Page 1: Huntington Levee Community Meeting: Oct. 26. 2016

Department of Public Works and Environmental Services

Huntington LeveeCommunity Meeting

October 26, 2016

Page 2: Huntington Levee Community Meeting: Oct. 26. 2016

2Building Design and Construction Division

AgendaHuntington Levee

I. Project Background

II. Levee System Design

III. Construction

IV. Community Amenities

V. Flood Modeling Results

VI. Permitting

VII. Schedule

VIII. Environmental Design

IX. Community Outreach

X. Questions

Page 3: Huntington Levee Community Meeting: Oct. 26. 2016

3Building Design and Construction Division

Project Background• June 2006 -160 homes were

flooded from a storm event

• 2009 – US Army Corps of Engineers (USACE) completed a study to evaluate flood damage reduction measures in the Huntington Community

• November 6, 2012 – Fairfax County voters approved stormwater bond referendum

• November 2013 – Phase I design completed

• January 2014 – Fairfax County and Huntington Community reached consensus on conceptual design features

Page 4: Huntington Levee Community Meeting: Oct. 26. 2016

4Building Design and Construction Division

Project Background• July 2014 – Hydraulic and Hydrologic Modelling for Cameron Run

• September 2014 – Schematic (30%) Design

• October 2014 - Value Engineering Workshop

• June 2015 – Design Development (60%) Design

• February 2016 – Construction Documents (100%) Design

• Spring 2016 – Technical review by County and Corps of Engineers

• July 2016 – CLOMR approved by FEMA

• August 2016 – Project advertised for bid to pre-qualified contractors

• September 2016 – Wetlands permitting approved by DEQ and Corps of Engineers

Page 5: Huntington Levee Community Meeting: Oct. 26. 2016

5Building Design and Construction Division

Levee System DesignLevee System

Page 6: Huntington Levee Community Meeting: Oct. 26. 2016

6Building Design and Construction Division

Levee System DesignKey Design Features

• Earthen Levee/I-Wall Combination• Pump Station • Stormwater Diversion

Page 7: Huntington Levee Community Meeting: Oct. 26. 2016

7Building Design and Construction Division

Levee System DesignRendering – Looking West

Levee I-WallOpen Channel

Ponding AreaCameron Run

Page 8: Huntington Levee Community Meeting: Oct. 26. 2016

8Building Design and Construction Division

Levee System DesignRendering – Looking East with Cross Section

Asphalt Trail

Open Channel with Drains

Ponding Area

Ponding Area

Slope SlopeSlope

Sloped to Pump Station

Page 9: Huntington Levee Community Meeting: Oct. 26. 2016

9Building Design and Construction Division

Levee System DesignRendering – Looking East from Top of Levee Trail

Asphalt Trail

Concrete I-Wall

Ponding Area

Page 10: Huntington Levee Community Meeting: Oct. 26. 2016

10Building Design and Construction Division

Levee System DesignRendering – Looking Northeast Toward Pump Station

Note: Fence with gate to be constructed around Pump Station

Page 11: Huntington Levee Community Meeting: Oct. 26. 2016

11Building Design and Construction Division

Levee System DesignRendering – Cross Section of Pump Station

Page 12: Huntington Levee Community Meeting: Oct. 26. 2016

12Building Design and Construction Division

ConstructionNext Steps in Construction

Bids Opened

Bid Evaluation

County Approval

of Contract

Notice of Award

Notice to Proceed

October 6, 2016

October 2016

November 2016

December 2016

January 2017

Page 13: Huntington Levee Community Meeting: Oct. 26. 2016

13Building Design and Construction Division

ConstructionKey Activities during Construction

Notice to Proceed

Site Manage

ment Plan

Contractor Mobilization

Substantial CompletionJanuary

2017January/ February

2017

January/ February

2017

February 2019

Page 14: Huntington Levee Community Meeting: Oct. 26. 2016

14Building Design and Construction Division

Site Management Plan

• Submitted by contractor 30 days after NTP

• Approved by County

Included in Site Management Plan

• Phasing of Construction

• Control of Water

• Emergency Response

Construction

Page 15: Huntington Levee Community Meeting: Oct. 26. 2016

15Building Design and Construction Division

Contractor Restrictions

• Construction activities limited to 7:00am to 7:00pm, Monday – Friday

• Weekend and holiday work to be approved by County

• Contractor parking prohibited in neighborhood

• Truck traffic through neighborhood restricted

• Noise per Fairfax County Noise Ordinance

Construction

Page 16: Huntington Levee Community Meeting: Oct. 26. 2016

16Building Design and Construction Division

ConstructionFirst Construction Activities

• Identification of Limits of Disturbance

• Safety Fencing

• Erosion and Sediment Control

• Construction of Access Road

Page 17: Huntington Levee Community Meeting: Oct. 26. 2016

17Building Design and Construction Division

ConstructionConstruction Extents

For General Reference – Actual Extent determined by Contractor

Construction Safety Fence around Site Perimeter

Construction Access Road

Utility Work

Location of Pump Station

Page 18: Huntington Levee Community Meeting: Oct. 26. 2016

18Building Design and Construction Division

ConstructionConstruction Access

• Route A: Primary Construction Access• Route D: Secondary Access for Pump Station• Routes B and C: Possible Tertiary Construction Access

