Page 1: Huckabee Project Update 12-05-11

Huckabee

GEORGETOWN ISD2010 BOND PROGRAM UPDATE

D E C E M B E R 2 011

Page 2: Huckabee Project Update 12-05-11

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 2

Huckabee

TABLE OF CONTENTS

East View High School Phase 2 Additions, Package 1 3

East View High School Phase 2 Additions, Package 2 4

New Warehouse Facility 8

Annie Purl Elementary School Roof and HVAC Modifications 9

Georgetown High School Additions and Renovations 10

Page 3: Huckabee Project Update 12-05-11

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 3

Huckabee

EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 1PROGRESS REPORT

MILESTONE DATES

Schematic Design Presentation November 11, 2010

Architect Signs Documents November 24, 2010

Pre-Proposal Meeting December 8, 2010

Proposal Part A Due December 21, 2010

Proposal Part B Due December 22, 2010

Proposal Evaluations January 4, 2011

General Contractor Recommendation to School Board January 10, 2011

First Owner/CO Meeting February 15, 2011

Construction Start Date February 18, 2011

Building Permit Issued March 16, 2011

Owner, Architect and Contractor Meeting June 7, 2011

Owner, Architect and Contractor Meeting June 21, 2011

Owner, Architect and Contractor Meeting July 5, 2011

Owner, Architect and Contractor Meeting July 19, 2011

Substantial Completion (Field/Track and Bleachers) August 1, 2011

Owner, Architect and Contractor Meeting August 2, 2011

Owner, Architect and Contractor Meeting August 16, 2011

Substantial Completion (Buildings) August 19, 2011

General Contractor

Field House Locker Room

Field House Weight Room

Page 4: Huckabee Project Update 12-05-11

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 4

Huckabee

EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2Original: $25,574,000

CATE Addition – $2,121,338Baseball & Softball Turf - $880,000

Total - $28,575,338

Existing East View High School

A. New Athletic AdditionB. New Fine Arts AdditionC. New Academic AdditionD. New CTE BuildingE. New ROTC Addition (Alt.)F. New Tennis CourtsG. New Tennis Building H. New Baseball/Softball Fieldhouse,

Bleachers, Lighting & Pressbox I. New Practice FieldsJ. New Parking (1,070 spaces)

A

B

C

D

F

J

GH

B

J

J

J

J

Bid Package 1

E

Highway 29

CR 104

HH

I

I

Academic Wing

CTE Building

Softball Field House

First Floor

Second Floor

New Academic Addition

New Academic Addition

New Fine Arts Addition

New Athletic Addition

New CTE/ROTC Addition

General Contractor

Page 5: Huckabee Project Update 12-05-11

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 5

Huckabee

EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2PROGRESS REPORT

MILESTONE DATES

Schematic Design Presentation January 1, 2011

Architect Signs Documents March 8, 2011

Building Permit Application Submittal March 15, 2011

Site Plan Application Submittal March 17, 2011

Pre-Proposal Meeting March 22, 2011

Tour with General Contractors at East View Ninth Grade Center March 30, 2011

Proposal Part A Due April 7, 2011

Proposal Part B Due April 8, 2011

Proposal Evaluations April 11, 2011

Received City Building Dept. Plan Review Comments April 14, 2011

General Contractor Recommendation to School Board April 18, 2011

Received City Planning Dept. Plan Review Comments April 25, 2011

Construction Start Date May 19, 2011

First Owner/CO Meeting May 24, 2011

Building Permit Issued June 1, 2011

Owner, Architect and Contractor Meeting November 8, 2011

Owner, Architect and Contractor Meeting November 15, 2011

Owner, Architect and Contractor Meeting November 22, 2011

Owner, Architect and Contractor Meeting November 29, 2011

Substantial Completion June 27, 2012

ACADEMIC ADDITION• Steel structure is making progress.• Overhead utility lines and CMU walls have begun.• 2ndfloorslabwillbegintheendofthisweek.

CATE/ROTC• Underground plumbing and electrical utilities are making progress.• Slab work will resume in January.• Afterslabworkiscompleteandmetalbuildinghasarrived,steelstructurewillbegin.

ATHLETIC ADDITION• CMU wall along the existing building is complete.• Steelstructurehasbegunatthelockerroomarea.Thegymareawillbestartedafterthelockerroom

area is complete.• CMU walls will begin next.

FINE ARTS ADDITION – DRAMA• Steelstructureandroofstructurearecomplete.Concreteslabsarecomplete.• Overhead utility lines have begun.• Metaldeckingandroofingwillbeginnext.

FINE ARTS ADDITION – ORCHESTRA• CMU walls are complete.• Interiormetalstudframinghasbegun.• Roofinghasbegun.

BASEBALL,SOFTBALL,TENNISANDSITE• CMUwallsatfieldhousearenearlycomplete.Mezzanineslabisinplace.• CMUwallshavebeenstartedateachpressbox.Roofsforpressboxes,dugouts,andtennisbuilding

will begin this week.• Fencingandnettingisbeinginstalledaroundthefields.Gradingatbothfieldsismakingprogress.• Grandstandswillarrivemid-DecemberandarescheduledtobecompletedbytheendofDecember.• Cuttingandgradingofparkinglotsanddrivescontinues.Concretewalkswillbeginthisweek.• Gradingandcuttingforthetenniscourtshasbeenstarted.

