AGENDA Introduction - Claire Holman, Brook Cottage Consultants Source-pathway-receptor approach Jon Pullen, RPS Site conditions Hugh Datson, Dustscan PM 10 and dust reduction with distance Ian Stone, Advance Environmental Determining ‘Residual Source Emissions’ Srinivas Srimath, RSK Planning inquiry decisions Mark Dawson, Wardell Armstrong Closing remarks Brook Cottage Consultants 1

Upload: ies-iaqm

Post on 10-Jan-2017

76 views

Category:

Environment


0 download

TRANSCRIPT

Page 1: IAQM Minerals Guidance Launch Introduction -IAQM Chair: Claire Holman, Brook Cottage Consultants

1

AGENDA

• Introduction - Claire Holman, Brook Cottage Consultants• Source-pathway-receptor approach Jon Pullen, RPS• Site conditions Hugh Datson, Dustscan• PM10 and dust reduction with distance Ian Stone, Advance

Environmental• Determining ‘Residual Source Emissions’ Srinivas Srimath,

RSK• Planning inquiry decisions Mark Dawson, Wardell

Armstrong• Closing remarks

Brook Cottage Consultants

Page 2: IAQM Minerals Guidance Launch Introduction -IAQM Chair: Claire Holman, Brook Cottage Consultants

2

IAQM Mineral Planning Guidance

Dr Claire HolmanChair: IAQM Minerals Working Group

IAQM Meeting24 May 2016

London

Brook Cottage Consultants

Page 3: IAQM Minerals Guidance Launch Introduction -IAQM Chair: Claire Holman, Brook Cottage Consultants

3

New IAQM guidance

Brook Cottage Consultants

Page 4: IAQM Minerals Guidance Launch Introduction -IAQM Chair: Claire Holman, Brook Cottage Consultants

4

Scope

• Sites extracting solid minerals• May include secondary aggregate processing• Specifically for planning not environmental permit

applications• Primarily for England

Brook Cottage Consultants

Photo: Rachel McHale. SLR Consulting Ltd

Page 5: IAQM Minerals Guidance Launch Introduction -IAQM Chair: Claire Holman, Brook Cottage Consultants

5

Approach

• Aims to:– promote good quality assessments provide framework– fill gap left by withdrawal of MP2 – supplement advice given in national Planning Practice Guidance

• To use the Source-pathway-receptor relationship• Otherwise non prescriptive

Brook Cottage Consultants

Page 6: IAQM Minerals Guidance Launch Introduction -IAQM Chair: Claire Holman, Brook Cottage Consultants

6

Assessing impacts

Mineral impacts

• Difficult to quantify • Little robust data of

impacts• Requires knowledge of

site operations & effectiveness of mitigation measures

Brook Cottage Consultants

Photo: Ian Stone, Advance Environmental

Page 7: IAQM Minerals Guidance Launch Introduction -IAQM Chair: Claire Holman, Brook Cottage Consultants

7

nPPG - Key stages to a dust assessment

1. Establish baseline conditions of the existing dust climate around the site of the proposed operations;

2. identify site activities that could lead to dust emissions without mitigation;

3. identify site parameters which may increase potential impacts from dust;

4. recommend mitigation measures, including modification of site design;  

5. make proposals to monitor and report dust emissions to ensure compliance with appropriate environmental standards and to enable an effective response to complaints.

  Brook Cottage Consultants

Page 8: IAQM Minerals Guidance Launch Introduction -IAQM Chair: Claire Holman, Brook Cottage Consultants

8

IAQM approach

• Assessments to use Source – pathway – receptor model

• Screening: Where there are no receptors near to a mineral site there will be no significant effect.– Distance based screening criteria for dust disamenity– Distance + background for PM10

• Assessment approach not prescriptive• Example provided evolved from Alex Grant’s approach• Modelling not generally required

Brook Cottage Consultants

Page 9: IAQM Minerals Guidance Launch Introduction -IAQM Chair: Claire Holman, Brook Cottage Consultants

