HCC WCMS Phase II Project Plan

Vignette Phase II – Status Report

Communications Department

Prepared by: Murali Venkatesh

Version. 2.0June 07 2006

Page 2: I gave Management Consulting Training - PPT Outline by Murali Venkatesh

WCMS Vignette Phase II Project Plan

2

Agenda

• Current State

• Desired State

– Project Schedule

– Milestones

– Organization Chart

– Resources

– Deliverables

• Presentation Wrap up

• Questions

Page 3: I gave Management Consulting Training - PPT Outline by Murali Venkatesh

WCMS Vignette Phase II Project Plan

3

Current State• WCMS team is spending some time to understand the previous

WCMS effort

• HCC already bought a Vignette WCMS Software

• HCC Board is committed to complete the pilot

• Full time Project Manager is on board

• PMO made a decision to expand WCMS project team work force – In progress

• For WCMS project knowledge repository, created an WebCT account

• PMO made a decision to get pilot hardware – Delayed

Page 4: I gave Management Consulting Training - PPT Outline by Murali Venkatesh

WCMS Vignette Phase II Project Plan

4

Desired State• Build a strong bridge between Steering committee and WCMS

team - In progress

• Create a clear plan for WCMS pilot project - In progress

• Place an order for pilot infrastructure – Delayed

• According to the plan bring the right resources on time- Delayed

• Find an Internal Business Analyst who can start defining the pilot scope document – In progress

• Setup a meeting with Trendec and Vignette team to have a follow up meeting - Done

Page 5: I gave Management Consulting Training - PPT Outline by Murali Venkatesh

WCMS Vignette Phase II Project Plan

5

Project Schedule

June 7th

Complete

Progress

Delayed

ID Task Name Start Finish DurationMay 2006 Jun 2006 Jul 2006 Aug 2006

5/7 5/14 5/21 5/28 6/4 6/11 6/18 6/25 7/2 7/9 7/16 7/23 7/30 8/6

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

22

23

24

25

26

2w 4d5/25/20065/8/2006Initiating

1w5/12/20065/8/2006Understand Current Environment

1w 1d5/16/20065/9/2006Meeting with Internal and external teams

2d5/15/20065/12/2006Understanding Current Infrastructure and Resources

1w5/18/20065/12/2006Understand the pilot Scope

1w5/25/20065/19/2006Prioritize the HCCS scope and high level tasks

4w 4d6/20/20065/18/2006Planning

2w6/8/20065/26/2006Resource Planning and Orientation

1w6/14/20066/8/2006Detail Pilot Scope Definition (CMS, HTML)

3w 1d6/8/20065/18/2006Order for the pilot Infrastructure

3d6/16/20066/14/2006Training and Resource Planning

3d6/12/20066/8/2006Time Frame and Cost Budgeting

3d6/20/20066/16/2006Detail Project plan Development

6w 4d7/28/20066/13/2006Executing

2w6/26/20066/13/2006Setup Pilot servers and Install Vignette

3d7/3/20066/29/2006Create the CMS templates

2w6/30/20066/19/2006Create new HTML look and feel for HCCS

4w7/24/20066/27/2006Develop new CMS look and feel pages for Pilot

1w7/28/20067/24/2006Integrate CMS with other websites

11w 4d8/2/20065/12/2006Controling

5w7/18/20066/14/2006Setup weekly meeting with program management

2d7/25/20067/24/2006Setup Meeting with Steering committee to show Pilot

11w 4d8/2/20065/12/2006Review project status, plan, scope, budget, resources with management and team

1w 4d8/7/20067/26/2006Closing

3d7/28/20067/26/2006Lessons learned meeting

1w 1d8/7/20067/31/2006Prepare for the full cycle development

Page 6: I gave Management Consulting Training - PPT Outline by Murali Venkatesh

WCMS Vignette Phase II Project Plan

6

Project Milestones

Complete

Complete

Delayed

June 07th

Progress

Delayed

Delayed

Progress

Delayed

ID Milestones Name FinishMay 2006 Jun 2006 Jul 2006 Aug 2006

5/7 5/14 5/21 5/28 6/4 6/11 6/18 6/25 7/2 7/9 7/16 7/23 7/30 8/6

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

5/9/2006Project Management Kick off

5/15/2006Project Schedule and Resources Document

5/16/2006Pilot Infrastructure order

5/22/2006Pilot Project Scope Document

5/23/2006Team Kick off meeting

5/23/2006Project best practices implimentation

6/2/2006Detail screen flow and Scope Document

6/5/2006Server and Vignette software setup

6/12/2006Pilot screen Template

6/19/2006HTML screen Templates

7/10/2006Complete the content migration

7/17/2006Vignette Coding complete

7/24/2006Complete Testing

7/31/2006Steering committee presentation

8/7/2006Lesson Learned

8/8/2006High level Phase 1 plan document

Page 7: I gave Management Consulting Training - PPT Outline by Murali Venkatesh

WCMS Vignette Phase II Project Plan

7

Organization Chart

Project Management Office

Steering Committee

Murali VenkateshProject Manager

Claudine IllgDirector

Claudine(Communication)Business Analyst

Jim HyltonInfrastructure

Lead (PT)

BhanuDatabase Lead (PT)

Sr. Technical Lead/Architect

Vignette Developer

HTML/Taxonomy Developer

HTML/Content Migration Developer

Vignette Team (PT)