Page 19: Huntington Levee Community Meeting: Oct. 26. 2016

19Building Design and Construction Division

Community AmenitiesTrails

• Native Grasses in Ponding Area, Mowed 1-3 times per Year• Coarse Turf Grass on Levee

Trail Atop Levee

Trail in Ponding Area

Pump Station

Existing Trail

Service Drive

Page 20: Huntington Levee Community Meeting: Oct. 26. 2016

20Building Design and Construction Division

Community AmenitiesPlayground Area in Farrington Park• Worked with Community Group in Fall 2015• Separate Equipment for Age Groups• Construction in December 2016/ January 2017

Page 21: Huntington Levee Community Meeting: Oct. 26. 2016

21Building Design and Construction Division

Community AmenitiesPlayground Area in Farrington Park – Proposed Design

Page 22: Huntington Levee Community Meeting: Oct. 26. 2016

22Building Design and Construction Division

Flood Modelling ResultsProtection of Homes from 100-Year StormFlood elevation 1-ft below lowest home opening

Page 23: Huntington Levee Community Meeting: Oct. 26. 2016

23Building Design and Construction Division

Flood Modelling Results100-year Stormwater Ponding

Some Street Flooding, but Water Surface Elevation Below Structures

Page 24: Huntington Levee Community Meeting: Oct. 26. 2016

24Building Design and Construction Division

Flood Modelling Results25-year Stormwater Ponding

Some Street Flooding, but Water Surface Elevation Below Structures

Page 25: Huntington Levee Community Meeting: Oct. 26. 2016

25Building Design and Construction Division

Flood Modelling Results10-year Stormwater Ponding

Some Street Flooding, but Water Surface Elevation Below Structures

Page 26: Huntington Levee Community Meeting: Oct. 26. 2016

26Building Design and Construction Division

Permitting UpdateAll Permitting Completed

• Joint Permit Application (Wetlands)

• Conditional Letter of Map Revision (CLOMR)

• DEQ Stormwater Permit

• Building Permit

• Site Permit

• Zoning

• Floodplain Study

Page 27: Huntington Levee Community Meeting: Oct. 26. 2016

27Building Design and Construction Division

Permitting UpdatePermitting Requirements

• Construction Limits marked with 4-foot tall orange fencing

• Non-impacted surface waters with 50-feet of construction limits clearly demarcated

• Monthly DEQ inspection checklist

• Inspections by DEQ and US Army Corps of Engineers

Tree Preservation Areas

Levee

Page 28: Huntington Levee Community Meeting: Oct. 26. 2016

28Building Design and Construction Division

Schedule

• Phase II (January 2014-Winter 2017)

Schematic Design (30%) Design Development (60%) Permitting (began March 2015) Land Acquisition (began September 2014) Construction Documents• Bidding

• Phase III (Winter 2017-Spring 2019)

• Construction

Project Remains on Schedule

Page 29: Huntington Levee Community Meeting: Oct. 26. 2016

29Building Design and Construction Division

Environmental Design

Envision• Rating System for Infrastructure Projects• Bronze Level• Similar to LEED

• 5 Categories:• Quality of Life• Leadership• Resource Allocation• Natural World• Climate and Risk

Page 30: Huntington Levee Community Meeting: Oct. 26. 2016

30Building Design and Construction Division

Community Outreach

Page 31: Huntington Levee Community Meeting: Oct. 26. 2016

31Building Design and Construction Division

Community Outreach

Page 32: Huntington Levee Community Meeting: Oct. 26. 2016

32Building Design and Construction Division

Community Outreach

• Bi-annually• Important Milestones• Next Community meeting – Spring 2017

Community Meetings

Page 33: Huntington Levee Community Meeting: Oct. 26. 2016

33Building Design and Construction Division

Community Outreach

• Similar to current response• Contractor responsible to maintain current condition (no

worse)• Temporary pumping as needed • Contractor will be notified when County dispatches to site

Storm Events

Page 34: Huntington Levee Community Meeting: Oct. 26. 2016

34Building Design and Construction Division

Community OutreachContact Information – Huntington Levee Project

Phone #: 703-324-5800 Email address: [email protected]

Huntington Levee Website: www.fairfaxcounty.gov/dpwes/huntingtonlevee

To request this document in an alternate format call 703-324-5800, TTY 711.