document

15
Cheryl Brackett, Lead Work Package Engineer, Cianbro Constructors Eric Crivella, Plant Construction Executive, Bentley Systems, Inc.

Upload: fiatech

Post on 23-Mar-2016

218 views

Category:

Documents


2 download

DESCRIPTION

http://fiatech.org/images/stories/events/techconference/2010/presentations/new_innovative_technologies/ConstructSim%20on%20Motiva%20Crude%20Expansion%20Project/constructsim-on-motiva-crude-expansion-project.pdf

TRANSCRIPT

Page 1: Document

Cheryl Brackett, Lead Work Package Engineer, Cianbro Constructors Eric Crivella, Plant Construction Executive, Bentley Systems, Inc.

Page 2: Document

•  Create $10 million, state-of-the-art Eastern Manufacturing Facility.

•  Build and ship 54 prefabricated modules, totaling 9,000 tons of steel and 200,000 lineal feet of pipe.

•  The modules average 40-feet-by-40-feet in cross section, about 120-feet long, and weigh up to 700 tons each.

•  ConstructSim to visualize and interpret the module, plan construction, and generate parts lists and other information

Page 3: Document

Construction Work Areas

Materials Management

Track Spools Track Modules Work Complete

Location

Expedite Install Work to Ready a System for

Testing

Expediting Reports •  Dwgs Not Released •  Spools Not Fab •  Field Mat’ls Not Onsite

Work Packs

Test Packs

Turnover Systems

Priorities

Feasibility Study

Issued

Shop Fab Work Pack Reports •  Spool List •  Field Matl Issue •  Steel Hang List •  Jobcards

Priorities

System Reports

Pressure Test Record Systems Completion

Page 4: Document

Cianbro

Bentley

Jacobs

•  PDS 3D CAD •  Module definition & tracking •  Isometrics •  ISO transmittal database •  Line List •  Equipment list •  CIS/2 & piecemark •  Fabrication status •  iTrack on-site & progress •  Pipe unit rates •  IMS QA/QC and weld tracking

Page 5: Document

The VPM is distributed into a shared workgroup environment.

A “Master Copy” of the VPM is archived on a server, with local copies resident on the user and data processing machines.

User Machine #1

User Machine #2

Uses

User Machine #3

Page 6: Document

•  3D Visualization, Interactive Planning & Construction Sequencing

•  WorkFace Planning –  Steel and Pipe (fab, install & hydro) Work Packs

•  Material & Constraint Analysis •  Rapid Queries •  Status Tracking & Progressing •  Crane Logistics planning •  Quality Assurance

Page 7: Document

•  Spool fabrication •  Equipment installation •  ISO release status •  Pipe material availability •  Work step tracking •  Test pack status •  QA/QC status •  Work package constraints

Page 8: Document
Page 9: Document
Page 10: Document

•  Top down management support and bottom up buy in from field supervision is key

•  Don’t underestimate the systems integration effort and the learning curve involved –  Start as early in the project as possible

•  VPM Admin role is critical –  Always train a backup Admin

•  Data validation is always a problem

•  Changing people & work processes is hard!

Page 11: Document

•  Improved constructability analysis, interactive planning and coordination between engineering office and site office in using Virtual Plant Model

•  Visually plan optimal steel and pipe work crew packages

•  Streamline material, equipment & sequencing

•  Reduce rework / out-of sequence work

•  Speed time to start-up by systems tracking

•  Automated task estimates / automate data entry

•  Reduce time looking for information via visual monitoring the status of engineering, materials and construction execution progress

Page 12: Document
Page 13: Document
Page 14: Document

•  Had direct comparison data because CIS/2 data was not available for 3 modules •  Steel MTOs – substantially reduced time and human

error (shin plates and bolts often get overlooked) •  CSim steel work pack in 4 hours; to do same work

pack manually would require 40+ hours

•  CSim saved a ton of time, effort and money on the structural steel

•  Bottom Line on the Business Case: •  ConstructSim saved Cianbro ~$7M and helped

ensure the project Key Performance Indicators of cost, schedule, safety and quality were met!!

Page 15: Document

Eric Crivella

Plant Construction Executive

Bentley Systems

+1 713 249 4407

[email protected]

If you would like more information contact:

Cheryl Brackett

Lead Work Package Engineer

Cianbro Constructors

+ 1 207 907 7405

[email protected]