Larry Wright

Lorah Gough

Avis Horde

Steering Committee Member 1

Steering Committee Member 2

Steering Committee Member 3

Steering Committee Member 4

Steering Committee Member 5

Carole HarringtonInterim Associate Vice Chancellor

Irene PorcarelloVice Chancellor of Student success Bill Meyer

Trendec Team (PT)

Mellissa(Student Services)Business Analyst

Page 8: I gave Management Consulting Training - PPT Outline by Murali Venkatesh

WCMS Vignette Phase II Project Plan

8

Resources

* (PT) – Part Time

June 07th

ID Responsibility NameMay 2006 Jun 2006 Jul 2006 Aug 2006

5/7 5/14 5/21 5/28 6/4 6/11 6/18 6/25 7/2 7/9 7/16 7/23 7/30 8/6

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

Project Manager - Murali

Project Monitry, control and Management

Business Analyst – Mellissa & Claudine

Analysis and Design of the Pilot

Infrastructure Lead (PT) - Jim

Setup Infrastructure for Pilot servers

Database Lead (PT) - Bhanu

Setup Vignette and Oracle database schemas

Sr. Technical Lead/Architect

Setup Pilot servers and implementation

Vignette Developer

Create the Vignette screen for Pilot

HTML/Taxonomy Developer

Modify the HTML screens

HTML/Content Migration Developer (PT)

Content Creating and Migration

Vignette Support Person (PT)

Guidance to setup application and portal servers

Page 9: I gave Management Consulting Training - PPT Outline by Murali Venkatesh

WCMS Vignette Phase II Project Plan

9

Project DeliverablesProject Manager

Business Analyst

Sr. Technical Architect/Lead

Vignette/JAVA Developer

HTML/Taxonomy Developer

HTML/Content Migration Developer

Project Charter,

RFP, SOW

Project Plan

Resource Skill

Request

Project Status Report

Presentation to Steering Commite

Project Scope

Infrastructure Proposal

CMS Knowledge

Sharing

Pilot Look and Feel

Lessons Learned

Prepare for the

Next Phase

Current HCCS status

Gather Pilot

scope

Pilot scope

document

Coordination with users/

business team

Current HCCS

Architecture

Pilot Integration approach

Technical Integration templates

Best practices for CMS

implimentation

Implimentation notes

HTML templates

HTML pages design

Content Migration

Workflow implimentation

Pilot Implimentation

Pilot Implimentation

Vignette support person

Infrastructure Lead Setup the Web server

Database Lead Setup Vignette user

database

Support to Install Vignette CMS

and Portal Servers

Support to setup CMS Database

Support to setup out of the

box Vignette system

Setup Oracle data storage

Setup Web Application

server

Setup File storage server

Setup Load balancer

Page 10: I gave Management Consulting Training - PPT Outline by Murali Venkatesh

WCMS Vignette Phase II Project Plan

10

Resource BudgetHCC’s Vignette Phase II Project Resource Cost (Planned)

ID Responsibility NameMay 2006 Jun 2006 Jul 2006 Aug 2006

5/7 5/14 5/21 5/28 6/4 6/11 6/18 6/25 7/2 7/9 7/16 7/23 7/30 8/6

1

2

3

4

Project Manager

Sr. Technical Lead/Architect

Vignette Developer

HTML Developer - 1

Start

5/8/2006

7/3/2006

7/3/2006

5/23/2006

Finish

7/7/2006

8/8/2006

8/8/2006

8/8/2006

Duration

9w

5w 2d

5w 2d

11w 1d

Cost as Planned

$24,000

$12,334

$10,000

$20,000

HCC’s Vignette Phase II Project Resource Cost (Proposing)

ID Responsibility Name Start Finish Duration Cost as Planned

May 2006 Jun 2006 Jul 2006 Aug 2006

5/7 5/14 5/21 5/28 6/4 6/11 6/18 6/25 7/2 7/9 7/16 7/23 7/30 8/6

1

2

5

6

7

8

13w 4d8/10/20065/8/2006Project Manager

8w 3d7/26/20065/29/2006Business Analyst (Internal Staff)

7w 2d8/9/20066/20/2006Sr. Technical Lead/Architect

5w 2d8/8/20067/3/2006Vignette Developer

11w 1d9/26/20067/11/2006HTML/Taxonomy Developer

3w 1d8/4/20067/14/2006HTML/Content Migration Developer(Part Time)

4 9w7/21/20065/22/2006Database Lead (Part Time)(Internal Staff)

3 9w 3d7/21/20065/17/2006Infrastructure Lead (Part Time) (Internal Staff)

9 5w 4d7/26/20066/16/2006Vignette Support person (Part Time)

Page 11: I gave Management Consulting Training - PPT Outline by Murali Venkatesh

WCMS Vignette Phase II Project Plan

11

Presentation Wrap Up• WCMS team did spend some time to understand the previous

effort– Capturing the previous effort and reviewing documents

• WCMS team will continue to build strong relationship with Steering committee– On regular basis have a project progress, presentation, and

knowledge sharing sessions • WCMS team is clearly defining future direction of pilot project

– Project schedule, and resources needed– Milestone and deliverables

• PMO is ready to– Place an order for pilot hardware– List a posting for external resource

Page 12: I gave Management Consulting Training - PPT Outline by Murali Venkatesh

WCMS Vignette Phase II Project Plan

12

Questions?