Hurricane Forecast Improvement Project (HFIP):Where do we stand after 3 years?
Bob Gall – HFIP Development Manager
Fred Toepfer—HFIP Project manager
Frank Marks – HFIP Research Lead
Ed Rappaport – HFIP Operations Lead
March 6, 2013
![Page 2: Hurricane Forecast Improvement Project (HFIP): Where do we stand after 3 years? Bob Gall – HFIP Development Manager Fred Toepfer—HFIP Project manager Frank](https://reader035.vdocuments.mx/reader035/viewer/2022070411/56649f3b5503460f94c59e92/html5/thumbnails/2.jpg)
2
The HFIP Project – Vision/Goals
• Visiono Organize the hurricane community to dramatically
improve numerical forecast guidance to NHC in 5-10 years
• Goalso Reduce numerical forecast errors in track and
intensity by 20% in 5 years, 50% in 10 yearso Extend forecasts to 7 dayso Increase probability of detecting rapid intensification
at day 1 to 90% and 60% at day 5
![Page 3: Hurricane Forecast Improvement Project (HFIP): Where do we stand after 3 years? Bob Gall – HFIP Development Manager Fred Toepfer—HFIP Project manager Frank](https://reader035.vdocuments.mx/reader035/viewer/2022070411/56649f3b5503460f94c59e92/html5/thumbnails/3.jpg)
HFIP Baselines and Goals:Track
3
![Page 4: Hurricane Forecast Improvement Project (HFIP): Where do we stand after 3 years? Bob Gall – HFIP Development Manager Fred Toepfer—HFIP Project manager Frank](https://reader035.vdocuments.mx/reader035/viewer/2022070411/56649f3b5503460f94c59e92/html5/thumbnails/4.jpg)
HFIP Baselines and Goals:Intensity
4
![Page 5: Hurricane Forecast Improvement Project (HFIP): Where do we stand after 3 years? Bob Gall – HFIP Development Manager Fred Toepfer—HFIP Project manager Frank](https://reader035.vdocuments.mx/reader035/viewer/2022070411/56649f3b5503460f94c59e92/html5/thumbnails/5.jpg)
HFIP Overall Strategy
• Use global models at as high a resolution as possible to forecast track out to 7 days
• Use regional models at 1-3 km resolution to predict inner core structure to meet intensity goals out to 5 days including rapid intensification
• Hybrid DA for both regional and global using as much satellite and aircraft data as possible
• Both regional and global models run as ensemblesBoth regional and global models run as ensembles
• Statistical post processing of model output to further increase forecast skill
![Page 6: Hurricane Forecast Improvement Project (HFIP): Where do we stand after 3 years? Bob Gall – HFIP Development Manager Fred Toepfer—HFIP Project manager Frank](https://reader035.vdocuments.mx/reader035/viewer/2022070411/56649f3b5503460f94c59e92/html5/thumbnails/6.jpg)
Track Error of Models (2010-2011)(% Improvement over HFIP baseline)
![Page 7: Hurricane Forecast Improvement Project (HFIP): Where do we stand after 3 years? Bob Gall – HFIP Development Manager Fred Toepfer—HFIP Project manager Frank](https://reader035.vdocuments.mx/reader035/viewer/2022070411/56649f3b5503460f94c59e92/html5/thumbnails/7.jpg)
Impact of Aircraft Data(% improvement over D-SHIFOR)
7
![Page 8: Hurricane Forecast Improvement Project (HFIP): Where do we stand after 3 years? Bob Gall – HFIP Development Manager Fred Toepfer—HFIP Project manager Frank](https://reader035.vdocuments.mx/reader035/viewer/2022070411/56649f3b5503460f94c59e92/html5/thumbnails/8.jpg)
How are we doing?