9

Screening – dust disamenity

Brook Cottage Consultants

Page 10: IAQM Minerals Guidance Launch Introduction -IAQM Chair: Claire Holman, Brook Cottage Consultants

10

Screening - PM10

National Planning Practice Guidance IAQM• Where receptors within 1

km and background PM10 concentration is less than 17 µg/m3

Brook Cottage Consultants

Figure 1: Site Assessment Flow Chart[1]

Paragraph: 032 Reference ID: 27-032-20140306

Page 11: IAQM Minerals Guidance Launch Introduction -IAQM Chair: Claire Holman, Brook Cottage Consultants

11

Minerals dust assessment - Content

• Existing PM10 concentration and dust deposition rates (where available)• Location of receptors and sensitivities to PM10 / dust• Dust sources associated with the proposed development• Control/mitigation measures • A prediction of the likely PM10 and dust impacts and resulting effects (on

health, amenity, and/or ecology) at relevant sensitive receptors:– likely magnitude of dust emissions (after mitigation) – meteorological characteristics at the site;– dispersion and dilution to the receptors, taking into account distance,

orientation, local terrain and features, and other relevant factors;– the sensitivity of the receptors to disamenity, health and/or ecology

effects; and– any likely cumulative interactions

Brook Cottage Consultants

Page 12: IAQM Minerals Guidance Launch Introduction -IAQM Chair: Claire Holman, Brook Cottage Consultants

12

Dust disamenity assessment steps

Step 1: Describe site characteristics and baseline conditions

Step 2: Estimate dust impact risk (with mitigation)

Step 3: Estimate likely magnitude of effect

Brook Cottage Consultants

Photo: Ian Stone, Advance Environmental

Page 13: IAQM Minerals Guidance Launch Introduction -IAQM Chair: Claire Holman, Brook Cottage Consultants

Assessment conclusion

• Assessment provides overall disamenity and, where required, the ecological and health effects, at individual receptors

• Conclusion must be drawn of overall effect Judgement must be used to determine effect is either “significant” or “not significant”

Brook Cottage Consultants 13

Photo: Hugh Datson, DustScan Ltd

Page 14: IAQM Minerals Guidance Launch Introduction -IAQM Chair: Claire Holman, Brook Cottage Consultants

14

Consultation: substantive comments

Brook Cottage Consultants

Issue Response Short term PM10 not included Lack of data available

PM2.5 not included Mineral site generally produce coarse PM > PM2.5

The graphs will be used as a proxy for an assessment

Clearly stated this is not to be done

Ecological receptors not the same as in the IAQM construction guidance background PM10 screening criteria

Now consistent

Unclear how to estimate PM10 process contribution

Now referred to Appendix 5

Page 15: IAQM Minerals Guidance Launch Introduction -IAQM Chair: Claire Holman, Brook Cottage Consultants

15

Review

• Guidance will be reviewed in 12-18 months in light of the experience of using it

• IAQM members will be asked to comment

Brook Cottage Consultants

Page 16: IAQM Minerals Guidance Launch Introduction -IAQM Chair: Claire Holman, Brook Cottage Consultants

Working group members

• Hugh Datson, DustScan• Mark Dawson, Wardell Armstrong• Claire Holman, Brook Cottage Consultants (Chair)• Rachel McHale, SLR • Jon Pullen, RPS• Srinivas Srimath, RSK • Matt Stoaling, Isopleth • Ian Stone, Advance Environmental • Penny Wilson, Air Quality Consultants

Brook Cottage Consultants 16

Page 17: IAQM Minerals Guidance Launch Introduction -IAQM Chair: Claire Holman, Brook Cottage Consultants

17

AGENDA

• Introduction - Claire Holman, Brook Cottage Consultants• Source-pathway-receptor approach Jon Pullen, RPS• Site conditions Hugh Datson, Dustscan• PM10 and dust reduction with distance Ian Stone, Advance

Environmental• Determining ‘Residual Source Emissions’ Srinivas Srimath,

RSK• Planning inquiry decisions Mark Dawson, Wardell

Armstrong• Closing remarks