HWCR, AT-ACR-IN, 12 May 2005 1 Cryogenic Instrumentation & Controls Commissioning Hardware Commissioning Review Juan CASAS

Upload: blaise-bryan

Post on 30-Dec-2015

223 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: HWCR, AT-ACR-IN, 12 May 2005 1 Cryogenic Instrumentation & Controls Commissioning Hardware Commissioning Review Juan CASAS

HWCR, AT-ACR-IN, 12 May 2005 1

Cryogenic Instrumentation & Controls Commissioning

Hardware Commissioning Review

Juan CASAS

Page 2: HWCR, AT-ACR-IN, 12 May 2005 1 Cryogenic Instrumentation & Controls Commissioning Hardware Commissioning Review Juan CASAS

HWCR, AT-ACR-IN, 12 May 2005 2

QRL versus LHC

QRL LHC

RIO Specs for UNICOS DONE In Preparation

Controls Specs for UNICOS Under Revision Time Critical

Hardware for Actuators Industrial Type Idem; Commissioned for QRL?

Tunnel Hardware Industrial Type

RadTol:

Critical Procurement Schedule

LSS8L: Internal production

Learning Contingency (50%) Integrated in planning NOT Accepted

Instrumentation Tasks No Repairs, Reporting Only Full Commissioning

Fieldbus Profibus Profibus & WorldFIP

Sectors 8-1 and part of 7-8All Sectors

QRL tasks not included in LHC tasks => extra time…

Page 3: HWCR, AT-ACR-IN, 12 May 2005 1 Cryogenic Instrumentation & Controls Commissioning Hardware Commissioning Review Juan CASAS

HWCR, AT-ACR-IN, 12 May 2005 3

QRL & LHC Schedules

QR

L >

18.

5 w

ks

LH

C –

41

wk

s

Page 4: HWCR, AT-ACR-IN, 12 May 2005 1 Cryogenic Instrumentation & Controls Commissioning Hardware Commissioning Review Juan CASAS

HWCR, AT-ACR-IN, 12 May 2005 4

QRL Actual ScheduleNote that AL Instrumentation Activity not into ACR-IN tasks

Page 5: HWCR, AT-ACR-IN, 12 May 2005 1 Cryogenic Instrumentation & Controls Commissioning Hardware Commissioning Review Juan CASAS

HWCR, AT-ACR-IN, 12 May 2005 5

LHC Pre-requisites

General Services

• UPS

• Tunnel access required during ALL commissioning tasks

• Safe access “paserelle” to tunnel-wall equipment

Controls

• Networks:

– Ethernet

• PLC – Gateway – Data Server communication

• Tunnel WiFi access (Technical & NICE)

– Profibus & WorldFIP

• Optical fiber-Copper couplers

• Gateways

• Hardware (Data server, SCADA, PLCs, Gateways, etc)

• Software for PLCs, Gateways and SCADA

Logistics

• MTF

– non-conformities referenced and retrievable

– Instrument & Host equipment identification (functional and physical) data

• Interpolation data generator

Page 6: HWCR, AT-ACR-IN, 12 May 2005 1 Cryogenic Instrumentation & Controls Commissioning Hardware Commissioning Review Juan CASAS

HWCR, AT-ACR-IN, 12 May 2005 6

LHC Resources & Tasks (per sector)

Generic Tools

• Transport Vehicle

• Electrician Tools

• Sensor/actuator simulation devices

• Ladder

• Computer with network access

Generic Tasks

• Track test data on MTF

• Declare & check in MTF for non conformities

•Crate Connection (CIW CC)

Per sector: avg 125 Crates, 10 cables/crate

Crew: 2 Technicians

Tasks:

•Cables Harness

•Crate Positioning

•Electrical connection at both ends

Duration: 10 weeks => 2 crates per working day

Page 7: HWCR, AT-ACR-IN, 12 May 2005 1 Cryogenic Instrumentation & Controls Commissioning Hardware Commissioning Review Juan CASAS

HWCR, AT-ACR-IN, 12 May 2005 7

LHC Resources & Tasks (per sector)

RadTol Crate stand-alone commissioning (CIW SU)

Per sector: avg 125 Crates, 10 cables/crate, 1900 channels

Crew: 2 x (1 instrumentation engineer + 1 Technician)

Tasks:

•EMC Cables Test

•Check Pressure sensors and hydraulic connections

•Functional Tests on all channels

•Repair all conforming channels

•Commission front-end electronics

•Check Crate Network Configuration Parameters

Duration: 2 x 9 weeks => 2 crates per working day

WorldFIP Initialization (CIW CE)

Per sector: avg 125 Crates, 2 nodes per crate

Crew: 1 fieldbus engineer + 1 Technician + AB-CO Support

Tasks:

•Connect Crate onto fieldbus network

•Verify Global WorldFIP availabiity

•Check Gateway availability

Duration: 8 weeks => 3 crates per working day

Page 8: HWCR, AT-ACR-IN, 12 May 2005 1 Cryogenic Instrumentation & Controls Commissioning Hardware Commissioning Review Juan CASAS

HWCR, AT-ACR-IN, 12 May 2005 8

LHC Resources & Tasks (per sector)

Controls at Warm (CIW CS)

Per sector: 1900 Channels,

Crew: 2 x (1 Control Engineer + 1 Technician)

Tasks:

•Channel Coherence checks SCADA to field:

– Actuators: Intelligent Valves, ON/OFF Valves & Heaters

– Sensors: Pressure, Temperature, Level, Position, etc.

•Synoptic conformance check

•Check that physical readout is coherent with ambient conditions

•Simulate/check logic seuqnces, PIDs, Linearization

Duration: 2 x 16 weeks

Page 9: HWCR, AT-ACR-IN, 12 May 2005 1 Cryogenic Instrumentation & Controls Commissioning Hardware Commissioning Review Juan CASAS

HWCR, AT-ACR-IN, 12 May 2005 9

LHC Resources & Tasks (per sector)

Controls during Cool-Down (CIC CT)Per sector: 1900 Channels, Crew: 2 Control Engineer + 1 TechnicianTasks:•Check Sensor evolution•Diagnostics of non conformities left from “Controls @ Warm”•Set appropriate control loop parametersDuration: 10 weeksControls during Nominal (CIC OP)Per sector: 1900 Channels, Crew: 1 Control Engineer + 1 TechnicianTasks:•Diagnostics of non conformities left from “Controls @ Cool-Down”•Set appropriate control loop parametersDuration: 11 weeksSurface Support•Database/Quality Assurance engineer for Thermometer, Parameters (Cabling, configuration, naming, location), sensor calibration (pressure)•Instrumentation Engineer to assess and provide support for field teams

Page 10: HWCR, AT-ACR-IN, 12 May 2005 1 Cryogenic Instrumentation & Controls Commissioning Hardware Commissioning Review Juan CASAS

HWCR, AT-ACR-IN, 12 May 2005 10

LHC Resources & Tasks (per sector)

teams/sector Eng Tek UNICOS1. CIW CC Crate Connection 10 1 22. CIW SU Crate Stand Alone Commissioning 10 2 2 23. CIW CE WorldFIP Initialization 8 1 1 14. CIW CS Controls at Warm 16 2 2 2 0.55. CIC CT Controls during Cool-Down 10 1 2 1 0.55. CIC OP Controls during Nominal 11 1 1 1 0.56. CIW SP on call 0.5 2

duration [week]

Professional Profile

Page 11: HWCR, AT-ACR-IN, 12 May 2005 1 Cryogenic Instrumentation & Controls Commissioning Hardware Commissioning Review Juan CASAS

HWCR, AT-ACR-IN, 12 May 2005 11

Shortcomings•InfrastructureEthernet connection very cumbersome:

– individual modem VDSL + base WIFI => additional jumping onto equipment– Several teams working in adjacent cells

• Please provide WIFI as a standard infrastructure inside the tunnel during commissioning– Access to BOTH technical and NICE networks

•ControlsReliability of controls:

– Communication Problems hamper operation– PVSS SCADA to be improved– Too many software versions

Profibus: Schneider fieldbus configuration tool is far from user friendly•LogisticsMTF:

– Non-conformities instrument retrieval interface for instrumentation required but non-existent– inner triplet data status?– Naming uniqueness

MTF interface required for tunnel reportingIS MTF ADEQUATE FOR INSTRUMENTATION COMMISSIONING TASKSDatabase/Quality Assurance Support shall be very responsive:

– Close to end-user– For AT-ACR depends on a temporary unit of personnel (fellow)

Automated Test Equipment development:– delayed continuously by on-site (SMI2, AL premises, etc) instrumentation support.