• The HFIP goals are for model products delivered from NCEP to NHC.– The delivery date for these goals is hurricane
season 2014
• The following show the operational models (Global and Regional) performance for hurricane track and intensity in the Atlantic for latest hurricane season (2012)
8
![Page 9: Hurricane Forecast Improvement Project (HFIP): Where do we stand after 3 years? Bob Gall – HFIP Development Manager Fred Toepfer—HFIP Project manager Frank](https://reader035.vdocuments.mx/reader035/viewer/2022070411/56649f3b5503460f94c59e92/html5/thumbnails/9.jpg)
Baseline skill
5-year skill goal
GFS
HWRFGFDL
Comparison of 2012 NCEP Operational Models to the 5 Year HFIP
Goal: Track
![Page 10: Hurricane Forecast Improvement Project (HFIP): Where do we stand after 3 years? Bob Gall – HFIP Development Manager Fred Toepfer—HFIP Project manager Frank](https://reader035.vdocuments.mx/reader035/viewer/2022070411/56649f3b5503460f94c59e92/html5/thumbnails/10.jpg)
Baseline skill
GFS
HWRF
Comparison of 2012 NCEP Operational Models to the 5 Year HFIP
Goal: Intensity
GFDL
HFIP 5 year Goal
![Page 11: Hurricane Forecast Improvement Project (HFIP): Where do we stand after 3 years? Bob Gall – HFIP Development Manager Fred Toepfer—HFIP Project manager Frank](https://reader035.vdocuments.mx/reader035/viewer/2022070411/56649f3b5503460f94c59e92/html5/thumbnails/11.jpg)
11
Stream 1.5 Results for 2012
![Page 12: Hurricane Forecast Improvement Project (HFIP): Where do we stand after 3 years? Bob Gall – HFIP Development Manager Fred Toepfer—HFIP Project manager Frank](https://reader035.vdocuments.mx/reader035/viewer/2022070411/56649f3b5503460f94c59e92/html5/thumbnails/12.jpg)
AHW
HWRF
FSU
FIMGFS
NOGAPS
TVCA
GFDL
ECMWF
UKMET
Canadian Model
![Page 13: Hurricane Forecast Improvement Project (HFIP): Where do we stand after 3 years? Bob Gall – HFIP Development Manager Fred Toepfer—HFIP Project manager Frank](https://reader035.vdocuments.mx/reader035/viewer/2022070411/56649f3b5503460f94c59e92/html5/thumbnails/13.jpg)
AHW
HWRF
FSU
Intensity Consensus
Wisconsin
GFDL
DSHPLGEM
SPC3
TC-COAMPS
![Page 14: Hurricane Forecast Improvement Project (HFIP): Where do we stand after 3 years? Bob Gall – HFIP Development Manager Fred Toepfer—HFIP Project manager Frank](https://reader035.vdocuments.mx/reader035/viewer/2022070411/56649f3b5503460f94c59e92/html5/thumbnails/14.jpg)
• The upgrade to the 3km triple-nested HWRF is a result of multi-agency efforts under HFIP support
– EMC - Computational tuning to speed up the model, nest motion algorithm, physics improvements, 3km initialization and pre-implementation T&E
– HRD/AOML - multi-moving nest, nest motion algorithm, PBL upgrades, interpolation routines for initialization and others.
– DTC - code management and maintain subversion repository
– ESRL - Physics sensitivity tests and idealized capability– NHC - Diagnose the HWRF pre-implementation results– URI - 1D ocean coupling in Eastern Pacific basin
2012 HWRF Upgrades
14
![Page 15: Hurricane Forecast Improvement Project (HFIP): Where do we stand after 3 years? Bob Gall – HFIP Development Manager Fred Toepfer—HFIP Project manager Frank](https://reader035.vdocuments.mx/reader035/viewer/2022070411/56649f3b5503460f94c59e92/html5/thumbnails/15.jpg)
2012 3km HWRF Operational Upgrade Summary
HOPS: oper. HWRF
H212: 2012 HWRF
ATL Tracks• Significant Improvements of H212
– Track/intensity forecast skills for 2011/2010 seasons on Atlantic basin 20-25% improvement against HOPS
– Track forecast skills of H212 of Eastern Pacific basin maximum 25% over the HOPS in 2011 season, but little degradation at day 4 and 5 in 2010 season mainly due to Hurricane Frank
– Intensity of 2011 EP basin with over 40% to HOPS. Significant improvements in intensity bias is noted for both Atlantic and Eastern Pacific, for both 2010-2011 seasons.
