتـدد و إبـداع مـؤسـسـة
ت للمـقـاوال
20 Oct., 2013 Page 14 of 21
EnergyServ Partners Previous Experiences:
Country Client Year Project Scope Details
Engineering Service
SOUTH SUDAN
Confidential IPP Developer
2011
Juba, South Sudan. 48MW (6x8MW) Diesel Power Plant
Prepare Preliminary Design Report and Cost Estimate
MAURITANIA
Confidential EPC Contractor
2012
Nouakchott , Mauritania. 120MW (8x15 MW) Diesel Power Plant.
Prepare Technical Proposal contents and Cost Estimate
NIGERIA Confidential EPC Contractor
2012
Azura, Nigeria. 500 MW (4x125MW) Gas Turbine Simple Cycle Power Plant.
Prepare Technical Proposal contents Preliminary BOQ’s Cost Estimate
IRAQ Confidential EPC Contractor
2012
Samawa, Iraq. 500 MW (4x125MW) Gas Turbine Simple Cycle Power Plant.
Prepare Technical Proposal contents Preliminary BOQ’s Cost Estimate
IRAQ Confidential EPC Contractor
2012
Diwania, Iraq. 500 MW (4x125MW) Gas Turbine Simple Cycle Power Plant.
Prepare Technical Proposal contents Preliminary BOQ’s Cost Estimate
EGYPT
Multipahrama for pharmaceutical and chemicals company
2012 Multipharma warehouse-New Cairo
Preparation of electromechanical systems Contractor Packages and Construction Management
EGYPT Roots Steel Systems
2012 Pre-Engineered Steel Factory
Preparation of electromechanical systems Contractor Packages and Construction Management
EGYPT Atlantic Industrial 2012
Coca Cola Egypt office building power distribution system improvement
Power distribution system improvement study and construction management
IBDAA W TAJADDOD
For Contracting
جتـدد و إبـداع مـؤسـسـة
ت للمـقـاوال
20 Oct., 2013 Page 15 of 21
Country Client Year Project Scope Details
EGYPT Tam Environmental Services
2011 To
2012
Matrouh city water RO desalination plant
Electromechanical systems detailed engineering and construction management
EGYPT Kharafi National 2011 W. Damietta –4X125MW SCPP
Pipe lines hydraulic calculations, for all auxiliary systems (water and fuel).
EGYPT HYOSUNG CORPORATION
2011
Damietta - 4x125MW SCPP, 220KV GIS Substation of Power Station.
- Relays setting Calculations
- Construction supervision
EGYPT Kharafi National 2011
Damietta - 4x125MW SCPP Elshabab - 8x125MW SCPP
For Firefighting, water systems and fuel oil system
- Pipe lines hydraulic
calculations - P&ID review
KSA Engineering Solutions ES
2011 El-Nafl Residential Complex-KSA
Preparation of electromechanical systems Contractor Packages3
EGYPT
Egyptian Canadian Pharmaceuticals ECAN Pharmaceuticals
2009 To
2010
With: Egypt. Comp. for Complementary Works ECC Facility – El Obour City, Cairo, Egypt.
Preparation of Electrical, Fire Fighting and plumbing systems Contractor Package.
EGYPT AIR LIQUIDE 2009 Gases Production Plant at the 6th of October City
Design Cooling System Logic Diagrams
EGYPT Global Partners – INITEC.
2008
El-Kuraimat (III) Power Plant Project CP-105 & CP-106 Scope,
Grounding System Design and BOQ within INITEC scope of supply.
EGYPT Global Partners – INITEC.
2008
El-Tebbin Power Plant Project CP-106 & CP-118 Scope
Grounding System Design and BOQ within INITEC scope of supply.
IBDAA W TAJADDOD
For Contracting
جتـدد و إبـداع مـؤسـسـة
ت للمـقـاوال
20 Oct., 2013 Page 16 of 21
Country Client Year Project Scope Details
EGYPT Global Partners – INITEC.
2008
Nubaria (III) Power Plant Project CP-106, CP-117 & CP-118 Scope
Grounding System Design and BOQ within INITEC scope of supply.
EGYPT US Filters “ 1998
To 2001
Water and Waste Water Treatments for many projects
Piping And Isometric Design. Mechanical and Piping Isometrics Design. Main Electrical and Control Panel design.
