I-64 Peninsula Widening ProjectUPC 104905
January 8, 2014Bruce Duvall, P.E.
I-64 Peninsula Widening
SEGMENT II
SEGMENT I
Exit 242Rt. 199 Humelsine Parkway
Exit 243US 60/Rt. 143 Busch Gardens
Exit 247Rt. 238/Yorktown Rd
Exit 247Rt. 143
Exit 255Jefferson Ave
Exit 250Fort Eustis Blvd
Exit 238Rt. 143 / Camp Peary
SEGMENT IIIExit 234
Rt. 199 Newman Rd
96,000 vpd
87,000 vpd
81,000 vpd
61,000 vpd
Williamsburg
2011 Traffic Volumes Shown
York River
James River
Begin Project
Begin project
Bridge Widening atIndustrial Park Dr and CSX
Bridge Widening at Fort Eustis Blvd
Exit 250Rt. 105 Fort Eustis Blvd
End project at Lee Hall Reservoir
I-64 Segment IExit 255 to Exit 250
Exit 255Jefferson Ave
City of Newport News Park
I-64 Peninsula Widening ProjectSegment I Overview• Length: 5 Miles
• Widening four bridges• I-64 over Industrial Park Dr and CSX• I-64 over Rt. 105 Fort Eustis Blvd
• City of Newport News Park• Section 4(f) property
• SWM Basins: Approx. 15
• Sound Barrier Under Consideration: 2 miles
• Stream Impacts: 4000 LF
• R/W and Easements: Approx. 15 acres
• Estimated Cost: $112.5 M (2016 dollars)
Bridge Widening atLee Hall Reservoir
Bridge Widening atRt. 238 Yorktown Rd
Bridge Widening at Rt. 641 Penniman Rd
EBL Bridge Widening EBL Bridge Widening at Busch Gardens Bridge Widening at Access Rd
and RR to Naval Weapons Sta
Bridge Widening atRt. 143
I-64 Segment IIExit 250 to Exit 242
Yorktown Naval Weapons Station
Exit 242
Exit 243
Exit 247
Exit 247
Exit 250
City of Newport News Park
• Length: 7 Miles
• Widening eleven bridges
• City of Newport News Park• Section 4(f) property
• Yorktown Naval Weapons Station • Borders 3.5 miles of project corridor• Underground detention to avoid property impacts
• SWM Basins: Approx. 34
• R/W and Easements: Approx. 30 acres
• Estimated Cost: $195 M (2016 dollars)
I-64 Peninsula Widening ProjectSegment II Overview
I-64 Segment IIIExit 242 to 234
Camp Peary
Williamsburg
Colonial Parkway Bridge&
Lakes Head Dr Bridge
Route 716 OverpassQueens Creek Bridge
Route 143 Overpass
Exit 234Route 199
Exit 238Route 143/Camp Peary
Waller Mill Park
Exit 242Route 199
• Widening four bridges• I-64 over Colonial Parkway and Route 1314 Lakes Head Drive
• Replacing two overpass bridges• Route 716 Queens Creek Drive and Route 143 at Camp Peary
• I-64 bridges over Queens Creek: 900’+ length• Camp Peary
• Borders 3 miles of project corridor
• Historic / archaeological sites• Avoid or minimize project effects• Avoid above-ground historic sites
• Coordination with National Park Service• SWM facilities located outside of view sheds• Aesthetic properties of existing bridges maintained
• Estimated Cost: $275 M(planning level estimate in 2016 dollars)
I-64 Peninsula Widening ProjectSegment III Overview
Moving Forward• Segment 1 (Exit 255 to Exit 250)
• Verify western project limits / termini• Coordinate with FHWA to issue ROD• Spring 2014 DB Advertisement• Advance plans to Public Hearing
• Segment 2 (Exit 250 to Exit 242)• Advance preliminary engineering• Advance to Public Hearing
• Segment 3 (Exit 242 to Exit 234)• Pre-scoping evaluations and risk
assessment • Refine cost estimate
Segment I Schedule
2013 2015
Sprin
g 2
014
Sprin
g 20
14
Sprin
g 2
014
Advertise Design-Build RFQ
Sum
mer
201
4
Design-Build RFP
Fall
2014
Final EIS Approved
FHWA Record of Decision
Award Design-Build Contract
Design Public Hearing
Today
Dece
mbe
r 20
13
• Est. Cost = $144 M• Prevents temporary impacts to Fort Eustis Interchange• Only one impacted property owner from Lee Hall
Reservoir Bridge to MM248 (City Newport News)
Alternate Proposal - Segment I TerminusExit 255 to MM 248
I-64 Peninsula Widening ProjectUPC 104905
January 8, 2014Bruce Duvall, P.E.