– The storm structure in terms of storm size and PBL height significantly improved
– Much improved wind-pressure relationship in high wind speed regime
15
ATL IntensityHOPS: oper. HWRF
H212: 2012 HWRF
20-25% improvement
![Page 16: Hurricane Forecast Improvement Project (HFIP): Where do we stand after 3 years? Bob Gall – HFIP Development Manager Fred Toepfer—HFIP Project manager Frank](https://reader035.vdocuments.mx/reader035/viewer/2022070411/56649f3b5503460f94c59e92/html5/thumbnails/16.jpg)
16
Impact of Radar Data
![Page 17: Hurricane Forecast Improvement Project (HFIP): Where do we stand after 3 years? Bob Gall – HFIP Development Manager Fred Toepfer—HFIP Project manager Frank](https://reader035.vdocuments.mx/reader035/viewer/2022070411/56649f3b5503460f94c59e92/html5/thumbnails/17.jpg)
Impact of TDR data assimilation to hurricane intensity forecast
2.2.2 (EMC)TDR assimilation
OPR HWRF
HWRF TDR
Cross section at initial time
17
![Page 18: Hurricane Forecast Improvement Project (HFIP): Where do we stand after 3 years? Bob Gall – HFIP Development Manager Fred Toepfer—HFIP Project manager Frank](https://reader035.vdocuments.mx/reader035/viewer/2022070411/56649f3b5503460f94c59e92/html5/thumbnails/18.jpg)
With TDR
Impact of TDR Data In Operational HWRF
Without TDR
Without TDR
With TDR
Track Error Intensity Error
![Page 19: Hurricane Forecast Improvement Project (HFIP): Where do we stand after 3 years? Bob Gall – HFIP Development Manager Fred Toepfer—HFIP Project manager Frank](https://reader035.vdocuments.mx/reader035/viewer/2022070411/56649f3b5503460f94c59e92/html5/thumbnails/19.jpg)
• Questions?
19
![Page 20: Hurricane Forecast Improvement Project (HFIP): Where do we stand after 3 years? Bob Gall – HFIP Development Manager Fred Toepfer—HFIP Project manager Frank](https://reader035.vdocuments.mx/reader035/viewer/2022070411/56649f3b5503460f94c59e92/html5/thumbnails/20.jpg)
Extra Slides
![Page 21: Hurricane Forecast Improvement Project (HFIP): Where do we stand after 3 years? Bob Gall – HFIP Development Manager Fred Toepfer—HFIP Project manager Frank](https://reader035.vdocuments.mx/reader035/viewer/2022070411/56649f3b5503460f94c59e92/html5/thumbnails/21.jpg)
Comparison of 2012 NCEP Operational Models to the 5 Year HFIP
Goal: Track
![Page 22: Hurricane Forecast Improvement Project (HFIP): Where do we stand after 3 years? Bob Gall – HFIP Development Manager Fred Toepfer—HFIP Project manager Frank](https://reader035.vdocuments.mx/reader035/viewer/2022070411/56649f3b5503460f94c59e92/html5/thumbnails/22.jpg)
Comparison of 2012 NCEP Operational Models to the 5 Year HFIP
Goal: Intensity
![Page 23: Hurricane Forecast Improvement Project (HFIP): Where do we stand after 3 years? Bob Gall – HFIP Development Manager Fred Toepfer—HFIP Project manager Frank](https://reader035.vdocuments.mx/reader035/viewer/2022070411/56649f3b5503460f94c59e92/html5/thumbnails/23.jpg)
Statistical Post Processing
• Statistical Post Processing can add skill to dynamical forecasts.
• There are a number of techniques based on ensembles or individual models.
• One method is shown in the following figure
– From the FSU Multi-Model Ensemble (MMEN) which forms a weighted mean of the many global and regional models run both operationally and by HFIP in real time.
![Page 24: Hurricane Forecast Improvement Project (HFIP): Where do we stand after 3 years? Bob Gall – HFIP Development Manager Fred Toepfer—HFIP Project manager Frank](https://reader035.vdocuments.mx/reader035/viewer/2022070411/56649f3b5503460f94c59e92/html5/thumbnails/24.jpg)
2012 all storms
![Page 25: Hurricane Forecast Improvement Project (HFIP): Where do we stand after 3 years? Bob Gall – HFIP Development Manager Fred Toepfer—HFIP Project manager Frank](https://reader035.vdocuments.mx/reader035/viewer/2022070411/56649f3b5503460f94c59e92/html5/thumbnails/25.jpg)
Genesis
25
![Page 26: Hurricane Forecast Improvement Project (HFIP): Where do we stand after 3 years? Bob Gall – HFIP Development Manager Fred Toepfer—HFIP Project manager Frank](https://reader035.vdocuments.mx/reader035/viewer/2022070411/56649f3b5503460f94c59e92/html5/thumbnails/26.jpg)
Verification of model genesis for operational global models
• All models have a bias towards over-prediction, caused by both false alarms as well as genesis occurring in the forecast long (>>48h) before observed genesis.
• 4-ensemble consensus close to reliable up through 50-60%.26
![Page 27: Hurricane Forecast Improvement Project (HFIP): Where do we stand after 3 years? Bob Gall – HFIP Development Manager Fred Toepfer—HFIP Project manager Frank](https://reader035.vdocuments.mx/reader035/viewer/2022070411/56649f3b5503460f94c59e92/html5/thumbnails/27.jpg)
NHC Hurricane Genesis Statistics
27