EGYPT PGESCo 2009
Design for New Transformer Factory – Badr City for ELMACO
Steel Structure Design as a sub-consultant to PGESCo
EGYPT AUG Pharmaceuticals
2008 To
2012
AUG Pharmaceuticals Facility – 6th of October City, Cairo, Egypt.
Preparation of electromechanical systems Contractor Packages and Construction Management
EGYPT GlaxoSmithKline 2005 2006
Egypt – Madinet El Salam Manufacturing Facility
Consultation Services for Survey for Factory Electrical stem as built drawings preparation.
Commissioning and Start-Up
KSA SAMSUNG C&T CORPORATION
2013
Qurayyah Independent Power Project (QIPP) 6 x 750MW
Commissioning of 6 Combined Cycle Modules (2x2x1)
EGYPT ALSTOM GRID
2013
Giza North PP 2X750MW
(500/220 KV SWYRD) Alstom
Test. &Comm. of SWYRD & Remote End Prot. Sys.
IBDAA W TAJADDOD
For Contracting
جتـدد و إبـداع مـؤسـسـة
ت للمـقـاوال
20 Oct., 2013 Page 17 of 21
Country Client Year Project Scope Details
EGYPT Ansaldo E (ABB)
2012
6th October, 4X150MW- AE (220 KV SWYRD) ABB
Test. &Comm. of SWYRD & Remote End Prot. Sys.
EGYPT HYOSUNG 2011
To 2012
Damietta SWYRD,
220KV - HYOSUNG
GIS Substation
- Test. &Comm. of SWY & Remote End Prot. Sys. - Relays setting Calc.
- Construction supervision
EGYPT ANSALDO ENERGIA
2011 To
2012
6th Of October Power Plant 4x150 MW
Commissioning, Start-up 4 × 150 MW Simple Cycle
EGYPT ANSALDO CALDAEI
2011 To
2012
Abu Qir 2x650MW Boilers
Commissioning, Start-up and Operation 2x650MW Boilers till handing over to Client
IRAQ ABB Mannheim 2011
To 2012
IRAQ - Erbil 2x125MW GE Gas T. IRAQ - Dohuk 4x125MW GE Gas T. IRAQ - Al-Solaimanyah 4x125MW GE Gas T.
Construction Supervision Commissioning and Start-up of GT & auxiliaries through a seconded commissioning manager
GE Gas Turbine
EGYPT AREVA T&D 2010
To 2011
Bahteem GIS S/S
220/66/11 kV,
AREVA
Test. &Comm. of Sub St. & TL Remote End Prot. Sys.
IBDAA W TAJADDOD
For Contracting
جتـدد و إبـداع مـؤسـسـة
ت للمـقـاوال
20 Oct., 2013 Page 18 of 21
Country Client Year Project Scope Details
EGYPT AREVA T&D 2010
To 2011
El-Mashtal GIS S/S,
66/11 kV - AREVA
Test. &Comm. of Sub St. & TL Remote End Prot. Sys.
EGYPT NEM Energy B.V.
2010 To
2011
Sidi Krir and El-Atf Combined Cycle Power Plant - 750MW each.
HRSG systems Commissioning & Operation till handing over to Owner.
EGYPT
Toyota Tsusho C. Toshiba Plant Systems & Services C.
2009
Sidi Krir and El-Atf Combined Cycle Power Plant - 750MW each
Preparation of Chemical cleaning procedure for the Condensate and Feed Water System.
EGYPT
Toyota Tsusho C. Toshiba Plant Systems & Services C.(TPSC)
2009 To
2013
El-Atf Simple Cycle Power Plant - 750MW
Lump Sum Contract Commissioning of the Electrical and Mechanical BOP, then warranty representation and related services.
EGYPT Toyota TC/ Toshiba (TPSC)
2009 To
2013
Sidi Krir Simple Cycle Power Plant - 750MW
Assist in the commissioning of Mechanical BOP, then warranty representation and related services.
QATAR ABB Mannheim 2009
QATAR - QATALUM Combined Cycle Power Plant
POB Construction and Commissioning Management.
