ias 11 construction contracts summary with example p4g
TRANSCRIPT
7/22/2019 IAS 11 Construction Contracts Summary With Example p4g
http://slidepdf.com/reader/full/ias-11-construction-contracts-summary-with-example-p4g 1/4
7/22/2019 IAS 11 Construction Contracts Summary With Example p4g
http://slidepdf.com/reader/full/ias-11-construction-contracts-summary-with-example-p4g 2/4
May/June 2011
23globalaccountantmagazine.com
construction contract.
directly attributable to the
contract.
assistance.
machinery to complete the
contract.
of plant and machinery used in
the construction contract.
IAS 11 recognises two types of
construction contract that are
distinguished according to their
pricing arrangements:
Fixed price contracts are con-
tracts for which the price is not
usually adjusted due to costs
incurred by the contractor. Where
contract, this essentially means
that the contractor agrees to a
per unit of output. These types of
contracts are sometimes subject to
escalation clauses.
Cost plus contracts are where the
contractor is reimbursed for costs
plus a provision for a fee. The
contract price is determined by
the total amount of reimbursable
expenses and a fee. The fee is the
as revenue less direct costs to be
earned on the contract.
Recognition of Contract
Revenue and Expenses
IAS 11 prohibits the use of the
percentage of completion method
if this method will not result in the
reasonable level of accuracy. It fol-
lows, therefore, that the percentage
of completion method can only
be used where the outcome of the
contract can be estimated reliably.
Where the contract is either a
contract, then the following criteria
must be met to determine whether
the outcome can be reliably esti-
mated:
Fixed price contract:
laid down in the Conceptual
Framework which is that total
contract revenue can be mea-
sured reliably and it is probable
to the entity.
-
plete and the stage of comple-
tion can be measured reliably.
properly and measured reliably
so that comparison of actual
contract costs with estimates
can be done.
Cost plus contract:
to the contract, whether or not
and measured reliably.
All the conditions above must be
7/22/2019 IAS 11 Construction Contracts Summary With Example p4g
http://slidepdf.com/reader/full/ias-11-construction-contracts-summary-with-example-p4g 3/4
7/22/2019 IAS 11 Construction Contracts Summary With Example p4g
http://slidepdf.com/reader/full/ias-11-construction-contracts-summary-with-example-p4g 4/4
May/June 2011
All the costs which have been in-
curred todate have all been debited
to the contract account in the gen-
eral ledger. Leah Inc have appointed
the reporting date (31 March 2009),
the contract was 40% complete at
which point the customer made a
progress payment amounting to £15
have credited this progress pay-
ment to the contract account. There
have been no other entries made in
respect of this contract.
Required
Show how the contract should be
accounted for under the provi-
statements of Leah Inc for the year
ended 31 March 2009.
Solution
The overall revenue for the contract
price agreed).
We know that Leah has incurred
the following costs and has made
estimates of costs to complete as
follows:
As costs are less than total
revenue we know the
of ($50 million less $44 million =
$6 million).
that the contract is 40%
FinancialStatementExtracts
Revenue(40%x $50
million)$20,000
Cost ofsales
(40%x $44
million)$17,600
Step 1
Working: Gross Amounts Due from
Costs to date: $,000 $,000
Purchase of materials 9,000 $17,600
Labour and other overheads 7,000
Plant depreciation ($15,000 x 6/12) 7,500
Total costs to date 23,500
6,000
29,500
Less progress payment received (15,000)
Gross amount due from customer 14,500
Step 2
Purchase of machine $15,000
Purchase of machine $ 9,000
Labour andoverheads
$ 7,000
Estimated costs tocomplete
$13,000
$44,000
Step 3
complete, so we take 40% of the
total costs to ‘cost of sales’ in the
income statement. We then add
40% of the expected revenue to
revenue in the income statement:
We then need to work out
how much should be in
-
tion as ‘gross amounts due from
customer’. We need a working as
follows:
The gross amount due
from customer can be
shown as an ‘other current asset’ in
Step 4
Conclusion
It is important that when you
are dealing with construc-
tion contract questions that
you adopt a logical method
of dealing with the numbers
and are familiar with how to
depending on whether a con-
or uncertain. Once you have
mastered the approach and
understand how IAS 11 works,
questions on construction
contracts become a favourite
topic. Lots of question prac-
tise is the key to this area of
25globalaccountantmagazine.com