Page 6: Huckabee Project Update 12-05-11

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 6

Huckabee

EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2

Academic Addition Locker Rooms

Interior View of Orchestra Baseball Field

Page 7: Huckabee Project Update 12-05-11

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 7

Huckabee

Aerial

EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2

Page 8: Huckabee Project Update 12-05-11

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 8

Huckabee

NEW WAREHOUSE FACILITYPROGRESS REPORT

MILESTONE DATES

Schematic Design Presentation January 10, 2011

Architect Signs Documents January 12, 2011

Building Permit Application Submittal January 25, 2011

Proposal Part A Due February 15, 2011

Proposal Part B Due February 16, 2011

Site Plan Application Submittal February 17, 2011

Proposal Evaluations February 17, 2011

Landscaping Plans Approved March 1, 2011

General Contractor Recommendation to School Board March 7, 2011

Job Coordination Meeting March 25, 2011

Grading/Utilities Permit Received March 31, 2011

First Amended Administrative Exception Submitted April 18, 2011

Second Amended Administrative Exception Submitted April 20, 2011

Final Planning Dept. Comments Received April 25, 2011

Building Permit Issued April 28, 2011

First Owner/CO Meeting May 5, 2011

Construction Start Date May 9, 2011

Substantial Completion November 9, 2011

Interior View of Warehouse

Storage Shed

General Contractor

Page 9: Huckabee Project Update 12-05-11

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 9

Huckabee

ANNIE PURL ELEMENTARY SCHOOL ROOF AND HVAC MODIFICATIONSContract Amount: $229,000

MILESTONE DATES

Schematic Design Presentation January 10, 2011

Architect Signs Documents February 3, 2011

Pre-Proposal Meeting February 9, 2011

Proposal Part A Due February 22, 2011

Proposal Part B Due February 23, 2011

Proposal Evaluations February 24, 2011

Building Permit Issued March 2, 2011

General Contractor Recommended to School Board March 7, 2011

First Owner/CO Meeting May 24, 2011

Construction Start Date June 6, 2011

Substantial Completion August 12, 2011

General Contractor

New HVAC Unit and Roofing

New Ceiling and Light Fixtures

Page 10: Huckabee Project Update 12-05-11

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 10

Huckabee

GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS

Construction Manager

BAIRD WILLIAMS CONSTRUCTION

Project Manager

CTE Wing

Science Labs

Academic

Special Education

Library

Cafeteria

Computer Labs

Athletics

Fine Arts

Academic

AuditoriumAthletics

Athletics

Athletics

Huckabee

BAIRD WILLIAMS CONSTRUCTION

GEORGETOWN HIGH SCHOOL3D Rendering

Front EntryBoards.indd 4 7/26/11 8:55 AM

Page 11: Huckabee Project Update 12-05-11

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 11

Huckabee

Material selection with GHS staff June 30, 2011

Cost Review with Construction Manager July 19, 2011

Interiors Presentation July 25, 2011

Architect Signs Documents for Site Utility Package July 26, 2011

CD Coordination Meeting on Site with Architect, Owner and Construction Manager

July 27, 2011

Final Review of FF&E with GHS staff July 27, 2011

City Comments Received for Site Utility package August 8, 2011

100 % CD Review August 15, 2011

Site Utility Package Bid August 17, 2011

Review Comments Due August 22, 2011

Guaranteed Maximum Price on Site Utility Package August 29, 2011

Architect Signs Documents September 1, 2011

Pre-Bid September 21, 2011

Pre-Bid (Technology) September 23, 2011

Bid October 4, 2011

Guaranteed Maximum Price Presented to School Board October 17, 2011

Construction Start Date October 18, 2011

Owner, Architect and Contractor Meeting November 10, 2011

Owner, Architect and Contractor Meeting November 17, 2011

Owner, Architect and Contractor Meeting December 1, 2011

Substantial Completion July 2013

GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONSMILESTONE DATES

Design Kick-off Meeting with Librarian, Science Dept. and Nurse

February 28, 2011

Design Kick-off Meeting with Athletics March 1, 2011

Initial Construction Phasing with Stakeholders March 3, 2011

Design Kick-off Meeting with Special Education March 4, 2011

Design Kick-off Meeting with Administration March 10, 2011

Advertisement for Construction Manager at Risk RFQ March 12, 2011

Received Construction Manager at Risk Step 1 (Qualifications)

March 29, 2011

Evaluation Team Grades and Develops Recommended Short List March 30, 2011

Facility Assessment of ADA, Code and Existing Conditions March 29 - 30, 2011

School Board Receives Recommended Short List April 4, 2011

Step 2 of RFQ Submitted to Short Listed Contractors (Fees and General Conditions)

April 5, 2011

Fees and General Conditions due by 3 PM April 8, 2011

Board of Trustees Select Construction Manager at Risk April 18, 2011

First Meeting with District, Architect, Project Manager and Construction Manager

April 19, 2011

Site Logistics Survey with District, Architect, Project Manager and Construction Manager

April 29, 2011

Schematic Design Presentation June 6, 2011

Kitchen Design Review with Staff June 14, 2011

Site Coordination Meeting with Architect, Owner and Construction Manager

June 16, 2011

MILESTONE DATES

Page 12: Huckabee Project Update 12-05-11

2010 BOND PROGRAM UPDATE

Georgetown Independent School District 12

Huckabee

SITEUTILITYPACKAGE–PHASEI• Existing canopy and sidewalks have been removed.• Sewerandstormdrainmainlinesarecompletearoundthecafeteriaand

athletics additions.• Finalgradehasbeenmadeonthebuildingpadforthecafeteriaand

athletic additions.• Under-padutilitiesandgradebeamexcavationwillbeginnext.• Interior demolition will begin during the Christmas break.

GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS

Site

Transformer and Pad