QATAR ABB Manheim 2007
To 2008
QATAR - Abu Fontas Power Plant Project (QEWC) – Qatar
POB Construction and Commissioning Management
LIBYA ABB Manheim 2006 LIBYA - Benghazi 319 pumping station
Electrical (LV & MV SWGR, Power Transformers, HV cables, Generator Circuit Breaker, and DC systems), Protection and Control Systems installations, commissioning and startup services.
IBDAA W TAJADDOD
For Contracting
جتـدد و إبـداع مـؤسـسـة
ت للمـقـاوال
20 Oct., 2013 Page 19 of 21
Country Client Year Project Scope Details
AFGHANISTAN
CONTRACK International Inc.
2004
U.S. Brigade Compound Kabul Military Training Facilities, Kabul, Afghanistan.
Full Engineering and Coordination with CONTRACK engineering and its system sub-suppliers for the Power Plant Fuel Oil System control system and piping.
EGYPT ALSTOM Power Inc.
2001 To
2003
Aswan High Dam Control System Upgrade 12x175MW
Commissioning and start- up of Aswan High dam new DCS system.
Construction Experiences:
EGYPT YoungJin Subcontractor of DOOSAN
2012 To
2013
Ain Sokhna Power Plant (2X650)MW
Erect, calibrate and Start –Up for Instrumentation and Electrical works of 2 Boilers.
EGYPT Tourah Cement Factory
2011 Tourah Cement Factory
Electrical work for replacing Packing Plant no. 3
EGYPT EMC 2012 Abu Sultan Power Plant (4x150)MW
Erection, Commissioning and Start–up for new Hydrogen generating plant
EGYPT EMC 2012 Attaka Power Plant (2x150+2X320)MW
Erection, Commissioning and Start-up for new Hydrogen generating plant
EGYPT EMC 2012 Abu Sultan Power Plant (4x150)MW
Mechanical and Electrical works for the replacement of 3 Feed Water Pumps
IBDAA W TAJADDOD
For Contracting
جتـدد و إبـداع مـؤسـسـة
ت للمـقـاوال
20 Oct., 2013 Page 20 of 21
Country Client Year Project Scope Details
Procurement Experiences:
EGYPT ASA Automation 2011 Closed water cycle-Tourah Cement Plant
Supplying instruments fitting
EGYPT EMC 2012 Abu Qir Power Plant (2x650)MW
Supplying all Electro-mechanical items for the Hydrogen generating plant.
EGYPT YoungJin 2012 Ain Sokhna Power Plant (2x650)MW
Supplying mechanical item and Scaffolds tools for Boiler #1,2
EGYPT Toyota TTC/ Toshiba TPSC.
2012
Sidi Krir Simple Cycle Power Plant -750 MW.
Supply Mechanical and Electrical items
EGYPT Suez Steel Factory
2012 Suez Steel Factory Supply Electrical and Mechanical items
Operation and Warranty Stage
EGYPT ANSALDO ENERGIA
2011 To
2012
6th Of October Power Plant 4x150 MW
Operation 4 × 150 MW Simple Cycle
EGYPT ANSALDO CALDAEI
2011 To
2012
Abu Qir 2x650MW Boilers
Operation 2x650MW Boilers till handing over to Client
EGYPT Toyota TTC/ Toshiba TPSC.
2011 To
2013
Sidi Krir Combined Cycle Power Plant 750 MW.
Warranty Period Representation & Closure of Punch List Items
EGYPT Toyota TTC/ Toshiba TPSC.
2011 To
2013
El-Atf Combined Cycle Power Plant 750 MW.
Warranty Period Representation & Closure of Punch List Items
IBDAA W TAJADDOD
For Contracting
جتـدد و إبـداع مـؤسـسـة
ت للمـقـاوال
20 Oct., 2013 Page 21 of 21
EnergyServ Contact Information:
Trade Name : EnergyServ للمقاوالت جتددو إبداع مؤسسة
Address : KSA – Riyadh – 547 Imam Saud bin Abdulaziz St. – District of Al-Taaon –
First Floor - Apartment 3
Contact Data :
Tel.: +966 (011) 4556842
Fax: +966 (011) 2032561
P.O. Box: 360090, Riyadh 11313, KSA
C.R.: 1010304064, CC: 248773
E-mail: [email protected]
Website: www.energy-serv-sa.com