Page 12: HWCR, AT-ACR-IN, 12 May 2005 1 Cryogenic Instrumentation & Controls Commissioning Hardware Commissioning Review Juan CASAS

HWCR, AT-ACR-IN, 12 May 2005 12

Shortcomings: MTF data retrieval

This quad does have:

1.Cold-mass t

hermometer

2.Electric

al Heater

3.…

How do I know that NC No 90 refers to

an electrical Heater?

Page 13: HWCR, AT-ACR-IN, 12 May 2005 1 Cryogenic Instrumentation & Controls Commissioning Hardware Commissioning Review Juan CASAS

HWCR, AT-ACR-IN, 12 May 2005 13

Shortcomings: MTF data retrieval

Page 14: HWCR, AT-ACR-IN, 12 May 2005 1 Cryogenic Instrumentation & Controls Commissioning Hardware Commissioning Review Juan CASAS

HWCR, AT-ACR-IN, 12 May 2005 14

Naming Conventions: How it works

PhysicalEquipment

Serial number

MTFSlot name + Tag name

Serial number

LHC Reference DBSlot name

Serial number

The slot name + tag name used by the Controls/Operation must coincide with the slot name + tag name registered in LHC Reference DB and in MTF.

Project engineerTag name

Controls/Operation

Slot name + Tag name

Page 15: HWCR, AT-ACR-IN, 12 May 2005 1 Cryogenic Instrumentation & Controls Commissioning Hardware Commissioning Review Juan CASAS

HWCR, AT-ACR-IN, 12 May 2005 15

• All machine components MUST be registered in MTF

• All instrumentation MUST be assigned to machine assemblies in MTF

Naming Conventions: How is it used? (1)

The tag name (e.g. TT821) MUST be included when the instrumentation is assigned to a machine assembly in MTF

Page 16: HWCR, AT-ACR-IN, 12 May 2005 1 Cryogenic Instrumentation & Controls Commissioning Hardware Commissioning Review Juan CASAS

HWCR, AT-ACR-IN, 12 May 2005 16

• The slot names MUST be identical

MQ.28LiMQ.29Li

QRLAA.30Li

MQ.27Li

QRLAB.28Li

MBC...MBA.29Li MBC...MBA.28Li

MQ.28LiMQ.29Li

QRLAA.29Li

MQ.27Li

QRLAB.27Li

MBC...MBA.29Li MBC...MBA.28Li

AT/ACR name (used by Controls/Operation)

Official name (used by MTF)

Naming Conventions: How is it used? (2)

Page 17: HWCR, AT-ACR-IN, 12 May 2005 1 Cryogenic Instrumentation & Controls Commissioning Hardware Commissioning Review Juan CASAS

HWCR, AT-ACR-IN, 12 May 2005 17

D4.6R7Q5R7

QRLIA.2R7

Q6R7

QRLEA.6R7

D3.6R7

… …

DFBM.6R7

D4.6R7Q5R7

QRLIA.6R7

Q6R7

QRLEA.6R7

D3.6R7

… …

DFBM.6R7

Naming Conventions: How is it used? (3)

• The slot names MUST be identical

AT/ACR name (used by Controls/Operation)

Official name (used by MTF)

Page 18: HWCR, AT-ACR-IN, 12 May 2005 1 Cryogenic Instrumentation & Controls Commissioning Hardware Commissioning Review Juan CASAS

HWCR, AT-ACR-IN, 12 May 2005 18

Naming Conventions: Summary

QRLAA.30L8QRLAA.29L8

What??? QRLAA.29L8

is not on MTF!!!

Page 19: HWCR, AT-ACR-IN, 12 May 2005 1 Cryogenic Instrumentation & Controls Commissioning Hardware Commissioning Review Juan CASAS

HWCR, AT-ACR-IN, 12 May 2005 19

Major Shortcomings•Missing Manpower

Cryogenic commissioning consist of a set of specialized tasks:

– Will there be a good match between professional qualifications & tasks?

– Is training required?

• If YES: additional resources shall be already at CERN

• 3-6 month seem the strict minimum

LHC schedule show activities in up to 3 sectors at the same time

– 1 team (warm commissioning) would then be missing

ACR-IN tasks planning does not foresee support for external teams

– Additional manpower autonomous from day 1; otherwise work can be significantly delayed

Is it possible to consolidate critical know-how/ressources:

• Database/Quality Assurance support relies on temporary personnel

• Additional process control engineers is required

•Various

No contingency allocation!